Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

SOILS AND FOUNDATIONS Vol. 51, No. 6, 1179–1190, Dec.

2011
Japanese Geotechnical Society

BREACHING FAILURE OF A HUGE LANDSLIDE DAM FORMED


BY THE 2005 KASHMIR EARTHQUAKE

TAKASHI KIYOTAi), AHSAN SATTARii), KAZUO KONAGAIiii),


ZAHEER ABBAS KAZMIiv), DAISUKE OKUNOv) and TAKAAKI IKEDAvi)

ABSTRACT
On February 9 2010, the landslide dam formed in the Kashmir earthquake that occurred on Oct 8 2005 at Hattian
Bala in Pakistan was breached after incessant rains. The authors had been involved in a research project to monitor the
long-lasting change of the landslide mass at regular 6 monthly intervals since June 2008, and they noticed that air-ex-
posed pieces of sandstones and mudstones of the landslide mass had disintegrated and crumbled due to slaking that
dated back to the breach. The change in the landslide mass shape observed between June 2008 and November 2009, did
not seem so signiˆcant except for a 300 m-long gulley that appeared all of a sudden at the toe of the mass during winter
time from 2008 to 2009. Displacements from GPS-measurements conducted in June and November 2009 showed that
the crest part subsided by about 10 cm while the toe part heaved slightly up where the over‰owed water fell into the
eroded gully. A ˆeld survey was conducted over the breached landslide dam in April 2010, two months after the
breaching event. A severely eroded breach channel was observed along the spillway, which was excavated immediately
after the formation of the dam. Given the chronological change in precipitation of the catchment area of Hattian Bala
obtained from the TRMM (Tropical Rainfall Measuring Mission) satellite data, the dam is considered to have been
breached due to the overtopping of water over the landslide mass of slakable nature. The slakable nature of the materi-
al is discussed through both standard slaking tests and advanced unconventional direct shear tests on prepared speci-
mens. Signiˆcant creep deformation and a reduction in their peak strength were observed as the slaking developed in
the specimens, suggesting that the slakable nature of the mudstones might have been responsible for the breach of the
landslide dam.

Key words: direct shear test, GPS, Hattian Bala, Kashmir Earthquake, landslide dam, slaking (IGC: B3)

dam and its vicinity, and Photo 1 is the satellite imagery


INTRODUCTION from QUICKBIRD taken on Oct. 27 2005, a few days af-
On October 8 2005 an earthquake of magnitude 7.6 ter the earthquake. The broken line and solid line show
Mw (USGS, 2005) hit Kashmir and other northern areas the perimeters of the landslide source area and the land-
of Pakistan. Figure 1 illustrates seismo-tectonic map of slide debris deposit, respectively. The shooting locations
Northern area of Pakistan. The epicenter marked in Fig. for site photographs that will appear in this paper are also
1 was located at about 30 km north-west of marked on Photo 1. The landslide debris formed a natur-
MuzaŠarabad, the capital of Azad Jammu and Kashmir al dam of about 85 million m3 volume and blocked the
State (AJK hereafter), and its focal depth was about 26 streams of both Karli and Tung valleys. These two lakes,
km. It is reportedly estimated that the earthquake caused created by the waters impounded by the natural dam-
respectively 87,350 and 10,300 fatalities in Pakistani- and ming, had been threatening downstream areas with a pos-
Indian-controlled parts of the former princely state of sible ‰ood risk.
Jammu and Kashmir (Hussain et al., 2006), and it is to be On February 9 2010, the Hattian Bala landslide dam
noted that the death toll associated with landslides was breached. The discharged water reportedly inundat-
reached about 26,500 (Petley et al., 2006). The biggest ed low-lying areas along Karli and Jehlum rivers, des-
landslide mass in this earthquake, located in Hattian troying two dozen houses and killing one child (The News
Bala, AJK, is shown in Fig. 1, buried more than 500 peo- International, 2010). Sattar et al. (2010), who conducted
ple. Figure 2 is a schematic map of Hattian Bala landslide a dam break analysis before this tragic event, reported
i)
Associate Professor, Institute of Industrial Science, University of Tokyo, Japan (kiyota@iis.u-tokyo.ac.jp).
ii)
Principal Engineer, Associated Consulting Engineers, Pakistan (formerly Graduate Student, University of Tokyo, Japan).
iii)
Professor, Institute of Industrial Science, University of Tokyo, Japan.
iv)
Graduate student, ditto.
v)
Civil Engineer, Chiyoda Corporation, Japan (formerly Graduate Student, Tokyo University of Science, Japan).
vi)
Division Chief, RIT, Tobishima Corp., Japan.
The manuscript for this paper was received for review on July 6, 2010; approved on June 22, 2011.
Written discussions on this paper should be submitted before July 1, 2012 to the Japanese Geotechnical Society, 4-38-2, Sengoku, Bunkyo-ku,
Tokyo 112-0011, Japan. Upon request the closing date may be extended one month.

1179

This is an Open Access article under the CC-BY-NC-ND license.


1180 KIYOTA ET AL.

Photo 1. Quick Bird view (27 Oct. 2005) of Hattian Bala landslide
dam

tinction between drying and wetting may have accelerated


the disintegration of the rocks of the landslide dam.
The ˆrst half of this paper describes the geological set-
tings for the areas surrounding Hattian Bala landslide
dam and the observed landform changes before and after
the breaching, and the second half deals with the descrip-
tion of the results of experiments carried out to explain
the triggering mechanism for the dam breaching. This ex-
Fig. 1. Seismo-tectonic map of Northern area of Pakistan (after perimental approach consists of: i) a series of accelerated
Schneider, 2009)
slaking tests (JGS 2125) to observe the eŠects of slaking
on the mechanical properties of mudstones and sand-
stones retrieved from the site; ii) a series of direct shear
tests on mudstone samples retrieved from the site, and on
Chiba gravel samples (gravelly soil accounting for sand-
stone), a material was chosen to draw comparisons.

GEOLOGICAL SETTING AND FEATURES OF THE


LANDSLIDE DAM
The Kashmir earthquake (Mw 7.6) of October 8 2005
was caused by the rupture of the MuzaŠarabad fault
(MF) and the Jhelum thrust Tanda fault (JT-TF) ( see
Fig. 1). MuzaŠarabad, Bagh and Balakot, major cities
located along the activated faults, which are called
Balakot-Bagh fault as a whole, were severely damaged.
The Hattian Bala landslide occurred at the southern end
of the Tanda fault about 33 km south-east of
Fig. 2. Schematic map of Hattian Bala landslide area (after Schneider, MuzaŠarabad. The source area of the landslide is com-
2009) posed of Miocene Murree Formation mudstones and
sandstones including minor proportion of limestone on
that although the Karli river and the Jhelum river would the hanging wall of the Tanda fault (Dunning et al.,
have the su‹cient capacity to convey the major ‰ood 2007).
wave, infrastructures on low terraces may be aŠected by The main features of the Hattian Bala landslide dam
the ‰ood wave, especially at the con‰uence of the two and of the two lakes that appeared behind it are given in
rivers. Table 1. Figure 3 shows the relationship between
As a part of a MEXT project (No. 20254003), routine volumes of landslide dams and their impounded lakes
ˆeld surveys have been conducted since June 2008, twice around the world. According to this ˆgure, the Hattian
a year with the monsoonal season in between, to observe Bala landslide dam is among the largest landslide dams in
landform changes occurring over the landslide dam. The the world. Since the formation of the landslide dam,
dam body was mainly composed of mudstones and sand- Water and Power Development Authority of Pakistan
stones which originally formed the ``Dana hill'' slope. had been monitoring water levels of the two lakes and
These sedimentary rocks, especially mudstones, are par- their discharges, and they conducted a stability analysis
ticularly susceptible to slaking disintegration. Broad dis- of the dam (WAPDA report, 2006). Based on their
BREACHING FAILURE OF LANDSLIDE DAM 1181

Table 1. Summary of information about the Hattian-Bala landslide of ‰ood in case of dam breaching ( see Photo 1). The
dam and lakes water level of Karli Lake reached the spillway at the end
Characteristics of landslide dam and lake Data (assessed and inferred) of March 2007, and from the ˆrst days of April, the water
started ‰owing gently along the spillway (Schneider,
1. Location and date of dam formation Hattian-Bala, 8 Oct 2005
(34908?N, 73943??E) 2009).
Ermini and Casagli (2003) proposed a Dimensionless
2. Trigger or cause of landslide 8th Oct. 2005 M=7.6,
44 km from epicenter Blockage Index, DBI, to estimate the stability of a land-
slide dam, as follows;
3. Type and characteristics of lan- Rock and debris avalanche

Ø »
dslide forming dam H
a) Landslide volume 80.78 million m3 DBI=log A× (1)
b) Landslide scar altitude 2040–1300 m V
c) Max. debris thickness above 250 m where A is the catchment area upstream the blockage (in
valley bottom
d) Landslide surface area 1.02 km2 km2), H is the maximum crest height of landslide dam (in
e) Source maximum length up to 1750 m m) and V is the volume of landslide dam (in million m3).
deposited surface It is considered that landslide dams with DBIs smaller
f) Source maximum width 520 m
g) Morphology (Costa and Type III
than 2.92 hardly collapse, while those with DBIs greater
Schuster, 1988) than 3.25 are susceptible to breaching. From Table 1, the
4. Rock type Miocene Murree formation
DBI for Hattian Bala landslide dam is estimated to be
Mudstones 1.85, allowing experts to have optimistic views that the
5. Underlying causes of landslide Seismically Reactivated
dam would not pose an imminent threat to people living
landslide in its downstream reaches.
6. Landslide dam
Pakistan has four distinct seasons; a dry cool winter
a) Height of landslide dam in front 130 m (from December through February); a dry hot spring
of spillway (from March through May); the early summer monsoon
b) Width of landslide dam at crest 700 m (from June through September); and the winter monsoon
c) Base length of landslide dam 1330 m
along spillway (October and November). Half of the annual rainfall is
d) Slope of dam faces Downstream 20–269/ usually concentrated in July and August with an average
Flat near crest monthly rainfall reaching 255 mm (Blood, 1994), suggest-
7. Karli Lake (Large lake) ing that the risk of dam breaching can be high during this
a) Volume 62 million m 3 period of year. However, the dam was breached on
b) Catchment area 44.17 km 2 February 9 2010 during the dry winter.
c) Maximum altitude 2497 m
d) Minimum altitude 1237 m

8. Tang Lake (Small lake) FIELD SURVEYS


a) Volume 5 million m 3
b) Catchment area 30.10 km 2
Before Breaching
c) Maximum altitude 2884 m (1) Field observations
d) Minimum altitude 1149 m The greater part of Hattian Bala landslide dam is made
up of both sandstones and mudstones of Murree forma-
tion which can be easily disintegrated because of their
weak and slakable nature ( see Photo 2). These geo-
materials seemed to have the same distribution quantity
on the surface of the dam. Figure 4 shows particle size
distributions of the surface soils (mixtures of sandstones
and mudstones) which were measured by grid by number
analysis (Casagli et al., 2003). The particle size of the sur-
face soils seems to have a wide distribution (Dmax=
525¿4,000 mm, D50=4.4¿430 mm with ˆnes content of
0¿25z).
The pairs of Photos 3 to 7 compare views of the land-
slide dam at diŠerent times (June 2008 and November
2009). The photo-shooting locations are marked on
Fig. 3. Location of Hattian Bala landslide dam on bivariate plot of Photo 1. Photo 3 shows the water ‰owing out from the
impounded lake volume versus landslide dam volume (after Korup, Karli Lake (large lake) along the spillway excavated
2004) across the crest. Photos 4 and 5 show the middle portions
of the landslide dam. The spillway and the dam surface
did not show any clear sign of change during this one-
results, Pakistan Army excavated a spillway across the and-half year period. Photo 6 shows the debris source
crest of the dam in order to lower the maximum water area and the spillway at the toe part of this source area.
level of Karli Lake (large lake) and thus to reduce the risk Since there were few changes in the slope of the source
1182 KIYOTA ET AL.

Photo 4. Middle portion of the dam (photographed toward down-


stream, Latitude 34.1381859, Longitude 73.7309119)

Photo 2. Mudstone weathered by slaking (Latitude 34.1428009, Lon-


gitude 73.7321839)

Photo 5. Middle portion of the dam (photographed eastward, Lati-


tude 34.1381859, Longitude 73.7309119)

Photo 6. Source area of landslide mass (photographed toward up-


stream, Latitude 34.1385629, Longitude 73.7288259)
Fig. 4. Particle size distribution of surface soil of landslide dam meas-
ured by grid by number analysis (Casagli et al., 2003).

Photo 7. Toe part of the dam (photographed toward downstream,


Latitude 34.1385649, Longitude 73.7255449)
Photo 3. Dam water ‰ow into the spillway at the crest part (Latitude
34.1378859, Longitude 73.7323429)
ing in 2010. The details about relationship between the
breaching and precipitation will be discussed later.
area, it can be assumed that there was limited discharge (2) GPS measurements
of debris to the dam body. This huge landslide dam was considered to be gradual-
No signiˆcant change in the shape of the dam was ob- ly deformed. Therefore, the exact locations were meas-
served between June 2008 and November 2009, except for ured at points marked over the landslide dam in June and
the erosion that appeared at the toe part of the dam November 2009 using a DiŠerential Global Positioning
(Photo 7). This erosion was ˆrst observed in the survey System (DGPS). Observation points were arranged along
carried out in June 2009, although no sign of this erosion two lines, one along the spillway (longitudinal line) and
had been noticed in the previous survey (November the other in its transverse direction (transverse line).
2008). According to an eye-witness, a rainfall event in Figures 5 and 6 show respectively in-plane and vertical
winter caused this erosion (the exact date of this event is displacement vectors along longitudinal and transverse
not known). Since the landslide dam was also breached lines.
after incessant rains in winter of the following year, the The perimeter of the gully erosion at the toe part of the
above erosion may have been an early sign of the breach- dam shown on Photo 7 was also traversed using a GPS
BREACHING FAILURE OF LANDSLIDE DAM 1183

Fig. 7. Contour map of landslide dam before and after breaching

Fig. 5. Deformation vectors obtained by comparing DGPS data for


June 2009 and November 2009 surveys. Perimeter of erosion chan-
nel observed in June 2009 and November 2009 survey is marked
near the toe of debris mass (after Sattar et al., 2010)

Photo 8. Panoramic view of the landslide dam (photographed toward


upstream, Latitude 34.1421839, Longitude 73.7423839)

Fig. 6. Settlements obtained by comparing DGPS data for June 2009


and November 2009 surveys. Erosion and breach perimeters are
marked on the map (after Sattar et al., 2010)

Photo 9. Panoramic view of the dam (photographed eastward, Lati-


receiver in June and November 2009. Both perimeters tude 34.13829, Longitude 73.7261679)
traversed at diŠerent times of the year were nearly identi-
cal to each other (Figs. 5 and 6), and showed little sign of
additional erosion during the ˆve months. After Breaching
In Fig. 5, the displacements are smaller than or at most (1) Landform changes and aŠected areas
equal to 5 cm, and do not show any clear orientation, in- A ˆeld survey was conducted from April 11 to 14 2010,
dicating that they are all local and do not show any sign roughly two months after the breaching occurred. Figure
of mass movement. Figure 6 shows that the maximum 7 shows a contour map of the landslide dam before and
settlement of about 10 cm is reached near the east end of after breaching, and the severely breach channel can be
the transverse line, where it is presumed that the dynami- seen along the spillway.
cally placed debris mass is the thickest. On the other The pairs of Photos 8 to 15 compare views of the land-
hand, a slight uplift was observed where the spillway slide dam before and after the breaching. The photo-
water falls in the eroded gully near the toe of the dam. shooting locations are shown on Photo 1. Points were
1184 KIYOTA ET AL.

Photo 14. Landslides on the right bank of the Karli Lake


(photographed toward upstream, Latitude 34.1421839, Longitude
73.7423839)

Photo 10. Panoramic view of source area (photographed westward,


Latitude 34.1376179, Longitude 73.7292179)

Photo 15. View of Tang Lake (photographed toward upstream, Lati-


tude 34.1399179, Longitude 73.7363679)

9. Although the surface of the dam was covered with both


Photo 11. Middle portion of the dam (photographed toward up-
stream, Latitude 34.1409679, Longitude 73.7290679) sandstones and mudstones of large particles, the dam
body was found to be comprised mainly of relatively
small mudstones that can be seen along the sides of the
exposed breach channel. Photo 10 shows the view from
the depositional area. The lower end of the debris mass
remaining on the naked slip surface has been deeply erod-
ed. A deeply scoured gorge (breached channel) can also
be clearly seen in Photo 11, showing the middle part of
the debris mass. Looking down the toe of the debris mass
(Photo 12), it is noted that the river bed has been raised
by about several tens of meters, while the toe slope has
Photo 12. Toe part of the dam (photographed toward downstream, been deeply scoured. Photo 13 shows the frontal view of
Latitude 34.1406179, Longitude 73.7305679)
the toe as far as about 1 km away from the downstream
side. A rock outcrop, observed in the deeply scoured
gorge, may have prevented the gorge from being scoured
deeper.
Photo 14 shows a village on a gentle grassy slope on the
right side of Karli lake (large lake). It was this village
which suŠered from the coherent landslide with its 300
houses destroyed. According to eye-witnesses, the mass
movement was remarkable a few hours after the breach-
ing. Water marks remaining on the left bank of Karli lake
Photo 13. Front view of the dam (photographed toward upstream, show that the water level for the full capacity of the lake
Latitude 34.1565679, Longitude 73.7448339) was lowered by about 45 m due to breaching. On the
other hand, the water level in the Tang Lake (small lake)
was slightly higher than that before the breaching (Photo
marked along the perimeter of the scraped gorge with 15).
handy GPS receivers and plotted on Figs. 6 and 7 ( see This outburst of landslide dam has caused a mud‰ow
open triangles and red lines, respectively). along Karli valley (Photos 16 and 17). Though the mud-
In Photo 9, showing the view from the debris source ‰ow reached several tens of meters above the original
area, there is a steep-sided gorge carved deeply by the riverbed, most houses resting on river terraces narrowly
breaching event, while the remaining debris deposit be- escaped from being swept away (Photo 17). The debris
hind it shows little sign of deformation with its surface deposit along Karli valley was roughly estimated to be
covered with thin grass. The side wall was the highest, about 40 m thick immediately below the toe of the dam,
reaching 80 m and dipping 50 degrees at Point A in Photo and it became less as we went down the valley. At the con-
BREACHING FAILURE OF LANDSLIDE DAM 1185

Photo 16. Downstream area inundated by debris ‰ow and ‰ood


(photographed toward upstream, Latitude 34.1565679, Longitude
73.7448339)

Fig. 8. Precipitation record by TRMM between Oct. 2005 and Feb.


2010

‰uence of the Karli and Jhelum rivers, about 3.5 km


Photo 17. Surviving settlement in the Karli valley (photographed
toward downstream, Latitude 34.1566179, Longitude 73.7448339) downstream of the dam (Fig. 2 and Photo 18), an old
bridge was completely swept away, suggesting that the
mud‰ow reached 20 m above the original river bed. This
mud‰ow swept away two dozen houses near the con-
‰uence, and ‰owed down the Jehlum river, decreasing in
height as it traveled. When the ‰ow reached
MuzaŠarabad, about 30 km downstream Hattian Bala,
low-rising river terraces were ‰ooded. Mud marks on
Photo 19 show that the ‰ow reached a height of about 2
to 3 m at this location.
The landslide dam was breached at 3:00 PST, before
dawn, and according to local witnesses, a large sound of
rock movements was heard 30 min before the breaching,
and the people of the Hattian Bala town evacuated on
their own initiative because they had been informed of
the possible risk of a breach. It is regrettable that one
child was killed in this event.
Photo 18. Junction of Karli river and Jhelum river inundated by ‰ood (2) Precipitation record
(photographed toward upstream, Latitude 34.1684239, Longitude
73.7399829).
The precipitation record of the catchment area of the
Karli River, obtained from the Tropical Rainfall Measur-
ing Mission (TRMM) satellite is shown in Fig. 8. The
TRMM is a cooperative mission between JAXA and
NASA, which estimates the rainfalls over tropical to sub-
tropical regions with 0.259 ×0.259resolution. Data are
open to public via their website.
Signiˆcant precipitations of about 50–60 mm/day were
recorded during the monsoon season every year since
April 2007 when Karli Lake was ˆlled up. However, the
dam was breached in February 2010 during the dry win-
ter. A peak precipitation of about 30 mm/day can be ob-
served on February 9 2010, the day of the breaching.
Although the water level of Karli Lake immediately be-
fore the breaching is not known, it is expected to be
higher than that observed in November 2009 ( see Photo 3
(right)). Figure 8 indicates that the accumulated precipi-
Photo 19. Muzafarabad city area inundated by ‰ood (photographed
tation between November 2009 and the day of the breach-
toward downstream, Latitude 34.3488949, Longitude 73.4701779). ing was lower than that before the survey in June 2008.
Therefore, it can be considered that the water level of the
lake was not higher than that shown in Photo 3 (left).
1186 KIYOTA ET AL.

In addition to the over‰ow surcharge, it is likely that To estimate the changes in shapes and colors of bedd-
this unseasonal rain has also accelerated the slaking of the ings and/or laminae, each specimen was photographed:
dam materials, especially mudstones. Soil dunes formed before the immersion, within 1 minute (t=0 min here-
over the dam body shown in Photo 2 suggest that the after), at 30 min., 1 hour, 2 hours, 6 hours and 24 hours
mudstones were highly susceptible to deterioration by after the start of pouring. The slaking class of the speci-
slaking. Figure 8 also shows that precipitations were ex- men was then identiˆed based on the illustrated features
tremely low during the months before the breaching day. of deterioration (Table 2).
Since the slaking phenomenon is caused by drying and (2) Test result
wetting cycles, sudden rain after this drought period Figure 9 shows the identiˆed slaking classes of the
might have caused the severe slaking of the mudstones. sandstone and the mudstone specimens with respect to
time during the ˆrst drying-wetting cycle. Photos 20 and
21 show the overall changes of the sandstone and the
LABORATORY TESTS mudstone specimens before and after completing the tests
The performed laboratory tests comprise a series of ac- (i.e. after the three drying-wetting cycles).
celerated slaking tests on sandstone and mudstone speci- Sandstone specimens showed little sign of slaking (esti-
mens to identify their standard slaking classes, and a mated slaking class=0), while small cracks and small
series of unconventional direct shear tests with an ad-
vanced direct shear apparatus in order to examine stress-
deformation characteristics of geomaterials which ex-
perienced the accelerated slaking process.

Accelerated Rock Slaking Test


(1) Test procedure and materials
Accelerated rock slaking tests on crushed sandstone
and mudstone samples retrieved from Hattian Bala land-
slide dam were conducted, in accordance with guideline
No. JGS 2125–2006 edited by the Japanese Geotechnical
Society.
Each specimen, approximately 50 cm3 in volume, was
ˆrst oven-dried at a temperature of 409C for 24 hours,
and then subsequently immersed in distilled water for 24
hours. In the immersion process, distilled water is to be
poured into a 20 cm-diameter container until the speci-
men is fully immersed (approximately within 1 minute). Fig. 9. Change in slaking class of sandstone and mudstone during ˆrst
This drying-wetting cycle was repeated three times. cycle

Table 2. Deˆnition of slaking classes (JGS 2125–2006)

A: Typical states for mudstone of ˆnegrained tuŠ


B: Typical states for siltstone, sand stone or coarse-grained tuŠ
BREACHING FAILURE OF LANDSLIDE DAM 1187

Photo 20. Sandstone samples before and after accelerated slaking test

Photo 21. Mudstone samples before and after accelerated slaking test

Fig. 10. Direct shear apparatus


bubbles appeared on surfaces of the mudstone specimens
30 minutes after the ˆrst pouring. The mudstone speci-
mens, however, did not exhibit any further changes dur- particle breakage due to compaction.
ing the subsequent wetting/drying cycles, and their A schematic view of the advanced direct shear appara-
shapes were kept intact (estimated slaking class=1). tus used in this study is shown in Fig. 10. The inside
specimen size is 12 cm×12 cm×12 cm. The apparatus
Direct Shear Test has the following essential features: 1) a feedback control
(1) Test procedure and materials of the normal stress (applied by two air pistons) to ac-
Samples subjected to direct shear tests include the curately keep the upper shear box at level; 2) a possible
mudstones retrieved from the Hattian Bala landslide dam feedback control on both normal loads and shear load to
and a gravelly soil consisting of crushed sandstones from impose any prescribed stress path in the shear stress-nor-
a quarry in Japan (so-called Chiba-gravel). Since the in- mal stress space; 3) a lower shear box moving on a very
situ sandstones were too large to be used in the direct low-friction rail, yet with two friction load cells to evalu-
shear tests and too solid to be crushed by a standard ham- ate any friction at the bottom of the lower shear box; 4)
mer, we used the Chiba-gravel as a substitute for the shear displacements between the upper and lower boxes
crushed in-situ sandstones with a smaller particle size. directly measured with a non contact laser transducer; 5)
Even though they are categorized as the same sandstone, shear load applied by a high precision gear loading device
their detailed mineral composition might diŠer. driven by a servo-motor, allowing easy and exact control
However, it was conˆrmed that the Chiba gravel had the of arbitrary shear displacement ratio as well as sustained
same slaking class (=0) as the in-situ sand stone. loading (by a feedback control on the shear load). The
The particle size of mudstone and Chiba gravel in importance of all these features to obtain reliable data of
direct shear tests was adjusted to the same size in order to direct shear tests on granular materials was demonstrated
simplify the testing condition and to focus on the eŠect of by Shibuya et al. (1997), Qiu et al. (2000) and Wu et al.
slaking of diŠerent geomaterials on the mechanical prop- (2008). More details of the apparatus are given by Duttine
erties. Both specimens of mudstone and Chiba gravel et al. (2008, 2009).
with sub-angular particles were prepared by removing The initial opening between the two boxes was set at 2
particles ˆner than 2 mm and larger than 4.75 mm as a cm. Other initial test conditions are listed in Table 3. In
necessary adjustment to the apparatus dimensions, then this study, the loading process during the test consisted of
oven-dried at a temperature of 1009C. The specimens three stages, as shown in Fig. 11: 1) the specimen was
were not thoroughly compacted to prevent particle break- subjected to shear and average normal stresses keeping
age and to realize similar conditions as those of the lan- their ratio R (= t/sv) set at either 0.5 or 0.8. Both t and
dslide dam, which was dynamically deposited without sv were steadily increased up to respectively 50 kPa and
strong compaction. The specimen densities are shown in 100 kPa for R= 0.5, and 80 kPa and 100 kPa for R=
Table 3. In this report, relative density of the specimens 0.8. R value of 0.5 simply corresponds to the approxi-
was not evaluated. Since the amount of in-situ mudstone mate maximum slope angle (25 to 30 degrees) of the Hat-
sample was limited, the test for minimum density tian Bala landslide dam while R=0.8 was chosen for
(JGS0162–2009) was not carried out since it could cause comparison. 2) After the prescribed t and sv values were
1188 KIYOTA ET AL.

Table 3. Tested materials

Specimen Initial Density


Stress ratio density
condition before
No. Sample during creep during creep, r0 ML, r1
at R=0.5 R [g/cm ] [g/cm 3]
3

CG1 Chiba gravel 6 hr (dry) 0.5 1.393 1.450


CG2 Chiba gravel 33hr
hr (dry) and
(saturated) 0.5 1.417 1.434
MS1 Mudstone 6 hr (dry) 0.5 1.393 1.458
3 hr (dry) and
MS2 Mudstone 3 hr (saturated) 0.5 1.419 1.486
3 hr (dry) and
MS3 Mudstone saturated 0.8 1.419 —
(failed)

Fig. 12. EŠect of slaking on creep deformation on Chiba gravel (as


sandstone) with R=0.5

Fig. 11. Stress-path during direct shear test

reached, these values were kept constant for six hours


(i.e., creep loading). 3) A monotonic shear loading was Fig. 13. EŠect of slaking on creep deformation on mudstone with R=
0.5
applied at a constant shear deformation rate of 0.2
mm/min under constant normal stress condition until the
specimen's residual state was reached. The slaking eŠects
were evaluated by applying to another sets of specimens on constant values after several tens of minutes.
the following alternative step: 2 bis) creep loading for On the other hand, the saturating process of the speci-
total 6 hours including a saturation process 3 hours after mens CG2 and MS2 (3 hours after creep loading has start-
the start of creep loading. The saturation process was car- ed) caused a drastic increase of the shear displacements.
ried out by pouring the distilled water from the bottom of This increase is particularly remarkable for the mudstone
the lower shear box until the specimen was fully im- specimen (MS2), whose slaking class is higher than those
merged. As shown in Fig. 10, the over‰owed water is of Chiba gravel and in-situ sandstone. The shear dis-
received from the opening between upper and lower shear placement of the mudstone specimen increased by about
boxes by an acrylic box that is ˆxed on the lower box. 3 mm, approximately seven times larger than the values
This creep loading process represent a situation that slope for the Chiba gravel specimen (CG2). Figure 14 shows
ground is saturated by rain fall under constant stress con- the creep test result for the mudstone specimen (MS3)
dition. consolidated at a stress ratio of R=0.8. The slaking
(2) Test result eŠects were remarkable in that shear displacement do not
Figures 12 and 13 show the time histories of shear dis- stop until failure.
placements for the Chiba gravel specimens (CG1, CG2) Figures 15 and 16 show the relationship between the
and for the mudstone specimens (MS1, MS2), respec- shear stress ratio, R, and the shear displacement, s,
tively. The specimens of CG2 and MS2 were subjected to together with the associated volume change (i.e., the ver-
the alternative step loading history (including saturation) tical displacement, d) for the specimens of CG1, CG2 and
while the specimens CG1 and MS1 were subjected to the MS1, MS2 respectively. The values of s and d were set at
original loading history mentioned above. The time t=0 zero at the end of step 2 or 2bis. In addition, the values of
corresponds to the start of creep loading. In the case of friction angles, qd, (assuming apparent cohesion cd=0) at
CG1 and MS1, the creep shear displacements converged peak strength were also indicated in these ˆgures. Figure
BREACHING FAILURE OF LANDSLIDE DAM 1189

stress softening appeared and the R-s curve converged


monotonously on the same residual state as dry specimen
(MS1). Consequently, the stress level at which signiˆcant
plastic (or irreversible) deformation develops (i.e., the
start of yielding or yield stress) is diŠerent between these
two specimens. The saturated specimen (MS2) continued
to exhibit contractive behaviour during the shearing.
Such stress-displacement characteristics are true of typi-
cal soft soils, indicating that the slaking process causes
the examined mudstone material to disintegrate and
therefore causes remarkable changes in its mechanical
features.

DISCUSSIONS
Fig. 14. EŠect of slaking on creep deformation on mudstone with R=
0.8 About a half of the annual rainfall occurs during the
monsoon season in Pakistan. Therefore, it was expected
that the landslide dam would be breached during mon-
soonal times. However, the landslide dam was breached
not in monsoon season but in February 2010 during oŠ-
monsoonal dry season. The signiˆcant erosion at the toe
part of the landslide dam also appeared during dry winter
time (between November 2008 and June 2009) and no
clear landform change was observed during monsoon
seasons (between June and November 2008, 2009).
From the accelerated rock slaking tests performed on the
mudstone and the sandstone specimens retrieved from
the site, it can be concluded that the slaking level of the
mudstone was slightly higher than that of the sandstone.
The results of direct shear tests performed on the mud-
stone and the Chiba gravel specimens suggest that sig-
niˆcant slaking-induced shear displacement can take
Fig. 15. EŠect of slaking on stress-deformation characteristics on Chi- place under constant shear and normal stress conditions,
ba gravel (as sandstone)
to a greater extent for the mudstones specimens than for
the Chiba-gravel specimens, a substitute for the in-situ
sandstones. The stress-displacement characteristics of the
slaked mudstone were clearly weakened during subse-
quent monotonic shear loading.
All the above suggests that both unseasonal rains in dry
winter seasons and slakable feature of the mudstone may
have been responsible for both the signiˆcant erosion that
occurred in winter from 2008 to 2009 and the breaching
of the landslide dam in February 2010. Panabokke and
Quirk (1957) reported that the slaking level of clay ag-
gregates became higher as the initial water content of the
specimen became lower. It is to be noted that the dam
failed on February 9 because of rain after the most severe
drought which followed the 2005 earthquake ( see Fig. 8).
In fact, the accumulated precipitation from October 2009
Fig. 16. EŠect of slaking on stress-deformation characteristics on to January 2010 represents only 27z of the average ac-
mudstone cumulated precipitation during the same periods, com-
puted between the 2005 earthquake and the breaching.
Therefore, it can be inferred that the signiˆcant slaking of
15 shows that the slaking eŠects on the R-s and d-s rela- the mudstones due to rain fall in February 2010 after the
tions during subsequent monotonic loading are less sig- long dry period caused a rapid reduction in the strength
niˆcant for Chiba gravel, while in Fig. 16, the saturated of the materials of the dam body, and/or accelerated the
mudstone specimen (MS2) exhibits largely diŠerent washout of ˆne substances of slaked mudstones by the
stress-displacement features from those for dry specimen spillway discharge. These processes are likely to have
(MS1). Neither the clear peak stress ratio nor post-peak been responsible for the destabilization of Hattian Bala
1190 KIYOTA ET AL.

landslide dam. ty) and GSP (Geological Survey of Pakistan) for their
It is to be noted that there are still a noticeable number collaboration and help during the authors' ˆeld surveys.
of unstable soil masses remaining with their toe soils all The authors also thank to Dr. Duttine Antoine and Dr.
scoured deep. If one of these unstable debris masses slides Ezaoui Alan (Tokyo University of Science) for their great
and blocks the stream, it will again pose a threat to people help during the experimental work reported here.
living downstream. Further investigations in this respect
are in progress.
REFERENCES
1) Blood, P. (1994): Pakistan: A Country Study, http://
CONCLUSION countrystudies.us/pakistan/.
2) Casagli, N., Ermini, L. and Rosati, G. (2003): Determining grain
On February 9 2010, a huge landslide dam at Hattian
size distribution of the material composing landslide dams in the
Bala, Azad Jammu and Kashmir State, Pakistan, com- Northern Apennines: sampling and processing methods, Engineer-
prising about 85 million m3, was breached by incessant ing Geology, 69, 83–97.
rains. This landslide dam was formed by the 2005 3) Dunning, S. A., Mitchell, W. A., Rosser, N. J. and Petley, D. N.
Kashmir earthquake. Since June 2008, landform changes (2007): The Hattian Bala rock avalanche and associated landslides
triggered by the Kashmir Earthquake of 8th October 2005, En-
and potential settlements that were thought likely to
gineering Geology, 93, 130–144.
aŠect the stability of the dam were monitored. The 4) Duttine, A., Tatsuoka, F., Kongkitkul, W. and Hirakawa, D.
present paper reports the results of the regular ˆeld sur- (2008): Viscous behavior of unbound granular materials in direct
veys as well as the associated laboratory tests. Attempts shear, Soils and Foundations, 48(3), 297–318.
were made to explain the cause of the breaching of the 5) Duttine, A., Tatsuoka, F., Lee, J. and Kongkitkul, W. (2009): Vis-
cous properties of Toyoura sand over a wide range of strain rate
landslide dam. The conclusions of this study are summa-
and its model simulation, Soils and Foundations, 49(2), 221–247.
rized as follows; 6) Ermini, L. and Casagli, N. (2003): Prediction of the behaviour of
a) The Hattian Bala landslide dam consists of both landslide dams using a geomorphological dimensionless index,
crushed sandstones and mudstones of Murree for- Earth Surface Processes and Landforms, 28, 31–47.
mation. The mudstones were expected to be 7) Hussain, S., Nisar, A., Khazai, B. and Dellow, G. (2006): The
Kashmir earthquake of October 8, 2005: Impacts in Pakistan,
weathered easily because of their slakable features.
Earthquake Engineering Research Institute Special Paper, 8.
b) Erosion at the toe part of landslide dam was ob- 8) Japan Aerospace Exploration Agency: TRMM web site, http//
served in June 2009 after dry winter while no clear www.eorc.jaxa.jp/TRMM/index_e.htm.
landform change was noticed in the surveys of 9) Korup, O. (2004): Geomorphometric characteristics of New
November 2008 and 2009 after monsoon seasons. Zealand landslide dams, Engineering Geology, 73, 13–35.
10) The News International (Pakistanis news paper), 10 February,
c) Based on the results of accelerated rock slaking tests,
2010.
the slaking level of both the sandstone and mudstone 11) Panabokke, C. R. and Quirk, J. P. (1957): EŠect of initial water
was found to be relatively low. However, results content on stability of soil aggregates in water, Soil Science, 83(3),
from advanced direct shear tests conˆrmed the sig- 185–196.
niˆcant slaking-induced shear deformation of the 12) Petley, D., Dunning, S., Rosser, N. and Kausar, A. B. (2006): In-
cipient landslides in the Jhelum valley, Pakistan following the 8 Oc-
mudstones under constant shear and normal stress-
tober 2005 earthquake, Disaster Mitigation of Debris Flows, Slope
es. Moreover, the stress-displacement characteristics Failures and Landslides, 47–55.
of the slaked mudstone severely deteriorated during 13) Qiu, J. Y., Tatsuoka, F. and Uchimura, T., (2000): Constant pres-
subsequent monotonic shear loading. sure and constant volume direct shear tests on reinforced sand,
d) Considering the fact that the Hattian Bala landslide Soils and Foundations, 40(4), 1–17.
14) Sattar, A., Konagai, K., Kiyota, T., Ikeda, T. and Johansson, J.
dam was breached by unseasonal heavy rainfall after
(2010): Measurement of debris mass changes and assessment of the
a drought, the mudstones that mainly formed the dam-break ‰ood potential of earthquake-triggered Hattian land-
landslide dam body likely suŠered signiˆcant slak- slide dam, Landslides, DOI: 10.1007/s10346–010–0241–9.
ing. This phenomenon is likely to have been respon- 15) Schneider, J. F. (2009): Seismically reactivated Hattian slide in
sible for the destabilization of the landslide dam. Kashmir, Northern Pakistan, Journal of Seismology, 13, 387–398.
16) Shibuya, S., Mitachi, T. and Tamate, S. (1997): Interpretations of
direct shear box testing of sands as quasi-simple shear, Geotech-
nique, 47(4), 769–790.
ACKNOWLEDGEMENT
17) U.S.G.S. (2005): Magnitude 7.6–Pakistan–2005 October 08 03:50:
This paper summarizes one of the outcomes of the 40 UTC, http://earthquake.usgs.gov/earthquakes/eqinthenews/
MEXT Research Project, ``Scientiˆc surveys for long- 2005/usdyae/
18) Water and Power Development Authority, Government of
lasting geotechnical problems caused by large earth-
Pakistan, WAPDA (2006): Study of Hattian Ballah Landslide,
quakes and their implementations for rational rehabilita- Potential Hazards of Land Sliding and Mitigation Measures at Hat-
tion strategies'', Konagai K. Leader of the project, 2008 tian Ballah and Other Earthquake Hit Area.
Grant-in-aid for scientiˆc research (A) No. 20254003. 19) Wu, P. K., Matsushima, K. and Tatsuoka, F. (2008): EŠects of
The authors would like to express their sincere gratitude specimen size and some other factors on the strength and deforma-
tion of granular soil in direct shear tests, Geotechnical Testing
to DAM (Development Authority MuzaŠarabad), ERRA
Journal, ASTM, 31(1), 45–64.
(Earthquake Reconstruction and Rehabilitation Authori-

You might also like