Report Field Joint Coating Pipe Line

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

PROJECT PENGEMBANGAN PIPA CY–III

(LOMANIS – REWULU)

FIELD JOINT COATING INSPECTION REPORT

Area : KESUGIHAN Report No : NK-CY3-IR-FJCR-019


Location (Kp) : 11 Issued date : 15 OKTOBER 2021
Page : 1 of 1

Surface Preparation Holiday Test


Pipe
Relative Surface Heating Adhesion Final
Time Dew Temperature Visual
No Joint No. KP Humadity Profile of Test/Peel Thickness Remark
(WIB) Point (Before Start Cleanliness Check Kv Result
(RH) (After Power Pipe (º C) Test (mm)
Work) (SSPC-SP3)
Brush)

1 J-59 T 11 8,30 77% 26⁰C 35⁰C ACC N/A 104 - 3,1 ACC 15 ACC
2 J-65 T 11 15,30 65% 26⁰C 34⁰C ACC N/A 103 - 3,1 ACC 15 ACC

NOTE : SSPC-SP3 : POWER TOOL CLEANING BY POWER WIRE BRUSH

PREVIOUS (JOINT) TODAY (JOINT) CUMULATIVE (JOINT) WEATHER


PROGRESS Clear √
52 2 54
Rainy

Prepared/Inspected By Checked/Witnessed By, Witnessed/Approved By,


PT. NINDYA KARYA (PERSERO) PT. NINDYA KARYA (PERSERO) PT. PERTAMINA PATRA NIAGA

Name : Name : Name :


Date : 15 OKTOBER 2021 Date : 15 OKTOBER 2021 Date : 15 OKTOBER 2021
PROJECT PENGEMBANGAN PIPA CY–III
(LOMANIS – REWULU)

FOTO DOKUMENTASI DFT