Project Management Techniques
Project Management Techniques
Techniques
SUSHANT SHARMA
Contents
• Introduction-Project Management
• Project Scope Management
– Work Breakdown Structure
• Project Time Management
– Gantt Chart
– Critical Path Method &Floats
– Precedence Network Analysis
– PERT (Program Evaluation &Review Technique)
– Line of balance technique
– Time Crashing techniques
• Project Resource Management
• Monitoring & Control
- Earned Value Analysis
SUSHANT SHARMA
Project Management
Characteristics of a “Project”
SUSHANT SHARMA
Project Objective /Project Constraints
SUSHANT SHARMA
SUSHANT SHARMA
Four Phase Project Lifecycle
Key Purpose
Propose a project to senior management Propose a project in more detail, and Do the work described in the Project Plan, Shut down the project in a controlled
with a brief written document to establish a outline a clear approach for executing the aligned with the Schedule and Budget manner
shared understanding of the proposal before project in a Plan, Schedule, and Budget
writing a Plan, Schedule,
and Budget
Key Questions
Is this the right project? How will the project achieve its How is project work progressing? Is the work of the project complete?
What results should it achieve? objectives? What issues and risks does the project Did the project achieve its
When will the project finish? face, and how should these be results/outcomes?
How will success be measured?
managed? What did the team learn that could
Who will do what? help other projects?
What will it cost? How much is the project actually
Where do project staff go next?
How will risks/issues be managed? costing?
Key Activities
Understand stakeholder interests Thoroughly plan the project activities, Mobilize the team to execute the Demonstrate that the project is
and expectations schedule, and resource requirements Project Plan complete
Establish a shared high-level Provide more detailed information to Control the execution of the Project Assess the success of the project
understanding of the proposed senior management for discussion and Plan Undertake administrative close-out
project and its intended results approval Communicate with stakeholders Transfer knowledge to the permanent
Report project status organization
Update the Project Plan, Schedule, Support departing staff
Key Deliverables Budget, and Business Case as needed
Project Definition Document and/or Project Plan Project Manual Final Acceptance Document
Business Case Project Schedule Status Reports Lessons Learned Document
Project Budget Risk, Issue, and Change Logs Project Archives
Updated Plans, Schedules, Budgets
Moving to the Next Phase
When your Project Definition Document When your Project Plan, Schedule, and As project deliverables near completion, When this phase is complete, the project
and/or Business Case are approved by Budget are approved by senior management, move to the Close Phase is finished
senior management, move to the Plan move to the Implement Phase
Phase
SUSHANT SHARMA
Project Management Processes
Initiating
Planning
Execution
Monitoring &Control
Closing
SUSHANT SHARMA
Project Scope Management
Processes required ensuring that the project includes work required and only
the work required. It includes:
• Collect Requirements
• Define Scope
• Create W.B.S
• Verify W.B.S
• Control W.B.S
SUSHANT SHARMA
WBS Tree Structure
Project
SUSHANT SHARMA
Divide the project work scope in terms of
deliverables
Select a deliverable
Process of creating
a WBS
No Does deliverables
accounts for 100%
Further divide the deliverable into work scope & are all internal
packages & further into activity which can be external & project
No assigned to a Foreman and can be estimated management deliverable
realistically has being included
Yes
1. The 100% Rule – Project Scope/Work Packages shall capture all the deliverables – internal ,external
,interim – in terms of works to be completed including project Management.
2. The deliverables should be logically decomposed to the level that represents how they will be
produced (designed, purchased, subcontracted, and fabricated). The partitioning of deliverables
from higher level with in the WBS to lower levels must be logically related.
3. Deliverables should be clearly defined to eliminate duplication of effort within WBS elements,
across organizations, or between individuals responsible for completing the work.
4. Deliverables should be limited in size and definition for effective control – but not so small as to
make cost of control excessive and not so large as to make the item unmanageable or the risk
unacceptable.
5. The PM should structure the project work into WBS elements (work packages) that are:
Tangible - real objects that can be seen felt & sensed and are not imaginary, vague or elusive. Should be
definable and easily understood by project participants.
Measurable – can be used to measure progress in quantitative terms using standard measurements.
Verifiable – the specified measures should be verifiable by any agency at the time of delivery and
acceptance.
Manageable – a meaningful unit of work where specific responsibility and authority can be assigned to a
responsible individual.
Estimatable – duration can be estimated in time required to compete, and cost can be estimated in
resources required to complete.
SUSHANT SHARMA
Independent – minimum interface with or dependence on other ongoing elements (i.e. assignable to a single
control account, and clearly distinguishable from other work packages).
Integratable – integrates with other project work elements and with higher level cost estimates and schedules to
include the entire project.
Adoptable – sufficiently flexible so the additions/ elimination of work scope can be readily accommodated in the
WBS.
• Can be completed without interruption (without the need for more information) and
There is a general ‘5% Rule’ that states that all and any Work Package should be about 5% of Project
duration.
SUSHANT SHARMA
Gantt-charts
Gantt-charts/Bar charts can be considered as
tools for portraying a project plan.
Gantt-Chart indicates the general sequence of
work tasks
It is an effective visual device showing the period
of commencement and duration of work in time
units of –Days, Weeks or Months of a Year.
It indicates the status of progress as per the
schedule.
Left side of the Gantt- chart contains the sheet
view and the right side the bar graph along a time
scale. SUSHANT SHARMA
Scheduling
SUSHANT SHARMA
NETWORK
SUSHANT SHARMA
DEFINITION OF TERMS IN A NETWORK
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
SUSHANT SHARMA
Emphasis on Logic in Network Construction
• Construction of network should be based on logical or technical
dependencies among activities
• Example - before activity ‘Approve Drawing’ can be started the
activity ‘Prepare Drawing’ must be completed
• Common error – build network on the basis of time logic (a feeling for
proper sequence ) see example below
SUSHANT SHARMA
Example 1
Develop the network for a project with following activities and
immediate predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
Try to do for the first five (A,B,C,D,E) activities
SUSHANT SHARMA
Network of first five activities
A D
1 3 4
E
B
C 5
2
We need to introduce
a dummy activity
SUSHANT SHARMA
Network of Seven Activities
1 A 3 D 4 G
7
dummy E
B
C 5 F
2 6
SUSHANT SHARMA
EXAMPLES OF THE USE OF DUMMY ACTIVITY
Network concurrent activities
a
a 2
1 2 1 Dummy
b 3
b
WRONG!!! RIGHT
SUSHANT SHARMA
WRONG!!! RIGHT!!!
a d a d
1 1
b e b
2 2 4
e
c f c f
3 3
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
Dummy Activity is used to provide a logical link to maintain the correct relationship of activities.
SUSHANT SHARMA
Scheduling with activity time
Activity Immediate Completion
predecessors Time
(week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
This information indicates that the total time required to complete activities
is 51 weeks. However, we can see from the network that several of the
activities can be conducted simultaneously (A and B, for example).
SUSHANT SHARMA
Earliest start & earliest finish time
• We are interested in the longest path through the network,
i.e., the critical path.
SUSHANT SHARMA
Arc with ES & EF time
EF = earliest finish time
Activity
1
t = expected activity
time
SUSHANT SHARMA
Network with ES & EF time
D[5,8] 5
2 3
7
4
1 6
SUSHANT SHARMA
Activity, duration, ES, EF, LS, LF
EF = earliest finish time
Activity
2
LF = latest finish time
LS = latest start time
SUSHANT SHARMA
Latest start & latest finish time
network computing a latest start (LS) and latest finish time for
each activity
D[5,8] 5
2 3[7,10]
7
4
1 6
SUSHANT SHARMA
Slack or Free Time or Float
Slack is the length of time an activity can be delayed without affecting the
completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3
weeks
3
(start anywhere between weeks 5 and 8).
2
ES LS EF EF
5 8 9 12
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
SUSHANT SHARMA
Activity schedule for our example
Activity Earliest Latest Earliest Latest Slack Critical
start (ES) start (LS) finish (EF) finish (LF) (LS-ES) path
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
SUSHANT SHARMA
IMPORTANT QUESTIONS
• What is the total time to complete the project?
– 26 weeks if the individual activities are completed on schedule.
• What are the scheduled start and completion times for each activity?
– ES, EF, LS, LF are given for each activity.
SUSHANT SHARMA
Importance of Float (Slack) and
Critical Path
1. Slack or Float shows how much allowance each activity
has, i.e. how long it can be delayed without affecting
completion date of project
GOING FORWARD
• ES = Maximum of EF’s for all predecessors
• EF = ES + t
GOING BACKWARD
• LF = Minimum of LS for all successors
• LS = LF – t
• Slack = LS – ES = LF – EF
SUSHANT SHARMA
Precedence Network Analysis
(PNA/PDM/AON)
SUSHANT SHARMA
Precedence Network Analysis
Elements of PNA Network
• Finish–to–Start.
• Start–to–Start.
• Start–to–Finish.
• Finish-to-Finish.
SUSHANT SHARMA
Types of Precedence
Relationships
SUSHANT SHARMA
• R e l a t i o n s h i p s are always defined from a preceding activity to its
successor activity.
• Lag means the delay from start or finish of an activity to its successor. It
can be specified in positive or negative time units. Lead implies a
negative lag.
SUSHANT SHARMA
SUSHANT SHARMA
PROGRAM EVALUATION
AND REVIEW TECHNIQUE
- PERT
SUSHANT SHARMA
PERT For Dealing With Uncertainty
• If the activity times are not known with certainty, PERT/CPM can
be used to calculate the probability that the project will complete
by time t.
• For each activity, make three time estimates:
– Optimistic time: o
– Pessimistic time: p
– Most-likely time: m
SUSHANT SHARMA
Beta Distribution
Assumption: The variability of the time estimates follows the
beta distribution.
Beta distribution
0 o m p
Elapsed time
SUSHANT SHARMA
Example
2-4-5 3-4-6
b d
0 2-3-4 0
START a FINISH
1-3-7 2-3-8
c e
Question: What is the probability that the project will be finished by day 12?
SUSHANT SHARMA
PERT with Uncertain Activity
Durations
Goal: Calculate the probability that the project is
completed by time t.
Procedure:
1. Calculate the expected duration and variance for each
activity.
SUSHANT SHARMA
Expected Duration and Variance for
Activities (Step #1)
• The expected duration of each activity can be approximated as follows:
o 4m p
6
SUSHANT SHARMA
Expected Length of Each Path (Step #2)
SUSHANT SHARMA
Standard Deviation of Mean Critical
Path (Step #3)
• The variance of the length of the path is the
sum of the variances of all the activities on the
path.
s2path all activities on path s 2
SUSHANT SHARMA
Probability Mean-Critical Path
Completes by t (Step #4)
• What is the probability that the mean critical path (with expected length tpath and
standard deviation spath) has duration t?
t (t path)
• Use Normal Tables z
path
Probability
Density
Function
3 2 tpath + +2 +3
Path duration
SUSHANT SHARMA
Expected Duration and Variance of Activities
(Step #1)
2
Activity o m p
o 4m p 2 p o
6 6
a 2 3 4 3.00 1/
9
b 2 4 5 3.83 1/
4
c 1 3 7 3.33 1
d 3 4 6 4.17 1/
4
e 2 3 8 3.67 1
SUSHANT SHARMA
Expected Length of Each Path
(Step #2)
Path Expected Length of Path
SUSHANT SHARMA
Standard Deviation of Mean-Critical
Path (Step #3)
2
path path 0.61 0.78
SUSHANT SHARMA
Probability Mean-Critical Path Completes
by t=12 (Step #4)
• The probability that the mean critical path (with expected length
11 and standard deviation 0.71) has duration 12?
t (t path) 12 11
z 1.41
path 0.71
SUSHANT SHARMA
SUSHANT SHARMA
Example -2 Precedence and Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
SUSHANT SHARMA
The complete network
d 6
2
(15,25)
j
a (8,4)
(20,4) e
(10,4)
1 f 7
3
b (14,4)
(20,0)
g
c
(4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
SUSHANT SHARMA
Figure The complete Network
EF=20 35
d 6
2
a (15,25) j
(20,4) (8,4)
b e
20 43
(20,0) (10,4)
f CRIT. TIME = 43
1 3 7
(14,4)
g
c (4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
10 24
SUSHANT SHARMA
Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes
b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
SUSHANT SHARMA
Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Calculate Z, where
Z = (D-S) / V
Example,
D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4)
=33
Z = (50 – 43) / 5.745
= 1.22 standard deviations.
1.22
SUSHANT SHARMA
What deadline are you 95% sure of meeting
D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days
SUSHANT SHARMA
Comparison Between CPM and PERT
CPM PERT
3 Used where times can be estimated with Used where times cannot be estimated with
confidence, familiar activities confidence.
Unfamiliar or new activities
5 Example: construction projects, building one off Example: Involving new activities or products,
machines, ships, etc research and development etc
SUSHANT SHARMA
Linear Scheduling Method
LINE OF BALANCE TECHNIQUE
SUSHANT SHARMA
Illustration (Line of BALANCE)
SUSHANT SHARMA
SUSHANT SHARMA
SUSHANT SHARMA
Line of Balance is a Project Management technique in which the production is modeled in terms of time
and location indicating milestones for the project.
The LOB is based on the underlying assumption that the rate of production for an activity is uniform or
the production rate of the activity is linear where time is plotted on one axis , usually horizontal , and units
of stages of the activity on other axis .
The production rate of any activity is the slope of the production line and is expressed in terms of units per
time
It is primarily used for scheduling involving construction of a large number of repetitive works
such as similar
This is a visual scheduling technique that allows the planner to explicitly account for flow of project. It uses
lines in diagrams to represent different types of work performed by various functional. In LOB all critical
activities are presented in the departments that work on specific locations in a project.
Analysis consists of: (Timing of Activities)
Same activity on several locations at the same time
Activities cross and order of completion changes.
Several activities start/ or end at the same time.
Dependencies between tasks are missing or estimated wrong.
Synchronization means that all the activities have similar production rate.
Pacing means that the activities to continue from one location to another without interruptions.
SUSHANT SHARMA
Steps for conducting Line of Balance Technique
5. Calculate the resource sets requirement and set the location-wise movements.
6. Checking the line of balance schedule
a) Choice of sections and order of completion match contracted plan and client requirements.
b )No free work points.
c )Margin allowed for disturbances.
D Time, inspection and certification.
Tasks paced and synchronized.
Labor availability at peak and in line with target.
Concrete hardening time and contractual constraints taken into consideration
SUSHANT SHARMA
RESOURCE ANALYSIS AND SCHEDULING
SUSHANT SHARMA
Activities D, E, F, G and H require fitters.
Construct a bar chart with activities at their EST indicating person required
and total float.
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
Add up across all activities to get the total number of men required.
SUSHANT SHARMA
Convert the bar chart to a histogram
SUSHANT SHARMA
Example
If only 8 fitters are available at any period during the projects:
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
SUSHANT SHARMA
Additional Restriction – no fitters available until the end of
week 5.
Revised Schedule:
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
SUSHANT SHARMA
Resource constraints relates to:
1. Variations in resource requirements
2. Resource availability
Smaller variations:
1. Easier control of the job
2. Better utilization of resources
Big variations:
1. Frequent moving of manpower
2. Require close control
3. Affect efficiency
SUSHANT SHARMA
Total number of man required
0 1
Time
Under this technique the total project duration is maintained at the minimum level. For example, if the duration of a project is
15 days, then the project duration is maintained, but the resources required for completing different activities of a project are
smoothened by utilizing floats available on non critical activities.
These non critical activities having floats are rescheduled or shifted so that a uniform demand on resources is achieved. In
other words, the constraint in the case of resource smoothing operation would be on the project duration time. Resource
smoothing is a useful technique or business managers to estimate the total resource requirements for various project activities.
In resources smoothing, the time-scaled diagram of various activities and their floats (if any), along with resource requirements
are used. The periods of maximum demand for resources are identified and non critical activities during these periods are
staggered by rescheduling them according to their floats for balancing the resource requirements
RESOURCE LEVELLING
•It is also a network technique which is used for reducing the requirement of a particular resource due to its paucity.
•The process of resource leveling utilize the large floats avail-able on non-critical activities of the project and thus cuts down
the demand on the re-source.
•In resource leveling, the maximum demand of a resource should not exceed the available limit at any point of time. In order
to achieve this, non critical activities are re-scheduled by utilizing their floats. Some times, the use of resource leveling may
lead to prolonging the completion time of the project. In other words, in resource leveling, con-straint is on the limit of the
resource availability.
SUSHANT SHARMA
PROJECT TIME CRASHING
SUSHANT SHARMA
Problem
A small project is having seven activities. The relevant data about these activities is given below:
(i) Find out the normal duration and the minimum duration.
(ii) What is the percentage increase in cost to complete the project in 21 days?
SUSHANT SHARMA
SUSHANT SHARMA
Step –1: Various paths of the network are given below:
1.With duration = 25 days
2.With duration = 24 days
100 = 15.5%. 3.With duration = 23 days
4.With duration = 24 days
In order to determine the cost of completing the project in 21 days, let us crash that activity on the critical path, which
has minimum cost slope. It can be seen that the minimum cost slope of Rs.100 corresponds to activity E (4-6) and it
lies on the critical path. Hence, we crash activity E (4 –6) by 1 day at an additional cost of Rs. 100.
Step- 2: Various paths now are:
1.With duration = 24 days
2.With duration = 23 days
3.With duration = 23 days
4.With duration = 24 days
An examination of the above four paths clearly points out that there are two critical paths namely 1-2-3-4-6-7 and 1-2-5-
6-7, each with duration = 24 days. To reduce the project duration by three days more, there are following possible
combination of activities.
Crash activities 4-6 on the path 1-2-3-4-6-7 and 5-6 on the path 1-2-5-6-7 by one day each at an addition cost of Rs. 100
+Rs. 200 = Rs. 300.
2. Crash activities 4-6 on path 1-2-3-4-6-7 and 2-5 on path 1-2-5-6-7 by one day each at an additional cost of Rs. 100
+Rs. 100 = Rs. 200
3. Crash activity 1-2 by one day at an additional cost of Rs. 200.
It can be observed that the additional cost of reducing the project duration by one day in combination 2 as well as
combination 3 is Rs. 200. Hence any of these two can be selected for crashing. However, since crashing activity 1-2 by
1 day reduces the duration of all the paths by1 day, we will crash it by I day. The project duration becomes = 23 days at
an additional cost = Rs. 200.
Step 3: Crash activity 1-2 by 1 day further, it would reduce the project duration to 22 days at an additional cost = Rs. 200.
Step 4: Activity 1-2 can not be crashed further. So, we now select the combination 2 stated above for crashing. Crash
activities 4-6 and 2-5 by one day each at an additional cost of Rs. 100 +Rs. 100 = Rs. 200.
Hence, in order to complete the project in 21 days, an additional cost of Rs. 100 +Rs. 200 +Rs. 200 +Rs. 200 = Rs. 700
will be incurred.
The normal cot of completing the project in 25 days =Rs. 4,500.
Hence, the percentage increase in cost to complete the project in 21 days = 100 = 15.5%.
Rs.700
SUSHANT SHARMA Rs.4,500
Purpose of Time Crashing
• To meet the Management’s need for the early completion of the
project with acceptable cost to be paid for gaining time.
SUSHANT SHARMA
Methods of Compressing the Schedule
SUSHANT SHARMA
Project Crashing
(Time cost trade off technique)
• Crashing a project involves paying more money to complete a project more
quickly.
• Since the critical path determines the length of a project, it makes sense to
reduce the length of activities on the critical path.
• Analyze cost & schedule tradeoff’s to determine how to obtain the greatest
amount of compression for the least incremental cost.
SUSHANT SHARMA
Time –Cost Trade off Technique
• The difference between the =(normal time and crash time of an
activity indicates its potential to undergo crashing . The slope of the
activity cost function shows the rate of increase of cost , with the
reduction in time for the activity.
SUSHANT SHARMA
Procedure for performing
Time crashing
Time analyze the network & determine the critical path
Tabulate normal and crash duration and normal & crash cost
for all the activities.
Estimate activity crashing potential for each activity.
Determine the rate of crashing of all activities.
Crash activities beginning with the activity having least rate
of crashing .Each activity is shortened until its crashing
potential is exhausted , or a new critical path is found.
If a new critical path is formed, reduce the combination of
critical activities having the combined lowest rate of crashing
, and continue till there is no more scope of crashing .
At each crashing incorporates the cost implication in a table.
SUSHANT SHARMA
Which Activities are the Best
Candidates for Crashing?
• Any activity that is on the critical path
• Activities with relatively long durations
• Bottleneck activities (that appear on multiple
critical paths)
• Activities with relatively low costs to crash
• Activities that are not likely to cause quality
problems if crashed
• Critical Activity with least cost slope
• Activities that occur relatively early in the schedule
and are labor intensive
SUSHANT SHARMA
PERT CPM
PROGRAM Evaluation & Review Technique Critical Path Method
Activity on Arrow type diagrams are more suitable for Activity on Node type diagrams are more suitable for
drawing network drawing network
Time estimates are based on ‘expert’ opinion due to lack of Time estimates are based on past experience, data based
past experience on identical tasks on past experience, data base or manuals for similar activities
There is no direct relationship established between the Direct relationship is established between the efforts spent
efforts spent on activity and the results obtained and the results obtained
Project control provides the systems and procedures to track and control the project’s scope, cost /Resources
,specifications, risk and schedule to support project managements objective of delivering a scope that meets project
requirements, within the budget and on schedule &specifications . Scope, cost/Resources , schedule, specifications ,risk
are interdependent on a project. For example a change that increases the project scope typically is associated with an
increase to the project cost or schedule or all .
Project control compares actual performance with plan (baseline), identifies variances and corrects adverse
variances.
SUSHANT SHARMA
Understanding Project Control &
reporting Performance through
EARNED VALUE MANAGEMENT
SUSHANT SHARMA
Earned Value Management Example
Task – Construction of a building
• Project Duration:4 Days
• Project Budget: Rs. 4,000 (i.e. BAC – Budget at completion)
But on Day 1, Only 75% of progress achieved and actually money spent to complete 75%
of works = Rs. 900.
SINCE ON Day 1, only 75% of progress achieved, idly expenditures should be Rs. 750.
It is Earned Value (EV) = Budgeted Cost of Work Performed (BCWP)
SUSHANT SHARMA
Earned Value Management Example
Performance Report: As on Day 1:
Behind
On Schedule Ahead Schedule
Schedule
If SV is Zero -ve +ve
If SPI is 1 Less than 1 More than 1
Within Budget Over Budget Under Budget
If CV is Zero -ve +ve
If CPI is 1 Less than 1 More than 1
SUSHANT SHARMA
Earned Value Management Example
The closer the CSI is to 1, the more likely the project’s can be
recovered from it’s deviation to the original baseline.
SUSHANT SHARMA
(June’2012 )Example 1 :Activity details of a Construction Projects are as below
Activity Duration Budgeted Preceding
(weeks) Cost (Rs in Activity
Lacs)
A 4 20 -
B 5 10 A
C 8 16 A
D 5 25 B
E 4 8 B,C
F 3 12 B,C
G 4 12 D
H 4 6 E
BCW P=Actual
Derivedfrom BCW P- BCW P- BCW P/ACW BCW P/BC
BAC Based on CPM Network Given % Complete X BAC-EAC ST- ETC
network ACWP BCWS P WS
BAC
SUSHANT SHARMA
F
12 17 3
E H
12 12 4 16 16 4 20 20
A B D G
0 0 4 4 9 11 14 16
4 5 5 H
SUSHANT SHARMA
Earned Value Management
What is needed for EVM?
• A firm baseline plan
• A project budget (BAC – Budget at
Completion)
• A project end date
• Tasks are identified & scheduled
• Each task has a budget or effort (resource
loaded / weighting) (Task refers to cost
account)
• Actual tracked
SUSHANT SHARMA
EVA Integrates –Three
Dimensional
• It compares the PLANNED amount of work
with what has actually been COMPLETED, to
determine if COST , SCHEDULE, and WORK
ACCOMPLISHED are progressing as
planned.
• Work is “Earned”
or credited as
it is completed.
SUSHANT SHARMA
What is Earned Value
Management (EVM)?
• A method of integrating scope, schedule, and
resources (cost data) objectives for measuring
project performance.
• It compares the amount of work that was
planned with what was actually earned with
what was actually spent to determine if cost and
schedule performance are as planned.
SUSHANT SHARMA
EVM Trend Analysis: Cumulative
At
Risk Complete
Time Now Variance (
Prog
Budget Min if MR is
Management Reserve over
ACWP
Resources
Cost BCWS
400 Variance (Planned
Value)
BCWP Schedule
(Earned Variance
300
Value)
200
100
Time
J F M A M J J A
Approx. Time Variance
SUSHANT SHARMA
Unfavorable Schedule Performance
Time Now
Prog
Budget
BCWS
Rs. Resources
(Planned
Value) Schedule Slip
400 Schedule
BCWP
Variance
(Earned
300 Value)
200
100
Time
J F M A M J J A
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
Schedule Performance
Index (SPI)
SPI = EV / PV
• Good News: If SPI value is >1 or =1, the project schedule trend
is currently ahead or on planned schedule
• Bad News: If SPI value <1, the project schedule trend is
currently behind schedule
SUSHANT SHARMA
Earned Value Management
SUSHANT SHARMA
Earned Value Management
Estimate at Completion
(EAC)
#1
Actual costs to date plus a new estimate for all remaining work
(original plan no longer valid)
EAC = AC + ETC
(ETC Estimate to Complete)
SUSHANT SHARMA
Earned Value Management
Estimate at Completion
(EAC)
#2
Actual costs to date plus remaining budget
(current variances are viewed as atypical
of future variances)
EAC = AC + BAC - EV
SUSHANT SHARMA
Earned Value Management
Estimate at Completion
(EAC)
#3 & #4
Actual costs to date plus remaining budget modified by a
performance factor (CPI) (current variances are viewed as typical of
future variances).
SUSHANT SHARMA
Value of Earned Value
SUSHANT SHARMA