Professional Documents
Culture Documents
Blasting Excavation and Stability Control Technology For Ultra High Steep Rock Slope of Hydropower Engineering in China A Review
Blasting Excavation and Stability Control Technology For Ultra High Steep Rock Slope of Hydropower Engineering in China A Review
To cite this article: Ke Deng & Ming Chen (2021) Blasting excavation and stability control
technology for ultra-high steep rock slope of hydropower engineering in China: a review, European
Journal of Remote Sensing, 54:sup2, 92-106, DOI: 10.1080/22797254.2020.1752811
Blasting excavation and stability control technology for ultra-high steep rock
slope of hydropower engineering in China: a review
Ke Deng and Ming Chen
State Key Laboratory of Water Resources and Hydropower Engineering Science, Wuhan University, Wuhan, Hubei, People’s Republic of
China; Key Laboratory of Rock Mechanics in Hydraulic Structural Engineering of Ministry of Education, Wuhan University, Wuhan, Hubei,
People’s Republic of China
CONTACT Ming Chen whuchm@whu.edu.cn Key Laboratory of Rock Mechanics in Hydraulic Structural Engineering of Ministry of Education,
Wuhan University, Wuhan, Hubei, People’s Republic of China
© 2020 The Author(s). Published by Informa UK Limited, trading as Taylor & Francis Group.
This is an Open Access article distributed under the terms of the Creative Commons Attribution License (http://creativecommons.org/licenses/by/4.0/), which permits
unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
EUROPEAN JOURNAL OF REMOTE SENSING 93
improved. Zhang et al. (2013) proposed the super- extremely poor geology, ordinary measurements may
posed simulated prediction model based on vibration not ensure the stability of slope and optimization
wave of single-hole blasting. It can predict peak of design is put forward. Song et al. (2011b) combined
blasting vibration velocity as well as the completed shearing-resistance tunnel, anchor cavern and
vibration waveform. J. Liu et al. (2014) proposed inclined shaft for a comprehensive treatment on large-
a method, which can automatically complete the scale rock slope. Yang and Huang (2006) developed
whole bench blast design according to blast area con- analysis database of reinforcement for an efficient and
figuration and several parameters. For the goal of low simple way to design the supporting structures. Also,
consumption and slight damage, Chen et al. (2016b) slope bioengineering (Zhou & Zhang, 2003) has been
applied the wide-space and air-decking pre-splitting a hotspot with focus on environmental awareness.
blasting technique into Xiangjiaba project and got During blasting and reinforcement process, slope
a good result. stability is the key point. There are many stability
After blasting, stability of reserved rock will reduce. control methods, such as static limit equilibrium to
In order to minimize the adverse effects of blasting, quasi-static limit equilibrium based on natural earth-
reinforcement measure was applied. At the early time, quake (Sarma, 1981), dynamic finite element method,
some rock mass were simply cut away to control the discrete element method (DEM), infinite boundary
sliding force and retaining wall was applied to make element method, etc. The limit equilibrium method
the slope keep balance by gravity. Obviously, previous (Gurocak et al., 2008; Ling & Cheng, 1997) can judge
reinforcements were not designed under precise cal- the security of slope intuitively based on safety factor;
culation and structural analysis. With the develop- Toki and Miura (1985) applied the numerical model to
ment of modern supporting theory, which is based solve safety factor based on dynamic finite element
on classical theory of pressure, medium pressure the- method; Cundall (1987) proposed DEM to solve the
ory proposed by Terzaghi et al. (1996) and New large deformation and instability of slope based on
Austrian Tunnelling Method (Rabcewicz, 2008), rein- rock discontinuity. Bhasin and Kaynia (2004) used
forcement technique update constantly. Panek (1956) DEM that contains Barton-Bandis non-linear joint
put forward the suspension effect theory, which shear strength criterion (Barton, 1990) on the stability
thought anchor is to make weak, loose and unstable analysis of a 700 m-high rock slope in western
rock hang on the deep stable rock to restrain rock Norway. Shi and Goodman (1985), Hatzor et al.
sliding by abscission layer. Based on it, composite (2004), and J. Wu et al. (2005) used discontinuous
beam effect theory was proposed. The lamellar rock deformation analysis (DDA) to study dynamic stabi-
was thought as a kind of beam and the anchor fasten lity of jointed rock slope. J. H. Zhang et al. (2001)
them to composite beams. Layers squeezed with each applied rigid body-spring element method (RBSM)
other and friction was increased while internal stress to static and dynamic stability on slope foundation.
and deflection was reduced greatly. However, for the Q. Yang et al. (2008) proposed deformation reinforced
94 K. DENG AND M. CHEN
Dynamic criterion
After blasting, strong dynamic response is generated in
the reserved rock. Mechanical properties of structural
plane reduced and creep process of sliding mass is
accelerated. Structural body may slide along advantage
Figure 2. Partition diagram of slope above 1885 m on the left
occurrence and landslides occur. Under strong blasting bank of Jinping I hydropower station.
load, static criterion is unsuitable to ensure slope sta-
bility and dynamic stability becomes more important.
Dynamic criterion is mainly summarized from engi- conducted excavation procedure will delay construc-
neering experience since dynamic load mechanism has tion period and cause rock mass secondary-broken
not been analyzed clearly enough. The main dynamic due to transient release (Lin et al., 2015). Thus, proper
factor is blasting vibration (Lu et al., 2012b). Lots of excavation procedure is indispensable for rock slope
experimental results show that vibration has a close with large scale.
relationship with peak particle velocity (PPV) (Nguyen General principle of excavation procedure is “top-
et al., 2019a, 2019b) which can be seen as the most down stratified excavation, tunnel excavation before
direct reflection of dynamic response. PPV of slope open cut, timely support”. According to engineering
toe is the common monitored data and PPV of the practice, partition is necessary for the large excavation
slope top is also necessary to prevent blasting vibration area. Blasting of a small part can create more free surfaces
amplification for high steep slope. Recently, blasting and deduce tension failures caused by adjacent blasting.
vibration frequency and peak particle vibration accel- As shown in Figure 2, slope on the left bank of Jinping
eration are also used to judge dynamic damage caused I was divided into three excavation zones and each block
by blasting excavation. According to Chinese <Safety was excavated from outside to inside. The slope was
regulations for blasting >(GB6722-2014), combined cri- stratified layout in vertical direction. Figure 3 (1–1 profile
teria of PPV and vibration frequency is recommended. in Figure 2) shows the bench excavation plan of the left
The seismic wave frequency band is divided into several slope. The bench height was determined based on actual
segments and allowable vibration velocity is set up for engineering environment. Average step of 30 m was set
each range. For blasting excavation of slope, allowable up. The height of each bench can be increased with wide
blasting vibration velocities are between 8 and 15 cm/s. application of large advanced equipment.
If the frequency is high, the values should be lower.
Excavation method of slope
Blasting excavation technique of ultra-high Bench blasting without contour borehole was the ori-
steep rock slope ginal blasting technique and then engineer began to
focus on the importance of contour borehole.
Excavation procedure of slope
However, large blasting vibration and severe damage
Blasting is a common method for ultra-high steep rock to the reserved slope were the troubles. At present,
slope. Requirements on protection of reserved rock digital electronic detonator is applied in slope engi-
and stability control after blasting are very strict. neering to control the effect of blasting vibration.
Slope excavation has a great impact on the whole Excavation methods of slope are mainly deep-hole
process of hydropower projects. It takes many steps blasting, presplitting blasting, smooth blasting or
from natural slope to engineering slope. Poorly- their combination. Deep-hole bench blasting (Zhang
96 K. DENG AND M. CHEN
Figure 4. Bench blast-holes design of slope on the left bank of Jinping I hydropower station.
EUROPEAN JOURNAL OF REMOTE SENSING 97
release of those energy stored in the rock lead to Furthermore, if the rock is fast weathered, shallow
internal stress redistribution and then local stress con- sliding, creeping or difficult to clean, it is time to
centration appeared. During the unloading process, apply active flexible protective measures. The contin-
tensile or shear failure are easy to form subject to the uous support surface protected system is formed of
circulation of stress concentration and relaxation. In bolts and supporting ropes to make the metal net
the meantime, vibration induced by in-situ stress cover the slope tightly.
unloading may exceed the blasting load and blasting In recent years, conventional reinforcement cannot
loose zone or damage range become larger (Lu et al., live up to the expectations with extremely complex
2012a). Thus, in terms of the special high in situ stress, condition. New types of reinforcement measure, such
blasting design must consider rock failure mechanism as shearing-resistance tunnel and anchor cavern, are
as much as possible and some special measures must proposed. Shearing-resistance tunnel is a kind of hor-
be taken on the quite weaken rock. Reasonable resis- izontal strip hole arranged along the sliding face and
tance line and procedure optimization can help con- filled with concrete. Its most prominent mechanism is
trol the unloading direction or limit excavation load. “replacement”. Anchor cavern refers to the horizontal
Also, shallow-hole blasting or reducing the single hole across sliding surface along with the direction of
explosive charge can help control unloading loose. sliding. It is also filled with concrete. Figure 5 shows
shearing-resistance tunnel applied in the slope on the
left bank of Jinping I. The tunnel is mainly set on the
Stability control technique of ultra-high steep jointed rock area, which consists of lamprophyre veins
rock slope X and f42-9. It will limit further deformation and avoid
slope slumping.
Reinforcement technique of slope
When the internal joint cracks are extremely devel-
Under blasting vibration, fissures, beddings and frac- oped or various types of faults, dykes, sliding surface
tures are easy to occur and expand. Physical charac- are quite deep, comprehensive reinforcement method
teristics of reserved rock mass are reduced. Stability is applied. Builders attempt to combine several rock
and safety of the project and relative buildings are replacement structures with traditional support for
difficult to ensure without scientific and rational rein- integrated treatment. As shown in Figure 6, Song
forcement measures. et al. (2011) arranged shearing-resistance tunnels
Reinforcement measures are often used in high alternately along sliding plane in compression-shear
slope engineering with complicated geological condi- zone and put anchor caverns perpendicular to sliding
tions (L. Zhang et al., 2015). Anchored structures, surface cross the shearing-resistance tunnels.
anti-slip support, slope flexible support and grouting Replaceable inclined shafts connect upper and lower
engineering are the common used reinforcement shearing-resistance into integration to replace weak
methods. The anchored structure components com- rock on sliding plane. This comprehensive manage-
prise (pre-stressed)anchor, pre-stressed cable, soil ment takes full advantage of various support struc-
nailing wall, bolt-shotcrete support and etc. Anti-slip tures and is beneficial to global and local stability.
support components include anti-sliding wall (such as
reinforced retaining wall, anchor slab retaining wall,
Control technique of blasting effect
pre-stressed anchor retaining wall, anchor retaining
wall) and anti-slide pile (anti-slide single pile, frame After blasting, reserved rock mass may get damaged
assembled anti-slide pile, bearing platform anti-slide and stability of the slope is difficult to ensure. Blasting
pile, anti-slide steel frame pile, steel pipe pile, sheet- damage and blasting loose are easily to appear on the
pile, anti-slide pile, anchor pile). Passive flexible struc- near field of blast source and blasting vibration is the
ture mainly consists of wire rope net, steel columns, main effect on the far field. Thus, some measures
support rope, tension anchored rope, decompression should be applied due to these negative blasting
ring, etc. Grouting is a method that strengthens the effects.
jointed rock by injecting grout into gaps inside the
rock. It is mainly applied in the slope engineering Blasting vibration control
where large faults exist. The influences of blasting vibration on high rock slope
Bolt and anchor cable are the most frequently used are mainly two aspects: on the one hand, frequent
measures. Bolt is used for seriously weathered slope vibration loads result in the decrease on anti-shear
with mature joint fissure. It consolidates weaken rock strength of structural plane; on the other hand, inertia
together by friction force between each other. Anchor force makes the whole downslide strength increase and
makes the weak, loose and unstable rock suspend in may lead to dynamic instability (Liu, 2007). In practice,
stable rock to prevent slipping separation. Currently, measures that can reduce blasting vibration are often
free single-hole multi anchorage antiseptic pre- taken from explosion source and transmission route of
stressed cable is often used in slope engineering. blast stress wave. For explosion source, it includes using
98 K. DENG AND M. CHEN
Figure 6. New concrete shearing structures for slope reinforcement (Song et al., 2011b) (a) Profile (b) Elevation drawing.
1-Designed contour, 2-Prestressed anchor, 3-Shearing-resistance tunnel, 4-Anchor cavern, 5-Replaceable inclined shafts, 6-Longitudinal drainage tunnel,
7-Drainage hole, 8-Sliding plane, 9-Dike, 10-Unloading crack.
EUROPEAN JOURNAL OF REMOTE SENSING 99
contrastive analysis (Cawood, 2006). (3) reliable, stable, support structures, such as random bolt, anchor, first
high precision and simple fast instruments and methods sprayed concrete and locked anchor bar of the last
are the prior choice. Multiple methods and apparatus bench, should be applied timely. (2) blasting excavation
should be adopted to monitor the same variable for the that carried out after reinforcement can minimize rock
key part and results need to be verified mutually. (4) sites deformation compared with blasting before reinforce-
and times of monitoring should meet blasting safety ment, especially for easily instable rock (Zhang et al.,
requirements to guarantee achievement data completed 2003). (3) for the potential sliding rock which is meet
and reliable. (5) construction environment or other out- the stable demands after anchor, timely reinforcement
side factors like weather conditions also need to be and drainage during the construction are essential. (4)
considered. pre-excavation of the drainage tunnels and anchor
Different projects need different monitor instru- caverns is beneficial to drainage, reduce groundwater
ments. Velocimeter, accelerometer and dynamic strain level, and enhance slope stability. For the slope, which
gauge are used to get the motion and dynamic para- is conducted with anchor caverns, shearing-resistance
meters of the rock. Peak particle vibration velocity is tunnels or drainage tunnels, excavation of these holes
the main monitored parameter, which is a reflection should be ahead of the slope excavation. Followed by the
about dynamic response after blasting. Likewise, bore- above principles, stability of slope can be ensured during
hole inclinometer and multi-point extensometer are construction period.
used to monitor displacement change. Integration of
collected data can analyze the stable state and slip
trend. As for the stress monitor, it often uses the Case Study – Excavation and reinforcement of
pressure cell, anchor dynamometer and etc. slope on the left bank of Jinping I hydropower
station
Optimization on blasting excavation and General situation of Jinping I hydropower station
reinforcement of slope
Jinping I hydropower station, located in a deep valley
Optimization technology of blasting and reinforcement of the Yalong River, is the first of five hydropower
has been discussed in Sections 3 and 4. In order to reduce stations to be constructed in middle and low reaches of
mutual interference between blasting excavation and the river (Huang et al., 2010). Figure 9 shows the
reinforcement, optimization on construction procedure general condition of Jinping I hydropower station.
is also necessary. Generally, the optimized principles is The dam is 305 m high, which is the world’s highest
guided by the following:(1) temporary or random double-curvature arch dam until now. The retained
Figure 9. General condition, (a) position of Jinping I hydropower station, (b) experimental model, (c) excavation and reinforcement
of slope on the left bank.
EUROPEAN JOURNAL OF REMOTE SENSING 101
reservoir level is EL.1880 m and storage capacity is of Jinping I can be called the largest scale but worst
7.765 billion m3. Total installed capacity is 3600 MW. stable slope among Chinese hydropower stations.
Geological cross-section of slope on the left bank is
shown in Figure 10. The excavated height was 530 m
Blasting excavation and reinforcement
and excavation area reached up to 5.5 million m3. The
left abutment formed a scarp slope with alternating The main design principles of blasting excavation and
weaken and strong rock. Deep fractures in groups, reinforcement were “less excavation, weak blasting,
commonly known as “Jinping deep crack”, were strong support, hierarchical partitioning support,
found within the superficial unloading belt and it is overall control, cover surface with points” (Song
definitely a threat to the left slope stability. It was et al., 2011). The procedures were hierarchical excava-
a special geological phenomenon that consists of fault tion from top to down and excavation with simulta-
f5, f8, f42-9, lamprophyre veins X and fissure SL44-1. The neous reinforcement. Figure 2 shows the diagram of
main strike direction was NE. Advantage dip was layering and zoning of the excavated area. The area
between N50° and 90°E. Fault f5, f8 and lamprophyre was mainly divided into three zones and each block
X were relatively long and wide with poor property. F5 applied blasting operation from outside to inside. In
was a strike-slip thrust fault of 1.8 km long. F8 was order to ensure the integrity of bedrock and surface
about 1.4 km long with a relative small thickness of smoothness after excavation, presplitting blasting was
crushed zone and crossed with f5 in the middle part of applied. Blasthole arrangement is shown in Figure 11
the slope. SL44-1 was a deep tensile crack at the and blasting parameters are shown in Table 1. Relative
upstream boundary. F42-9 was at the downstream blasting parameters were set strictly according to spe-
boundary with lamprophyre X as the internal sliding cifications and field test. For the part that was not
face. These faults may produce a wedge failure mode suitable to apply presplitting blasting, protective layer
that controlled the slope deformation. Under particu- was reserved and single-row drilling blasting method
lar high in-situ stress environment and lithologic con- was used.
ditions, stress released intensely accompanied with According to fundamental topographic and geolo-
valley cutting. The deep unloading fissure system was gic conditions, overall stability was set as the control
formed on the basis of unloading rifting on original mode and targeted reinforcement was designed for
structures (S. Qi et al., 2004). Due to the above, the sub-surface, shallow surface and deep surface respec-
geological conditions are so complex that it is tively (Song et al., 2011; Li et al., 2007). Pre-
a challenge on slope excavation. Thus, the left slope consolidated grouting was implemented firstly by
102 K. DENG AND M. CHEN
Figure 11. Hole arrangement of slope on the left bank of Jinping I hydropower station (unit: cm) (a) Planar graph of hole
arrangement (b) Profile of hole arrangement.
Table 1. Excavation design parameters of slope on the left strength. Contact grouting was used to strengthen
bank of Jinping I hydropower station. replaced concrete and rock interface. Consolidation
Bench Berm grouting was to improve stability of the faults on
Layer Elevation height(m) width(m) crushing zone. Deformation of lamprophyre veins
Cableway platform EL1960 m / 19
Slope at abutment EL1885 m ~ 1960 m 30 3 X was chiefly caused by dislocation of f42-9. Thus,
Crest platform EL1885 m / 6 reinforcement of f42-9 can inhibit deformation of lam-
Slope at spandrel Slope Below EL1885 m 15 2
at groove
prophyre veins X in a way. System anchor was
employed on the fractured zone and shallow-buried
section of faults. This comprehensive treatment pro-
gram enhanced overall stability, and ensured slope
arranging pre-consolidated grouting holes between safety in construction and operation successfully.
two berms to improve slope integrity and avoid rock
relaxation or slide after blasting. For deep rock stabi-
lity, pre-stress anchor cable and shearing-resistance Stability control and safety monitor
tunnel were the main reinforcement measurements. According to the report compiled by Chengdu
For the superficial rock, reinforcement was concrete Engineering Corporation Limited of PowerChina,
framed beam, shotcrete, anchor, anchor beam and the rock above EL.1885 m were broken sand slate
pre-stress anchor. For the part out of slope opening that was easy to occur partial sliding and toppling
line 8–15 m, shotcrete with wire mesh, anchor and failure. During blasting excavation, undesirable struc-
flexible passive protected network were the prime tural planes, such as f42-9, f5, exposed gradually and
measures after covering layer was cleaned away. In stability of reserved rock was decreased. The stability
the meantime, anti-seepage and drainage system of slopes was analyzed by the limit equilibrium analy-
were set to reduce potential rock mass failure due to sis, which provided a direct measure of stability in
seepage. For the dangerous rock body outside the terms of the safety factor (Kentli & Topal, 2004).
opening line, partly clear-away, bolt, anchor or active Under normal circumstances, safety factor of natural
protected network support was applied due to the slope remained at 1.0. After blasting excavation, safety
actual engineering geological conditions. Above rein- factors changed from 1.13 to 0.99 with the different
forcement plans have obtained desired effect. The occurrence simulation on SL44-1. Safety of factor was
slope deformation has settled to negligible amounts calculated by limit equilibrium method or finite-
with no further significant degree. element-based strength reduction method. The finite
As for the special Jinping deep crack, concrete element strength reduction method was used for over-
shearing structure and anchoring system were all stability. It was among 1.75–1.70 on natural condi-
adopted. As shown in Figure 5, there were three shear- tion, 1.67–1.40 when excavating to El.1885 m, and
ing-resistance tunnels in the EL.1883, 1860 and 1.05–0.95 after excavation completed.
1834 m arranged along fault f42-9 to replace the bottom It is noted that stability of the slope was decreased
slip surface of tensile cleft body. Configuration of steel after blasting excavation. Thus, reinforcement plan
bar has been set to further increase the anti-shearing was indispensable. In the designed stage of
EUROPEAN JOURNAL OF REMOTE SENSING 103
Table 2. Summary on stability analysis of slope on the left bank of Jinping I hydropower station.
No. Author Method Criteria Conclusion
1 Li et al. (2007) FINAL safety factor Four conditions are set and conclude that the safety factor
will increase after the pre-stressed anchor cable.
2 Fei et al. (2010) Geo-mechanical model testing with safety factor Overloading, strength decreasing are applied to simulate
temperature-analogue material different condition and conclude that the reinforcement
treatment is necessary.
3 S. W. Qi et al. (2010) FLAC3D with Sarma limited safety factor Some remedial works are beneficial to improve stability.
equilibrium approach, Griffith and
Lane’s strength reduction method
4 Q. Y. Chen et al. (2011) ANSYS/LS-DYNA safety factor, PPV Fault f5 and f8 will influence the blasting excavation of
1910 m-1885 m.
5 Xu et al. (2011b) RFPA-SRM safety factor The slope is subject to brittle tensile fracturing subparallel
to the maximum principal stress.
6 Z. F. Qi et al. (2012) ANSYS with finite element-based safety factor Put forward a new criterion to calculate safety factor. And it
Strength reduction method will get increasing after the three shearing-resistance
tunnels.
7 Y. Liu et al. (2013) Multi-grid method safety factor The safety factor decreased with the excavation going on,
some measures should be taken to ensure stability.
8 Xu et al. (2014a) RFPA3D–centrifugal model damage vibration Microseismic activity induced by construction disturbance
considering microseismic damage only slightly affects the stability of the slope.
9 Y. Chen et al. (2015) 3D geomechanical model test by Overloa-ding The treament measures combining with concrete cushion,
Overloading test method and multiple concrete replacement grids and slot-cutting replacement
strength reduction test method are feasible to improve the stability.
10 Lin et al. (2015) Large-scale rotating 3D safety factor Reinforcement installed in the weak rock can improve the
geomechanical model anti-slide safety factor of the slope.
reinforcement plan, engineers have studied stability of slope innovate continuously. Main works and conclu-
the slope by kinds of experimental and numerical sions of this article are summarized as follows:
methods and put forward possible failure may occur.
Relative researches are shown in Table 2. Operating (1) A series of design principles and stability criter-
conditions were mainly aimed at potential sliding part ion of ultra-high steep rock slope was summed
of f5, f8, SL44-1 and lamprophyre veins X. Dynamic up. Stability analyze mainly includes static and
finite element method (Y. Liu et al., 2013; Xu et al., dynamic analysis. Safety factor of static criter-
2011) was used on numerical simulation of blasting ion and PPV combining with dominant vibra-
excavation process of the left slope to analyze global tion frequency of dynamic criterion are the two
and local stability. The effect of blasting vibration on most frequently used index in practice.
pre-stressed anchor on the upper part was evaluated. (2) Blasting excavation procedures are generally
And some critical advices were also proposed to opti- excavation from top to down and reasonable
mize the construction program. layer and zone division. Proper arrangement,
Thorough monitoring system, which includes such as reinforcement before excavation, rein-
appearance, inward vision, stress, deformation, special forcement and excavation at the same time, can
structures border and reinforcement, has been estab- reduce adverse blasting effects. Moreover, pre-
lished to ensure slope safety under continuous excava- splitting blasting with lateral free face or opti-
tion (Xu et al., 2014a). Eighty external observation piers mized smooth blasting can be selected to
were set up on three divided monitoring areas to reduce damage on reserved rock and control
arrange monitoring instruments objectively. In allusion blasting vibration. And high in situ stress in
to deep cracks, deformation detectors, such as graphite southwest China should not be neglected.
rod meter, were put in the exploratory adit and drainage Combination of presplitting and smooth blast-
tunnel for deep deformation monitor. Furthermore, ing or procedure optimization can be applied to
PPV was monitored after every blasting excavation control the effect of in-situ stress to some
and the harmful effects were evaluated timely. extent.
Thanks to the above, Jinping I hydropower station, (3) Conventional reinforcement measures, such as
which has the most difficult slope on excavation and bolt, anchor, anti-slide pile, just can solve part of
reinforcement, can be built successfully. stability problems. When it comes to the complex
geological conditions, new technology, such as
anchor cavern, shearing-resistance tunnel, may
Conclusions be better choice for large-scale slope engineering.
Blasting damage and blasting loose are easy to
With the construction of many hydropower stations in
occur on the near-field of blast source, and blast-
China, unprecedented challenges make blasting exca-
ing vibration is generated on the far field. In
vation and stability control of ultra-high steep rock
practice, blasting parameters optimization, scale
104 K. DENG AND M. CHEN
and Rock Engineering, 47(4), 1307–1320. https://doi.org/ African Institute of Mining and Metallurgy, 116(5),
10.1007/s00603-013-0475-7 379–385. doi: 10.17159/2411-9717/2016/v116n5a3.
Huang, R., Lin, F., & Yan, M. (2010). Deformation mechan- Nguyen, H., Bui, X., Bui, H., & Cuong, D. T. (2019a).
ism and stability evaluation for the left abutment slope of Developing an XGBoost model to predict blast-induced
Jinping I hydropower station. Bulletin of Engineering peak particle velocity in an open-pit mine: A case study.
Geology and the Environment, 69(3), 365–372. https:// Acta Geophysica, 67(2), 477–490. https://doi.org/10.1007/
doi.org/10.1007/s10064-010-0283-1 s11600-019-00268-4
Hustrulid, W., & Lu, W. (2002). Some general design con- Nguyen, H., Bui, X., & Moayedi, H. (2019b). A comparison
cepts regarding the control of blast-induced damage during of advanced computational models and experimental
rock slope excavation [Paper presentation]. The techniques in predicting blast-induced ground vibration
Proceedings of the seventh international symposium on in open-pit coal mine. Acta Geophysica, 67(4),
Rock Fragmentation by Blasting, Beijing, China. 1025–1037. https://doi.org/10.1007/s11600-019-00304-3
Kentli, B., & Topal, T. (2004). Assessment of rock slope Panek, L. A. (1956). Principles of reinforcing bedded mine
stability for a segment of the Ankara-Pozanti motorway, roof with bolts. us dept. of the Interior, Bureau of Mines.
Turkey. Engineering Geology, 74(1–2), 73–90. https://doi. Qi, S., Wu, F., Yan, F., & Lan, H. (2004). Mechanism of deep
org/10.1016/j.enggeo.2004.03.002 cracks in the left bank slope of Jinping first stage hydro-
Li, N., Zhang, P., Yu, C., & He, M. (2007). Research on power station. Engineering Geology, 73(1–2), 129–144.
stability of left abutment slope of Jinping hydropower https://doi.org/10.1016/j.enggeo.2003.12.005
station and reinforcement measurements of prestressed Qi, S. W., Wu, F. Q., Zhou, Y., & Gong, M. (2010). Influence
anchorage cable. Chinese Journal of Rock Mechanics & of deep seated discontinuities on the left slope of Jinping
Engineering, 26(1), 36–43. doi: 10.3321/j.issn:1000- I Hydropower Station and its stability analysis. Bulletin of
6915.2007.01.005. Engineering Geology and the Environment, 69(3),
Lin, P., Liu, X., Hu, S., & Li, P. (2016). Large deformation 333–342. https://doi.org/10.1007/s10064-010-0268-0
analysis of a high steep slope relating to the Laxiwa Qi, Z. F., Jiang, Q. H., Tang, Z. D., & Zhou, C. B. (2012).
Reservoir, China. Rock Mechanics & Rock Engineering, 49 Stability analysis of abutment slope at left bank of
(6), 2253–2276. https://doi.org/10.1007/s00603-016-0925-0 Jinping-I Hydropower Project during construction.
Lin, P., Liu, X. L., Zhou, W. Y., Wang, R. K., & Wang, S. Y. Rock & Soil Mechanics, 33(2), 531–538. doi: 10.16285/j.
(2015). Cracking, stability and slope reinforcement ana- rsm.2012.02.032.
lysis relating to the Jinping dam based on Rabcewicz, L. V. (2008). The New Austrian Tunnelling
a geomechanical model test. Arabian Journal of Method. Springer Berlin Heidelberg.
Geosciences, 8(7), 4393–4410. https://doi.org/10.1007/ Sarma, S. K. (1981). Stability analysis embankments and
s12517-014-1529-1 slopes: Discussion and closure. Journal of Geotechnical
Ling, H. I., & Cheng, H. D. (1997). Rock sliding induced by and Geoenvironmental, 107, 691–698. doi: 10.1680/
seismic force. International Journal of Rock Mechanics geot.1973.23.3.423.
and Mining Sciences, 34(6), 1021–1029. https://doi.org/ Shi, G. H., & Goodman, R. E. (1985). Two dimensional
10.1016/S1365-1609(97)80011-1 discontinuous deformation analysis. International
Liu, J., Sun, P., Liu, F., & Zhao, M. (2014). Design and Journal for Numerical & Analytical Methods in
optimization for bench blast based on Voronoi diagram. Geomechanics, 9(6), 541–556. https://doi.org/10.1002/
International Journal of Rock Mechanics and Mining nag.1610090604
Sciences, 66, 30–40. https://doi.org/10.1016/j.ijrmms. Song, S., Feng, X., Xiang, B., Xing, W., & Zeng, Y. (2011a).
2013.11.012 Research on key technologies for high and steep rock
Liu, M. S. (2007). The effect of blasting excavation technique slopes of hydropower engineering in Southwest China.
on stability for ultra-high steep rock slope [PhD, Chinese Journal of Rock Mechanics and Engineering, 30
University of Science and Technology of China]. (1), 1–22. doi: 10.3901/CJME.2011.01.160.
Liu, Y., He, Z., Li, B., & Yang, Q. (2013). Slope stability Song, S. W., Zhou, Z, Gong, M. F., Huang, Y. K., Li, W. G.,
analysis based on a multigrid method using a nonlinear Rao, H. L, Shao, J. D., et al. (2011b) Slope reinforcement
3D finite element model. Frontiers of Structural and Civil methods and the structures. (Chinese patent 102021911).
Engineering, 7(1), 24–31. https://doi.org/10.1007/s11709- Terzaghi, K., Peck, R. B., & Mesri, G. (1996). Soil mechanics
013-0190-1 in engineering practice. Journal of Geology, 76, 149–150.
Lu, W., Yang, J., Yan, P., Chen, M., Zhou, C., Luo, Y., & doi: 10.1007/978-3-642-41714-6_195275
Jin, L. (2012b). Dynamic response of rock mass induced Toki, K., & Miura, F. (1985). Simulation of a fault rupture
by the transient release of in-situ stress. International mechanism by a two-dimensional finite element method.
Journal of Rock Mechanics and Mining Sciences, 53, Earth Planets and Space, 33(6), 485–511. doi: 10.4294/
129–141. https://doi.org/10.1016/j.ijrmms.2012.05.001 jpe1952.33.485
Lu, W. B., Luo, Y., Chen, M., & Shu, D. (2012a). An Wang, S., Guohe, L. I., Zhang, Q., & Lan, C. (2000).
introduction to Chinese safety regulations for blast- Engineering geological study of the active tectonic region
ing vibration. Environmental Earth Sciences, 67(7), for hydropower development on the Jinsha River,
1951–1959. https://doi.org/10.1007/s12665-012-1636- Upstream of the Yangtze River. Acta Geologica Sinica,
9 74(2), 353–361. doi: 10.1111/j.1755-6724.2000.tb00474.x
Malmgren, L., Saiang, D., Yr, J. T., & Bodare, A. (2007). The Wu, F., Liu, T., Liu, J., & Tang, X. (2009). Excavation
excavation disturbed zone (EDZ) at Kiirunavaara mine, unloading destruction phenomena in rock dam
Sweden—by seismic measurements. Journal of Applied foundations. Bulletin of Engineering Geology and the
Geophysics, 61(1), 1–15. https://doi.org/10.1016/j.japp Environment, 68(2), 257–262. https://doi.org/10.1007/
geo.2006.04.004 s10064-009-0202-5
Newcomen, W., & Dick, G. (2016). An update to the Wu, J., Ohnishi, Y., Shi, G., & Nishiyama, S. (2005). Theory
strain-based approach to pit wall failure prediction, and of Three-dimensional discontinuous deformation analy-
a justification for slope monitoring. Journal of the South sis and its application to a slope toppling at Amatoribashi,
106 K. DENG AND M. CHEN
Japan. International Journal of Geomechanics, 5(3), application to high arch dams. Science in China, 51
179–195. https://doi.org/10.1061/(ASCE)1532-3641 (2), 32–47. https://doi.org/10.1007/s11431-008-6016-z
(2005)5:3(179) Yang, Y. F., & Huang, X. P. (2006). Computer aided
Xu, N. W., Dai, F., Liang, Z. Z., Zhou, Z., & Sha, C. (2014a). design for anti-sliding pile using finite difference
The dynamic evaluation of rock slope stability consider- method. Chinese Journal of Geological Hazard and
ing the effects of microseismic damage. Rock Mechanics Control, 17(2), 95–98. doi: 10.16031/j.cnki.issn.1003-
and Rock Engineering, 47(2), 621–642. https://doi.org/10. 8035.2006.02.021
1007/s00603-013-0432-5 Zhang, J. H., He, J. D., & Fan, J. W. (2001). Static and
Xu, N. W., Tang, C. A., Li, L. C., Zhou, Z., Sha, C., dynamic stability assessment of slopes or dam founda-
Liang, Z. Z., & Yang, J. Y. (2011). Microseismic monitor- tions using a rigid body-spring element method.
ing and stability analysis of the left bank slope in Jinping International Journal of Rock Mechanics and Mining
first stage hydropower station in southwestern China. Sciences, 38(8), 1081–1090. https://doi.org/10.1016/
International Journal of Rock Mechanics and Mining S1365-1609(01)00072-7
Sciences, 48(6), 950–963. https://doi.org/10.1016/j.
Zhang, L., Liu, Y. R., & Yang, Q. (2015). Evaluation of
ijrmms.2011.06.009
reinforcement and analysis of stability of a high-arch
Xu, W. Y., Zhang, J. C., Wang, W., & Wang, R. B. (2014b).
dam based on geomechanical model testing. Rock
Investigation into in situ stress fields in the asymmetric
Mechanics and Rock Engineering, 48(2), 803–818.
V-shaped river valley at the Wudongde dam site, south-
https://doi.org/10.1007/s00603-014-0578-9
west China. Bulletin of Engineering Geology and the
Environment, 73(2), 465–477. https://doi.org/10.1007/ Zhang, Z. Y., Yang, N. H., Lu, W. B., Zhao, G., & Shi, F. Q.
s10064-013-0494-3 (2013). Progress of blasting vibration control technology
Yang, J., Lu, W., Jiang, Q., Yao, C., Jiang, S., & Tian, L. in China. Blasting, 30 (2), 25–32. (in Chinese). doi:
(2016). A study on the vibration frequency of blast- 10.3963/j.issn.1001-487X.2013.02.006
ing excavation in highly stressed rock masses. Rock Zhang, Z. Y., Yang, N. H., Lu, W. B., Zhao, G., and Shi, F. Q.
Mechanics and Rock Engineering, 49(7), 2825–2843. (2003). Blasting of modern water hydropower engineering.
https://doi.org/10.1007/s00603-016-0964-6 China Water and Power Press.
Yang, Q., Liu, Y., Chen, Y., & Zhou, W. (2008). Zhou, D. P., & Zhang, J. Y. (2003). Slope bioengineering.
Deformation reinforcement theory and its China Communications Press.