DAILY TPE MANPOWER ARRANGEMENT

DATE 06/05/2022
Manpower
Supervisor Activity Rajaram RP Singh Srinivasan Total
0 48 70
STAFF 22
DIRECT LABOUR 0 0 38 38
IWAN Preparation Air blowing TP-187 9
10
PARLINDUNGAN Foreman 1
HOLILUR Prepare open flap CRH Check Valve 4 4
Killing Punchlist Line Main Condensate ( Drain Line ) 3
ROHMADI 5
Killing Punchlist Line Close Cooling Water ( Drain Line ) 2
RIGGER Clearing wire sling and maintenance chainblock all area 3 3
Touch up Paint Joint Welding TP-187 5
PAINTER 6
Foreman 1
Welder Pipe 1
Welder Plate 4
Skill Welder 1
WELDING 10
Semi Skill 1
Helper 2
Foreman 1
INDIRECT LABOUR 0 0 10 10
ELECTRICAL Monitoring Electric All Area 2 2
HSE Monitoring Safety All Area 2 2
Monitoring Receiving and issuing material consumable, Tool &
WH/MC 3 3
Permanent Material
DRIVER 2 2
QC Admin 1 1