Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 62

CHAPTER ONE

Introduction

1.1 Background to the Study

Risk is inherent in all human endeavours, including construction activities, and the risk

elements involved are diverse and varied (Ede, 2016). The scope of building activities

extends to risk management in planning, arranging and controlling activities and resources in

order to minimise the impact of uncertain events. Risk in construction has been the object of

attention because of time and cost associated with construction projects (Akintoye &

MacLeod, 2017). The collapse of building has been an issue of great concern to all and

sundry in Nigeria and yet these buildings are major contributors to the development of any

nation. Therefore, when a building collapses, it fails to render the functions which it should

perform to the people and the government. A building is regarded as collapsed if the whole

structure or part thereof has fallen down and therefore cannot serve the purpose for which it

was intended (John, 2017). When building collapses, it generates deep emotional reactions

from every segment of the population constituting great losses to the country in terms of

physical, human and material resources.in recent past there has been a lot of building collapse

and most of them are not insured (Obodoh, 2019). Mustafa and Al-Bahar (2015) have

identified some risk sources central to construction activities. These are physical,

environmental, design, logistics, financial, legal, political, construction and operation risks.

Carruth (2017) also identified some risk elements inherent in construction works. These

include site security and health and welfare requirements. However, the prudent contractor

will make sure that he has effectively managed his risk to the maximum extent possible,

including the use of insurance (Hansen, 2014; Charles, 2012). Also, the Nigerian construction

industry of today has been identified as an avenue for human tragedies and losses. Successful

1
project deliveries are sometimes difficult to achieve, because of the various challenges

encountered, which result in failure of the building structure, total collapse, loss of lives and

property as well as unsustainability of our built environment (Kawu, 2013). Guiding against

these, Insurance Act Number 37 of 2003 was passed into law. Section 64(1) of the Insurance

Act 2003 stipulated that any building under construction above two floors should be insured

with a registered insurer in order to cover the owner/contractor’s liability in respect of

construction risks caused by his negligence or the negligence of his servants, agents or

consultants which may result in bodily injury or loss of life to or damage to property of any

workman on the site or of any member of the public (Insurance Act, 2015).

Furthermore, Charles (20013) observed that insurance coverage is needed during

construction to cover the value of the building itself, should the building being constructed be

damaged since buildings under construction present several special problems from a property

insurance standpoint. The problem is dynamic as the work progresses and the value of the

property changes virtually on a day-to-day basis. Ensuring effective compliance with rules

and regulations is an important factor in creating a well-functioning society and trust in

government. It is a key element in safeguarding health and safety, protecting the

environment, securing stable state revenue and delivering other essential public goals. This is

important from a social perspective and as a foundation of economic growth (Organization

for Economic Co-operation and Development OECD, 2013). Enforcement of regulations is

very vital in ensuring the effectiveness of regulations (Nnedinma, Umeokafor, David &

Boniface, 2014). The challenge for governments is to develop and apply enforcement

strategies that achieve the best possible outcomes by achieving the highest possible levels of

compliance, while keeping the costs and burden as low as possible (OECD, 2013). Some of

the challenges in the area of compulsory insurance of buildings under construction revolve

around poor compliance structure, ineffective implementation strategy by the insurance

2
regulator and lack of awareness on the part of the Nigerian public (Nigerian Business News,

2011). However, in spite of these laudable provisions of the law, majority of the buildings

under construction in the country that need to be insured according to the Insurance Act 2015,

do not have insurance cover and this trend has to be reversed in the interest of all

stakeholders (Adeusi, n.d.).

1.2 Statement of the Problem

The incidence of buildings failure and collapses in Nigeria has reached an alarming level and

the stakeholders need to wake up and stop treating these continuous occurrences with levity

(Akinyemi, 2016). On several occasions, it led to unnecessary loss of lives and destruction of

peoples’ properties, thus becoming an issue of major concern since it poses threat to the

national development of our great nation. The Nigerian Institute of Building (NIOB) has said

that Lagos State accounts for 60 per cent of reported cases of building collapse in Nigeria.

Because, on such every occasion, affected individuals are rendered homeless while

businesses are lost. Building collapse, though a common phenomenon all over the world is

more rampant and devastating in developing countries. It is a major problem in Nigeria and

mostly occurred in Lagos, which has the largest population of residents in the country. In

fact, it has now become a familiar occurrence, even to laymen on the streets in Nigeria. It is

established that in every stage of the building construction process, from initial investment

appraisal through to construction and use, the building construction is subjected to risks for

the parties involved. In recent times, there has been a lot of building collapse and most of

them are not insured as confirmed by the commissioner for insurance in the recent collapse of

21-story building at Gerard Road, Ikoyi which necessitated the call for enforcement of

compulsory insurance by the federal government. It seems there is apathy for risk financing

strategy by most building contractors either by transferring or retaining the risk to ensure

3
safety and completion of building projects. Therefore the study seeks to investigate risk

financing strategy and project success among building contractors in Lagos state.

1.3. Aim and Objectives of the Study

The aim of the study is to evaluate the significant effect of risk financing strategy among

building contractors in Nigeria in Lagos State. The specific objectives are to:

i. Examine the effect of risk transfer strategy on project success among building

contractors in Lagos State, Nigeria.

ii. Examine the effect of risk retention strategy on project success among building

contractors in Lagos state, Nigeria.

1.4. Research Questions

In line with the research objectives, the followings are the research questions of the study:

i. What is the significant influence of risk transfer strategy on project success among

building contractors in Lagos state?

ii. How does risk retention strategy influence project success among building contractors

in Lagos State?

1.5. Research Hypotheses

In line with the research objectives, the following null hypotheses were formulated for the

study:

H01: Risk transfer strategy does not have significant effect on project success among

building contractors in Lagos State, Nigeria.

H02:   Risk retention strategy does not have significant effect on project success among

building contractors in Lagos State, Nigeria.

4
1.6 Significance of the Study

The risks in building construction site today in Nigeria calls for a great concern upon

insurance companies which protection against damages to buildings while they are under

construction or renovation. This paper work intends to assist the clients and contractors on

the necessary precaution to follow during design and construction stage of a building project

to minimize the cost of risk that does occur in building projects since it constitute huge

amount of capitals. The study will also help the government ensure strategies to put in place

to ensure drastic reduction in building collapse by enforcing compulsory building

construction insurance and quality assurance test by relevant regulatory bodies before any

contractor can go ahead with any construction. The study will also help building contractors

to have a keen understanding of the likely risk that building construction is exposed to and

how they can be mitigated either through risk retention or risk transfer mechanism. The study

will help insurance companies to design an holistic and appropriate comprehensive cover for

builders and building contractors so that building collapse can be minimized.

1.7 Scope and Delimitations of the Study

The scope of the study is limited to the examining risk financing and project success in

building construction in Lagos State, Nigeria. The specific variables of interest are risk

retention and risk transfer strategies. The study covers 3 major clustered areas where there are

heavy construction sites frequently which are Ikoyi, Victoria Island and Lekki Phase 1 in

Lagos State. The study is also limited to the influence of risk transfer strategy and risk

retention strategy on project success among building contractors in Lagos State, Nigeria.

1.8 Definition of Terms

Client – a part that carries out or assigns others to carry out construction, demolition or land

work

5
Contract – a mutually binding agreement that obligates the seller to provide the specified

product and obligates the buyer to pay for it.

Contractor – a performing organisation whose employees are most directly involved in

doing the work on the project.

Design-bid-build – a traditional procurement option where the client contracts separately

with a designer and a constructor.

Design-build – a procurement option where the contractor is responsible for construction and

the full design.

Effective risk management - doing the right things in a way to ensure that the project is risk

efficient and project objectives are achieved.

Partnering – a structured management approach to facilitate team working across

contractual boundaries.

Project – a unique process, consisting of a set of coordinated and controlled activities with

start and finish dates, undertaken to achieve an objective conforming to specific

requirements, including the constrains of time, cost and resources.

Project life cycle – a collection of generally sequential project phases whose name and

number are determined by the control needs of the organisation or organisations involved in

the project.

Risk – an implication of significant uncertainty, which may be upside and downside.

Risk management – a systematic process of identifying, analysing and responding to project

risks.

6
Risk identification – a process of determining which risks might affect the project and

documenting their characteristics (PMI 2000).

Risk assessment – a process of assessing the impact and likelihood of identified risks (PMI

2000).

Risk response – a process of selection and implementation of measures to modify risk (IEC

2001). Uncertainty – a lack of certainty, involving variability and

7
CHAPTER TWO

Literature Review

2.1 Preamble

This chapter presents relevant theoretical and empirical literature from similar earlier findings

in order to give necessary support and solid foundation to the study.

2.2 Conceptual Framework

2.2.1 Risk Management and Building Construction

The scope of building activities requires risk management as all the stages of building

construction has inherent risk (Drakes, 2016).The risk management in building construction

involves planning, arranging and controlling activities and resources in order to minimise the

impact of uncertain events. Risk in construction has been the object of attention because of

time and cost associated with construction projects (Akintoye & MacLeod, 2017). McKim

(2012), Healey (2012) and Perry and Hayes (2015) expressed risk as an exposure to

economic loss or gain arising from involvement in the construction process, but Mason

(2013) Moavenzadeh and Rossow (2016) regarded it as an exposure to loss only. According

to McKim (2012), it is necessary to understand the nature of risk before any knowledgeable

management of risk can occur.

Risk comes in many forms, and often the nature of risk depends on the situation. For

example, health risks cannot generally be managed in the same manner as the risks associated

with the transportation of toxic materials, and the risks associated with a space mission

cannot be managed the same as construction risks. Akintoye and Macleod (2017), Raftery

(2014), Williams and Heims (2019) and Toakley and Ling (2016) identified the current usage

or risk management techniques in the construction industry. These include risk premium, risk

adjusted discount rate, subjective probability, decision analysis, sensitivity analysis, Monte

Carlo simulation, stochastic dominance, Casper and intuition. However, in a study conducted

8
by Odeyinka (2017) it was found that one of the major methods of managing construction

risks in the Nigerian construction industry is through transfer to insurance companies. Until

now the effectiveness of this method in managing construction risks in Nigeria has not been

investigated.

2.2.2 Risk in Building Construction Projects

According to Hamza et al., (2015), Construction projects are very complex and can pose

various internal and external risks. Construction risk is defined as any exposure to possible

loss (Surety, 2014). A strict set of codes, laws, and regulations must be followed during the

construction process to best avoid these risks. Unfortunately, there is no way to completely

avoid risks as there are bound to be unknown factors that arise over the course of a project.

One of the best ways to manage risks is to know the various types and how you can manage

them. If you can identify and categorize risks before you start a project, you can optimize

your risk management and avoid any possible losses. Renuka (2014), in their study pointed

some type of risks in the construction projects which include technical risks, environmental

risks, financial risks, logistical risks, socio-political risks and management related risks.

i. Technical Risks: Technical risks include anything that restricts you from creating the

product that your client wants. This can include uncertainty of resources and availability of

materials, inadequate site investigation, or incomplete design. These risks can commonly

occur when there are changes in project scope and requirements, and if there are design errors

or omissions.

ii. Environmental Risks: Environmental risks include natural disasters, weather, and

seasonal implications (Rausand, 2015). These risks are commonly overlooked when people

are unfamiliar with local conditions. If you are going to be working on a project in a new city,

9
you need to become familiar with that region’s weather patterns. If you prepare for possible

weather risks, you are much more likely to avoid potential delays and losses.

iii. Financial Risks: Inflation, local taxes, and availability and fluctuation in foreign

exchange are a few of the possible financial risks you might incur during a construction

project. If you are working on a project internationally, it is important that you understand

how the foreign currency will be exchanged. Different countries have drastically different

taxes as well, so you need to take this into account before starting a project. Your finances are

going to look a lot different if you are working in a tax-free city versus a high-tax city.

iv. Logistical Risks: According to Rausand (2014), there are various logistical risks that need

to be addressed before starting a project. These risks include the availability of transportation

facilities and availability of equipment such as spare parts, fuel, and labour. Without

addressing these logistical issues, you risk huge project delays and losses.

v. Socio- Political Risks: Customs and import restrictions and difficulties disposing of

equipment are a few of the socio-political risks you may face during a construction project

(Rasand , 2011). Depending on where your project is, there are going to be different

regulations and codes that you must abide by. If you assume that each project is going to have

the same codes and regulations, you will be in for a rude awakening.

vi. Management Related Risks: The most common management related risk is uncertain

productivity of resources. Before you begin a project you need to be sure that you have

sufficient skilled staff and that you have adequately defined their roles and responsibilities.

Failing to do this can lead to disastrous losses. According to (Hair, 2013) As per Abrahamson

principles owner of the project is known as principal party. In this context, some critical risks

bore by principal party of the construction contract can be elaborated as below:

10
i. Land Acquisition Risk: This is the prime risk for the principal of the project. The owner

of the project needs to have proper and legal; acquisition of the land for his construction

project, in the absence of proper acquisition of land, the entire project can be hindered due to

different legal obligations.

ii. Insufficient resources: Insufficiency of some crucial resources like land, finance, human

power can also be proved critical risk for a construction project. As construction project are

commenced for a longer period of time, sufficient amount of resources for contingent

situation is quite necessary for the owner.

iii. Delay in the project completion: The completion of project on time is one of the major

factors of the success of a construction project. Delay in the overall completion of the project

due to natural or manmade reasons, can cost quite heavily for owner of the project as he has

to invest a significant amount of money and time in such types of projects.

iv. Increased cost of the project: As generally construction projects are carried out for

longer period of time, fluctuations in the overall cost and prices of raw material and labor

over such a long period of time are quite natural phenomena. These fluctuations may lead to

increase the projected cost of the entire project. Although principals generally undertake

contingency reserves for such type of fluctuations, yet still these increments in cost of the

project can be probed quite critical risk for the project owner.

v. Deficiencies in infrastructure or services: There are a number of different other

infrastructural services that can affect the successful completion of the project. for insurance,

for a residential or commercial construction project, there is need of better electricity and

water facilities and better access of road. Deficiencies in infrastructure or services can lead to

make the project unsuccessful.

11
vi. Design and construction defects: Defects in designing and constructing of the project

can lead to efficiency of the internal operations and quality of the output of the project. In this

direction, the project owner needs to have proper monitoring and effective evaluation of

outcome of the project.

vii. Political risk: Different types of political risks such as rules and regulation of

government regarding construction activities, frequent changes in the government and its

priorities, and incentives can hamper the success of construction projects in the most aversive

manner

viii. Market risk: In addition to other risks, risk related with market characteristics as well as

trends can also be considered some of the critical risks availed by the owner of the project.

Different types of market risks such as advertising of the project, Switching of potential

customers of the project towards other alternative projects and competitive rivalry within the

construction industry are some of the prominent market risk which decreases the profitability

of the construction project for its owner. According to Akinbola, (2015) a contractor is

required to face some critical risks throughout the entire stage of a construction project i.e

negotiation over contract terms and conditions deigning and construction of the building and

proper and careful maintenance and follow up the contract in the most effective manner.

Some of these risks can be listed as below:

i. Condition of Site: The existing working conditions of the construction site leads to present

risks in front of the contractors to finish the entire project on time. Different natural or

manmade problems can lead to delay the project delivery, which is quite problematic aspect

for a contractor.

ii. Social conditions: Lack of acceptance of the construction project by the society is the

factor that can lead to put question mark over successful accomplishment of the project and

12
viability of project deliverable. There can be some unexpected incidents like labour strike,

religious and social belief of local people, and so on which are to be handled by the

contractor only.

iii. Defects in the construction and engineering: There can be some of critical defect in the

project which can only be identified in the finished project. The detection of such types of

defect becomes quite difficult for the contract during the construction process. These defects

can be proved quite critical

2.2.3 Concept of Builders Risk Insurance Policy

This is a policy designed to provide coverage for buildings while under construction in

Nigeria Construction Industry. It covers the contractor’s interest in materials in transit

intended for the job and the value of the property being constructed until it is completed and

accepted by the owner. The policy may be written to cover the whole structure for new

construction or the cost of remodelling or renovation projects. It can be used to cover specific

projects such as a new room addition, a deck or a remodelled kitchen (Odeyinka, 2015).

Builders risk insurance also known as “course of construction”, “construction all risk” and “

contractors all risk insurance”, is a specialized form of insurance designed to insure buildings

or project against repair or replacement cost while they are under construction and in some

cases, for a specific period afterwards. This insurance will usually also cover build materials,

fixtures and appliances all of which are intended to become an integral part of the structure

under construction Boswall and Clark (2015).

2.2.4 Compulsory Builders Risk Insurance Policy in Nigeria, benefits/Claims

The National Insurance Commission “NAICOM” said that in the pursuance of the provision

of the Nigeria Insurance Act (2003), and in a renewed attempt to negotiate insurance use,

13
practice and regulations. Fixed the end of March 2011 as the cut-off date from when all

compulsory insurance policies under various Nigeria statutes will be fully enforced and

penalties applied to this legal alert. Builders’ liability insurance as required by section 64 of

the insurance act. All builders of real property that have more than two floors must

compulsorily register and insure such a building against all construction risks resulting from

the builders negligence or the builders servants, agents or consultants which negligence may

result in bodily injury or loss of life or damage to the property. Soladoye (2012) a consultant

of NAICOM, also said that all the owners and contractors of building under construction that

are more than two floors were mandated to have the policy, according to him he said if

covered construction risk resulting from death or injury to site workers or members of the

public and property damage. In case of death or permanent disability, claims could be up to

two million naira, property damage claims could be up to five million to fifty million naira,

while reimbursement for defense cost to the contractor if the case goes to court could reach

one million naira, under the policy compensation is to be paid to any user of such buildings

who dies or injured as a result of fire, flood, storm, and earth quake of collapse buildings in

the occurrence of death or permanent disability, the claimant could be settled to the tune of

two million naira while damage to public utility or third party property could be between ten

million naira and thirty five million naira when coverage ceases.

2.2.5 Coverage of Builders Risk Insurance

The builders risk policy typically lists the owner/developer and general contractor by name as

the insured parties. Because they are identified by their own names, they are known as

“Named insured” in addition, the builders risk policy often covers most others and person

involved with the projects. This is either because the policy identifies them in a generic

category of insured parties (e.g. all “sub-contractors” or persons for whom the named insured

has contracted to obtain builders risk insurance). Clark and Boswall (2005) The coverage is

14
further extended to the building supplies and materials and the property including the

building or structure on the site. The materials are covered while they are in transits or at

temporary location. If the project is a sizable venture you could pursue additional coverage in

case the earth should move as a result of exaction. Other all-risk policies cover all risks

unless they fall outside of the meaning of “occurrence” in the insuring agreements or are

otherwise removed from coverage by the exclusions. Examples of typical risks covered by a

builder’s risks policy include: - Fire - Lighting - Explosion - Impact by air craft or vehicles -

Riot, Vandalism - Windstorm, hail and rain - Burglary and theft - Collapse of the structure -

subsidence

2.2.6 Excluded Builders Risk Policy

According to Clark and Boswall (2015), the major risk usually excluded under “all risk”

policies are: - Faulty design, material or workmanship - Latent defect - Inherent vice -

Breakdown or derangement, and Wear and tear. A Builders risk policy often covers a number

of parties. As such, the standard policy can usually be obtained by any of the owner,

contractor, architect, engineer or project manager. Generally the industry expectation is that

the general contractor or owner will obtain the policy. Whether this expectation is followed

or not, there are a number of point that need to be considered by all parties involved in the

project in order to properly determine exactly who should obtain the policy for the project in

question Clark and Boswall (2015). The owner may be required to provide or maintain the

policy if the contractor fails to do so. However, if such is the case, the owner is then allowed

to demand the cost of obtaining and maintaining the policy from the contractor or

alternatively can deduct such amount from its payment to the contractor (per condition GC

11.1.4). The party that obtains the insurance is in the best position to ensure that the policy

provides for the precise coverage that it wants. Thus includes what risks to include or

exclude. According to Nicon (2018) construction insurance is usually a percentage of the

15
total construction budget. The size of the percentage is wholly dependent to the scope of the

project at hand. You may find that a small house may be around 1% of the total cover

whereas a high rise building may be over 5%. The exact percentage is then determined by the

level of coverage required and the insurer you chose to go with. The amount of coverage

should adequately cover the full value of the project in its finished state. Indeed most policy

wording often require coverage of the “full value” may differ depending on the view of each

of the insured parties. Unlike other property policies, the builders risk policies is intended to

terminate when the work has been completed and the property is ready for use or occupancy.

Even though some minor finishing work might remain. Because a precise completion date is

often difficult to predict insurers will generally extend coverage until such a time can be

determined. Typical provisions in the policy that terminate coverage are when any of the

following firs occur. -The policy expires or is cancelled -The project is accepted by its owner

or purchaser -The named insured insurable interest is the covered property ends. Some

policies also provide that coverage ends ninety (90) days after construction is completed sixty

(60) days after the project has been occupied in whole or in part or when the property is put

to its intended use Clark (2015). Collapse of building either total or partial collapse of some

of its components leads to the failure of building to perform its intended function of

protection, safety or stability (Olagunyi, 2017) According to Ikpo, (2018), the degree of

building failure can be related to the degree of deviation of the building from its “as built”

state which in most cases represents the acceptable standard within the neighbourhood,

locality, state or country.

16
Some of the recent collapsed buildings and their insurance status

S/N Structure Date Location Cause of collapse Fatality Insurance


policy
status
1 Residential under June 2010 Oniru Estate, Substandard 1 Not
construction Victoria Island materials, insured
haphazard works.

2 4-storey building September, 28 Tinubu Structural 3 Not


2010 street VI Lagos defect/overloading insured

3 Five-storey June 2011 11 Aderibigbe No geotechnical None -


street investigation
Maryland,Lagos
4 3-storey building July 2011 Oloto street off Non-adherence to 10 Not
cement road, building standards insured
Ebute & regulations
Metta,Lagos
5 3-storey building August Orosanye Wrong supervision None Not
2011 street Lagos insured
6 Building in use November Jakande estate Structural failure 3 Not
20, 2012 oke afa, Isolo and occupants insured
Lagos ignored the
government’s
safety warning
7 A twin four storey duplex November Victoria unknown 4 -
3, 2013 island,Lagos
8 Synagogue Church of September Ikotun-Egbe Structural failure 116 Not
All Nations (SCOAN) 12,2014 area of Lagos insured
state

9 Synagogue Warehouse September Ikotun-Egbe Demolition 4 Not


Church, Lagos. 12,2014 area of Lagos process insured
state

10 Four storey building March 13, 6 Mogaji Unknown 1 -


2015 Street Idumota
Lagos island

11 3 storey building July 15, Ebute Metta Structural defect None Not
2015 Lagos insured

12 3 storey building October Swamp street Structural defect None Not


21,2015 Odunfa Lagos insured
island.

13 A five-story building March Lekki Lagos Addition to the 34 Not


under construction 9,2016 approved number insured
of floors.

14 Two storey building March 19, Mile 12,Lagos Structural defect 1 -


2016

17
15 Residential building April 2016 Horizon 1, Structural defect 18 -
Lekki Garden,
Ikate.

16 3 storey building February Lagos island Not reported 2 -


3, 2019

17 Three storey building March Ita Faaji area The change of use 20 -
13,2019 of Lagos state, of the building
Nigeria from the intended
purpose
Source: Lagos State Building Control Agency 2020

2.3 Theoretical Framework

The theoretical framework outlines the main areas considered in developing the research

hypothesis. The major theory that this research work is thrusting on is Catastrophe Risk

(CAT Risk) model.

2.3.1 Catastrophe Risk (CAT Risk) Model

This model has proved valuable to international insurance markets. They develop a view of

risk beyond the historical occurrence of catastrophes, for calculation of potential future

impacts. Their strength is that they consider an extensive range of possible event scenarios

well beyond the historical record. To date, CAT risk model has been primarily developed to

output risk in financial terms. However, the potential to use it to support disaster risk

management more broadly have been recognized in schemes such as Risk Information

System and Africa Risk View platform. The relevance of this model to this study is the fact

that most building construction in the area of study is always high-rise which makes any

collapse to be catastrophic any time it happens.

2.4 Empirical Framework

Oloyede, (2015) attributed causes of building collapse as due to man’s negligence in some

vital areas in construction such as soil investigation, incorporating design for extra loads,

18
stress from winds, earthquakes, uneven terrain, use of substandard building materials, poor

monitoring and overall poor workmanship.

Madu, (2015), identified causes of building failure as due to natural occurrences such as

earthquakes, tornadoes, flood, etc. Other causes according to him include factors such as

omission, carelessness, leading to use of deficient structural drawings, absence of proper

supervision of projects, alteration of approved drawings, use of substandard materials,

corruption in the Nigerian system, building without approved drawings and translocation of

building plans to different sites.

Adebayo, (2016), opined that efficiency in skill and experience is important in creating

valuable workmanship in building construction. Ayinuola, (2014), pointed accusing finger to

all parties in the building industry, clients, architects, engineers, town planners in the local

authorities and contractors stating that they have contributed to building failures in various

dimensions.

Tyagler, (2017) traced the causes of building failures to defects or deficiencies at designand

construction stages. Ukpata, (2016), opined that the spate of building collapse in the country

can always be traced to unsafe actions of parties involved in building process starting from

clients to building consultants, contractors and users.

Adebayo, (2016), opined that building collapse incidences can be controlled or minimized if

the client is ready to pay for high quality materials and for expert professional services.

19
CHAPTER THREE

Research Methodology

3.1 Preamble

This chapter is essentially designed to examine the various methods and procedure adopted at

various stages of this project work. This chapter dealt with Research Design, Population of

the study, Sample and sampling technique, Instrument and Procedure for data collection.

3.2 Research Design

This study employed a descriptive survey research design. The choice of descriptive survey

research design is due to the fact surveys are useful in describing the characteristics of a large

population (Osula, 2014). Surveys provide a high level of general capability in representing a

large population, low costs, and convenient data gathering, good statistical significance, little

or no observer subjectivity and precise results. The study adopts descriptive survey research

design because the complexity of identifying the risk financing strategy of most building

construction is better examined through the use of proper and well planned research

instrument capable of eliciting necessary information that is needed in the research.

3.3 Population of the Study

The population of the


study comprises all forty-
one (41) licensed non-life
insurance
20
companies operating in
Nigeria as at 1st of January
2019 (National Insurance
Commission,
2019
The population of the
study comprises all forty-
one (41) licensed non-life
insurance
companies operating in
Nigeria as at 1st of January
2019 (National Insurance
Commission,
2019
The population of the
study comprises all forty-
21
one (41) licensed non-life
insurance
companies operating in
Nigeria as at 1st of January
2019 (National Insurance
Commission,
2019
The population of the study comprises all registered builders in Lagos State which are 2,422

builders (CORBON, 2020) validated by the study of (Babatunde, 2020). Lagos state was a

choice of the selected building contractors because it is the state with highest number of

registered builders in Nigeria and is the commercial nerve of Nigeria. It is assumed that

responses obtained from the sample respondents would be representative of the opinion of all

the registered building construction companies in Nigeria.

3.4 Sampling, Procedure and Sampling Size

The study adopted a convenience sampling method of selection and to be able to draw the

right sample for the purpose of this study. The choice of convenience sampling is because it

helps to meet with registered building contractors in the selected areas which show the

readiness and availability to respond to the questionnaire in the clustered location. 942 of the

registered builders are fully functional and 281 building contractors are operative on island

area of Lagos state where the study is conducted, the areas include Ikoyi, Victoria Island and

22
Lekki phase 1. The Taro Yamani formula was used to determine the sample size. The

formula is given below as:

N
n=
1+ N ( e ) 2

Where n = sample size, N = population size e = error limit

N = 281 e = 0.05

Therefore n = 165 approximately. 5 group head of property insurance department of the big 5

insurance companies were also selected for the study (Axa Mansard Insurance,

NEM insurance plc, Custodians & Alliance insurance, Mutual Benefits plc and Leadway

Assurance).Therefore the total sample used for the study is 170 respondents.

3.5 Data Collection Instrument and Validation

This study employed a structured questionnaire as its instrument for data collection. This

instrument is relevant in collecting feedbacks from respondents based on their perceptions

and opinions. Furthermore, it is suitable for collecting data from respondents within a

relatively short period.

In line with extant literature, the response options provided in this study's questionnaire

follow the 5-point Likert-type scale, consistent with (Binuyo, 2019). This scale, being an

ordinal interval scale, is numbered from 5 to 1. The response options in the questionnaire

follow strongly agree (SA) = 5, Agree (A) = 4, Undecided (U) = 3, Disagree (D) = 2, strongly

disagree (SD) = 1. The questionnaire will have two sections: Section A will cover the

23
demographic information with five (5) items. Section B covered questions which were

tailored to flow from the research questions of this study.

3.6 Method of Data Analysis

Data collected will be analysed using Statistical package for social science students (SPSS)

which expresses the data in tables, frequencies and percentages while regression analysis will

be used to test the hypotheses formulated in order to evaluate the significant effect of risk

financing strategy among building contractors in Lagos State, Nigeria. The regression

equation will be

Y = a + bX

Where:

a = intercept

b = slope or gradient

X = Independent

Y = dependent variable

CHAPTER FOUR

Data Presentation and Analysis

24
4.1 Introduction

This chapter explains the presentation and analysis of data from the questionnaires that were

retrieved from a total of Two hundred questionnaires administered through online survey.

The Statistical Package for Social Sciences (SPSS) was used to analyse the information

provided.

The results are presented under the following headings

(1) Presentation of Data

(2) Analysis of research Objectives

(3) Tests of Research hypotheses

4.2 Presentation of Data

The Analysis of the bio- data of the respondents, the analysis was done with respect to

gender, age, Work experience, educational qualification and position at work. The results are

presented in tables 4.1, 4.2, 4.3 and 4.4.

Table 4.1

VARABLES FREQUENCY PERCENTAGE (%)

25
GENDER Male 120 70.6
Female 50 29.4
Total 170 100
AGE (YEARS) 18 but less than 30 86 50.6
30 but less than 40 27 15.9
40 but less than 50 40 23.5
50 but less than 60 10 5.9
60 and above 7 4.1
Total 170 100
EDUCATIONAL Bachelor’s degree/HND 13 7.6
QUALIFICATION Master’s degree 53 31.2
Doctorate degree 81 47.6
Professional certificate 12 7.1
OTHERS(ND,SSCE,etc) 11 6.5
Total 170 100
WORK Less than 5 years 23 13.5
EXPERIENCE 5 yrs but less than 10 yrs 39 22.9
(YEARS) 10 yrs but less than 15 yrs 62 36.5
15 yrs and above 46 27.1
Total 170 100
BUSINESS SIZE Small 45 26.5
CLASSIFICATION Medium 86 50.6
Large 39 22.9
Total 170 100
POSITION IN Owner 78 45.9
BUSINESS Partner 40 23.5
Supervisor 37 21.8
Others 15 8.8
Total 170 100
RISK Yes 96 56.5
MANAGEMENT No 74 43.5
GUIDELINE Total 170 100
INSURANCE Yes 63 37.1
POLICY No 107 62.9
Total 170 100

Source: Field survey 2021

Table 4.1 above shows that 70.6% of the respondents were male while 29.4% of the

respondents were female.

It can also be seen that 50.6 % of the respondents were between the ages of 18 but less than

30years, 15.9% were between the ages of 30 but less than 40 years old, 23.5% respondents

26
were between the ages of 40 but less than 50 years, while 5.9% of the respondents were

between the ages of 50 but less than 60 years, and 4.1% of the respondents were between the

ages of 60 years and above.

Table 4.1 above shows that 7.6% represent Bachelor’s degree/HND, 31.2% of the

respondents were master’s degree, 47.6% of the respondents were holders of doctorate

degree while 7.1% of the respondents were professional certificate holders and 6.5%

represent other qualifications (SSCE, ND, GCE)

It can also be seen that 13.5% of the respondents are at less than 5 years work experience,

22.9% are at 5 years but less than 10 years work experience, 36.5% of the respondents are at

10 years but less than 15 years work experience and 27.1% of the respondents are at fifteen

years and above work experience.

Table 4.1 also shows that, 26.5% of the respondents are small business size, 50.6% of the

respondents are medium business size and 22.9% of the respondents are large business

size.The table also shows that, 45.9% of the respondents are owners, 23.5% of the

respondents are partners, while 21.8% of the respondents are supervisor and 8.8% of the

respondents are others.

It can also be seen that 56.5% of the respondents have risk management guideline for

managing risk while, 43.5% of the respondents does not have risk management guideline for

managing risk. Table 4.1 also shows that, 37.1% of the respondents have insurance policy

and 62.9% does not have insurance policy.

4.2 Data Analysis According to Research Questions

27
Section B of the questionnaire will be analyzed using frequency tables and simple
percentages and the test of hypotheses will be done using chi square.

Table 4.2 Building construction risk management process; risk transfer strategy

S/N Statement SA (%) A(%) U(%) D(%) SD(%) Total

5 4 3 2 1 (%)
1 We have insurance policy for 47 37 51 20 15 170
all building constructions that
(27.6) (21.8) (30) (11.8) (8.8) (100)
we do
2. Construction insurance policy 33 61 14 42 20 170
gives confidence in the process
(19.4) (35.9) (8.2) (24.7) (11.8) (100)
of building construction
3 Most building contractors do 58 27 11 43 31 170
not have construction policy
(34.1) (15.9) (6.5) (25.3) (18.2) (100)
because it is too expensive
4 Builders risk policy is relevant 18 26 39 54 33 170
to building construction
(10.6) (15.3) (22.9) (31.8) (19.4) (100)
projects

Source: Field survey 2021

In the table 4.2 above which is to explain the building construction risk management process;

the risk transfer strategy shows that 47 of the respondents representing 27.6 percent strongly

agreed that they have insurance policy for all building constructions that they do, 37

respondents representing 21.8 percent agreed that they have insurance policy for all building

constructions that they do even though 51 respondents representing 30 percent are undecided

about them having insurance policy for all building constructions that they do , while 20

respondents representing 11.8 percent disagree that they have insurance policy for all

building constructions that they do and 15 respondents representing 8.8 percent strongly

disagree that they have insurance policy for all building constructions that they do.

28
It also shows that 33 respondents representing 19.4 percent strongly agree that Construction

insurance policy gives confidence in the process of building construction, 61 respondents

representing 35.9 percent agree that Construction insurance policy gives confidence in the

process of building construction, 14 respondents representing 8.2 percent are undecided about

Construction insurance policy giving confidence in the process of building construction,

while 42 respondents representing 24.7 percent disagree that Construction insurance policy

gives confidence in the process of building construction, and 20 respondents representing

11.8 percent strongly disagree that Construction insurance policy gives confidence in the

process of building construction.

The table also shows that 58 respondents representing 34.1 percent strongly agree that Most

building contractors do not have construction policy because it is too expensive, 27

respondents representing 15.9 percent agree that Most building contractors do not have

construction policy because it is too expensive, 11 respondents representing 6.5 percent are

undecided about Most building contractors not having construction policy because it is too

expensive, while 43 respondents representing 25.3 percent disagree that Most building

contractors do not have construction policy because it is too expensive, and 31 respondents

representing 18.2 percent strongly disagree that Most building contractors do not have

construction policy because it is too expensive.

It can also be seen from the table that 18 respondents representing 10.6 percent strongly agree

that Builders risk policy is relevant to building construction projects, 26 respondents

representing 15.3 percent agree that Builders risk policy is relevant to building construction

projects, 39 respondents representing 22.9 percent are undecided about Builders risk policy

being relevant to building construction projects, even though 54 respondents representing

31.8 percent disagree that Builders risk policy is relevant to building construction projects,

29
and 33 respondents representing 19. 4 percent strongly disagree that Builders risk policy is

relevant to building construction projects.

Table 4.3 risk retention strategy

5 We consider experience in 25 36 18 33 58 170


choosing the project team
management members (14.7) (21.2) (10.6) (19.4) (34.1) (100)

6 We revise design documents and 43 41 27 36 23 170


drawings to ensure compliance to
(25.3) (24.1) (15.9) (21.2) (13.5) (100)
building standards

7 Communication and coordination 14 43 36 46 31 170


between parties (clients,
(8.2) (25.3) (21.2) (27.1) (18.2) (100)
consultants and contractors) is
very sound
8 Decision making process is 37 28 49 32 24 170
scrutinized to avoid errors during
(21.8) (16.5) (28.8) (18.8) (14.1) (100)
construction

9 Test and inspection of materials 36 22 41 19 52 170


and labour are thoroughly done
in every phase of the building
(21.2) (12.9) (24.1) (11.2) (30.6) (100)
construction

Source: Field survey 2021

From table 4.3 above which to find out the risk retention strategy shows 25 respondents

representing 14. 7 percent strongly agreed that they consider experience in choosing the

project team management members, 36 respondents representing 21.2 percent agree with the

fact that they consider experience in choosing the project team management members, 18

respondents representing 10.6 percent are undecided about the fact that they consider

30
experience in choosing the project team management members, even though 33 respondents

representing 19.4 percent disagree about the fact that they consider experience in choosing

the project team management members, and 58 respondents representing 34.1 percent

strongly disagree with the fact that they consider experience in choosing the project team

management members.

The table also shows that 43 respondents representing 25.3 percent strongly agree that they

revise design documents and drawings to ensure compliance to building standards, 41

respondents representing 24.1 percent agree that they revise design documents and drawings

to ensure compliance to building standards, 27 respondents representing 15.9 percent are

undecided about the fact that they revise design documents and drawings to ensure

compliance to building standards, 36 respondents representing 21.2 percent disagree that they

revise design documents and drawings to ensure compliance to building standards, and 23

respondents representing 13.5 percent strongly disagree that they revise design documents

and drawings to ensure compliance to building standards.

It can be seen in the table that 14 respondents representing 8.2 percent strongly agree with the

fact that communication and coordination between parties (clients, consultants and

contractors) is very sound, 43 respondents representing 25.3 percent agree with the fact that

communication and coordination between parties (clients, consultants and contractors) is very

sound, 36 respondents representing 21.2 are undecided with the fact that communication and

coordination between parties (clients, consultants and contractors) is very sound, even though

46 respondents representing 27.1 percent disagree with the fact that communication and

coordination between parties (clients, consultants and contractors) is very sound, and 31

respondents representing 18.2 percent strongly disagree with the fact that communication and

coordination between parties (clients, consultants and contractors) is very sound.

31
From the table, it can also be seen that 27 and 28 respondents representing 21.8 percent and

16.5 percent strongly agree and agree respectively about the fact that decision making process

is scrutinized to avoid errors during construction, 49 and 32 respondents representing 28.8

percent and 18.8 percent are undecided and disagree respectively about the fact that decision

making process is scrutinized to avoid errors during construction and 24 respondents

representing 14.1 percent strongly disagree about the fact that decision making process is

scrutinized to avoid errors during construction.

The table also shows that 36 and 22 respondents representing 21.2 percent and 12.9 percent

strongly agree and agree respectively that test and inspection of materials and labour are

thoroughly done in every phase of the building construction, while 41 and 19 respondents

representing 24.1 percent and 11.2 percent are undecided and disagree respectively that test

and inspection of materials and labour are thoroughly done in every phase of the building

construction, and 52 respondents representing 30.6 percent strongly disagree that test and

inspection of materials and labour are thoroughly done in every phase of the building

construction.

Table 4.4 Awareness of building construction policy by building contractors

32
10 Punitive Measures imposed on 47 37 51 20 15 170
Contractors for non-
(27.6) (21.8) (30) (11.8) (8.8) (100)
compliance with Insurance of
Building under construction is
poor
11 Most building contractors are 32 15 46 28 49 170
not aware of the construction
(18.8) (8.8) (27.1) (16.5) (28.8) (100)
policy

12 Construction policy is not 41 38 24 16 51 170


compulsory for all types of
(24.1) (22.4) (14.1) (9.4) (30) (100)
construction

13 Most building contractors have 28 48 47 36 11 170


apathy for construction policy
despite the awareness (16.5) (28.2) (27.6) (21.2) (6.5) (100)

14 Most builders have alternative 34 53 26 18 39 170


for construction insurance
(20) (31.2) (15.3) (10.6) (22.9) (100)

Source: Field survey 2021

From table 4.4 above is to find out awareness of building construction policy by building

contractors and it shows 47 respondents representing 27.6 percent strongly agreed to the fact

that punitive Measures imposed on Contractors for non-compliance with Insurance of

Building under construction is poor, 37 respondents representing 21.8 percent agree to the

fact that punitive Measures imposed on Contractors for non-compliance with Insurance of

Building under construction is poor, 51 respondents representing 30 percent are undecided to

the fact that punitive Measures imposed on Contractors for non-compliance with Insurance of

Building under construction is poor, even though 20 respondents representing 11.8 percent

33
disagree to the fact that punitive Measures imposed on Contractors for non-compliance with

Insurance of Building under construction is poor, and 15 respondents representing 8.8 percent

strongly disagree to the fact that punitive Measures imposed on Contractors for non-

compliance with Insurance of Building under construction is poor.

The table also shows 32 respondents representing 18.8 percent strongly agree that most

building contractors are not aware of the construction policy, 15 respondents representing 8.8

percent agree that most building contractors are not aware of the construction policy, 46

respondents representing 27.1 percent are undecided as to if most building contractors are not

aware of the construction policy, while 28 respondents representing 16.5 percent disagree that

most building contractors are not aware of the construction policy, and 49 respondents

representing 28.8 percent strongly disagree that most building contractors are not aware of

the construction policy.

It can also be seen from the table that 41 respondents representing 24.1 percent strongly agree

that construction policy is not compulsory for all types of construction, 38 respondents

representing 22.4 percent agree that construction policy is not compulsory for all types of

construction, 24 respondents representing 14.1 percent are undecided about the fact that

construction policy is not compulsory for all types of construction, while 16 respondents

representing 9.4 percent disagree that construction policy is not compulsory for all types of

construction, and 51 respondents representing 30 percent strongly disagree that construction

policy is not compulsory for all types of construction.

The table also shows that 28 and 48 respondents representing 16.5 percent and 28.2 percent

strongly agree and agree respectively with the fact that most building contractors have apathy

for construction policy despite the awareness, while 47 and 36 respondents representing 27.6

percent and 21.2 percent are undecided and disagree respectively with the fact that most

34
building contractors have apathy for construction policy despite the awareness, and 11

respondents representing 6.5 percent strongly disagree with the fact that most building

contractors have apathy for construction policy despite the awareness.

It can also be seen from the table that 34 and 53 respondents representing 20 percent and 31.2

percent strongly agree and agree respectively that most builders have alternative for

construction insurance, even though 26 and 18 respondents representing 15.3 percent and

10.6 percent are undecided and disagree respectively that most builders have alternative for

construction insurance, and 39 respondents representing 22.9 percent strongly disagree that

most builders have alternative for construction insurance.

35
Table 4.5 project success of building construction

Building project success factors Measuring scales

Material related factors SA(%) A(%) U(%) D(%) SD(%) TOTAL


5 4 3 2 1 (%)

Quality of materials used influence building 11 31 58 43 27 170


project success (6.5) (18.2) (34.1) (25.3) (15.9) (100)
Change in material type and specifications 39 26 18 33 54 170
affects building project success (22.9) (15.3) (10.6) (19.4) (31.8) (100)
Compliance of materials to specifications 20 37 15 47 51 170
affect building project success (11.8) (21.8) (8.8) (27.6) (30) (100)
Labour and equipment related factors
Labour performance and productivity affect 52 22 41 19 36 170
building project success (30.6) (12.9) (24.1) (11.2) (21.2) (100)
Availability and efficiency of equipment 49 46 15 28 32 170
affect building project success (28.8) (27.1) (8.8) (16.5) (18.8) (100)
Finance related factors
Cost estimation accuracy helps in achieving 53 13 11 81 12 170
project success (31.2) (7.6) (6.5) (47.6) (7.1) (100)
Source of finance for the building project 54 33 39 18 26 170
affect project success (31.8) (19.4) (22.9) (10.6) (15.3) (100)
External related factors
Changes in building construction regulations 28 11 47 36 48 170
affect project success (16.5) (6.5) (27.6) (21.2) (28.2) (100)
Government permits are difficult to get 18 36 25 33 58 170

(10.6) (21.2) (14.7) (19.4 (34.1) (100)


)
We experience civil disturbances at the 51 15 47 20 37 170
construction sites (30) (8.8) (27.6) (11.8) (21.8) (100)

Source: Field survey 2021

Table 4.5 above is to find out the project success of building construction. In material related

factors, it can be seen that 11 respondents representing 6.5 percent strongly agree that quality

36
of materials used influence building project success, 31 respondents representing 18.2 percent

agree that quality of materials used influence building project success, 58 respondents

representing 34.1 percent are undecided about the fact that quality of materials used influence

building project success while 43 respondents representing 25.3 percent disagree that quality

of materials used influence building project success and 27 respondents representing 15.9

percent strongly disagree that quality of materials used influence building project success

It can also be seen that 39 and 26 respondents representing 22.9 percent and 15.3 percent

strongly agree and agree respectively that change in material type and specifications affects

building project success, even though 18 and 33 respondents representing 10.6 percent and

19.4 percent are undecided and disagree respectively that change in material type and

specifications affects building project success and 54 respondents representing 31.8 percent

strongly disagree that change in material type and specifications affects building project

success

The table also shows that 20 and 37 respondents representing 11.8 percent and 21.8 percent

strongly agree and agree respectively to the fact that compliance of materials to specifications

affect building project success, 15 and 47 respondents representing 8.8 percent and 27.6

percent are undecided and disagree respectively to the fact that compliance of materials to

specifications affect building project success and 51 respondents representing 30 percent

strongly disagree to the fact that compliance of materials to specifications affect building

project success

It can be seen from the table that in labour and equipment related factors 52 and 22

respondents representing 30.6 percent and 12.9 percent strongly agree and agree respectively

that labour performance and productivity affect building project success, 41 and 19

respondents representing 24.1 percent and 11.2 percent are undecided and disagree

37
respectively that labour performance and productivity affect building project success, while

36 respondents representing 21.2 percent strongly disagree that labour performance and

productivity affect building project success

It also shows that 49 and 46 respondents representing 28.8 percent and 27.1 percent strongly

agree and agree that availability and efficiency of equipment affect building project success,

15 and 28 respondents representing 8.8 percent and 16.5 percent are undecided and disagree

that availability and efficiency of equipment affect building project success, and 32

respondents representing 18.8 percent strongly disagree that availability and efficiency of

equipment affect building project success

The table also shows the finance related factors that 53 and 13 respondents representing 31.2

percent and 7.6 percent strongly agree and agree respectively that cost estimation accuracy

helps in achieving project success, while 11 and 81 respondents representing 6.5 percent and

47.6 percent are undecided and disagree respectively that cost estimation accuracy helps in

achieving project success, and 12 respondents representing 7.1 percent that cost estimation

accuracy helps in achieving project success

It also shows that 54 and 33 respondents representing 31.8 percent and 19.4 percent strongly

agree and agree respectively that source of finance for the building project affect project

success, 39 and 18 respondents representing 22.9 percent and 10.6 percent are undecided and

disagree that source of finance for the building project affect project success and 26

respondents representing 15.3 percent strongly disagree that source of finance for the

building project affect project success.

The table also shows external related factors that 28 and 11 respondents representing 16.5

percent and 6.5 percent strongly agree and agree respectively that changes in building

38
construction regulations affect project success, 47 and 36 respondents representing 27.6

percent and 21.2 percent are undecided and disagree that changes in building construction

regulations affect project success and 48 respondents representing 28.2 percent strongly

disagree that changes in building construction regulations affect project success.

It also shows 18 and 36 respondents representing 10.6 percent and 21.2 percent strongly

agree and agree respectively that government permits are difficult to get, 25 and 33

respondents representing 14.7 percent and 19.4 percent are undecided and disagree that

government permits are difficult to get, and 58 respondents representing 34.1 percent strongly

disagree that government permits are difficult to get.

It also shows 51 and 15 respondents representing 30 percent and 8.8 percent strongly agree

and agree respectively that they experience civil disturbances at the construction sites, while

47 and 20 respondents representing 27.6 percent and 11.8 percent are undecided and disagree

that they experience civil disturbances at the construction sites and 37 respondents

representing 21.8 percent strongly disagree that they experience civil disturbances at the

construction sites .

4.3 TEST OF HYPOTHESIS

Hypothesis I
H01: Risk transfer strategy does not have significant effect on project success among building

contractors in Lagos State, Nigeria.

Regression

Model Summaryb
Change Statistics
R Adjusted R Std. Error of the R Square F Sig. F Durbin-
Model R Square Square Estimate Change Change df1 df2 Change Watson
1 .701a .000 -.021 1.439 .000 .000 1 48 .995 2.928
a. Predictors: (Constant), Risk transfer Strategy

39
Model Summaryb
Change Statistics
R Adjusted R Std. Error of the R Square F Sig. F Durbin-
Model R Square Square Estimate Change Change df1 df2 Change Watson
1 .701a .000 -.021 1.439 .000 .000 1 48 .995 2.928
b. Dependent Variable: project success among building contractors

ANOVAb
Model Sum of Squares df Mean Square F Sig.
1 Regression .000 1 .000 .000 .995a
Residual 99.380 48 2.070
Total 99.380 49
a. Predictors: (Constant), Risk transfer strategy
b. Dependent Variable: Project success among building contractors

Coefficientsa
Standardized
Unstandardized Coefficients Coefficients
Model B Std. Error Beta t Sig.
1 (Constant) 3.177 .481 6.599 .000
Risk transfer strategy .001 .141 .001 .007 .995
a. Dependent Variable: project success among building contractors

The regression result above showed a strong positive relationship between risk transfer

strategy and project success among building contractors in Lagos State which is indicated by

the R value (.701) at 5% significance level and it is statistically significant at .000 which is

less than (P<0.05)

Hypothesis II

H02:   Risk retention strategy does not have significant effect on project success among

building contractors in Lagos State, Nigeria.

Model Summaryb
Change Statistics
R Adjusted R Std. Error of the R Square F Sig. F Durbin-
Model R Square Square Estimate Change Change df1 df2 Change Watson
1 .811a .000 -.021 1.439 .000 .000 1 48 .995 2.928
a. Predictors: (Constant), Risk retention strategy
b. Dependent Variable: project success among building contractors.

40
ANOVAb
Model Sum of Squares df Mean Square F Sig.
1 Regression .000 1 .000 .000 .995a
Residual 99.380 48 2.070
Total 99.380 49
a. Predictors: (Constant), Risk retention strategy
b. Dependent Variable: project success among building contractors.

The regression result above showed a strong positive relationship between risk retention

strategy and project success among building contractors in Lagos State which is indicated by

the R value (.811) at 5% significance level and it is statistically significant at .000 which is

less than (P<0.05)

Discussion of Findings

The regression result above showed a strong positive relationship between risk transfer

strategy and project success among building contractors in Lagos State which is indicated by

the R value (.701) at 5% significance level and it is statistically significant at .000 which is

less than (P<0.05). The second hypothesis regression result above showed a strong positive

relationship between risk retention strategy and project success among building contractors in

Lagos State which is indicated by the R value (.701) at 5% significance level and it is

statistically significant at .000 which is less than (P<0.05).

This result is supported by the previous studies (Beuselinck and Manigart, 2016; FASB,

2015; and Beest, 2016). The findings indicate that risk financing strategy helps builders to

mitigate unplanned risk. The findings also indicated, the power of the quality of risk

financing strategy could explain 62% of the variance in project success among building

contractors in Lagos State, Nigeria. To the best knowledge of the researcher, this result has

never been examined before. Theoretically, the vast majority of studies that have used the

effect of risk management on construction work as a theoretical foundation in their

41
conceptual models have confirmed the importance of risk financing strategy on project

success among builders in lagos state. (e.g. Beuselinck and Manigart, 2017; FASB, 2013;

Beest, (2018); Mamic, Sacar & Oluic, 2013). Furthermore, the analysis also provides

empirical evidence that the variation of the effect of risk transfer or retention strategy could

be due to their size and business experience but not to their types of business. This result is

supported by many studies (Chalaki et al., 2017; Huang, Rose-Green and Lee 2018).

42
CHAPTER FIVE

Summary, Recommendations and Conclusions

5.0 Introduction

This is the concluding chapter of this research work, summary of findings is stated, necessary

deductions are drawn, recommendation and suggestions are made for those that will benefit

from the result of this study.

5.1 Summary of findings

The data from the analysis of the survey carried out showed the need for government

agencies responsible for construction in Nigeria to enforce quality assurance on every project.

Thorough examinations and checks must be carried out during designs and construction by

duly certified professionals. Awareness should be carried out to educate investors and owners

of buildings about possible collapse from over interference in the construction process.

Considering the effects that risk financing has on a project’s goals in the form of quality and

cost, it should be an open and conscious process through all phases of the project. According

to project actors, risk management is strongly linked to the production phase. Most of risk

processes are performed in that phase and contractors tend to be the most active group with a

large influence on the risk management process. These findings confirm some results of

previously conducted surveys. Despite of the recognised importance of the programme phase,

this study showed that this phase does not play an important role in the risk management

process. Identifying risks is not a science: it is an art. It does not require a sophisticated,

mathematical exercise, although some measurement may be useful to dimension the risk.

Given a project description including project goals, work breakdown, schedule, and resource

assignments, potential risks can be identified and categorized using various tools such as

43
brainstorming. Risk is always present and must be dealt with accordingly. Risk management

can be sophisticated and complicated, but the starting point should always be a simple

assessment of the problem and possible solutions.

5.2 Conclusion

The construction industry is prone to several risks which the contractor or client cannot

shoulder alone when it occurs. Therefore, there is a need for the contractor to take up

insurance to cover these risks. But from the survey carried out, the awareness and

enforcement has not yet sink into majority of contractors and clients. It is therefore pertinent

to stress here that for the contractors to escape all risks and disputes, he needs to take the

contractors or builders all risk insurance as elaborately discussed in this paper, Builders and

other professionals also need to take professional liability insurance to free them from

liabilities. Again, commissions such as NAICOM, CORBON are to create awareness, embark

on confidence building, ensure implementation and enforcement of the insurance Act in order

to bring about compliance in the Building industry.

The compliance level of the contractors with regards to the stipulation of section 64(1), No.37

of Insurance Act 2003 was very low compared to their high level of awareness with the

stipulation. The compliance level was less than 20% compared to the awareness level that

was more than 20%. Also, the compliance level of insurance with the payment of fire

services management funds for provision of fire service equipment for fire fighting as

stipulated in section 66, No.37 of Insurance Act of 2003 was very low. The NAICOM since

the commencement of the Act had not been enforcing the stipulation of this Act. Finally, the

compliance of the notable section in Insurance Act of 2003 with regards to insurance of

property had not been satisfactory due to low enforcement of the punitive measures for non-

compliance with the Act and inadequate provision of the Act in terms of enforcement of the

44
provision of the Act by the regulatory body NAICOM. Based on these, the following are

hereby recommended towards improving the compliance level of the Act.

The National Insurance Commission should collaborate with the relevant professional bodies

such as NIOB, CORBON, COREN, ARCON, NIQS and Planning authority that are involved

in the development process of building property in order to improve the implementation

process as a whole. The contractors should accept insurance as a complementary tool for

improvement in the building and housing sector and cultivate the habit of entrusting the

insurance experts by engaging in their policies if the need arises. Offenders should be

punished to serve as deterrent to others in order to stem the tide of incessant building collapse

5.3 Recommendations

The findings of this research are expected to contribute to more effective financing strategy

implementation and, therefore, should benefit the construction industry as a whole. To

achieve this objective the following recommendations are made:

(i) The majority of respondents evaluated their knowledge of Risk financing strategy for

building construction as intermediate; it would therefore be reasonable to suggest risk

financing strategy workshops for building constructions to further educate all parties involved

with construction projects. With adequate training opportunities in place, an increase in

knowledge of the subject and an awareness of the importance of risk management throughout

the construction project life cycle can be achieved.

(ii) All built environment stakeholders should become more involved in the implementation

of risk management. Their early involvement will facilitate a better understanding of each

party’s roles and enhance collaboration and communication within the Nigerian construction

industry. Based on the research results, the recommendations are made to the construction

contractors to cope with the major risks in the industry and to improve their risk financing

strategy practice.

45
(iii) The attitude of accepting the lowest bid should be reviewed in order to facilitate

quality works. Some criteria should be used to select because most of the times the lowest

bids are not the best especially in relation to risk management. Further studies need to be

undertaking in order to explore the extent of impact of certain risk factors or sources like

materials price fluctuation, unfavourable weather condition, political risks etc.

(iv) Communication; key to construction risk minimization, construction organizations must

form effective communication links in order to realize the benefits of partnerships and

alliances.

(v) Insurance companies should endeavour to carry out proper documentation and make

their policies well known and understood by operators of Building industries. Insurance

company should try as much as possible to honour settlement of claims as at when due.

(vi) Government should monitor control and enforce insurance Act so that Builders risk

insurance will be taken very often on projects.

(vii) Level of awareness of insurance services should be increased to create an

understanding of the administration of insurance service in the industry through seminars ,

workshops and advertisement

46
REFERENCES

Adebayo, S. (2016) Religious building collapses: The heavy price of short cuts in places of

worship and pilgrimage site construction. Procedia Engineering,196 (June), 919–

929. https://doi.org/10.1016/j.proeng.2017.08.025

Adeusi, A. (n.d.) Legal issues in promoting the contribution of insurance sector to the growth

of

Ahmad, S. M, Ahmad, R, and Saram, D. D. (2017). Risk management trends in the Hong

Kong construction industry: A Comparison of Contractors and Owners Perceptions.

Construction and Architectural Management, 6( 3), pp. 225-234.

Ahmed, S. M., Ahmed, R., and De Saran, D. D. (2016) Risk Management Trends in the

Aibinu, A. A. and Odeyinka, A. (2016). Construction Delays and Their Tausative Factors in

Nigeria. Journal of Construction Engineering Management, 132(7), pp. 667-677.

Ajufoh, M. O, Gumau, W. A & Inusa, Y. J. (2014). Curbing the Menace of Building

Collapse in Nigeria. International Letters of Natural Sciences, 168–178.

https://doi.org/10.18052/www.scipress.com/ilns.20.168.

Akintoye, A. S. and MacLeod, M. J. (2017). Risk analysis and management in construction.

International Journal of Project Management, 15(1), 31- 38.

Akintoye, A.S. and MacLeod, M. J. (2017). Risk analysis and management in construction.

International Journal of Project Management, 15(1), 31–8.

Akinyemi, A. P, Dare, G. M, Anthony, A. I, & Dabara, D. I. (2016). Building Collapse in

Nigeria: Issues and Challenges Building Collapse in Nigeria: Issues and Challenges.

Conference of the International Journal of Arts & Sciences, 9(1), 99–108.

Akinyemi. (2016).Modelling Global Risk Factors Affecting Construction Cost

Performance.International Journal of Project Management, 21, pp. 261-269.

47
Banaitiene, N. And Banaitis, A. (2012). Risk management in Construction Projects. Current

Issues and Challenges, pp. 429-448.

Al-Moumani, A. (2000). Construction Delay: A Quantitative Analysis. International Journal

of Project Management, 20, pp. 51-59.

Anegbe, E. (2016). insurance Act: Implication for the stakeholders, paper, presented at the

Augie, M. and Kreiner, K. (2016). Rationality, Imagination and Intelligence: Some

Boundaries in Human Decision-making. Industrial and Corporate Change, 9(4), pp.

659-679.

Awodele, O. A, Ogunlana, S. O. and Motawa, I. (2017). Understanding and Managing Risks

Necessary Condition for Success and Sustainability of Privately Finance Market

Projects in Nigeria. Proceedings of the Fourth 69

Baccarini, D. and Archer, R. (2016). The risk ranking of projects: a methodology.

International Journal of Project Management, 19(3), 139- 145.

Baloi, D. and Price, A. D. F. (2016). Modelling global risk factors affecting construction cost

performance. International Journal of Project Management, 21(4), 261-269.

Barber, R. B. (2015). Understanding internally generated risks in projects. International

Journal of Project Management, 23(8), 584-590.

Barkley, B. T. (2004). Project risk management. McGraw-Hill, New York. Belel, Z. and

Mahmood, H. (2012). Risk Management Practices in the Nigerian Construction

Industry- A Case Study of Yola. Journal of Engineering Sciences, 7(3), pp. 1-6.

Binuyo, M. (2019). Risk management in small construction projects. Department of Civil

and Environmental Engineering. Licentiate thesis, (Luleå: LTU).

Carpenter, M. A. and Frederickson, J. W. (2015). Top Management Teams, Global Strategic

Posture and the Moderating Role of Uncertainty. Academy of Management Journal,

48
44(1), pp. 533-545. Chapman, C. and Ward, S. (2017). Project Risk Management:

Techniques, and Insights. 2nd Ed, Wiley, New York, NY.

Carruth, M. J. (2017). Notes for site management on construction insurance, in The Practice

of Site Management

Charles, W. M. (2012). Insurance Coverage for Construction Projects. Construction Law,

1(1), 1-3.

Clark, W. and Glen, B. (2015). Jardin Insurance Service Construction Bonds and insurance

(7th ed.) “Jardin” at pp 46- 48

Clement, O. J. (2013). Design and Construction Supervision As Structurally Sustainable

Tools For Building Failure / Collapse In Nigeria. International Journal of Computer

Science and Information Technology & Security (IJCSITS), ISSN: 2249-9555 Vol. 3,

3(3), 271–281.

Corbon . (2020). “Risk Management: The undiscovered Dimension of Project

Deviprasadh, A. (2017). “Risk Assessment and Management in Construction Projects.

College of Engineering, Guindy, Anna University, Chennai- 600025. 70

Drakes. (2016). Management of Small Construction Projects, McGraw-Hill, New York.

Ede, A. (2016). Structural Stability in Nigeria and worsening Environmental Disorder: the

way forward. The West Africa Built Environment Research Conference (WABER),

Accra, Ghana.

Ede, A. (2016). Building Collapse in Nigeria: the Trend of Casualties in the Last Decade

(2000 -2010). International Journal of Civil & Environmental Engineering IJCEE-

IJENS IJENS I J E N S, 10 (January 2010), 6–32.

European Photovoltaic Industry Association EPIA. (2011). Solar photovoltaic electricity:

Empowering the world. EPIA: Brussel

Festus, A. (2011). Enforcement of Compulsory Insurance begins September. This Day Live

49
Financial System Strategy 2020. (2007). Insurance Sector Presentation. International

Conference for the Insurance Market Team, June.

Flanagan, R, and Norman, G, (2016). Risk Management and Construction. Blackwell

Scientific Publications, London. general meeting of Nigerian institute of Building

Extra Ordinary General Meeting National

Håkansson, U, Hässler, L, Bröchner J, (2017). Risk exposure in designbuild contracts.

Byggteknik, 1, 33-34. (in Swedish).

Hansen, J. K. (2014). Insurance Requirements and Costs in the Construction Industry. An

Healey, J.R. (2012). Contingency funds evaluation, Transaction of American Association of

Cost Engineers

Herman, S, Getz B, Michael C. (2003). Project Management – A Multi-Disciplinary

Approach, South Africa.

Holmes, A. (2016). Risk management. Capstone Publishing, Oxford.

IEC, (2016). Project risk management – Application guidelines, International Standard,

(Genève: IEC).

Ikpo, G. (2018). Analysis of the Basic Principles of Insurance under the Nigerian Law of

Industry. Journal of Insurance Operation, 1(1), 1-6.

Institute of Building Extra Ordinary General Meeting. National seminar with the theme “The

Insurance Act and the Built Environments” held at the National University Commission 19th

- 22nd march.

Insurance. An unpublished bachelor of law project in Common Law, University of Ilorin,

Ilorin.

John, K. (2017). Risk Management and Trends of US Construction. Journal of construction

Engineering and Management, 422-429.

50
Joseph, W. (2011). Effective Compliance Programs: Best Practices in the Property and

Casualty

Kadefors, A. (2017). Trust and collaboration in construction process - conditions and

experiences. (Gothenburg: Chalmers University of Technology).

Kawu, L. A. (2015). Incessant Collapse of Building: A Big Challenge to the Professional

Women Builders. Journal of Environmental Sciences and Resources Management,

5(1), 88-91.

Kremljak, Z. (2016). Risk Management. Proceedings of the 21st International DAAAM

Symposium, 21(1), pp. 253-254.

Kremljak, Z. (2014). Decision Making Under Risk. DAAAM International, Vienna.

Leung, H.M, Chuah, K.B. and Rao Tummala, V.M, (2018), A knowledgebased system for

identifying potential project risks. Omega, 26, 623-638.

Li, B, Akintoye, A, Edwards, P. J. and Hardcastle, C. (2015). The allocation of risk in

PPP/PFI construction projects in the UK. International Journal of Project

Management, 23(1), 25-35.

Lin, C. H. and Tseng, S. M. (2015). The Implementation Gaps for the Knowledge

Management System. Industrial Management and Data Systems, 105(2), pp. 208-222.

Liu, J, Li, B. and Nguyen, V. (2017). Key Issues and Challenges of Risk Management and

Insurance in China’s Construction Industry. Industrial Management and Data

Systems, 107(3) pp. 382-396.

Liyadu, Y. (1985). On the Responsiveness of Insurance Industry in Nigeria to Social Needs,

Lyons, T. and Skitmore, M. (2014). Project risk management in the Queensland engineering

construction industry: a survey. International Journal of Project Management, 22(1),

51-61.

51
Madu. O. (2015). Assessment of Building Collapse in Lagos Island, Nigeria. American

Journal of Sustainable Cities and Society, 1(7). https://doi.org/10.26808/rs.aj.i7v1.04

Management, 25(6), pp. 601 - 614. Management”, PM Network, Volume.14, pp.31-

40, 36770 edition.

Mason, G.E. (2012). A quantitative risk management approach to the selection of a

construction contract provisions,Ph.D. thesis, Stanford University.

McKim, R.A. (2012). Risk management—back to basics. Cost Engineering, 34(12), 7–16.

Mills, A. (2001). A Systematic Approach to Risk Management in Construction. St. Survey,

19(5), pp. 245-252. 71

Moavenzadeh, F. and Rossow, J. (2016). Risk and risks analysis in construction

management, in Proceeding of the CIB W65, Symposium on Organisation and

Management of Construction, US National Academy of Science,Washington, D. C.

Motawa, I. A, Anumba, C. J, El-Hamalawi, A. (2016). A fuzzy system for evaluating the risk

of change in construction projects. Advances in Engineering Software, 37(9), 583-

591.

Mustafa, M. A and Al-Bahar, J. F. (2015). Project risk assessment using the analysis

hierarchy process. IEE Transaction of Engineering Management, 38, pp. 46–52.

52
National Bureau of Statistics. (2018). Facts and Figures About Nigeria, Available on

http://www.nigerianstat.govt.ng.

National Insurance Commission. (2019). Enforcement of compulsory Insurance provisions in

Nigeria, Daily Trust Monday November 30th

National Insurance Company of Nigeria. (1992). NICON Handbook Abuja News

www.thisdaylivenews.com (Retrieved May 15 2015)

Nicon . (2018). Peg Helps Pull SAR Down in Global Rank. South China Morning Post,

October, 2001.

Nigeria case. Journal of Applied Finance & Banking, 1(3), 15-32

Nigeria Insurance Act. (2003). Insurance of Property. Lagos: Federal Government

Publisher.

Nigerian Business Finance News. (2011). Compulsory Building Insurance: Another Ritual or

Nnedinma, U, David, I, Keith, J. & Boniface, U. (2014). Enforcement of Occupational Health

Nwagbara, C. (n.d.). A critique of the role of the insurance sector in Nigeria.

www.academia.edu/35360760 [Retrieved December 11 2019]

Nwankwo, S. I, Nwankwo, C. V, & Okafor, M. U. (2015). An Investigation of Incessant

Building Collapse in Selected Cities of Nigeria. The International Journal of the

Constructed Environment, 6(2), 17–39.

https://doi.org/10.18848/2154-8587/cgp/v06i02/37445

Nworuh, G.E. and Nwachukwu, G.O.C. (2004). Risk Management Approach to Claims in

Contracts Administration. The Nigerian Quantity Surveyor. Vol.46, No.5. January,

Pg. 24-31.

Obasi, N. (2010). Policies, challenges, reforms and Nigerian deposition to insurance

contracts.

53
Odeh, A. M. And Battaineh, H.T. (2012). Causes of Construction Delays: Traditional

Contracts. International Journal of Project Mnagement, 20, pp. 67-73.

Odeyemi, S., Giwa, Z. T, & Abdulwahab, R. (2019). Building Collapse in Nigeria (2009-

2019) Causes and Remedies – A Review. USEP: Journal of Science and Engineering

Production, 1(1), 123–135.

Odeyinka H.A, Oladapo A.A, & Akindele O. (2006). Assesing Risk Impacts on Construction

cost. Proceedings of the Annual Research Conference. Journal of Engineering and

Management, 116(3), 533-546.

Odeyinka, H .A. (2017). An Evaluation of the use of Insurance in Managing Construction

Risk,

Odeyinka, H. A, Oladapo, A. A. & Dada, J. O. (2017). An Assessment of Risk in

Construction in the Nigerian Construction Industry. International Symposium on

Globalisation and Construction, Construction in Developing Economies, 107, pp.

359-368.

Odeyinka, H. A. (2016). An Evaluation of the Use of Insurance in the Managing Construction

Risks”. Construction Management and Economics, 18, pp. 519-524.

Odeyinka, H.A. (2015). The effect of risk and its management on construction projects’ cost,

M.Sc. thesis,University of Lagos.

OECD. (2013), perspective on global development 2013; social cohesion in a shifting world,

OECD publishing, http://dx.doi.org/10.1787/persp_glob_dev-2013-en

Okuwoga, A. A. (2018). Cost-time Performance of Public Sector Housing Projects in

Nigeria. Habitat International, 22(4), pp. 389-395.

54
Olagunyi. (2017). Risk Management in Pakistani Construction Projects. 3rd IEEE

Conference on Computer Science and Information Technology, pp. 16-21.

Olaoye, S. A, Omoogun, C. B. & Akinjare, O. A. (2012). Tackling Causes of Frequent

Building

Oloke, O, Ogunde, A, Joshua, O, & Babalola, O. D. (2017). Incessant Building Collapse in

Nigeria : A Framework for Post-Development Incessant Building Collapse in

Nigeria : A Framework for Post- Development Management Control.

Oloyede. (2015). The insurance industry and Nigeria economy. Nigerian Journal of

Accounting Research, 1(2), 50-56

Oluwakiyesi. T, (2011). Nigerian Construction Industry: A Haven of Opportunities. A Report

on Construction Industry, www.proshare.com, pp. 2-31. 72

Organization for Economic Co-operation and Development (OECD, 2013). Best practice

Principles for Improving Regulatory Enforcement and Inspections. Brussel: OECD

Osula. (2014). Surveys. Research Methods: Guidance for Postgraduates, Edward Arnold,

London, pp. 115-124.

Oyegbile, O. B, Tat, T. N, & Olutoge, F. A. (2016). Management of Building Collapse in

Nigeria: A Lesson from Earthquake-Triggered Building Collapse in Athens , Greece.

2(6), 36–42.

Oyewobi, L. O, Ganiyu, B. O, Oke, A. A, Ola-Awo, A. W. and Shittu, A. A. (2011).

Determinants of Unethical Performance in Nigerian Construction industry. Journal of

Sustainable Development, 4(4), pp. 175-182.

Öztas, A. and Ökmen, O. (2015). Judgmental risk analysis process development in

construction projects. Building and Environment, 40(9), 1244-1254.

Öztas, A. and Ökmen, O. (2016). Risk analysis in fixed-price design-build construction

projects. Building and Environment, 39(2), 229-237.

55
paper presented to the public service lecture series Lagos.

Pasquire C. and Collins S. (1997). The Effect of competitive tendering on value in

Construction. RICS, Research Papers 2(2), Royal Institution of Chartered Surveyors,

London. Risk Assessment and Estimating in Building Contracts in Nigeria 532

Patel, A. M, Jayeshkumar, R. P. & Bhavsar J. J. (2013). A Study of Risk Management

Techniques for Construction Projects in Developing Countries. International Journal

of Innovative Technology and Exploring Engineering, 3(5), 139-142

Sesel, J. (2003). Article on History of Professional Risk Managent in Australia: Adison

Soladoye, Y. (2012). Insurers and the buildings: A synergistic Approach to the Nigerian

Tah, J. H. M. and Carr, V. (2016). A proposal for construction project risk assessment using

fuzzy logic. Construction Management & Economics, 18(4), 491-500.

Taiwo, A. A, & Afolami, J. A. (2011). Incessant building collapse: A case of a hotel in

Akure, Nigeria. Journal of Building Appraisal, 6(3–4), 241–248.

https://doi.org/10.1057/jba.2011.1

Tang, W, Qiang, M, Duffield, C. F, Young, D. M, and Lu, Y. (2017). Risk Management in

Chinese Construction Industry. Journal of Construction Engineering and

Management, 133(12), pp. 944-956.

The Fronteira Post, 1-6

the Nigerian economy. www.academia.edu/10144777 [Retrieved December 11 2019]

Toakley, A. R. and Ling, S. M. C. (2016). Risk management and the building procurement

process in Proceedings of the Innovation and Economics in Building Conference,

Brisbane, Australia, September, pp. 63–7.

Toolanen, B. (2017). The choice of implementation, compensation and collaboration form in

construction, Licentiate thesis, (Luleå: LTU).

56
Turner, D.F. (1979). Quantity Surveying Practice and Administration, George Godwin,

London.

Turning Point. www.editor@thenigeriavoice.com [Retrieved May 18 2015]

Tyagler, N. (2017). Assessing Risk Probability: Alternative Approach. PMI Global Congress

Proceedings - Prague, Czech Republic.

Uher, T. E. and Toakley, A. R. (2016). Risk management in the conceptual phase of a project.

International Journal of Project Management, 17(3), 161-169.

Ujunwa, A. & Modebe, N. J. (2011). Repositioning insurance for operational efficiency:

The

Ukpata. (2016). Analysis Of The Impact Of Building Collapse Risks In The Nigerian

Econmy. Environmental Review ER. https://www.researchgate.net/journal/0147-2496

Unpublished Master of Science thesis in Civil Engineering, University of Washington,

Walsh, K. and Sawhney, A. (2012). International Comparison of Costs for the Construction

Sector Towards a Conceptual Model for Purchasing Power Parity. Report Submitted

to the World Bank Group.

Ward, S. and Chapman, C. (2016). Transforming project risk management into project

uncertainty management. International Journal of Project Management, 21(2), 97-

105.

Washington DC.

Wiley

Williams, C.A. and Heims, R.M. (2019). Risk Management and Insurance, McGraw-Hill,

New York.

Zou, P. X.Y, Zhang, G. and Wang, J.Y. (2016). Identifying Key Risks in Construction

Projects: Lifecycle and Stakeholder Perspectives. Proceedings of 12th Rim Real

Estate Society Conference, Auckland, New zealand.

57
Zou, P.X.W, Zhang, G. & Wang, J. Y. (2007). Identifying key risks in Construction

58
APPENDIX

UNIVERSITY OF LAGOS
FACULTY OF MANAGEMENT SCIENCES
DEPARTMENT OF ACTUARIAL SCIENCE AND INSURANCE

RESEARCH QUESTIONNAIRE
Dear Sir/Ma,

I am a Ph.D student of the University of Lagos conducting a study on “Risk management and project success
in building constrction in Lagos State, Nigeria”. In order to successfully carry out this research, this
questionnaire is being sent to you for the purpose of obtaining necessary information that will aid the study.
Your assistance in filling this questionnaire will be highly appreciated. You are assured that any information
provided will be treated with utmost confidentiality.

Thank you for your cooperation!

Akindipe Leke Ebenezer


Research Student
GSM: 08026553197
E-mail (s): lekelymome@yahoo.com
---------------------------------------------------------------------------------------------------------------------------------------
--------
Please indicate your answer by ticking (√) the option that is most appropriate
SECTION A: BACKGROUND INFORMATION OF RESPONDENTS.
i. Indicate your gender
1 [ ] Male 2[ ] Female
ii. Indicate your age bracket
1[ ] 18 but Less than 30 2 [ ] 30 but less than 40 3 [ ] 40 but less than 50
4[ ] 50 but less than 60 5 [ ] 60 and above
iii. Indicate your educational qualifications
1[ ] Bachelor’s Degree / HND 2 [ ] Master’s Degree
3[ ] Doctorate Degree 4 [ ] Professional Certificate (s) (please specify) ………………
5 [ ] Others ………………………. (ND, SSCE, GCE etc.)
iv. Indicate your years of existence in the business 1 [ ] less than five years 2 [ ] five years but
less than ten years 3 [ ] ten years but less than fifteen years 4 [ ] fifteen years and above
v. How do you classify your business size? 1 [ ] Small 2 [ ] Medium 3 [ ] Large
vi. What is your position in this business? 1 [ ] Owner 2 [ ] Partner 3 [ ] Supervisor 4 [ ] Any
other, specify.....................................................................................
vii. Do you have risk management guidelines for managing your risks?
1[ ] Yes 2 [ ] No
viii. Do you have insurance policy?
1[ ] Yes 2 [ ] No

SECTION B: Building construction Risk Management Processes


Risk transfer strategy
Using a five-point Likert scale from ‘1’ = strongly disagree to ‘5’ = strongly agree; please indicate by ticking
the appropriate box that explain the extent to which you agree or disagree with the following statement that
reflect your agreement or disagreement being possibly influenced by survey items below

59
Survey items/questions Strongly Disagree Undecide Agree Strongly
Disagree d Agree
We have insurance policy for all building
constructions that we do
Construction insurance policy gives confidence in
the process of building construction
Most building contractors do not have construction
policy because it is too expensive
Builders risk policy is relevant to building
construction projects

SECTION C: Risk Retention Strategy


Using a three-point Likert scale from ‘1’ = low extent to ‘3’ = high extent; please indicate by ticking the
appropriate box that explain risk retention strategy adopted to achieve project success in building construction.
Survey items/questions Strongly Disagree Undecide Agree Strongly
Disagree d Agree
We consider experience in choosing the project
team management members
We revise design documents and drawings to
ensure compliance to building standards
Communication and coordination between parties
(clients, consultants and contractors) is very sound
Decision making process is scrutinized to avoid
errors during construction
Test and inspection of materials and labour are
thoroughly done in every phase of the building
construction

SECTION D: Awareness of building construction policy by building contractors


Using a three-point Likert scale from ‘1’ = low extent to ‘3’ = high extent; please indicate by ticking the
appropriate box that explain the awareness building contractors to building construction policy.
Survey items/questions Strongly Disagree Undecide Agree Strongly
Disagree d Agree
Punitive Measures imposed on Contractors for non-
compliance with Insurance of Building under
construction is poor
Most building contractors are not aware of the
construction policy
Construction policy is not compulsory for all types of
construction
Most building contractors have apathy for
construction policy despite the awareness
Most builders have alternative for construction
insurance

SECTION E: Project Success of Building Construction

60
Using a five-point Likert scale from ‘1’ = strongly disagree to ‘5’ = strongly agree; please indicate by ticking
the appropriate box that explain the extent to which you agree or disagree with the following statement that
reflects project success of building construction

Building project success factors Measuring scales

Material related factors Strongly Disagree Undecide Agree Strongly


Disagree d Agree
Quality of materials used influence building project
success
Change in material type and specifications affects
building project success
Compliance of materials to specifications affect
building project success
Labour and equipment related factors Strongly Disagree Undecide Agree Strongly
Disagree d Agree
Labour performance and productivity affect
building project success
Availability and efficiency of equipment affect
building project success
Finance related factors Strongly Disagree Undecide Agree Strongly
Disagree d Agree
Cost estimation accuracy helps in achieving project
success
Source of finance for the building project affect
project success
External related factors Strongly Disagree Undecide Agree Strongly
Disagree d Agree
Changes in building construction regulations affect
project success
Government permits are difficult to get
We experience civil disturbances at the
construction sites

61
62

You might also like