Control point check surveying record

Construction unit:WAPDA No.: KIV-FP3-WAPDA-CLJL-001

No. KIV-FP3 “Construction of R3 Water Filtration


Project Plant and Reservoir (65MGD) Near Pipri/Eastern
Bypass”
SCHEMATIC
Surveying
Plant site
area
Surveying
GEOLINE Total Station
machine

FP3/A N:2779135.72 E:307445.346 H:94.642


Basis for FP3/B N:2779040.026 E:307706.794 H:95.302
surveying FP3/C N:2778939.071 E:307805.758 H:95.126
FP3/D N:2778607.207 E:307614.623 H:92.832

Date 3 DEC,2022

After measurement,the control points (FP3/A,FP3/B,


FP3/C,FP3/D) provided by the client meet the
Conclusion
requirements for close error review,thesesix control
points are approved for surveying.