Republic of the Philippines

BATANGAS STATE UNIVERSITY


The National Engineering University
Alangilan Campus
Golden Country Homes, Alangilan, Batangas City, Batangas, Philippines 4200
Tel Nos.: (+63 43) 425-0139 loc. 2121 / 2221
E-mail Address: ceafa@g.batstate-u.edu.ph | Website Address: http://www.batstate-u.edu.ph

College of Engineering – Department of Civil Engineering

DETAILED QUANTITY SURVEY: CONCRETE, MASONRY, AND STEEL


LABORATORY TASK #1

In Partial Fulfillment of the Requirements for the Course


CE 413 - QUANTITY SURVEYING

GROUP 8
DEL MUNDO, JASMIN FAYE M.
GALAY, JESSICA ANN G.
LATAY, ERAIN ANGELLIE M.
LUBUGAN, CARL JUSTINE R.
VILLANUEVA, JAN ISAAC L.
BSCE-3208

April 2023

Leading Innovations, Transforming Lives


I. CONCRETE WORKS

I.1. COLUMN FOOTINGS

LENGTH WIDTH THICKNESS

2.2 m 2.2 m 0.55 m

Quantity : 152 column footings


𝑉 = (𝐿) (𝑊) (𝑇)
𝑉 = (2. 2 𝑚) (2. 2 𝑚) (0. 55 𝑚)
𝑉(𝑐𝑜𝑙𝑢𝑚𝑛 𝑓𝑜𝑜𝑡𝑖𝑛𝑔𝑠) = 404. 32 𝑚3

I.2. WALL FOOTINGS

PERIMETER WIDTH THICKNESS

707.49 m 0.6 m 0.3 m

𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙) = [11(11 − 0. 28 − 0. 55 − 0. 28)] + [11 − 2(0. 28)]

+ 2[3 − 2(0. 28)] + [9(12 − 0. 28 − 0. 55 − 0. 28)] + [11(6 − 2(0. 28))]


+ [12 − 2(0. 28)] + [20 − (2 × 0. 28) − (3 × 0. 55)] + [3(5. 5 − 2(0. 28)]
+ [14 − (2 × 0. 28) − 0. 55] + [4(4 − 0. 28)] + [2(3 − 0. 28)] + [2(3. 5 − 0. 28)]
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙) = 365. 66 𝑚

𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙) = [6(8 − 0. 28 − 0. 55 − 0. 28)] + [12 − (2 × 0. 28)]

+ [8(4 − (2 × 0. 28))] + [6(8 − (2 × 0. 28) − 0. 55)] + [5 − 2(0. 28)]


+ [2(12 − (2 × 0. 28) − (2 × 0. 55))] + [4(5 − (2 × 0. 28))]
+ [8(10 − (2 × 0. 28) − 0. 55)] + [6(20 − (2 × 0. 28) − (3 × 0. 55)]
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙) = 342. 38 𝑚

Leading Innovations, Transforming Lives


𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(𝑇𝑂𝑇𝐴𝐿) = 𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙) + 𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙)

𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟(𝑇𝑂𝑇𝐴𝐿) = 365. 66 𝑚 + 342. 38 𝑚 = 708. 04 𝑚

𝑉 = (𝑃) (𝑊) (𝑇)


𝑉 = (708. 04 𝑚) (0. 6 𝑚) (0. 3 𝑚)
𝑉(𝑤𝑎𝑙𝑙 𝑓𝑜𝑜𝑡𝑖𝑛𝑔𝑠) = 127. 45 𝑚3

I.3. COLUMNS

HEIGHT WIDTH THICKNESS

16.4 m 0.55 m 0.55 m

C1 : 60 pieces
𝑉 = (𝐻) (𝑊) (𝑇)
𝑉 = (16. 4 𝑚) (0. 55 𝑚) (0. 55 𝑚)
3
𝑉 = (4. 96 𝑚 ) (60 𝑝𝑖𝑒𝑐𝑒𝑠)
𝑉(𝐶1) = 297. 6 𝑚3

C2 : 92 pieces
𝑉 = (𝐻) (𝑊) (𝑇)
𝑉 = (16. 4 𝑚) (0. 55 𝑚) (0. 55 𝑚)
3
𝑉 = (4. 96 𝑚 ) (92 𝑝𝑖𝑒𝑐𝑒𝑠)
𝑉(𝐶2) = 456. 32 𝑚3

3 3
𝑉(𝑇𝑂𝑇𝐴𝐿) = 456. 32 𝑚 + 297. 6 𝑚
3
𝑉(𝑐𝑜𝑙𝑢𝑚𝑛𝑠) = 753. 92 𝑚

I.4. BEAMS

PERIMETER WIDTH THICKNESS

TB1=RB1=2B1=3B1 173.52 m 0.35 m 0.45 m

Leading Innovations, Transforming Lives


RB2=2B2=3B2 428.88 m 0.35 m 0.45 m

TB2 112.54 m 0.35 m 0.45 m

𝑃𝑇𝐵1 = [3(11 − (2 × 0. 28) − 0. 55)] + [4(3 − 2(0. 28))] + [12 − (2 × 0. 28) − 0. 55]

+ [18 − (2 × 0. 28) − (2 × 0. 55)] + [12 − (2 × 0. 28) − 0. 55] + [6(4 − 2(0. 28))]


+ [2(8 − (2 × 0. 28) − 0. 55)] + [3(10 − (2 × 0. 28) − 0. 55)] + [20(5 − 2(0. 28)]
+ [7(6 − 2(0. 28)] + [2(5. 5 − 2(0. 28)]
𝑃𝑇𝐵1 = 275. 4 𝑚
3
𝑉𝑇𝐵1 = (275. 4 𝑚)(0. 35 𝑚)(0. 45 𝑚) = 43. 38 𝑚

𝑃𝑇𝐵2 = [18(11 − (2 × 0. 28) − 0. 55] + [20(3 − 2(0. 28)] + [8(12 − (2 × 0. 28) − 0. 55]

+ [4(18 − (2 × 0. 28) − (2 × 0. 55)] + [9(8 − (2 × 0. 28) − 0. 55]


+ [21(4 − (2 × 0. 28)] + [20(10 − (2 × 0. 28) − 0. 55)] + [4(5 − (2 × 0. 28)]
+ [6 − (2 × 0. 28)]
𝑃𝑇𝐵2 = 714. 55 𝑚
3
𝑉𝑇𝐵2 = (714. 55 𝑚)(0. 35 𝑚)(0. 45 𝑚) = 112. 54 𝑚

𝑃𝑅𝐵2 = [22(11 − (2 × 0. 28) − 0. 55) + [22(3 − 2(0. 28))] + [6 − 2(0. 28)]

+ [12(12 − (2 × 0. 28) − 0. 55)] + [6(18 − (2 × 0. 28) − (2 × 0. 55)]


+ [24(8 − (2 × 0. 28) − 0. 55)] + [12(9 − (2 × 0. 28) − 0. 55)]
+ [12(10 − (2 × 0. 28) − 0. 55] + [8(5 − 2(0. 28))]
𝑃𝑅𝐵2 = 907. 66 𝑚
3
𝑉𝑅𝐵2 = (907. 66 𝑚)(0. 35 𝑚)(0. 45 𝑚) = 142. 96 𝑚

3 3
𝑉𝑇𝐵1 = 𝑉𝑅𝐵1 = 𝑉2𝐵1 = 𝑉3𝐵1 = (43. 38 𝑚 )(4) = 173. 52 𝑚
3 3
𝑉𝑅𝐵2 = 𝑉2𝐵2 = 𝑉3𝐵2 = (142. 96 𝑚 )(3) = 428. 88 𝑚
3
𝑉𝑇𝐵2 = 112. 54 𝑚

𝑉𝑇𝑂𝑇𝐴𝐿 = 173. 52 + 428. 88 + 112. 54

Leading Innovations, Transforming Lives


3
𝑉𝑏𝑒𝑎𝑚𝑠 = 714. 94 𝑚

I.5. SLAB

SECTION LENGTH WIDTH THICKNESS

A-D / 8-13 25 m 14 m 0.125 m

K-N / 8-13 25 m 14 m 0.125 m

A-N / 1-8 70 m 30 m 0.125 m

3 3
𝑉1 = (25 𝑚)(14 𝑚)(0. 125 𝑚) = 43. 75 𝑚 (2) = 87. 5 𝑚
3
𝑉2 = (70 𝑚)(30 𝑚)(0. 125 𝑚) = 262. 5 𝑚
3 3
𝑉𝑠𝑙𝑎𝑏 = 87. 5 𝑚 + 262. 5 𝑚
3
𝑉𝑠𝑙𝑎𝑏 = 350 𝑚

I.6. STAIRS
Quantity : 4 stairs

𝑅𝑖𝑠𝑒 = 18 𝑠𝑡𝑒𝑝𝑠 = 0. 22/𝑠𝑡𝑒𝑝 ; 𝑅𝑢𝑛 = 18 𝑠𝑡𝑒𝑝𝑠 = 0. 33/𝑠𝑡𝑒𝑝

For Steps
Quantity : 20 steps

2 2
𝑏= (3) + (1. 98) = 3. 59 𝑚
2 2
𝑐= (3) + (1. 98) = 3. 59 𝑚
2 2
𝑎= (0. 33) + (0. 22) = 0. 40 𝑚

0.22×0.33×0.4 3
𝑉1 = ⎡20( )⎤ = 0. 29 𝑚
⎣ 2 ⎦

Leading Innovations, Transforming Lives


For Landing
Quantity : 1 landing

LENGTH WIDTH THICKNESS

4.0 m 1.0 m 0.125 m

3
𝑉2 = (4. 0 𝑚)(1. 0 𝑚)(0. 125 𝑚) = 0. 5 𝑚

For Waist Slab


Quantity : 2 waist slabs

LENGTH WIDTH THICKNESS

3.59 m 1.90 m 0.125 m

3 3
𝑉3 = (3. 59 𝑚)(1. 90 𝑚)(0. 125 𝑚) = 0. 85 𝑚 (2) = 1. 7 𝑚
3 3 3 3
𝑉𝑇𝑂𝑇𝐴𝐿 = 𝑉1 + 𝑉2 + 𝑉3 = 0. 29 𝑚 + 0. 5 𝑚 + 1. 7 𝑚 = 2. 49 𝑚
3
𝑉𝑠𝑡𝑎𝑖𝑟𝑠 = (2. 49 𝑚 )(4 𝑠𝑡𝑎𝑖𝑟𝑠)(3 𝑓𝑙𝑜𝑜𝑟 𝑙𝑒𝑣𝑒𝑙𝑠)
3
𝑉𝑠𝑡𝑎𝑖𝑟𝑠 = 29. 88 𝑚

I.7. SEPTIC TANK

For Slab

LENGTH WIDTH THICKNESS

10 m 6m 0.15 m

𝑉1 = (𝐿) (𝑊) (𝑇)


3
𝑉1 = (10 𝑚) (6 𝑚) (0. 15 𝑚) = 9 𝑚

Leading Innovations, Transforming Lives


For Vault Cover (Slab)

LENGTH WIDTH THICKNESS

10 m 6m 4” = 0.10 m

𝑉2 = (𝐿) (𝑊) (𝑇)


3
𝑉2 = (10 𝑚) (6 𝑚) (0. 10 𝑚) = 6 𝑚
3 3
𝑉𝑠𝑒𝑝𝑡𝑖𝑐 𝑡𝑎𝑛𝑘 = 9 𝑚 + 6 𝑚
3
𝑉𝑠𝑒𝑝𝑡𝑖𝑐 𝑡𝑎𝑛𝑘 = 15 𝑚

VOLUME (m3)

COLUMN FOOTINGS 404.32 m3

WALL FOOTINGS 127.45 m3

COLUMNS 753.92 m3

BEAMS 714.94 m3

SLABS 350 m3

STAIRS 29.88 m3

SEPTIC TANK 15 m3

TOTAL VOLUME 2395.51 m3

CLASS “A” MIXTURE

MIXTURE PROPORTION CEMENT IN BAG SAND GRAVEL


CLASS (m3) (m3)
40 kg 50 kg

A 1:2.5:5 9.0 7.0 0.5 1.0

3
𝐶𝑒𝑚𝑒𝑛𝑡40𝑘𝑔 = (2395. 51 𝑚 )(9. 0) = 21559. 59 ~ 21560 𝑏𝑎𝑔𝑠
3 3
𝑆𝑎𝑛𝑑 = (2395. 51 𝑚 )(0. 5) = 1197. 76 𝑚
3 3
𝐺𝑟𝑎𝑣𝑒𝑙 = (2395. 51 𝑚 )(1. 0) = 2395. 51 𝑚

Leading Innovations, Transforming Lives


SUMMARY OF MATERIALS FOR CONCRETE WORKS

CEMENT @ 4Okg 21,560 BAGS

SAND 1,197.76 m3

GRAVEL 2,395.51 m3

Leading Innovations, Transforming Lives


II. MASONRY WORKS

II.1 EXTERIOR WALLS


For first floor,
𝑃 = 55 + 70 + 55 + 11 + 11 + 30 + 30 + 18 + 18 + 5 + 5 + 6 = 314 𝑚
For second floor and third floor,
𝑃 = 320 𝑚

Height per floor:


𝐹𝑖𝑟𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 − 4 𝑚
𝑆𝑒𝑐𝑜𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 − 5 𝑚
𝑇ℎ𝑖𝑟𝑑 𝑓𝑙𝑜𝑜𝑟 − 4 𝑚

Area
2
𝐹𝑖𝑟𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 = 314(4 − 0. 45) = 1114. 7 𝑚
2
𝑆𝑒𝑐𝑜𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 = 320(5 − 0. 45) = 1456 𝑚
2
𝑇ℎ𝑖𝑟𝑑 𝑓𝑙𝑜𝑜𝑟 = 320(4 − 0. 45) = 1136 𝑚
2 2 2 2
𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 = 1114. 7 𝑚 + 1456 𝑚 + 1136 𝑚 = 3706. 7 𝑚

Area of windows and doors per floor


QUANTITY OF WINDOWS AND DOORS

1st floor Quantity 2nd floor Quantity 3rd floor Quantity

W/1 32 W/1 44 W/3 45

W/2 10 W/2 16 W/4 16

W/7 15 W/6 6 W/7 11

W/8 12 W/7 4 W/8 4

D/1 12 W/8 4 W/9 1

D/5 1 W/9 1 D/3 3

D/8 1 D/3 6 D/4 1

(FE)D/5 11 (FE)D/5 10

Leading Innovations, Transforming Lives


AREA QUANTITY TOTAL AREA

W/1 = 2.24 76 170.24

W/2 = 3.36 26 87.36

W/3 = 3.20 45 144

W/4 = 5.16 16 82.56

W/6 = 4.5 6 27

W/7 = 1.35 30 40.5

W/8 = 0.48 20 9.6

W/9 = 11.5 2 23

D/1 = 7.25 1 7.25

D/3 = 3.78 9 34.02

D/4 = 3.78 1 3.78

D/5 = 1.68 12 20.16

D/8 = 3.87 1 3.87

FIRE EXIT = 1.68 21 35.28

TOTAL AREA 688.62

Area of Exterior Walls


2
𝐴𝐸𝑋𝑇𝐸𝑅𝐼𝑂𝑅 = 3706. 7 − 688. 62 = 3018. 08 𝑚

Concrete Hollow Blocks


𝑃𝐹𝐼𝑅𝑆𝑇 𝐹𝐿𝑂𝑂𝑅 = 314𝑚

𝐻 = (4 − 0. 45) = 3. 55 𝑚
2
𝐴𝑇 = (314)(3. 55) = 1114. 7 𝑚

2 2
𝑊/1 = 32(2. 24) = 71. 68 𝑚 𝐷/5 = 12(1. 68) = 20. 16 𝑚
2 2
𝑊/2 = 10(3. 36) = 33. 36 𝑚 𝐷/1 = 1(7. 25) = 7. 25 𝑚

Leading Innovations, Transforming Lives


2 2
𝑊/7 = 15(1. 35) = 20. 25 𝑚 𝐷/8 = 1(3. 87) = 3. 87 𝑚
2
𝑊/8 = 12(0. 48) = 5. 76 𝑚
2
𝐴𝑇 = 162. 33 𝑚

2
𝐹𝐼𝑅𝑆𝑇 𝐹𝐿𝑂𝑂𝑅 = 1114. 7 − 162. 33 = 952. 37 𝑚
952. 37(12. 5𝑃𝐶𝑆) = 11904. 625 ~ 11, 905 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

𝑃𝑆𝐸𝐶𝑂𝑁𝐷 𝐹𝐿𝑂𝑂𝑅 = 320 𝑚

𝐻 = (5 − 0. 45) = 4. 55 𝑚
2
𝐴𝑇 = 320(4. 55) = 1456 𝑚

2 2
𝑊/1 = 44(2. 24) = 98. 56 𝑚 𝑊/8 = 4(0. 48) = 1. 92 𝑚
2 2
𝑊/2 = 16(3. 36) = 53. 76 𝑚 𝑊/9 = 1(11. 5) = 11. 5 𝑚
2 2
𝑊/6 = 6(4. 5) = 27 𝑚 𝐷/3 = 6(3. 78) = 22. 68 𝑚
2 2
𝑊/7 = 4(1. 35) = 5. 4𝑚 𝐷/5 = 11(1. 68) = 18. 48 𝑚
2
𝐴𝑇 = 239. 3 𝑚

2
𝑆𝐸𝐶𝑂𝑁𝐷 𝐹𝐿𝑂𝑂𝑅 = 1456 − 239. 3 = 1216. 7 𝑚
1216. 7(12. 5) = 15208. 75~15209 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

𝑃𝑇𝐻𝐼𝑅𝐷 𝐹𝐿𝑂𝑂𝑅 = 320 𝑚

𝐻 = (4 − 0. 45) = 3. 55 𝑚
2
𝐴𝑇 = 320(3. 55) = 1136 𝑚

2 2
𝑊/3 = 45(3. 20) = 144 𝑚 𝑊/9 = 1(11. 5) = 11. 5 𝑚
2 2
𝑊/4 = 16(5. 16) = 82. 56 𝑚 𝐷/3 = 3(3. 78) = 11. 34 𝑚
2 2
𝑊/7 = 11(1. 35) = 14. 85 𝑚 𝐷/4 = 1(3. 78) = 3. 78 𝑚
2 2
𝑊/8 = 4(0. 48) = 1. 92 𝑚 𝐷/5 = 10(1. 68) = 16. 8 𝑚

Leading Innovations, Transforming Lives


𝐴𝑇 = 286. 75 𝑚

2
𝑇𝐻𝐼𝑅𝐷 𝐹𝐿𝑂𝑂𝑅 = 1136 − 286. 75 = 849. 25 𝑚
849. 25(12. 5) = 10, 615. 625~10, 616 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

𝑇𝑂𝑇𝐴𝐿 𝐶𝐻𝐵 𝑂𝐹 𝐸𝑋𝑇𝐸𝑅𝐼𝑂𝑅 𝑊𝐴𝐿𝐿𝑆 = 11, 905 + 15, 209 + 10, 616 = 37, 730 𝑝𝑐𝑠

Mortar for Block Laying


15 x 20 x 40 CHB ; CLASS “B” MIXTURE

Size of CHB Number Bags Cement Mixture


in cm per sq. m
A B C D Sand (m3)

15 x 20 x 40 12.5 1.526 0.0844

2
𝐴𝑟𝑒𝑎 𝑜𝑓 𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑊𝑎𝑙𝑙𝑠 = 3018. 08 𝑚
𝑆𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵 = 15𝑥20𝑥40

By area method and referring to the table,


2
𝐶𝐸𝑀𝐸𝑁𝑇: 3018. 08 𝑚 (1. 526) = 4605. 59 𝑜𝑟 4606 𝑏𝑎𝑔𝑠
2
𝑆𝐴𝑁𝐷: 3018. 08 𝑚 (0. 0844) = 254. 725 𝑜𝑟 254. 73 𝑐𝑢. 𝑚.

Plaster
2 2
𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝐴𝑟𝑒𝑎 𝑜𝑓 𝐸𝑥𝑡𝑒𝑟𝑖𝑜𝑟 𝑊𝑎𝑙𝑙𝑠 = 3018. 08 𝑚 (2 𝑠𝑖𝑑𝑒𝑠) = 6036. 16 𝑚

20mm THICKNESS ; CLASS “B” MIXTURE

Mixture Cement in Bags


Class Thickness of Plaster

8mm 12mm 16mm 20mm 25mm

B 0.240

Sand 0.020

Leading Innovations, Transforming Lives


By area method and referring to the table,
2
𝐶𝐸𝑀𝐸𝑁𝑇: 6036. 16𝑚 (. 240) = 1448. 68 𝑜𝑟 1449 𝑏𝑎𝑔𝑠
2
𝑆𝐴𝑁𝐷: 6036. 16𝑚 (0. 020) = 120. 72 𝑐𝑢. 𝑚.

II.2 INTERIOR WALLS


Perimeter
𝐹𝑖𝑟𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 = 460. 25 𝑚
𝑆𝑒𝑐𝑜𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 = 396 𝑚
𝑇ℎ𝑖𝑟𝑑 𝑓𝑙𝑜𝑜𝑟 = 43 𝑚

Height per floor:


𝐹𝑖𝑟𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 − 4 𝑚
𝑆𝑒𝑐𝑜𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 − 5 𝑚
𝑇ℎ𝑖𝑟𝑑 𝑓𝑙𝑜𝑜𝑟 − 4 𝑚

Area
2
𝐹𝑖𝑟𝑠𝑡 𝑓𝑙𝑜𝑜𝑟 = 460. 25(4 − 0. 45) = 1633. 89 𝑚
2
𝑆𝑒𝑐𝑜𝑛𝑑 𝑓𝑙𝑜𝑜𝑟 = 396(5 − 0. 45) = 1801. 8 𝑚
2
𝑇ℎ𝑖𝑟𝑑 𝑓𝑙𝑜𝑜𝑟 = 439(4 − 0. 45) = 1558. 45 𝑚
2 2 2 2
𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 = 1633. 89 𝑚 + 1801. 8 𝑚 + 1558. 45 𝑚 = 4994. 14 𝑚

QUANTITY OF WINDOWS AND DOORS

1st floor Quantity 2nd floor Quantity 3rd floor Quantity

W/5 7 W/5 9 W/5 5

W/6 1 W/6 3 W/7 10

W/7 4 W/7 4 D/2 1

D/3 7 D/2 1 D/3 8

D/4 3 D/3 12 D/4 6

D/2 1 D/5 2 D/5 10

D/5 10 D/6 4 D/6 4

Leading Innovations, Transforming Lives


D/6 2

D/7 7

AREA QUANTITY TOTAL AREA

W/5 = 3 21 63

W/6 = 4.5 4 18

W/7 = 1.35 18 24.3

D/2 = 7.92 3 23.76

D/3 = 3.78 27 102.06

D/4 = 3.78 9 34.02

D/5 = 1.68 22 36.96

D/6 =1.89 10 18.9

D/7 = 1.26 7 8.82

TOTAL AREA 329.82

Area of Interior Walls


2
𝐴𝐼𝑁𝑇𝐸𝑅𝐼𝑂𝑅 = 4994. 14 − 329. 82 = 4664. 32 𝑚

Concrete Hollow Blocks


𝑃𝐹𝐼𝑅𝑆𝑇 𝐹𝐿𝑂𝑂𝑅 = 460. 25 𝑚

𝐻 = (4 − 0. 45) = 3. 55 𝑚
2
𝐴𝑇 = 460. 25(3. 55) = 1633. 89 𝑚

2 2
𝑊/7 = 7(3) = 21𝑚 𝐷/2 = 1(7. 92) = 7. 92 𝑚
2 2
𝑊/6 = 1(4. 5) = 4. 5 𝑚 𝐷/5 = 10(1. 68) = 16. 8 𝑚
2 2
𝑊/7 = 4(1. 35) = 5. 4 𝑚 𝐷/6 = 2(1. 89) = 3.78 𝑚
2 2
𝐷/3 = 7(3. 78) = 26. 46 𝑚 𝐷/7 = 7(1. 26) = 8. 82 𝑚

Leading Innovations, Transforming Lives


2
𝐷/4 = 3(3. 78) = 11. 34 𝑚
2
𝐴𝑇 = 106. 02 𝑚
2
𝐹𝐼𝑅𝑆𝑇 𝐹𝐿𝑂𝑂𝑅 = 1633. 89 − 106. 02 = 1527. 87 𝑚
1527. 87(12. 5) = 19, 098. 375~19 098 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

𝑃𝑆𝐸𝐶𝑂𝑁𝐷 𝐹𝐿𝑂𝑂𝑅 = 396 𝑚

𝐻 = (5 − 0. 45) = 4. 55 𝑚
2
𝐴𝑇 = 396(4. 55) = 1801. 8 𝑚

2 2
𝑊/5 = 9(3) = 27 𝑚 𝐷/3 = 12(3. 78) = 45. 36 𝑚
2 2
𝑊/6 = 3(4. 5) = 13. 5𝑚 𝐷/5 = 2(1. 68) = 3. 36 𝑚
2 2
𝑊/7 = 4(1. 35) = 5. 4 𝑚 𝐷/6 = 4(1. 89) = 7.56 𝑚
2
𝐷/2 = 1(7. 92) = 7. 92 𝑚
𝐴𝑇 = 110. 1 𝑚
2
𝑆𝐸𝐶𝑂𝑁𝐷 𝐹𝐿𝑂𝑂𝑅 = 1801. 8 − 110. 01 = 1691. 7 𝑚
1691. 7(12. 5) = 21, 146. 25~21 146 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

𝑃𝑇𝐻𝐼𝑅𝐷 𝐹𝐿𝑂𝑂𝑅 = 439 𝑚

𝐻 = (4 − 0. 45) = 3. 55 𝑚
2
𝐴𝑇 = 439(3. 55) = 1558. 45 𝑚

2 2
𝑊/5 = 5(3) = 15 𝑚 𝐷/4 = 6(3. 78) = 22. 68 𝑚
2 2
𝑊/7 = 10(1. 35) = 13. 5𝑚 𝐷/5 = 10(1. 68) = 16. 8 𝑚
2 2
𝐷/2 = 1(7. 92) = 7. 92 𝑚 𝐷/6 = 4(1. 89) = 7. 56 𝑚
2
𝐷/3 = 8(3. 78) = 30. 24 𝑚
2
𝐴𝑇 = 113. 7 𝑚
2
𝑇𝐻𝐼𝑅𝐷 𝐹𝐿𝑂𝑂𝑅 = 1558. 45 − 113. 7 = 1444. 75 𝑚
1444. 75(12. 5) = 18 059. 375~18 059 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

Leading Innovations, Transforming Lives


𝑇𝑂𝑇𝐴𝐿 𝐶𝐻𝐵 𝑂𝐹 𝐼𝑁𝑇𝐸𝑅𝐼𝑂𝑅 = 19 098 + 21 146 + 18 059 = 58 303 𝑝𝑐𝑠

Mortar for Block Laying


15 x 20 x 40 CHB ; CLASS “B” MIXTURE

Size of CHB Number Bags Cement Mixture


in cm per sq. m
A B C D Sand (m3)

15 x 20 x 40 12.5 1.526 0.0844

2
𝐴𝑟𝑒𝑎 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑊𝑎𝑙𝑙𝑠 = 4664. 32 𝑚
𝑆𝑖𝑧𝑒 𝑜𝑓 𝐶𝐻𝐵 = 15𝑥20𝑥40
By area method and referring to the table,
2
𝐶𝐸𝑀𝐸𝑁𝑇: 4664. 32𝑚 (1. 526) = 7117. 75 𝑜𝑟 7118 𝑏𝑎𝑔𝑠
2
𝑆𝐴𝑁𝐷: 4664. 32𝑚 (0. 0844) = 393. 67 𝑐𝑢. 𝑚.

Plaster
2 2
𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝐴𝑟𝑒𝑎 𝑜𝑓 𝐼𝑛𝑡𝑒𝑟𝑖𝑜𝑟 𝑊𝑎𝑙𝑙𝑠 = 4664. 32 𝑚 (2 𝑠𝑖𝑑𝑒𝑠) = 9328. 64 𝑚
20mm THICKNESS ; CLASS “B” MIXTURE

Mixture Cement in Bags


Class Thickness of Plaster

8mm 12mm 16mm 20mm 25mm

B 0.240

Sand 0.020

By area method and referring to the table,


2
𝐶𝐸𝑀𝐸𝑁𝑇: 9328. 64 𝑚 (. 240) = 2238.87 or 2239 bags
2
𝑆𝐴𝑁𝐷: 9328. 64 𝑚 (0. 020) = 186.57 𝑐𝑢. 𝑚

II.3. SEPTIC TANK


Concrete Hollow Blocks
𝐴 = [3(1. 2192 × 6)] + [2(1. 2192 × 10)]

Leading Innovations, Transforming Lives


𝐴 = (7. 32 × 3) + (12. 19 × 2)
2
𝐴 = 21. 96 + 24. 38 = 46. 34 𝑚

𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐶𝐻𝐵 = 𝐴 × 12. 5 = 46. 34 × 12. 5 = 579. 25


𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐶𝐻𝐵 = 580 𝑝𝑐𝑠 𝑜𝑓 𝐶𝐻𝐵

Mortar for Block Laying


15 x 20 x 40 CHB ; CLASS “B” MIXTURE

Size of CHB Number Bags Cement Mixture


in cm per sq. m
A B C D Sand (m3)

15 x 20 x 40 12.5 1.526 0.0844

2
𝐴 = 46. 34 𝑚
𝐶𝑒𝑚𝑒𝑛𝑡 = 46. 34 × 1. 526 = 70. 71
𝐶𝑒𝑚𝑒𝑛𝑡 = 71 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 46. 34 × 0. 0844 = 3. 911
3
𝑆𝑎𝑛𝑑 = 3. 91 𝑚

Plaster
20mm THICKNESS ; CLASS “B” MIXTURE

Mixture Cement in Bags


Class Thickness of Plaster

8mm 12mm 16mm 20mm 25mm

B 0.240

Sand 0.020

3
𝐴 = 46. 34 × 2 = 92. 68 𝑚
𝐶𝑒𝑚𝑒𝑛𝑡 = 92. 68 × 0. 240 = 22. 24
𝐶𝑒𝑚𝑒𝑛𝑡 = 23 𝑏𝑎𝑔𝑠
𝑆𝑎𝑛𝑑 = 92. 68 × 0. 020 = 1. 8536
3
𝑆𝑎𝑛𝑑 = 1. 85 𝑚

Leading Innovations, Transforming Lives


SUMMARY OF MATERIALS FOR MASONRY WORKS

NUMBER OF CHB 96,613 pcs

CEMENT @ 4Okg 15,506 bags

SAND 961.45 cu.m.

Leading Innovations, Transforming Lives


III: STEEL REINFORCEMENTS

III.1. COLUMN FOOTINGS

LENGTH WIDTH THICKNESS NO. OF CF

2.2 m 2.2 m 0.55 m 152

For Rebar
= 10(2) = 20
20 𝑝𝑐𝑠 𝑜𝑓 2. 25 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
6
= 2.25
= 2. 67
7.5
= 2.25
= 3. 33
9
= 2.25
= 4

= 20(152) = 3040 𝑝𝑐𝑠


3040
= 9
= 337. 78

= 338 𝑝𝑐𝑠 𝑜𝑓 9 𝑚 − 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


For Tie Wire
= 10 × 10 = 100 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠 𝑡𝑜 𝑏𝑒 𝑡𝑖𝑒𝑑
= 100 × 152 𝑐𝑜𝑙𝑢𝑚𝑛𝑠 = 15 200 𝑡𝑖𝑒𝑠
= 15 200 × 0. 4 𝑚 = 6 080 𝑚 𝑜𝑓 𝑇𝑖𝑒 𝑊𝑖𝑟𝑒
6080
= 53
= 114. 72

= 115𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒 𝑖𝑠 𝑛𝑒𝑒𝑑𝑒𝑑

II.2. COLUMNS
For Ground floor

Length of Column Depth Slab Thickness Column Depth


Column on Footing

4m 3m 0.125 m 0.475 m 0.4 m

𝐿 = 0. 4 + 4 + 3 + 0. 125 + 0. 475 = 8 𝑚

Leading Innovations, Transforming Lives


8 𝑝𝑐𝑠 𝑜𝑓 8 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
1.
𝑆 = 16𝑑𝑏 = 16(25) = 400 𝑚𝑚

𝑆 = 48𝑑𝑡 = 48(12) = 576 𝑚𝑚

𝑆 = 550 𝑚𝑚
2.
8
= 0.4
= 20 + 1 = 21 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛

3.
= 21 × 152 = 3192 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
4.
= 0. 39 × 4 = 1. 56 = 1. 7 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒
5.
6
= 1.7
= 3. 53
7.5
= 1.7
= 4. 41
9
= 1.7
= 5. 29

6.
3192
= 9
= 354. 67

= 355 𝑝𝑐𝑠 9 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


7.
= 3192 × 8 𝑝𝑐𝑠 𝑟𝑒𝑏𝑎𝑟 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛 = 25 536 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
8.
= 25 536 × 0. 4𝑚 𝑜𝑓 𝑡𝑖𝑒𝑠 𝑝𝑒𝑟 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 = 10 214. 4 𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
9.
10 214.4𝑚
= 53𝑚/𝑘𝑔
= 192. 72𝑘𝑔𝑠

= 193 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑇𝑖𝑒 𝑊𝑖𝑟𝑒

Leading Innovations, Transforming Lives


For Second Floor

Length of Column Slab Thickness

5m 0.125 m 0.4 m

𝐿 = 5 + 0. 4 + 0. 125 = 5. 525
𝐿 =6m
8 𝑝𝑐𝑠 𝑜𝑓 6 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
1.
𝑆 = 16𝑑𝑏 = 16(25) = 400 𝑚𝑚

𝑆 = 48𝑑𝑡 = 48(12) = 576 𝑚𝑚

𝑆 = 550 𝑚𝑚
2.
6
= 0.4
= 15 + 1 = 16 𝑝𝑐𝑠 𝑜𝑓 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛

3.
= 16 × 152 = 2432 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
4.
= 0. 39 × 4 = 1. 56 = 1. 7𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒
5.
6
= 1.7
= 3. 53
7.5
= 1.7
= 4. 41
9
= 1.7
= 5. 29

6.
2432
= 9
= 270. 22

= 271 𝑝𝑐𝑠 𝑜𝑓 9 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


7.
= 2432 × 8 𝑝𝑐𝑠 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛 = 19 456 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
8.
= 19 456 × 0. 4 𝑚 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒 𝑝𝑒𝑟 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 = 7782. 4 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
9.

Leading Innovations, Transforming Lives


7782.4
= 53𝑚/𝑘𝑔
= 146. 84 𝑘𝑔𝑠

= 147 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒


For Third floor

Length of Column

4m 0.4 m

𝐿 = 4 + 0. 4 = 4. 4
𝐿 = 5𝑚
8 𝑝𝑐𝑠 𝑜𝑓 5 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
1.
𝑆 = 16𝑑𝑏 = 16(25) = 400 𝑚𝑚

𝑆 = 48𝑑𝑡 = 48(12) = 576 𝑚𝑚

𝑆 = 550 𝑚𝑚
2.
5
= 0.4
= 12. 5 = 13 + 1 = 14 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛

3.
= 14 × 152 = 2128 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
4.
= 0. 39 × 4 = 1. 56 = 1. 7 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒
5.
6
= 1.7
= 3. 53
7.5
= 1.7
= 4. 41
9
= 1.7
= 5. 29

6.
2128
= 9
= 236. 44

= 237 𝑝𝑐𝑠 𝑜𝑓 9𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


7.
= 2 128 × 8 𝑝𝑐𝑠 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 𝑝𝑒𝑟 𝑐𝑜𝑙𝑢𝑚𝑛 = 17 024 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
8.

Leading Innovations, Transforming Lives


= 17 024 × 0. 4 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒 𝑝𝑒𝑟 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 = 6809. 6𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
9.
6809.6
= 53𝑚/𝑘𝑔
= 128. 48

= 129 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

III.3. WALLS
Reinforcement of Wall

Area of Exterior Walls 3018.08 m2

Area of Interior Walls 4664.32 m2

TOTAL AREA (AT) 7682.4 m2

@80cm spacing ; 3 layers


Vertical Steel Bar Length (VSBL)
= 𝐴𝑇 × 1. 60 = 7682. 4 × 1. 60 = 12291. 84 ~ 12292 𝑚

Horizontal Steel Bar Length (HSBL)


= 𝐴𝑇 × 2. 15 = 7682. 4 × 2. 15 = 16517. 16 ~ 16518 𝑚

𝑇𝑂𝑇𝐴𝐿 𝐿𝐸𝑁𝐺𝑇𝐻 = 𝑉𝑆𝐵𝐿 + 𝐻𝑆𝐵𝐿 = 12292 + 16518 = 28810 𝑚


28810 𝑚
𝑇𝑆𝐵 = 12 𝑚
= 2400. 83

𝑇𝑆𝐵 = 2401 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑜𝑓 12𝑚 𝑙𝑜𝑛𝑔

Tie Wire for Wall


𝑊𝑇𝑊 = 𝐴𝑇 × 0. 024 = 7682. 4 × 0. 024 = 184. 38

𝑊𝑇𝑊 = 185 𝑘𝑔 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

Leading Innovations, Transforming Lives


III.4. BEAMS

Leading Innovations, Transforming Lives


Leading Innovations, Transforming Lives
For Stirrups
𝑇𝐵1 = 2𝐵1 = 3𝐵1 = 𝑅𝐵1
14 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 14 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 210
34 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 17 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 578
14 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 20 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 280
𝑡𝑜𝑡𝑎𝑙 = 1068
𝑙 = 2(0. 35) + 2(0. 45) = 1. 60
𝑙 = 1. 7 𝑚
6
1.7
= 3. 53
7.5
1.7
= 4. 41
9
1.7
= 5. 29
1068
5
= 213. 6

= 214 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑏𝑎𝑟


𝑇𝐵2
59 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 15 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 885
80 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 17 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 1360
29 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 20 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 580
𝑡𝑜𝑡𝑎𝑙 = 2825
𝑙 = 2(0. 35) + 2(0. 45) = 1. 60
𝑙 = 1. 7 𝑚
6
1.7
= 3. 53
7.5
1.7
= 4. 41
9
1.7
= 5. 29
2825
5
= 565

= 565 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑏𝑎𝑟


2𝐵2 = 3𝐵2 = 𝑅𝐵2
72 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 15 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 1080
88 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 17 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 1496
43 𝑏𝑒𝑎𝑚𝑠 𝑤𝑖𝑡ℎ 20 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠 = 860
𝑡𝑜𝑡𝑎𝑙 = 3436

Leading Innovations, Transforming Lives


𝑙 = 2(0. 35) + 2(0. 45) = 1. 60
𝑙 = 1. 7 𝑚
6
1.7
= 3. 53
7.5
1.7
= 4. 41
9
1.7
= 5. 29
3436
5
= 687. 2

= 688 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑏𝑎𝑟


Total Stirrups
4(1068) + 2825 + 3(3436) = 17405
17405
= 5
= 3481

= 3481 𝑡𝑜𝑡𝑎𝑙 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑏𝑎𝑟


For Tie Wires
=3481 × 0. 4 = 1392. 4 𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒𝑠
1392.4
= 53
= 26. 27

= 27 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒


III.5. SLAB
First Floor
For One-way Slab

Slab Qty Length Width

2-S14 and 3-S14 2 1.5 m 4m

2-S15 and 3-S15 2 3m 1m

2-S16 and 3-S19 2 1.5 m 4.25 m

2-S17 and 3-S20 2 1.25 m 5m

2-S21 and 3-S24 2 1.5 m 5m

2
2 − 𝑆14 𝑎𝑛𝑑 3 − 𝑆14 = 1. 5 × 4 = 6 𝑚
2
= 6 𝑚 × 2 𝑝𝑐𝑠
2
𝐴1 = 12 𝑚

2 − 𝑆15 𝑎𝑛𝑑 3 − 𝑆15 = 3 × 1

Leading Innovations, Transforming Lives


2
= 3 𝑚 × 2 𝑝𝑐𝑠
2
𝐴2 = 6 𝑚

2 − 𝑆16 𝑎𝑛𝑑 3 − 𝑆19 = 1. 5 × 4. 25


2
= 6. 38 𝑚 × 2 𝑝𝑐𝑠
2
𝐴3 = 12. 76 𝑚

2 − 𝑆17 𝑎𝑛𝑑 3 − 𝑆20 = 1. 25 × 5


2
= 6. 25 𝑚 × 2 𝑝𝑐𝑠
2
𝐴4 = 12. 5 𝑚

2 − 𝑆21 𝑎𝑛𝑑 3 − 𝑆24 = 1. 5 × 5


2
= 7. 5 𝑚 × 2 𝑝𝑐𝑠
2
𝐴5 = 15 𝑚

𝐴𝑇 = 12 + 6 + 12. 76 + 12. 5 + 15
2
𝐴𝑇 = 58. 26 𝑚
2
𝐴𝑇 = 58. 26 𝑚 , 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚, 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 = 9 𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒 = 30 𝑐𝑚
2
@6𝑚 = 58. 26 𝑚 × 2. 584 = 150. 54384 ~150. 54
2
@7. 5𝑚 = 58. 26 𝑚 × 2. 004 = 116. 75304~116. 75
2
@9𝑚 = 58. 26 𝑚 × 1. 636 = 95. 31336~95. 31
@12𝑚 = 58. 26 × 1. 197 = 69. 73722~69. 74
@7. 5𝑚 = 117 𝑝𝑐𝑠 𝑜𝑓 7. 5 𝑚 25𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
-Tie Wire
2
@30𝑐𝑚 = 58. 26 𝑚 × 0. 217 = 12. 64242~12. 64
@30𝑐𝑚 = 13 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

For Two-way Slab

Slab Qty Length Width AREA

1-3/A-C = 2 11 m 8m 176 m2
1-3/L-M

Leading Innovations, Transforming Lives


3-5/A-C = 2 11 m 8m 176 m2
1-3/I-M

1-3/C-D = 2 3m 8m 48 m2
1-3/K-L

3-5/C-D = 4 3m 4m 48 m2
3-5/I-L

5-6/A-C = 4 5.5 m 4m 88 m2
5-6/L-M

6-7/A-C = 2 3m 5m 30 m2
6-7/K-L

7-8/A-C = 12 5.5 m 5m 330 m2


7-8/L-M

5-6/C-D = 2 3m 4m 24 m2
5-6/K-L

6-13/C-D 14 3m 4m 168 m2

1-3/D-F 1 12 m 8m 96 m2

3-5/D-F 1 12 m 8m 96 m2

5-6/D-F 2 6m 4m 48 m2

6-8/D-E 2 6m 5m 60 m2

6-8/E-F 2 6m 5m 60 m2

4-5/F-G 6m 4m 24 m2

6-8/F-G 2 6m 5m 60 m2

4-5/G-H 2 6m 4m 48 m2

7-9/G-H 2 6m 5m 60 m2

4-5/H-I 6m 4m 24 m2

6-8/H-I 2 6m 5m 60 m2

1-4/F-I 1 18 m 12 m 216 m2

1-4/I-K 1 12 m 12 m 144 m2

4-5/I-K 2 6m 4m 48 m2

5-6/I-K 2 6m 4m 48 m2

Leading Innovations, Transforming Lives


5-8/I-J 2 6m 5m 60 m2

4-5/J-K 2 6m 4m 48 m2

5-6/J-K 2 6m 4m 48 m2

6-8/J-K 2 6m 5m 60 m2

ATOTAL 2396 m2

2
𝐴𝑇 = 2396 𝑚 , 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚, 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 = 9𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒 = 30 𝑐𝑚

Rebar
2
@6 𝑚 = 2396 𝑚 × 3. 221 = 7717. 52
2
@7. 5 𝑚 = 2396 𝑚 × 2. 296 = 5501. 22
2
@9 𝑚 = 2396 𝑚 × 1. 921 = 4602. 72
2
@12 𝑚 = 2396 𝑚 × 1. 382 = 3311. 272
@9 𝑚 = 4603 𝑝𝑐𝑠 𝑜𝑓 9𝑚 25𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟

-Tie Wire
2
@30 𝑐𝑚 = 2396 𝑚 × 0. 257 = 615. 77
@30𝑐𝑚 = 616 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

Second and Third Floor


For One-way Slab

Slab Qty Length Width

2-S14 and 3-S14 2 1.5 m 4m

2-S15 and 3-S15 2 3m 1m

2-S16 and 3-S19 2 1.5 m 4.25 m

2-S17 and 3-S20 2 1.25 m 5m

2-S21 and 3-S24 2 1.5 m 5m

2
2 − 𝑆14 𝑎𝑛𝑑 3 − 𝑆14 = 1. 5 × 4 = 6 𝑚
2
= 6 𝑚 × 2 𝑝𝑐𝑠 × 2 𝑓𝑙𝑜𝑜𝑟𝑠

Leading Innovations, Transforming Lives


2
𝐴1 = 24 𝑚

2 − 𝑆15 𝑎𝑛𝑑 3 − 𝑆15 = 3 × 1


2
= 3 𝑚 × 2 𝑝𝑐𝑠 × 2 𝑓𝑙𝑜𝑜𝑟𝑠
2
𝐴2 = 12 𝑚

2 − 𝑆16 𝑎𝑛𝑑 3 − 𝑆19 = 1. 5 × 4. 25


2
= 6. 38 𝑚 × 2 𝑝𝑐𝑠 × 2 𝑓𝑙𝑜𝑜𝑟𝑠
2
𝐴1 = 25. 52 𝑚

2 − 𝑆17 𝑎𝑛𝑑 3 − 𝑆20 = 1. 25 × 5


2
= 6. 25 𝑚 × 2 𝑝𝑐𝑠 × 2 𝑓𝑙𝑜𝑜𝑟𝑠
2
𝐴1 = 25 𝑚

2 − 𝑆21 𝑎𝑛𝑑 3 − 𝑆24 = 1. 5 × 5


2
= 7. 5 𝑚 × 2 𝑝𝑐𝑠 × 2 𝑓𝑙𝑜𝑜𝑟𝑠
2
𝐴1 = 30 𝑚

𝐴𝑇 = 24 + 12 + 25. 52 + 25 + 30
2
𝐴𝑇 = 116. 52 𝑚

2
𝐴𝑇 = 116. 52 𝑚 , 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚, 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 = 9 𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒 = 30 𝑐𝑚

-Rebar
2
@6 𝑚 = 116. 52 𝑚 × 2. 584 = 301. 09
2
@7. 5 𝑚 = 116. 52 𝑚 × 2. 004 = 233. 51
2
@9 𝑚 = 116. 52 𝑚 × 1. 636 = 190. 63
2
@12 𝑚 = 116. 52 𝑚 × 1. 197 = 139. 47
@9 𝑚 = 191 𝑝𝑐𝑠 𝑜𝑓 9 𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
-Tie Wire
2
@30𝑐𝑚 = 116. 52 𝑚 × 0. 214 = 24. 94
@30𝑐𝑚 = 25 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

Leading Innovations, Transforming Lives


For Two-way Slab

Slab Qty Length Width

1-5/A-N 1 70 m 16 m

5-6/A-N 2 26 m 4m

5-6/F-G 2 2.5 m 4m

6-7/A-G 2 26.5 m 5m

7-8/A-N 1 70 m 5m

8-13/A-D 2 14 m 25 m

8-9/G-H 1 5m 6m

𝐴 = (16 × 70) + (4 × 26)2 + (2. 5 × 4)2 + (25. 5 × 5)2 + (70 × 5) + (14 × 25)2
+ (5 × 6)
𝐴 = 1120 + 208 + 20 + 255 + 350 + 700 + 300
𝐴 = 2683 × 2
2
𝐴 = 5366 𝑚
2
𝐴 = 5366 𝑚 , 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚, 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 = 6 𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒 = 30 𝑐𝑚
-Rebar
2
@6 𝑚 = 5366 𝑚 × 3. 221 = 17283. 89
2
@7. 5 𝑚 = 5366 𝑚 × 2. 296 = 12320. 34
2
@9 𝑚 = 5366 𝑚 × 1. 921 = 10308. 09
2
@12 𝑚 = 5366 𝑚 × 1. 382 = 7415. 81
@6 𝑚 = 17284 𝑝𝑐𝑠 𝑜𝑓 6 𝑚 25𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
Tie Wire
2
@30 𝑐𝑚 = 5366 𝑚 × 0. 350 = 1878. 1
@30 𝑐𝑚 = 1879 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

III.6. STAIRS
For Waist slab
𝐿 = 3𝑚

Leading Innovations, Transforming Lives


𝑊 = 1. 9 𝑚
2
𝐴 = 3 × 1. 9 = 5. 7 𝑚
2
𝐴 = 5. 7 × 2 = 11. 4 𝑚
2
𝐴 = 11. 4 𝑚
12
11.4
= 1. 05

𝑠𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 = 7. 5 𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒𝑠 = 30 𝑐𝑚


-Steel Bars
@6 𝑚 = 11. 4 × 2. 584 = 29. 46
@7. 5 𝑚 = 11. 4 × 2. 004 = 22. 85
@9 𝑚 = 11. 4 × 1. 636 = 18. 65
@12𝑚 = 11. 4 × 1. 197 = 13. 65
@7. 5 𝑚 = 23 𝑝𝑐𝑠 𝑜𝑓 7. 5𝑚 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
-Tie Wire
@30𝑐𝑚 = 11. 4 × 0. 217 = 2. 47
@30𝑐𝑚 = 3𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
For Landing
𝐿 = 4𝑚
𝑊 = 1𝑚
𝐴=4 ×1
2
𝐴 = 4𝑚
12
= 4
= 3

𝑠𝑝𝑎𝑐𝑖𝑛𝑔 = 15 𝑐𝑚,
𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 = 12 𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒𝑠 = 30 𝑐𝑚

-Rebars
@6 𝑚 = 4 × 2. 584 = 10. 34
@7. 5 𝑚 = 4 × 2. 004 = 8. 016
@9 𝑚 = 4 × 1. 636 = 6. 54
@12 = 4 × 1. 197 = 4. 79
@12 = 5 𝑝𝑐𝑠 𝑜𝑓 25 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟

Leading Innovations, Transforming Lives


-Tie Wire
@30 = 4 × 0. 207 = 0. 83
@30 = 1 𝑘𝑔 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

For Steps
1.
𝑆 = 16𝑑𝑏 = 16(25) = 400 𝑚𝑚

𝑆 = 48𝑑𝑡 = 48(12) = 576 𝑚𝑚

𝑆 = 442. 2 𝑚𝑚
2.
3
= 0.4422
= 6. 78 = 7 + 1 = 8 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠 𝑝𝑒𝑟 𝑠𝑡𝑎𝑖𝑟

3.
= 8 × 18 = 144 𝑡𝑜𝑡𝑎𝑙 𝑡𝑖𝑒𝑠
4.
= 0. 17 + 0. 18 + 0. 06 = 0. 41 = 0. 5
= 0. 6𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑡𝑖𝑒
5.
6
= 0.6
= 10

6.
144
= 6
= 24

= 24 𝑝𝑐𝑠 𝑜𝑓 6 𝑚 10 𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


7.
= 144 × 3 = 432 𝑡𝑜𝑡𝑎𝑙 𝑙𝑎𝑡𝑒𝑟𝑎𝑙 𝑡𝑖𝑒𝑠
8.
= 432 × 0. 4 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑝𝑒𝑟 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 = 172. 8𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

172.8
= 53𝑚/𝑘𝑔
= 3. 26

= 4 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

Leading Innovations, Transforming Lives


III.7. SEPTIC TANK
For Walls
𝑡𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐶𝐻𝐵 = 580 𝑝𝑐𝑠

𝑉𝑟 = 580 × 0. 128 = 74. 24

𝑉𝑟 = 75𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙 𝑓𝑜𝑟 𝑣𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑏𝑎𝑟𝑠


75
𝑉𝑟 = 12
= 6. 25

𝑉𝑟 = 7 𝑝𝑐𝑠 𝑜𝑓 12𝑚 10𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟

𝐻𝑟 = 580 × 0. 172 = 99. 76

𝐻𝑟 = 100𝑚 𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙 𝑓𝑜𝑟 ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 𝑏𝑎𝑟𝑠


100
𝐻𝑟 = 9
= 11. 11

𝐻𝑟 = 12 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟

For Slab of Leaching Chamber


𝐿 = 3𝑚
𝑊 = 6𝑚
𝐴=3 ×6
2
𝐴 = 18 𝑚
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 = 15𝑐𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 = 12𝑚, 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡𝑖𝑒 = 30𝑐𝑚
-Rebars
@6𝑚 = 18 × 2. 584 = 46. 51
@7. 5 𝑚 = 18 × 2. 004 = 36. 07
@9 𝑚 = 18 × 1. 636 = 29. 45
@12 𝑚 = 18 × 1. 197 = 21. 55
@12𝑚 = 22 𝑝𝑐𝑠 𝑜𝑓 12 𝑚 10𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
-Tie Wire
@30𝑐𝑚 = 18 × 0. 207 = 3. 73
@30𝑐𝑚 = 4 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
For Slab of Digestion Chamber
𝐿 = 7𝑚
𝑊 = 6𝑚
𝐴=7 ×6

Leading Innovations, Transforming Lives


2
𝐴 = 42 𝑚
-Rebars
@6 𝑚 = 42 × 2. 584 = 108. 53
@7. 5 𝑚 = 42 × 2. 004 = 84. 17
@9 𝑚 = 42 × 1. 636 = 68. 71
@9 𝑚 = 42 × 1. 197 = 50. 27
@9 𝑚 = 69 𝑝𝑐𝑠 𝑜𝑓 9𝑚 10𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
-Tie Wire
@30 𝑐𝑚 = 42 × 0. 214 = 8. 99
@30 𝑐𝑚 = 9 𝑘𝑔𝑠 𝑜𝑓 𝐺𝐼 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒
For Slab of Vault Cover
-vertical bars
22 𝑝𝑐𝑠 𝑜𝑓 9. 85 100𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
6
5.85
= 1. 02

= 22 × 5. 85 = 128. 7
128.7
= 6
= 21. 45

= 22 𝑝𝑐𝑠 𝑜𝑓 6𝑚 100𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟


4 𝑝𝑐𝑠 𝑜𝑓 5. 85 100𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟
10.5
9.85
= 1. 07

= 4 × 9. 85 = 39. 4
39.4
= 10.5
= 3. 75

= 4 𝑝𝑐𝑠 𝑜𝑓 10. 5 𝑚 100𝑚𝑚Ø 𝑟𝑒𝑏𝑎𝑟

STRUCTURAL BAR LENGTH STEEL BAR GI TIE WIRES STIRRUPS


ELEMENT (m) (pieces) (kg)

Column 9 338 115


Footings

Columns (1st 9 355 193


floor)

Columns (2nd 9 271 147


floor)

Columns (3rd 9 237 129


floor)

Leading Innovations, Transforming Lives


Walls 12 2401 185

Beams 12 1446 821

For Stirrups 9 3481 7329

Slab (One Way, 7.5 117 13


1st floor)

Slab (Two Way, 9 4603 616


1st floor)

Slab (One Way, 9 191 25


2nd and 3rd floor)

Slab (Two Way, 6 17284 1879


2nd and 3rd floor)

Stairs (Waist 7.5 23 3


Slab)

Stairs 12 5 1
(Landings)

Stairs (Steps) 6 24 4

Septic Tank 12 7
(Walls, Vertical
Bars)

Septic Tank 9 12
(Walls,
Horizontal Bars)

Septic Tank 12 22 40
(Slab of
Leaching
Chamber)

Septic Tank 9 69 9
(Slab of
Digestion
Chamber)

Septic Tank 6 22
(Slab of Vault
Cover)

Septic Tank 10.5 4


(Slab of Vault
Cover)

Leading Innovations, Transforming Lives


SUMMARY OF MATERIALS FOR STEEL REINFORCEMENTS

6 meter-REBARS 17,330 pieces

7.5 meter-REBARS 140 pieces

9 meter-REBARS 9,557 pieces

10.5 meter-REBARS 4 pieces

12 meter-REBARS 3,881 pieces

GI TIE WIRES @6 m 1,883 kgs

GI TIE WIRES @7.5 m 16 kgs

GI TIE WIRES @9 m 1,234 kgs

GI TIE WIRES @12 m 1,047 kgs

STIRRUPS 17,405