Download as pdf or txt
Download as pdf or txt
You are on page 1of 265

Bentec Document No.

: EU 5-MC-PR-01-00
Issue
Bentec Project No.: B-05272 / 900663 01

CONTRACT TITLE

350 to Bentec AC Drilling Rig

For

DAFORA SA

DOCUMENT TITLE

Commissioning Documentation

Document No.: EU5-MC-PR-01_Rev. 04

04 Converted E IV GW Jan. 09
03 Converted E III GW Oct.02
02 Converted EII GW Aug.08
01 Updated GW GNK Aug.08
00 Issue GW Jul: 08

ISSUE ISSUE OR REVISION BY CHECK APP'D BY DATE APP'D BY DATE


REV. DESCRIPTION BENTEC BENTEC PROJECT CLIENT APPROVAL
ENGINEERING MANAGER
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

Table of Content:

1. Introduction

2. Terminology and Procédures in General

3. Layout Drawing

4. Piping and Instrumentation Diagrams (P&ID's)

5. Responsibilities / nominated personnel

6. Overview of Testing for Main Equipment

7. Mechanical Completion / Commissioning Check Sheets & Acceptance Certificates

8. Commissioning / Testing Time Table

2
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

1. Introduction

The Bentec "350 – t- AC Euro Rig" is a Drilling System designed and engineered to operate
under European conditions. All equipment and materials are in compliance with the current
ISO. DIN, and European standards including the ATEX specification.

The system is designed to be highly mobile; capable of being easily disassembled into truck
package sizes for easy transportation.

The whole package consists of:

- Main Rig Structure Models


- Special Drilling Machinery
- Drilling Instrumentation Package
- Special Drilling Enhanced Equipment
- Power Generation Plant

This comprehensive set of documents will demonstrate "completeness and functionality" of the
assembled and function tested drilling rig.

This document is part of Bentec's overall "Quality Management System".

3
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

2. Terminology and Procedures in General

Factory Acceptance Test (FAT)


The FAT is based on test protocols prepared by the sub-suppliers which might be witnessed
by DAFORA SA. The FAT certificate follows the sub-suppliers standard procedures.
Considering the use of standard drilling equipment – not all sub-suppliers are performing FAT
tests.

Mechanical Completion (MC)


Commissioning activities are based on mechanical completion checks to assure the
completeness of mechanical, electrical and instrumentation installation.
Additionally all required safety systems must be available.
- support structures, platforms, access structures
- safety precautions
- equipment – erection and alignment
- electrical wiring completion
- instrumentation installation completion
- loop check completion
- pressure tests

Cold Commissioning (CC)


Cold commissioning is split in activities first without energizing the equipment and second with
energizing the equipment.
- check of equipment tags and coding (if required)
- check of dimensions, clearness, movements
- check of equipment lubrication
- tests according to sub-suppliers requirements
- rotation testing
- data exchange to the Digital Control System (DCS)
- interlock testing
- functional test as far as possible (mud & high pressure system with water, etc.)

Hot Commissioning (HC)


Hot commissioning is performed under operation conditions as far as possible.
- re-adjustment of mechanical equipment (if necessary)
- adjustment and calibration of instruments and control loops (if necessary)
- vibration-, noise-performance tests under operating conditions as far as possible
- performance checks
- reliability checks
- as-built documentation update

4
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

3. Layout Drawings

• RIG LAYOUT DRILLING RIG : 1-97.98-1035981


• LOAD PLAN : 1-98.03-1039666
• HAZARDOUS ZONE CLASSIFICATION : 1-98.09-1039667

5
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

4. Piping and Instrumentation Diagrams (P&ID's)

• High Pressure Mud System 5000 PSI WP : 1-98.11-1035813


• LP-Mud Flow Scheme : 1-98.11-1035811
• Air Flow Scheme : is being revised
• Hydraulic Flow Scheme Drilling Equipment : is being revised
• Water Flow Scheme : is being revised

6
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

5. Responsibilities / Nominated Personnel

Key personnel for mechanical completion / commissioning and testing

Structural H. Fischer

Mechanical G. Niemeier-Krönke

Mud Systems H. Horstjan

Low & High Pressure Systems H. Horstjan

Electrical C. Klein

Instrumentation C. Klein

Rig Up R. Brüggemann
L. Kalmer
H. Ekelhoff

DAFORA SA can nominate their own responsible commissioning team to follow and
sign off activities as per contract.

7
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

6. Proposal / Test Program for Main Equipment

Please find attached a short list of activities during testing of main equipment (not all
equipment is described in detail)

VFD container FAT at Bentec. Testing and commissioning during rig up


Drawworks FAT at Bentec. Function testing and commissioning during rig-up
HPU Drilling Equipment FAT at manufacturer. Test run during start up of drilling equipment like
cathead, Iron Roughneck and mast raising system.
Cathead Functional test, pull test and commissioning
Rotary table Functional test and commissioning
Utility Winches FAT at manufacturer EMCE
Test run, load test and commissioning during rig up
BOP Lifting Hoists Load test at sub-supplier JDN
Test run without overload during rig up
Rig floor, mast and Functional test and commissioning during rig up
overhead drilling
equipment
Power Generation Plant FAT at manufacturer. Function testing, load testing and commissioning
during rig up period.
Mud pumps FAT at manufacturer. Function testing, load testing and commissioning
during rig-up
Mud System Assembling, function testing and commissioning during rig-up period.
Electric motors Installation, testing and commissioning
Mechanical equipment Installation, testing and commissioning

8
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

7. Mechanical Completion / Commissioning Check Sheets & Acceptance


Certificates

This chapter includes the different MCC-check sheets for the main equipment. Also the
acceptance certificates which have to be signed off by DAFORA SA. and Bentec are included.
Therefore DAFORA SA has not to sign off each individual activity shown in MCC-check
sheets.

The following MCC-check sheets are attached:

No. Section Description


1000 Main Rig Structure
01 1001 A Rig Structure
02. 1000,10001N Derrick and Substructure
03 1001 Mast Telescoping System
04 1111 Casing Stabbing Board
05. 1001 Mast Telescoping System
06 1001 I BOP Frame 13-5/8”
2000 Drilling Equipment installed in section 1000
07. 2001 Draw Works
08. 2002 Rotary Table
09. 2003 Traveling Block
10. 2004-A Drill Line Reel
11. 2005 Hydraulic Power Unit
12 2006 Top Drive System
13 2007 Spin Torue
14. 2008 Drill Floor Winch A
15. 2008 Drill Floor Winch B
16 2008 A Man Riding Winch
17 2009 Hydraulic Cathead
18. 2010 Monkey Board Air Hoist
19 2010 A Wireline Unit
20. 2011 Dead Line Anchor
21. 2012 Mast Telescoping Winch A
22 2013 Catwalk Winch
23. 2012 Mast Telescoping Winch B
24 2015 BOP Air Hoist A
25 2015 BOP Air Hoist B
26. 2016 Crown Block
3000 Power Equipment
27 3001 Main Generator Plant
28 3001 A Emergency Generator Set
29 3002-A Grass Hopper system
30 3003-5 Air Compressor System
4000 Mud System
31 4000 Mud Tank System
32 4001-A Emergency Shower

9
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

33 4003 Mud Agitators


34 4004 Desander Pump
35 4004 Desilter Pump
36 4004 Mixing Pumps 1 & 2
37 4004 Triptank Pump
38 4005 Mud Charging Pumps
39 4008 Shale Shaker Package
40 4011 Mud Gas Separator
41 4012 Vacuum Degasser

42 5002 Fuel Storage / Distribution System

43 9001 Triplex Mud Pumps

44 9002 High Pressure Mud System

10
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrick and Substructure

Discipline Electrical Mechanical Structural Piping No. 1000,1001A-N


SCOPE OF ACCEPTANCE

Operation and System of Derrick and Substructure (inkl. Accessories)

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast equipment


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP frames for 13-5/8" and / or 21-1/4" BOP

Discipline Electrical Mechanical Structural Piping No. 1001 I / 17003


SCOPE OF ACCEPTANCE

Operation and System of BOP storing frames

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the BOP storing frames, equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping System

Discipline Electrical Mechanical Structural Piping No. 1001


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Erection System equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rig Structure

Discipline Electrical Mechanical Structural Piping No. 1001 A


SCOPE OF ACCEPTANCE

Operation and System of Rig Structure (inkl. Accessories)

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of Rig Structure modules


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Casing Stabbing Board

Discipline Electrical Mechanical Structural Piping No. 1111


SCOPE OF ACCEPTANCE

Operation and System of Casing Stabbing Board

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the installed Casing Stabbing Board, equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORE
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drawworks

Discipline Electrical Mechanical Structural Piping No. 2001


SCOPE OF ACCEPTANCE

Operation and System of Drawworks

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Drawworks equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rotary Table

Discipline Electrical Mechanical Structural Piping No. 2002


SCOPE OF ACCEPTANCE

Operation and System of Rotary Table

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Rotary Table equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Traveling Block

Discipline Electrical Mechanical Structural Piping No. 2003


SCOPE OF ACCEPTANCE

Operation and System of Traveling Block

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Traveling Block equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drill Line Reel

Discipline Electrical Mechanical Structural Piping No. 2004A


SCOPE OF ACCEPTANCE

Operation and System of Drill Line Reel

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Drill Line Reel equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Hydraulic Power Unit

Discipline Electrical Mechanical Structural Piping No. 2005


SCOPE OF ACCEPTANCE

Operation and System of Hydraulic Power Unit

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HPU "Drilling Equipment" equipment and operation has
been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Top Drive

Discipline Electrical Mechanical Structural Piping No. 2006


SCOPE OF ACCEPTANCE

Operation and System of Top Drive

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Top Drive equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Spin Torque

Discipline Electrical Mechanical Structural Piping No. 2007


SCOPE OF ACCEPTANCE

Operation and System of Spin Torque

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Iron Roughneck equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.1

Discipline Electrical Mechanical Structural Piping No. 2008


SCOPE OF ACCEPTANCE

Operation and System of Drillfloor Winch No.1

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the Drill Floor Winch No.1, equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora sa


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.2

Discipline Electrical Mechanical Structural Piping No. 2008


SCOPE OF ACCEPTANCE

Operation and System of Drillfloor Winch No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all the Drill Floor Winch No.2, equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Manriding Winch

Discipline Electrical Mechanical Structural Piping No. 2008A


SCOPE OF ACCEPTANCE

Operation and System of Manriding Winch

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Manriding Winch equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Cathead

Discipline Electrical Mechanical Structural Piping No. 2009


SCOPE OF ACCEPTANCE

Operation and System of Cathead Serial No. 022

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Cathead equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrickman Hoist

Discipline Electrical Mechanical Structural Piping No. 2010


SCOPE OF ACCEPTANCE

Operation and System of Derrickman Hoist

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the Derrickman Hoist, equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Wireline Unit

Discipline Electrical Mechanical Structural Piping No. 2010-A


SCOPE OF ACCEPTANCE

Operation and System of Wireline Unit.

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Wire Line Unit equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Dead Line Anchor

Discipline Electrical Mechanical Structural Piping No. 2011


SCOPE OF ACCEPTANCE

Operation and System of Dead Line Anchor.

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Dead Line Anchor equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch

Discipline Electrical Mechanical Structural Piping No. 2012


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping Winch A

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Telescoping Winch A equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch

Discipline Electrical Mechanical Structural Piping No. 2012


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping Winch B

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Telescoping Winch B equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Catwalk Winch

Discipline Electrical Mechanical Structural Piping No. 2013


SCOPE OF ACCEPTANCE

Operation and System of Catwalk Winch

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Catwalk Winch equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist

Discipline Electrical Mechanical Structural Piping No. 2015


SCOPE OF ACCEPTANCE

Operation and System of BOP hoist A

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP hoist equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist

Discipline Electrical Mechanical Structural Piping No. 2015


SCOPE OF ACCEPTANCE

Operation and System of BOP hoist B

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP hoist equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Sets #1 - #3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Set No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Set No.3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Generator

Discipline Electrical Mechanical Structural Piping No. 3001A


SCOPE OF ACCEPTANCE

Operation and System of Emergency Generator

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Emergency Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System

Discipline Electrical Mechanical Structural Piping No. 3003,3004,3005


SCOPE OF ACCEPTANCE

Operation and System of Air Compressor System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Air Compressor equipment and operation has been carried out

2.) Function test has been witnessed by: DAFOR A SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System

Discipline Electrical Mechanical Structural Piping No. 3003,3004,3005


SCOPE OF ACCEPTANCE

Operation and System of Air Compressor No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Air Compressor equipment and operation has been carried out

2.) Function test has been witnessed by: DAFOR A SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Tank System

Discipline Electrical Mechanical Structural Piping No. 4000


SCOPE OF ACCEPTANCE

Operation and System of Mud Tank System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Tank System equipment


has been carried out
2.) Function test has been witnessed by: Dafors SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Shower

Discipline Electrical Mechanical Structural Piping No. 4001E


SCOPE OF ACCEPTANCE

Operation and System of Emergency Shower

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.1 Degasser tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.10: Reserve tank No.1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.11: Reserve tank No.1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.12: Reserve tank No.2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.13: Reserve tank No.2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.2 Desilter tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.3 Desilter tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.4 Suction tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.5 Suction tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.6 Mix tank 2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.7 Mix tank 1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.8 Intermediate tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.9 Intermediate tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump B

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump C

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump A

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafors SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desander pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desilter pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump A

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump B

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Triptank pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Jardboranir
Dafors SA

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Mud cleaner

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Shale shaker No.1

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Shale shaker No.2

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Gas Separator

Discipline Electrical Mechanical Structural Piping No. 4011


SCOPE OF ACCEPTANCE

Operation and System Mud Gas Separator

As per attached: Completion & Commissioning Records


COMMENT. Mud Gas Separator

1.) Successful testing of all installed Degasser equipment and operation


has been carried out
2.) Function test has been witnessed by: Darfora
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Degasser

Discipline Electrical Mechanical Structural Piping No. 4012


SCOPE OF ACCEPTANCE

Operation and System of Degasser

As per attached: Completion & Commissioning Records


COMMENTS Rotary degasser

1.) Successful testing of all installed Degasser equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Fuel Distribution System

Discipline Electrical Mechanical Structural Piping No. 5002A


SCOPE OF ACCEPTANCE

Operation and System of Fuel Distribution System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.1

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud System

Discipline Electrical Mechanical Structural Piping No. 9002


SCOPE OF ACCEPTANCE

Operation and testing of High Pressure Mud System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Piping System equipment


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
Commissioning Check Sheet

Rig Substructure
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client Darfora Date 06-09-2008 of
File Name 1000 A- Rig Substructure.doc Originator GW 3

Description: Rig Substructure


Section: 1001A
Manufacturer: BENTEC GmbH Type: 350 to Land Drilling Rig
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The rig structure is a box to box system. This system can be
delivered in the required height to meet the customer’ s
requirements When required, the sub structure can be fitted on a
skidding mat.
The main dimensions of the standard sub structure are:
Drill floor height……………9.000 mm
Lifting height under RT……7.400 mm
Beam………………………..11.000 mm
Long…………………………11.000 mm
The sub structure has been designed for simultaneous loading of
casing and drillpipe. Quick connections between the boxes and
beams are easily accessible

1.0 Equipment Documentation, Completeness Verification


Review the manufacturer’s documentation, equipment data and
1.1
specification.
Confirm that relevant drawings of the structure are available.
1.2 Review the filing system of the sub structure drawings and confirm
possible additions as per contract.
Check that the sub structure has been assembled as per the
1.3
available drawings

2.0 Factory Acceptance Test & Site Acceptance Test.


2.1 Not Applicable

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Verify that all handrails, ladders and gratings are complete and
3.2
secure.
3.3 Verify that all open ladder voids and landing areas are protected.
3.3 Verify that all loose equipment has been removed.
3.4 Inspect all ladder steps for damages, defects or unsafe items
Verify that all ladders above 2 meters have safety device or anti-
3.5
fall device if not side-stepped.
Commissioning Check Sheet

Rig Substructure
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client Darfora Date 06-09-2008 of
File Name 1000 A- Rig Substructure.doc Originator GW 3

Visually inspect all connecting bolts, nuts and washers for


3.6
accessibility, damage, corrosion etc.
Visually inspect all sections of the structure for paint damage or
3.7
other defects.
Visually inspect coaming strips and drain facilities in each
3.8
compartment
Visually inspect equipment and piping in each compartment.
3.9
Check for proper fastening and installation
Visually inspect (air) valves and hoses. Can all valves accessible
3.10
and can they be operated
Inspect all hydraulic hoses for fastening, damage and proper
3.11
bending radius

4.0 Electrical Installation Verification


Check that all cables are supported in trays or are suspended on
4.1
hooks
Visually inspect bulk head penetrations. Have proper glands and
4.2
other components been used.
4.3 Check the bonding strips in each structure box.
Inspect all junction boxes, starters and electrical appliances for
4.4
condition and marking.

5.0 Internal Inspection


Lower base box on surface, driller side
5.1 11.0 meter x 2.5 meter x 3.1 meter
Visual inspection and recording of defects
Lower base box on surface, off driller side
5.2 11.0 meter x 2.5 meter x 3.1 meter
Visual inspection and recording of defects
Intermediate box, drillers side
11.0 meter x 2.5 meter x 3.1 meter
5.3
The HPU is installed in this box. Visual inspection and recording
of defects
Intermediate box, off drillers side
11.0 meter x 2.5 meter x 3.1 meter
5.4
The trip tank and Trip tank pump are installed in this box. Visual
inspection of all sections and recording of defects
5.5 One set of 5 rig floor sections
Drill floor section one: 11 m x 1.25 m x 2. 8 m
5.6
Visual inspect connecting bolts. Record damage or defects.
Drill floor section two: 11 m x 2.5 m x 2.8 m
5.7 Visual inspect all sections, connecting bolts etc.. Record damage
or defects.
Drill floor section three: 11 m x 2.5 m x 2.8 m
Fittings for drillers cabin.
Hast supports, mouse hole, rotary table, tong posts, one set of
5.8
rotary beams, support for ST 80
Visually inspect all sections, connecting bolts etc. Record
damage and / or defects
Drill floor section four : 11 m x 2.5 m x 2.8 m
5.9
With provisions for Bentec 1500 AC draw works, mast support and
Commissioning Check Sheet

Rig Substructure
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client Darfora Date 06-09-2008 of
File Name 1000 A- Rig Substructure.doc Originator GW 3

mast raising winches


Visually inspect all sections, connection bolts etc. Record damage
and / or defects
Drill floor section five: 11 m x 2.25 m x 2.8 m
Drill floor area.
5.10
Visually inspect all sections, connecting bolts etc. Record
damages and defects.
Visually inspect the wind wall around the drill floor. Height is 5
meters Insulation is mineral wool with plastic liners. Inside
5.11
covered by stainless sheeting, outside is steel painted in rig
colour. Inspect for proper installation, damages and / or defects
Inspect both stairs from ground floor to rig floor. Visual inspect
5.12
steps, hand rails and general structure.
Visually inspect both trolley beams for the BOP hoists. Capacity
5.13 of each beam is 40 MT: Inspect fastening bolts and washers.
Check that beams are straight and evenly spaced.
Visual inspect the cat walk and pipe racks. Catwalk of two
sections of 7.5 m x 9.9 m, height of 0.33 m and beam of 1.4 m.
5.14
Eight pipe racks of 6 m long, 0.33 m high and 0.16 m wide.
Inspect for mechanical defects / damages, paint etc..
Commissioning Check Sheet

Derrick and Substructure


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 1000,1001A-N_Derrick and Substructure.doc Originator GW 4

Description: Derrick and Substructure


Section: 1000, 1001A-N
Manufacturer: BENTEC GmbH Type: 350 to Land Drilling Rig
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
1.2 Review the system’s class authority and statutory certification.
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


GENERAL
Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify that all handrails, ladders and gratings are complete and
3.2
secure.
3.3 Verify that all open ladder voids and landing areas are protected.
3.3 Verify that all loose equipment has been removed.
Verify that a bumper frame is fitted to the crown block cluster, is
3.4
suitable for purpose and has a steel cage and safety sling attached.
Verify that all ladders above 2 meters have safety device or anti-fall
3.5
device if not side-stepped.
Verify the fast-line and deadline does not touch any derrick
3.6
members.
Verify the fast-line stabilizer is properly assembled and wire rope
3.7 and sheaves are free to operate with no binding or interference with
other structures.
Verify that all auxiliary equipment sheaves are of the correct
3.8
capacity and radius for the line installed.
Verify that safety wires are correctly installed so that the line is
3.9
captured if the sheave fails.
Commissioning Check Sheet

Derrick and Substructure


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 1000,1001A-N_Derrick and Substructure.doc Originator GW 4

Verify the name identification plate are mounted at the derrick and
3.10
substructure.
3.11 Verify that toe boards are fitted to overhead walkways.
3.12 Verify that all piping is properly secured and clamped appropriately.
Ensure all derrick-mounted sheaves are fitted with grease lines and
3.13
run in a manner to allow easy maintenance access.
Visually inspect all pin / hole connections. Check that the fitting is
3.14
acceptable (maximal gap is 1/8”)
3.15 Check that safety pins / clips are fitted to all pins
Carry out a thorough inspection of the substructure, the telescoping
3.16 system with its wire lines, sheaves, lifting eyes and connecting
points.
3.17 Verify all high pressure lines are adequately secured.
3.18 Verify that service loops are fitted with safety slings.

Performance Acceptance Testing.


The derrick and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
3.19
installation drawing / procedure. All equipment shall be permanently
mounted.
Verify during commissioning of the various items of drilling
equipment; the workability of the derrick, substructure, all derrick
3.20
and substructure mounted systems. Note that this also includes the
cantilever’s raising system.
Verify satisfactory operation of the following derrick mounted
3.21
equipment:
3.22 1. Fast Line Stabilizer. (if installed)
3.23 2. Tong Counter Weights and tong lifting system.
3.24 3. Derrick Mans Escape Device (As per manufactures procedures).
4. Operate all self closing doors, bars, gates or safety closure
3.25
chains as required.
5. Function test Monkey Board, fingers, locking devices, its
3.26 winches and verify for suitable operation and arrangement for
intended purpose.
3.27 6. Function test the climbing devices at the mast ladders
Check the visibility of all items of equipment the driller and a/driller
3.28
will need to monitor with the CCTV system.
Derrick Lighting:
3.29 Check the lighting has been installed as per installation drawings.
Check that each fitting has been installed as per drawing. Mark off
on the attached drawings.

3.30 Note whether an aircraft warning and clearance light is fitted at the
crown.
Note that fittings in Hazardous Areas must be properly rated for use
in that zone.
Ensure each fitting is undamaged and has a safety sling which is
3.31
secured to a permanent beam or structure.
Commissioning Check Sheet

Derrick and Substructure


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 1000,1001A-N_Derrick and Substructure.doc Originator GW 4

3.32 Apply power to the derrick lighting and ensure all units are operating.
Ensure that all pneumatic pipework and hoses are correctly installed
3.33 and connected to the equipment interfaces. Check all air valves and
quick connections on the Rigfloor and Substructure
Ensure that all water pipes are correctly installed and the valves are
3.34
operated.

Night time checks:


Inspect all work areas in the derrick at night and ensure they are
3.35
adequately lit to enable safe operations.
Operate the CCTV system at night while observing the monitors and
3.36 ensure no lights are shining directly into the camera causing loss of
visibility.
Check the visibility of all items of equipment the driller and a/driller
3.37
will need to monitor with the CCTV system.
Check and confirm that the identification in the distribution panels to
3.38
each derrick lighting supply circuit is correct.

4.0 Electrical Installation Verification.


GENERAL
Verify that all cables for the derrick auxiliary equipment and the
4.1 starter boxes are properly and securely installed on cable trays or
fixed in a proper manner.
4.2 Confirm operation of helicopter warning light on the water table
Verify that the electrical equipment is adequately protected for short
4.3 circuit, overloading and against accidental contact with live
conductors.
Confirm the junction boxes, terminal boxes and controls are properly
4.4
identified.
Ensure that the cable glands of the terminal and junction boxes are
4.5
properly installed and the cables correctly terminated.
Ensure that all electrical cables have been checked for continuity
4.6
and are properly and adequately identified.
Confirm that the electrical cables and equipment electrical integrity
4.7
have been verified by means of an insulation test.
4.8 Check the direction of rotation of electric motors, where applicable.
4.9 Verify that the electrical equipment is properly earthed / bonded.

Data and Details.

Remarks:
Commissioning Check Sheet

Derrick and Substructure


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-2008 of
File Name 1000,1001A-N_Derrick and Substructure.doc Originator GW 4

Others:
Commissioning Check Sheet

BOP Transport Frame


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client Darfora Date 07-08-2008 of
File Name 1001 I_BOP frame 13.62.doc Originator GW 3

Description: BOP Transport Frame 13-5/8” BOP


Section: 1001 I
Manufacturer: Bentec Type:
Date of
2008 Serial No.:
manufacture:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The BOP transport frame is a L shaped frame equipped with a set
of rollers and a test stump. This frame has been designed to
handle the 13-5/8” BOP consisting of one double and one single
ram type preventer, and one annular type preventer The frame
can be moved mechanically. When fitted on the frame, the BOP is
secured by a front beam that is connected to the frame by pins.
The transport frame is equipped with a ladder to the working
platform where there is access to these pins.
The 10,000 psi test stump has a BX 159 ring groove and a welded
on 4-1/2” IF box for the test joint. One test port for the test pump
connection and one open hole for leak indication of the test joint
are machined in the test stump. Lifting lugs (2 x ) must be fitted
directly on the preventer
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
3.2 Inspect unit for possible transportation damage
Inspect the locking pin and safety pins of the front beam / frame
3.3
connection.
Visually inspect the welds on the frame, front beam and lifting lugs
3.4
for flaws
Visually inspect the condition of preservation and paint. Look for
3.5
damages or imperfections
Commissioning Check Sheet

BOP Transport Frame


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client Darfora Date 07-08-2008 of
File Name 1001 I_BOP frame 13.62.doc Originator GW 3

When possible, manually rotate the rollers under the transport


3.6
frame. Look for any damages
3.7 Confirm that the rollers have been greases
Visually inspect the test stump
3.8
Inspect the BX groove and feel for any damages
Confirm the the BX groove is well conserved and protected
3.9
against impact or mechanical damages.
Visually inspect the thread in the welded on DP box. Confirm that
3.10
the threads are undamaged and have been preserved
Confirm that a thread protector has been installed in / over the DP
3.11
box.
Inspect the test hole and confirm that the internal port is clean and
3.12
not blocked. (1/2” API)
Inspect the open hole and confirm the the internal port is clean
3.13
and not blocked. (1/2” API)
Inspect the test hose connection for damages and proper pressure
3.14
rating of connectors (when fitted)
3.15 Visually inspect the studs and nuts for the test stump connection.

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


When available, mount the BOP on the frame and check seating
5.1
and securing of BOP to the frame
Fit the BOP and frame under the RT, connect the BOP hoists to
5.2
the lifting lugs on the BOP and lift the BOP and frame
Transport the BOP and frame a few meters till under the RT:
5.3 Reverse the operation and move the BOP and frame to its storing
location.

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1 destination and before operation) and perform a pressure test on
the BOP to full working pressure.
6.2
Others:
Commissioning Check Sheet

BOP Transport Frame


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client Darfora Date 07-08-2008 of
File Name 1001 I_BOP frame 13.62.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Mast telescoping System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-072008 o
File Name 1001_Mast Telescoping System.doc Originator GW 3

Description: Mast Telescoping System


Section: 1000
Manufacturer: BENTEC GmbH Type:
Serial
Date:
No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The mast raising / lowering system is done by operating an
electric remote panel. This panel is fitted with an electrical
cable, a long hose and a plug. This plug must be plugged into
a socket that is located next to the HPU.
On the remote panel are two joysticks (Driller Side and Off
Driller Side) that control the two hydraulic winches in the box
structure of the rig. The wires on this winch drum are
connected to the lower mast section via deviation sheaves
and snatch blocks. Load indicators are fitted between the
wire end and the connection point. The load signal is
transferred to load indication recorders at the DS and ODS
via high-pressure hydraulic lines. For both sides a stainless
suitcase with pressure measuring devices (load indicator and
recorder) is available
1.0 Equipment Documentation, Completeness Verification
For the remote panel (1x) and the pressure monitoring
suitcase (2x)
Review the manufacturer’s documentation, equipment data
1.1
and specification.
Review the system’s class authority and statutory
1.2 certification. (As and when required, such as API, NACE,
IEEE, ANSI, ATEX.)
Check that all relevant instruction manuals, workshop
1.3
manuals and spare parts manuals are on file onboard the
installation.
Review calibration certificates for: pressure recorders in the
suitcases, the load cells in the mast and the load indicator
gauges on the remote panel and in the suitcase

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance
2.1 documentation, and confirm the unit has been released for
installation.
Review and amend the equipment acceptance and
2.2 performance tests. (As required) Note: Testing of Erection
lines has been done

3.0 Mechanical and / or Structural Completion Verification


3.1 Ensure all relevant personal protection equipment and
Commissioning Check Sheet

Mast telescoping System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-072008 o
File Name 1001_Mast Telescoping System.doc Originator GW 3

procedural requirements have been satisfied prior to


accessing the equipment. This may include, but is not limited
to, lockout / tag-out, ventilation, work permits and safety
barriers.
Remote control
Check the location and condition of the socket for the remote
3.2
panel plug. Should be next to the HPU unit
Inspect the condition of the plug, cable and remote panel for
3.3
damage and completeness
Confirm indications and markings on the remote panel:
Two control handles for winches (DS and ODS hoisting and
lowering)
3.4
Two control lamps for DS and ODS winches
Tow pressure indicators in % from 0 to 100
One Emergency Stop button
3.5 Fit the plug in the socket and see if it is lined up and fitting
Load indication and sheaves
Check availability and location of the two suitcases with
3.6 pressure monitoring equipment.
Check for damages
Inspect the load indicator gauge and pressure recorder for
3.7 condition
Start pressure recorder and confirm that it turns
Visually inspect the hydraulic hose and the connection from
3.8
the suitcase
Check the condition of the sheaves & erection lines for
3.9 damage, cracks, and ensure the sheave profile is correct.
Ensure that the sheaves rotate freely.

3.10 Check installation and condition of the load cells in the mast

Visually inspect the shackle for the wire / mast connection.


3.11
Inspect for condition and locking of separate components.
Particular attention must be given to that all nuts and bolts
3.12 are properly lock wired, and that the grease points are
adequately protected and easy accessible.
3.13 Check lubrication of all rotating equipment

4.0 Electrical Installation Verification.


N/A
Note: when raising or lowering the mast, visually check that
electrical cables will not interfere with moving parts of the
mast

5.0 Pre Commissioning


First stat of winches should be without wires
Start HPU, when running normal, plug in the remote control
5.1
unit and jog start both winches
Commissioning Check Sheet

Mast telescoping System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-072008 o
File Name 1001_Mast Telescoping System.doc Originator GW 3

Confirm direction of rotation and per marking on the remote


panel
Confirm that both indication lamps for “winches on” are
5.2
working
5.3 Test emergency stop button. Both winches should be cut out
When spooling the wire, check operation of both winches and
5.4
indications on the remote panel
5.5 Connect the two suitcases before raising or lowering the mast
5.6 Perform raising / lowering as per operation procedure.
Witness load gauges and pressure recorders for
5.7
discrepancies in indications and read outs.

6.0 Others:
The mast upper section and the mast top section are installed
6.1
with the crane
The mast intermediate section and the mast lower section are
6.2
raised with the erection winches.

Attachments:
Commissioning Check Sheet

Casing Stabbing Board


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DaforA SA Date 10-11--2008 of
File Name 1111_Casing Stabbing board.doc Originator G.W 3

Description: Casing Stabbing Board


Section: 1111
Manufacturer: Bentec Type: CSB-7800-200-AO
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The casing stabbing board is used for guiding casing joints in the
derrick that are connected and made up by the casing tongs on the
rig floor during the process of running casing. Basically the stabbing
board is a work basket that can be moved by an air hoist along a
frame that is fixed in the derrick. The air hoist is fitted to the top of
the frame and connected to the work basket by a chain or hoisting
wire.
The capacity of the basket is max. 2 persons or max. 150 kg. The
air hoist requires a minimum of 6 bar air pressure and a volume of
1500 liters / min. The output of this hoist is 1 Kw. Maximum vertical
travel of the unit is 7.8 meter. Lifting speed with max. load is 5 m /
min and without load 11 m / min. Lowering speed with max. load is
12 m / min.
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Check the installation of the stabbing board for completeness and
3.2
confirm that it is properly supported in the mast.
Commissioning Check Sheet

Casing Stabbing Board


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DaforA SA Date 10-11--2008 of
File Name 1111_Casing Stabbing board.doc Originator G.W 3

Visually inspect all clamps, bolts and nuts. Are they all in good
3.3
condition and properly secured.
Are end stoppers fitted to the guide beams and can they support the
3.4
impact of the falling basket
Check that the board can be safely entered and that a safety belt
3.5
and inertia reel are available and are properly connected.
The Maximum Work Load should be clearly displayed at the
3.6
stabbing board.
Is the stabbing board fitted with a two brake system. One free fall
3.7
brake and one parking brake.
3.8 The hoisting chains must be lubricated before starting operation
3.9 Check that the hoist hook is equipped with a safety latch

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


Verify that there is an emergency stop fitted which shut off the air
5.1 supply to the hoist. The emergency stop should be installed as close
as possible to the operator.
5.2 A load test of 125 % ( 250 kg) must be performed
5.3 Test the emergency stop of the air hoist
Test the upper limit switch of the air hoist. The air should be cut off
5.4
and only lowering should be possible.
Test the operation of the folding board on the stabbing board. Can it
5.5
be securely locked in the retracted position.
It the stabbing board of one of its components implemented in the
5.6
ACS. When this is required, it must be tested.
5.7 Test the board anti fall system
5.8 Test the board parking brake system

Operation
5.9 Raise and lower the board several times
Confirm that, when required, the operator can abandon the basket at
5.10
any position.

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Notes:
01 SWL to be displayed at the stabbing board
Both control hoses for remote units to be stored in a proper way
02
during operation of the board.
Commissioning Check Sheet

Casing Stabbing Board


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DaforA SA Date 10-11--2008 of
File Name 1111_Casing Stabbing board.doc Originator G.W 3

Attachments:
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Description: Drawworks
Section: 2001
Manufacturer: Bentec Type: DW-E-1500-AC-1 3/8
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
An electric driven draw works type E-1500-AC with a power input of
2 x 600 kW (805 hp)by two AC electric motors in 4 quadrant service.
The draw works, electric motors, gearbox, mechanical brake and the
electro magnetic brake are all fitted on a common steel skid.
Technical details:
Output power is 1100 kW, drilling line is 1-3/8”.
Fitted with a 2 speed gear box, max. pull in low gear is 389 kN or 40
mt. Max. hook speed in high gear is 18 m/sec. The maximum hook
load with 8 wires is 284 mt, with 10 wires this is 352 mt. The total
weight of the unit is 45 mt.
The draw works is equipped with a regenerative braking system, a
Bentec type air cooled EB 5032, a type EB 6032 A electromagnetic
brake and a “failsafe” air operated mechanical disc brake. This disc
brake is air cooled and can only be used for parking brake and
emergency brake. All brake systems are incorporated in the Anti
Collision System (ACS)
The main motors can be used in the feed-off mode.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
1.2 Check that all operation manuals, workshop manuals are on file
onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Procedure as per BENTEC document 9843
Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements are in place prior to accessing the equipment. This
3.1
may include, but is not limited to, lockout / tag-out, ventilation, work
permits and safety barriers.
3.2 Physically check for any transportation damage.
Carry out an internal inspection of the drawworks prior to start-up.
3.3 Check the condition and installation of couplings, clutches, bearings,
shafts.(Visual)
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Check air system connections for proper tightness, and check for
leaks when the respective systems are charged.
3.4
Required is a minimum of 300 ltr/min. with min. pressure of 7.5 bars
and max. pressure of 8.5 bars.
Operate all valves (manual and remote) and verify free movement,
3.5
and the valves are easily accessible.
Check the skid installation and verify that it is properly secured to the
3.6
substructure.
Verify the air supply for the drawworks blowers is drawn from a non-
3.7
hazardous area.
3.8 Check the blower motor ducting.
Confirm proper spooling of the drill line, the drill line should be well
3.9
clear of derrick mounted obstacles and the derrick structure.
Check the condition and length of the drill line. Confirm that the drill
3.10
line carries proper and valid documentation.
Check that the drill line anchoring mounting point on the drum is
3.11 properly installed, that the bolts and nuts are sufficiently torqued and
secured.
Check that at least 12 wraps are left on the drum with the elevators
3.12
at the Rig floor level.
Check the condition of the lebus grooved drum, the kick plates on
3.13
the drum and the drill line kick back rollers.
3.14 Check that all guards are in place and properly secured.
Check that the oil sump is clean and that the condition of the oil is
3.15
acceptable.
3.16 Remove the strainer, inspect, clean and re-install this.
3.17 Check for proper and secure installation of the lubricating oil pumps.
3.18 Check disc brake, for proper and secure installation.
3.19 Check operation of friction brake by applying and releasing of air
3.20 Check operation of HIGH and LOW gear and Feed Off switching.
3.21 Check electromagnetic brake for proper and secure installation..
3.22 Check electromagnetic brake air cooling system.

4.0 Electrical Installation Verification.


Verify that the supply cables to the main AC motors and the auxiliary
4.1
AC motors are properly connected.
Inspect all the motor cable entries and the junction box cable entries,
4.2
for proper sealing and for correct termination.
4.3 Ensure that all electrical cables have been checked for continuity.
Confirm that all electric motors and the electrical cables electrical
4.4 integrity has been verified by means of 1000 volt insulation
resistance test.
4.5 Check the size and connections of the earth / bonding straps.
Ensure that all AC motors are properly and securely mounted, that
4.6 the attached motor junction boxes are tightened up and sealed, and
that all covers are in place.
Start all auxiliary AC motors and positively confirm the direction of
4.7
rotation. Verify for correct amperage.
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Start the main AC motor cooling fans and positively confirm the
4.8
direction of rotation of the fans.
4.9 Confirm operation of the anti condensation heaters in the AC motors
4.14 Verify the correct operation of the motor ‘Lockout” switches.
Verify that at AC motor overpressure loss an alarm is initiated. The
assignment and controls remain active, until the throttle is set for
4.15 zero. Verify that AC motors can only be started after return of
overpressure and system reset. (As per the European standard EN
50016, the unit will not shut down at loss of purging).
4.16 Verify the proper operation of the gear oil low level alarm.
Check electromagnetic brake for proper and secure electrical
4.17
installation.
Energize electromagnetic brake with 250V DC and measure brake
4.18
current for all four coils.

5.0 Commissioning
The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned and installed
5. 2 properly. All cables and systems shall be tested for continuity,
electrical integrity (1000 volt) and have been released for service.
Check that couplings and bushings have been greased according to
the instructions in the service manual
Coupling for electric brake requires approx. 5 kg of grease
Coupling between gearbox & main drum requires 1.5 kg of grease
Gear box
Visually inspect gear box for damages, leaks or other defects
Inspect pneumatic piping, hoses and equipment for damages or
defective connections.
Confirm level in gearbox oil tank. Volume of tank is 370 ltr. Check
level in sight glass to be above mid level
Jog start the two electrical oil pumps and check rotation and delivery
pressure. When OK, maintain oil pressure, check pressure gauge
and check for leaks in hydraulic system
Test operation of low level oil switch. Confirm alarm or tripping of
unit
Confirm operation and read out (alarm) of both flow switches (11) in
the hydraulic system
Test operation and alarm of temperature transmitter (13) in oil
system
Test operation of electric heater (6) in oil tank. Heater should
switch off at 15 C
Check setting of overpressure valve (17) at 3 bars
Test pneumatic gear shift system and confirm operation and signal
of both proximity switches.
Check for noise, vibration and temperatures during test run of
drawworks.
After testing check oil filter and magnet (14)
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Friction brake
Visually inspect friction brake unit for damages
Visually inspect air connections, air vessel and fast exhaust valves
Check air operation of brake unit. Brake is spring set and air
pressure released.
Brake is set at 0 bar and starts opening at 6.5 bar.
Test Emergency Release of the brake as per procedure 6.5 of the
BENTEC operations manual
Check connections and availability of Nitrogen cylinder for activating
Emergency Release System in case of total black-out
Test tripping of draw works due to low air pressure. When air
pressure drops under 7 bars for mote than 5 minutes, the draw
works must trip out.

Electric Eddy Current brake


Visually inspect the electric brake and air cooling system for
damages or other defects.
Confirm direction of operation of the three air cooling fan motors
Inspect filters in air intake of the cooling fans
Run the air cooling fans and check integrity of in – and outlet ducting
Check flow rate of the cooling air fans. Test low flow alarm
Inspect and test temperature transmitter and alarm for the electrical
coils. Maximum allowable air temperature is 60 C
Test the RPM read out of the electric brake in the drillers control
house
Coupling shifter ??
During commissioning / testing of the draw works, check integration
of the Electric brake in the operations brake of the unit.
When dynamic braking, reactive braking of the motors should
increase and dynamic braking of the electric brake (el. current)
should decrease when rpm reduces.

Wire drum system


Check that grease lines to bearings, bushings and couplings have
been fitted and that undamaged nipples are available.
Confirm that all these items have been greased
Check condition and operation of wire kick back spooler.
Witness running of drum with one motor at a time. Check for noises,
vibrations and smoothness of turning
Witness running of drum with the feed-off system
Test all emergency stop buttons (local and from drillers chair) .
Test activation of Emergency Stop system by the following:

Signal loss of high or low gear

Signal loss of feed-off “on” or feed-off “off”


Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Pressure drop in air supply system below 7 bars for more than 5
minutes

ACS alarm signal

Manually operated emergency stops


Test pneumatic gear shifter of feed-off coupling
Test and confirm interlock which prevent feed-off from engaging
when draw works is in operation
Test and confirm starting interlock: when air pressure is below 7
bars, the unit will not start
Test high oil temperature alarm at 80 C
Test high oil temperature trip at 85 C
Test low oil flow trip when oil flow drops below 10 liters/minute
Test low oil level alarm (only works with low motor rpm)

Operational checks without drill line installed


First gear: Run motors in hoisting mode at 520 rpm for 10 minutes
and check drum speed approx 52 rpm
Repeat this in the lowering mode
First gear: run motors at 1000 rpm for 10 minutes and check drum
speed approx. 100 rpm
Repeat this in the lowering mode
First gear: run motors in hoisting mode at 1600 rpm for 5 minutes
and check drum speed at approx. 159 rpm
Repeat this in the lowering mode
Second gear: run motors in hoisting mode at 520 rpm for 10
minutes and check drum speed approx. 115 rpm
Repeat this in the lowering mode
Second gear: run motors at 1000 rpm in hoisting mode for 10
minutes and check drum speed at approx. 221 rpm.
Repeat this in the lowering mode
Second gear: run motors at 1600 rpm in the hoisting mode for 5
minutes and check drum speed at approx. 354 rpm
Repeat this in the lowering mode
Feed-off
Run motor at 100 rpm in hoisting mode for 10 minutes and check
drum speed at 0.16 rpm
Feed-off
Repeat this test in the lowering mode
Feed-off
Run motor at 800 rpm in hoisting mode for 10 minutes and check
drum speed at 0.81 rpm
Feed-off
Repeat this in the lowering mode
Feed-off
Run motor at 1500 rpm in the hoisting mode for 10 minutes and
check drum speed at 1.3 rpm
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Feed-off
Repeat this in the lowering mode
Feed-off
Run motor at 2600 rpm in the hoisting mode for 10 minutes and
check drum speed at 2.4 rpm
Feed-off
Repeat this in the lowering mode

Operational checks with drilling line installed

Very slowly pick up the traveling block, constantly check that the Top
5.6 Drive moves free in the rails. Also check the crown sheaves to
ensure proper reaving, adequate fleet angle and clearances.
Hoist the block towards the crown. Watch for interference between
5.7 the drill line, crown block and service hoses / loops. Solve any
interference problems before proceeding.
5.8 Lower the traveling block down slowly.
Again, slowly hoist the traveling block towards the crown, watching
5.9
for any irregularities. Lower the block down.
Activate and test ACS-System after full commissioning of the
5.10
complete DW-System.

Attachments

Temperature monitoring of draw works gearbox


Item Position Start One Hour After testing
Ambient temperature
Bearings:
Driven shaft (drum side) 1
Idler shaft I (drum side) 2
Idler shaft II (drum side) 3
Drive shaft I (drum side) 4
Drive shaft II (drum side) 5
Drive shaft II (motor side) 6
Idler shaft II (motor side) 7
Driven shaft (motor side) 8
Feed-off idler shaft (motor side) 9
Idler shaft (motor side) 10
Drive shaft I (motor side) 11
Feed-off driven shaft (motor side) 12
Feed-off driven shaft (drum side) 13
Commissioning Check Sheet

Drawworks
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 7
Client DAFORA SA Date 15-07-2008 of
File Name 2001_Drawworks.doc Rev GUS 1.doc Originator GW 7

Feed-off idler shaft (drum side) 14


Oil sump 1 planetary gear 15
Oil sump 2 planetary gear 16
Oil sump gear box 17
Bearing bracket drum (brake side) 18
Commissioning Check Sheet

Rotary Table

Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1


Client DAFORA SA Date 15-07-2008 of
File Name 2002_Rotary Table.doc Originator G:Wijdenes 4

Description: Rotary Table


Section: 2002
Manufacturer: Bentec / Mud King Type: ZP-375
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Check the skid installation and verify that it is properly secured to the
3.2
substructure.
3.3 Verify that all covers and guards are in place.
Verify that the centre of the rotary and the primary drilling hoisting
3.4
equipment is in line.
Check the installation and alignment of the shaft between motor and
3.5 RT. Confirm that the shaft is not touching anything and is well
guarded.
Check oil level in rotary table. SAE90 extreme-pressure gear oil
3.6
should be used.
Verify that the electric motor to proper shaft alignment is correct and
3.7
the motor hub is properly fastened and secured.
3.8 Confirm that the lock pawl pin has been greased. Rotate RT by hand
Commissioning Check Sheet

Rotary Table

Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2


Client DAFORA SA Date 15-07-2008 of
File Name 2002_Rotary Table.doc Originator G:Wijdenes 4

and test operation of manual locking device


Verify that all main hold down and connection bolts and nuts have
3.9
been properly torqued, and secured
Confirm the backlash adjustment of the bevel gears. Should be
3.10
within the 0.34 – 0.68 mm range
4.0 Electrical Installation Verification.
Verify that the supply cables to the AC motors and the blowers are
4.1 of the proper size, run correctly and secured in accordance wit the
relevant regulations.
Inspect the motor cable entries and the junction box cables entries,
4.2 for proper sealing and for correct termination. Also verify that all
terminal connections are tight.
4.3 Ensure that all electrical cables have been checked for continuity.
Start the AC motor cooling fan and confirm the correct direction of
4.4
rotation. Minimum air flow is 1.4 cub.meter/sec
Remove the AC motor inspection cover and check that there is no
4.5
debris in the motor.
4.6 Confirm operation of anti-condensation heater in the AC motor.
Ensure the purge cycle is completed before the RT motor
4.7
assignment is enabled.
Assign the drive motor and open the hand throttle slightly, check the
4.8
motor rotation.
Verify that upon AC blower loss an alarm is initiated, but the
assignment and controls remains available and an alarm sound, until
4.9 the throttle is cycled through “0”, then the power should not come
back to the AC motors. (As per the European standard EN 50016,
the unit will shut down at loss of purging).
4.10 Verify the correct operation of the motor’s ‘Lockout’ switch.
When running, check motor for excessive noises, vibrations and
4.11
temperature

5.0 Cold Commissioning


The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned, and installed
conforming to their legislative requirements. All cables and systems
5.2
shall be tested for continuity, electrical integrity (megger tested) and
have been released for service.
Note: Perform the following operational checks by using the controls
on the driller’s console. It is recommended that this test is
5.3 performed during low activity on rig floor, to avoiding disruptions of
other events around test area. Take the necessary safety
precautions prior to operating the rotary and seal off the area.
5.4 Confirm operation and setting of motor brake
Start and run the table in forward direction at low speed and check
5.5
for any abnormal sounds, vibration or other irregularities. Repeat the
Commissioning Check Sheet

Rotary Table

Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3


Client DAFORA SA Date 15-07-2008 of
File Name 2002_Rotary Table.doc Originator G:Wijdenes 4

exercise in reverse direction.


Verify the calibration of the RPM gauge by manual counting at this
5.6
time.
Check the seal on the pinion shaft assembly when the RT is turning
5.7
and make sure that it is properly sealed
Run the table in forward direction at half speed for 30 minutes and
5.8 then full speed for 30 minutes. Check for any excessive temperature
rise in the bearings and gears
Repeat the above step and carry out the exercise in reverse
direction, at half speed for 30 minutes and then full speed for 30
5.9
minutes. Check for any excessive temperature rise in the bearings
and gears.
Upon completion of the full load test run while the oil is warm,
5.10 inspect the magnetic plug for any metal particles in the oil system
and take an oil sample for analysis.
Verify the calibration of the rotary torque indicator. This can be
5.11
checked against the motor current.
Simulate loss of blower pressure to check the pressure switch. The
5.12 loss of blower pressure should inhibit the assignment but only give
an alarm if loss occurs while the motor is running.
5.13 Specify retest program on production site

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
6.2 Complete open check items of cold commissioning program

Others:

Attachments:
Commissioning Check Sheet

Rotary Table

Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4


Client DAFORA SA Date 15-07-2008 of
File Name 2002_Rotary Table.doc Originator G:Wijdenes 4
Commissioning Check Sheet

Traveling Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2003_Traveling Block.doc Originator GW 3

Description: Traveling Block


Section: 2003
Manufacturer: Bentec Type: TB-400-5-50-1 3/8
Date: 12 / 2008 Serial No.: 0027

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1 02 / 02 GW
specification.
Review the system’s class authority and statutory certification. (As
1.2 02 / 02 GW
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
02 / 02 GW
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1 N/A
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2 N/A
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Inspect for proper mechanical and/or structural completion of the
traveling block & guide dollies and its associated equipment and
supporting systems. This also includes the physical interface with
3.2
other systems and that all requirements and standards are met
(included in this is also the “Becket” type adapter between the block
and top drive).
Check the condition of the sheaves for damage, cracks, and ensure
3.3 02 / 02 GW
the sheave profile is correct. Ensure that the sheaves rotate freely.
Check for proper and secure mounting of the traveling block.
Particular attention must be given to that all nuts and bolts are
3.4 02 / 02 GW
properly lock wired, and that the grease points are adequately
protected and easy accessible.
Confirm that all preservatives have been removed and that the
3.5 02 / 02 GW
assembly is in a clean, good condition.
3.6 Physically check the traveling block for any transportation damage. 02 / 02 GW
Commissioning Check Sheet

Traveling Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2003_Traveling Block.doc Originator GW 3

Visually check that the sheaves are equally spaced and that bearing
3.7 02 / 02 GW
seals are in place

4.0 Cold Commissioning


The assembly and all its associated equipment shall be connected,
fully assembled and adjusted in accordance with their applicable
4.1
installation drawing / procedure. All equipment shall be permanently
mounted prior to startup of the function tests for the traveling block.
Verify that rigging of tong wire lines, tugger wire lines and the like
4.2 has been inspected to ensure that they will not interfere with the
operation of the traveling block & guide dollies.
Ensure that grease have been added to the bearings of the traveling
4.3 02 / 02 GW
block (grease manifold).
After reaving the drill line, ensure that the drill line is clear of the
4.4
traveling block guards.
After reeving of the drill line, very slowly pick up the traveling block
4.5 and constantly. Also check the crown sheaves to ensure proper
reaving and minimal fleet angle and clearances.
Proceed to hoist the block up to the crown. Watch for interference
4.6 between the drill line, crown block and service hoses / loops. Solve
any interference irregularities prior to continue the tests.
Once at the crown, slowly lower the traveling block down and
4.7
continue to check for any irregularities.
Repeat the above two steps with slowly hoist the traveling block to
4.8
the crown, watching for any abnormalities. Lower the block down.
In conjunction with the primary drilling hoisting equipment, verify and
4.9 test the anti-collision system (ZMS), crown saver and floor saver
functions prior to simulated RIH/POH operations.
Carry out an extended run and cycling test (simulate tripping) prior to
and after applying heavy load to the hoisting machinery. Operate the
hoisting equipment with different loads and check for smooth
4.10 operating of the traveling block, its sheaves and the guide dollies.
Check for excessive temperature in the running gear (smell, smoke),
if possible measure temperature of bearings using an extendable
probe.
Carry out a thorough post operational inspection of the traveling
block & guide dollies and its associated equipment upon completion
of endurance test. Check the foundation bolts for proper tightness, to
4.11
see if there is any indication of wear on the sheaves and/or
misalignment of the sheaves due to bearing damage. Also confirm
footprints of the guide dolly wheels.
4.12 Specify retest program on production site

5.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
5.1
destination and before operation)

Others:
Commissioning Check Sheet

Traveling Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2003_Traveling Block.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Drill Line Reel


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-05-2008 of
File Name 2004A_Drill Line Reel.doc Originator GW 3

Description: Drill Line Reel including Drill Line


Section: 2004A
Manufacturer: Bentec Type: DLR-1 3/8-2300-EO
Date: 2007 Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The drill line reel is an electrical driven reel for storage of the 1-
3/8” drill line.
The reel is designed to store 2300 meters of 1-3/8” drill line with a
total weight of 12,400 kg
The OD of he reel drum is 2000 mm, the weight of the empty drum
is 1200 kg and with the storage of 2300 meters of wire, the total
weight of the drum and wire will be 15,600 kg. The weight of the
skid is 2,000 kg.
The drum is driven by a 5.5.kW electric motor through a gear box
with a 1: 86.5 ratio. The controls for operating the reel are located
at the unit
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
3.2 Inspect unit for possible transportation damage
Inspect that the locking pin and retaining chain are in place and
3.3
can be moved
Visually inspect drive chain and chain drive for condition and
3.4
lubrication
3.5 Verify free movement of drum
Check wire rope clamps are properly bolted to drum flange and
3.6
that wire has been spooled in the right direction
Commissioning Check Sheet

Drill Line Reel


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-05-2008 of
File Name 2004A_Drill Line Reel.doc Originator GW 3

3.7 Check drum bearing has been greased


Verify that all transportation locks, lifting pad eyes and eye bolts
3.8
have been removed
3.9 Check free movement of the drum
3.10 Check the control panel. Are all controls identified and marked

4.0 Electrical Installation Verification.


4.1 Electrical wiring is complete
4.2 Instrumentation installation is complete
Check that all equipment is in accordance with the requirements
4.3
for the areas in which the equipment operates.
Ensure that the cable glands of the terminal and junction boxes
4.4
are properly installed and that the cables are correctly terminated
4.5 Ensure that all electrical cables have been checked for continuity.

5.0 Cold Commissioning


With drum empty, operate the reel and check motor controls and
5.1
operation of motor drive
Witness the spooling of wire on the drum. Check for excessive
5.2
noises, temperatures and excessive vibrations
Is the electrical motor powerful enough to pull the wire and rotate
5.3
the storing reel
5.4 Test the locking mechanism of the drum
Witness the reeving of the wire onto the traveling block and draw
5.5 works drum. Check for excessive noises, temperatures and
vibrations

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
6.2 Apply a cover for weather protection of wire and reel unit
Others:
Commissioning Check Sheet

Drill Line Reel


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-05-2008 of
File Name 2004A_Drill Line Reel.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Hydraulic Power Unit


Project No. 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DARFORA SA Date 15-07-2008 of
File Name 2005_Hydraulic Power Unit.doc Originator GW 4

Description: Hydraulic Power Unit


Section: 2005
NHY-630-102-10-140 / 10-
Manufacturer: Bentec/Niehues Type: 37/400-690V-3/400-690V/24V DC
ATEX

Date: 12/2008 Serial No.: 481675

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The HPU is equipped with two electric driven hydraulic pumps for
delivering hydraulic fluid to the consumers and a small hydraulic
pump for the cooling system.
The hydraulic pumps are each equipped with 690V/50Hz electric
motors of 37 kW. Capacity of each pump is 102 l/min at 1450 rpm
and a system pressure of 210 bars. System pressure is maintained
by pressure regulating valves and over pressure safety valves.
Capacity of the oil tank is 630 liters and the tank is fitted with filters,
electrical heaters, a level sight glass and level switches.
The HPU delivers hydraulic fluid to the two mast raising winches, the
hydraulic cat head and the iron roughneck.
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, ATEX etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Physically check the power packs for any transportation damage
3.2 29 / 01 GW
(after arrival on the production sight).
3.3 Walk the hydraulic piping systems and check that all piping is well
Commissioning Check Sheet

Hydraulic Power Unit


Project No. 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DARFORA SA Date 15-07-2008 of
File Name 2005_Hydraulic Power Unit.doc Originator GW 4

supported and protected from mechanical damage, and that no


leaks are present.
Exercise all remote and manually operated hydraulic system valves
3.4 and confirm that they are operating smoothly, without binding and
are easily accessible.
Check that all the hydraulic system valves have been properly and
3.5
correctly identified.
Check whether the setting of the hydraulic system safety valves is in
3.6
accordance with the various connected systems working pressures.
Check whether all piping is colour coded and/or otherwise identified
3.7
at least at each bulkhead penetration.
Check condition of all hydraulic hoses and couplings and confirm
3.8 29 / 01 GW
sufficient pressure rating of the hoses

HYDRAULIC PUMP UNITS


Turn the motor/pump shaft by hand and ensure the pump is running
3.9 29 / 01 GW
freely.
Confirm that the coupling between the AC motors and the pumps
3.10 29 / 01 GW
are adequately protected with guards.
Confirm that the hydraulic system strainers and filters are installed
3.11 29 / 01 GW
and clean.

HYDRAULIC OIL TANKS


3.12 Verify that the oil tanks are adequately sized. 29 / 01 GW
Verify that the oil tanks are equipped with a low-level alarm, which
3.13 29 / 01 GW
should prevent the hydraulic pumps from running dry.
3.14 Verify that the hydraulic oil tanks are equipped with a sight-glass. 29 / 01 GW
Verify that the hydraulic oil tanks have sufficient venting to the open
3.15 29 / 01 GW
air.
Verify that there is a containment dam around the HPU to prevent oil
3.16 29 / 01 GW
spillage or leakage from becoming a safety or environmental hazard
Verify the installation of filters in the delivery and suction lines. Do
3.17 29 / 01 GW
all filters have condition indicators or switches
Verify that the distribution system was flushed with air for cleaning
3.18 29 / 01 GW
and is free of cutting residues.
Confirm proper installation and connection of electrical heaters in the
3.19 29 / 01 GW
tank
3.20 Test emergency stop of the HPU
4.0 Electrical Installation Verification.
4.1 Verify that all I/O checks have been conducted as part of the FAT.
Verify whether all cables to the electric motors and the starter boxes
4.2 29 / 01 GW
are properly and securely installed on the cable tray.
Check that all equipment is in accordance with the requirements for
4.3 29 / 01 GW
the areas in which the equipment operates.
Confirm that the contactors, fuses and cables of the electric motors
4.4 29 / 01 GW
and the control circuitry are of the suitable type and rating.
Ensure that the junction boxes, terminal boxes and controls are
4.5 29 / 01 GW
properly identified.
Commissioning Check Sheet

Hydraulic Power Unit


Project No. 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DARFORA SA Date 15-07-2008 of
File Name 2005_Hydraulic Power Unit.doc Originator GW 4

Ensure that the cable glands of the terminal and junction boxes are
4.6 29 / 01 GW
properly installed and that the cables are correctly terminated.
4.7 Ensure that all electrical cables have been checked for continuity.

5.0 Cold Commissioning


5.1 Check the level and quality of the hydraulic oil 29 / 01 GW
5.2 Check operation of low oil level alarm (at 250 mm) 29 / 01 GW
5.3 Check operation of low oil level trip (at 300 mm) 29 / 01 GW
Confirm operation of electric heaters (minimum temperature is 07C,
5.4 29 / 01 GW
auto switch off at 10 C)
Confirm operation of radiator cooling system (start at 50 C and stops
5.5 29 / 01 GW
at 40 C)
5.6 Test or simulate high oil temperature alarm at 65 C 29 / 01 GW
5.7 Test or simulate high oil temperature trip at 70 C 29 / 01 GW
Test or simulate clogged filter indication alarm of supply filter (pos.
5.8 29 / 01 GW
20)
5.9 Test or simulate dirty filter alarm of return filter (pos.13) 29 / 01 GW
Test or simulate dirty filter alarm of pressure filter in oil cooling
5.10 29 / 01 GW
system (pos 46)
Start up each hydraulic pump and check rotation and pressure
5.11
settings. Delivery pressure is 230 bar, system pressure is 210 bar
When system under pressure, walk all piping and hoses and check
5.12
for leaks.
Run both pumps for one hour minimum and check automatic
5.13
pressure control of the hydraulic system.
N / A This is
Test automatic starting of stand-by pump and low system pressure not a
5.14
alarm standby
function

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
6.2 Confirm operation of hydraulic end consumers
6.3 End consumers to be commissioned independently
Cat head cylinder : 100 liter/min at 140 bar
6.4 Iron Roughneck: 150 liter/min at 140 bar or 105 liter/min at 170 bar
2 x rig up winches: each 95 liter/min at 195 bar
Commissioning Check Sheet

Hydraulic Power Unit


Project No. 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DARFORA SA Date 15-07-2008 of
File Name 2005_Hydraulic Power Unit.doc Originator GW 4

Others:

Attachments:
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

Description: Top Drive System


Deutag Code: 2006
Manufacturer: NOV Type: TDS-11-SA
Date of manufact. 2008 Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
TDS 11 SA:
Part No. M614000512-1. Fitted with PH 50 pipe handler
Gross weight is 30,000 lbs. Maximum RPM = 228
Maximum pressure = 7,500 psi. Power requirements: 700 KVA
@ 575-600 VAC, 50 / 60 Hz.
Fitted with two AC motors of each 400 hp for a continuous
torque output of 37,000 ft lb. Intermittent @stall torque is 55,000
ft lb

1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Check and confirm that all equipment has been installed according
to manufacturer’s specifications and drawings. This also includes
3.2 inspection of proper mechanical and/or structural installation of
ancillary equipment, controls and integrated systems servicing the
TDS.
Inspect during the installation that all requirements and standards
3.3
are met. This also includes the interface with other systems.
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

3.4 Visually check there is no interference with equipment in the mast.


Inspect all connections / bolts to make sure they are secured and
3.5
safety wired as required.
Inspect the auxiliary piping installations and check for adequate pipe
3.6 hangers, hangers bolted up tight, completeness, welding quality and
system tightness.
Verify that the guide rails and bracing have been installed and
3.7 inspected and are within specifications and installation tolerances.
Verify that adequate rail stops have been installed.
Verify that the alignment of the dolly to track and to the RKB centre
3.8
has been confirmed.
Inspect the torque wrench jaw and insure that tong dies are properly
installed and serviceable. Make sure that the torque wrench jaw
3.9
assembly has the correct tong dies for the pipe size to be used in
the operational test segment of this procedure.
Check the clearance between the split load collar and link hanger.
Note! The distance from the top face of link hanger to the tip of the
3.10
“V” hard die stamp on the main shaft shall be 10mm +/- 3, with no
load in the elevator.
Check that the service loops are installed properly and all
connections are checked. Verify that the hoses are properly routed
and supported in the derrick and the TDS.
3.11
Ensure that the loop does not receive any axial torsion or twisting.
The service loop should not exceed the minimum bend radius in any
position of the blocks.
Verify that the service loops and mud hose clear all obstacles, such
as rails stops, stabbing basket, cables and the like over the full travel
3.12
of the TDS. Also check that adequate service loop bracket supports
have been made and fitted.
Verify that the rotary hose has been fitted with proper safety slings
3.13
and clamps
Check that the swivel link retainer plates have been mounted and
3.14
that the bolts have been lock-wired.
Check that the link-tilt stops have been adjusted to clear the racking
3.15
board, and that the bolts have been safety-wired.
Confirm that all top drive grease points take grease and have been
3.16
greased before starting the performance test.
Confirm that the AC motor bearings have been greased before
3.17
starting the performance test.
Confirm that all logic tests have been carried out to simulate top
3.19
drive control and signals prior to testing
Verify that rigging of the tong lines, tuggers etc. has been inspected
3.20 to ensure that they will not interfere with the operation of the top
drive or its related main hoisting equipment.
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

Hydraulic System
Pre charge the System Accumulator (125 cub. Inch) with 800 psi
3.21
Nitrogen at port SA
Pre charge the Counterbalance Accumulator (728 cub.inch) with 900
3.22
psi nitrogen at port CB
Pre charge the Time-delay Accumulator (30 cub.inch) with 800 psi
3.23
nitrogen at port C4
Inspect level of hydraulic fluid through the sight glass @ the
3.24
reservoir. Reservoir capacity is 25 USG (90 ltr)
Check hydraulic oil filter and confirm that the red “pop-up” dirty filter
3.25
alarm has not been activated
Set up the Fixed Displacement (lube) pump as per procedure @ 9-
3.26
18 of TDS manual SM00856
Set pressure of lubricating oil system of 400 psi at port PF by
3.27
adjusting relief valve RV2
Set up the Variable Displacement (hydraulic) pump as per procedure
3.28
@ 9.19 and 9.20 of TDS manual SM00856
Set relief valve RV1 at 2,200 psi and adjust manifold pressure
3.29
setting of UV1 at 2,000 psi
Set up the counterbalance circuit and start jump circuit as per
procedure @ 9-22, 9-24 and 9-25 of TDS manual SM00856
3.30 PRV at counterbalance cylinder at 1,500 psi
PCC to be adjusted to 1,200 psi
Relief valve SJR to be adjusted to 200 psi
Set up the AC motor brake system as per procedure @ 9-26 of TDS
manual SM00856
3.31
Adjustment pressure control reducing valve PC1 to 1,500 psi. This
can be measured at port B1
Set up the Short Pin circuit as per procedure @ 9-27 of TDS manual
SM00856
3.32
Set relief valve pressure at 400 psi. To be measured at port B5
Adjust reducing valve AR5 to 1,000 psi.To be measured at port C5
Set up the Link Tilt cylinder circuit as per procedure @ 9-29 of TDS
3.32 manual SM00856
Correct pressure setting for this system is 1,500 psi
Set up the Rotating Link Adapter hydraulic motor relief circuit as per
3.33 procedure @ 9-30 of TDS manual SM00856
Set the relief valves at the rotation motor at 1,700 psi
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motor and the blower are of
the correct size, run correctly and are secured in accordance with
4.1 the relevant regulations. Conduct a verification of area classification
(Zone I and Zone II) and nameplate verification of the electrical
cables and motors.
Inspect the motor cable entries and the junction box cables entries,
4.2 for proper sealing and for correct termination. Also verify that all
terminal connections are tight.
4.3 Ensure that all electrical cables have been checked for continuity.
Remove the AC motor inspection cover and check that there is no
4.4
debris in the motor.
4.5 Confirm operation of anti-condensation heater in the AC motor.
Ensure the purge cycle is completed before the AC motor
4.6
assignment is enabled.
Verify that upon AC blower loss an alarm is initiated, but the
assignment and controls remains available and an alarm sound, until
4.7 the throttle is cycled through “0”, then the power should not come
back to the AC motors. (As per the European standard EN 50016,
the unit will shut down at loss of purging).
When running, check motor for excessive noises, vibrations and
4.8
temperature
Confirm that any driller’s alarm is repetitive, i.e. if it is accepted and
4.9 further neglected that the alarm horn will sound again after a set
period.
Check that the electrical service loop is installed properly and the
connections are checked. Verify that the cables are properly routed
and supported in the derrick and the TDS.
4.10
Ensure that the loop does not receive any axial torsion or twisting.
The service loop should not exceed the minimum bend radius in any
position of the blocks.
Verify that all terminals are tight and the J-boxes properly closed and
4.11
sufficiently grounded.
4.12 Perform a lamp test on the driller’s console.

5.0 Cold Commissioning


The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned, and installed in
conformance with legislative requirements. All cables and systems
5.2 shall be tested for continuity, electrical integrity (insulation tested)
and have been released for service. All motor control circuits in the
MCCs and SCR systems should already be commissioned.
Check the function of all switches and solenoids prior to turning on
5.3 the hydraulic pressure. There is an audible click when each solenoid
is operated.
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

Pressure up the hydraulic system on the TDS. inspect the system


5.4
and check for leaks.
Setting up and function testing of start-up positions of the
Varco Drillers Console. As per TDS system guide 127425 Rev.B
Test Emergency stop switch and put in the reset position (Pulled
out)
Make-up current limit. potentiometer
VDC 1 The torque can be adjusted by turning the potentiometer to increase
or decrease the torque
Oil press loss. Red indicator
VDC 2 Indicator flashes and horn sounds when an oil pressure loss in the
gearcase lubrication system is detected
VDC pressure loss. Red indicator
VDC 3 Indicator flashes and horn sounds when purge pressure loss in the
drillers console is detected
Drill Motor Over temperature Red indicator
VDC 4 Indicator flashes and horn sounds when one of the two motors
overheats
Drill /Spin /Torque 3-position selector switch
VDC 5
To be tested in FORWARD and RESERVE position
Blower loss Red indicator
VDC 6 Indicator flashes and horn sounds if there is a failure in one or both
of the air cooling motors
Alarm silence / Lamp check Pushbutton switch
When alarm flashes and horn sounds, this function will silence the
VDC 7 horn but light will keep on flashing until fault has been fixed. When
fault is not fixed within 5 minutes, the horn will sound again
When pressed and held for 2 seconds, all lamps on VDC will be lit
Hydraulic power auto / on 2-position switch
VDC 8
When at AUTO, turns on hydraulic pump when commanded by PLC.
When set to ON, turns on hydraulic pump regardless of operating
mode
(Pipehandler) rotate left/right 3-position switch
VDC 9
Moves the drill pipe elevator to left/right. This switch automatically
returns to center (off) position
Note: this works only after the LINK TILT FLOAT switch is pressed
(Pipehandler) link tilt float pushbutton switch
VDC10 The elevator links float to the center (neutral) position when pushed,
enables that the pipehandler can be turned
(Pipehandler) torque wrench push & hold pushbutton switch
VDC 11
When pressed and held, rotates pipe handler to engage slot pin
which will engage pipe clamp
Note: torque wrench cannot clamp with the brake on or throttle open
(Pipehandler) link tilt drill/off/tilt 3-position switch
Set at DRILL: link tilt cylinders retract to place elevators in drill down
position
VDC 12
Set at TILT: link tilt cylinders are extended
Set at OFF: elevators remain in present position until LINK TILT
FLOAT is pushed
Brake on Red indicator
VDC 13
Illuminates when brake solenoid valve is energized
Brake off / auto / on 3-position switch
VDC 14
Set at ON: brake solenoid is energized and lights the BRAKE ON
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

light
Set at Auto: brake is released when THROTTLE is advanced and
brake is set when THROTTLE is turned off
Set at Off: brake is released
Brake will be energized when there is a drive fault with the VFD
regardless of switch position
IBOP closed Amber indication
VDC 15 Lits when hydraulic pressure is applied to the cylinder that closed
IBOP valve
IBOP open / close 2- position switch
VDC 16 Open position extends the actuator cylinder to open the IBOP valve
Close position retracts the actuator cylinder to close the IBOP valve
Emergency Stop Mushroom pushbutton
VDC 17
This switch is hardwired to the VFD and deselects the VFD
regardless of throttle position
Note: all other auxiliary functions remain on
Throttle: 0 to MAX Potentiometer
VDC 18 Controls speed of the AC drilling motors when in drill mode. The
resulting drill pipe speed is displayed on the RPM meter
Drive fault Red indicator
VDC 19 Indicator flashes and horn sounds when a drive(VFD)fault is
detected
Reverse / off / forward 3-position switch
OFF position is used to deselect the VFD
VDC 20
FORWARD and REVERSE are used when drilling or
making/breaking connection.
Switch acts as assignment which energizes the blower/hydraulic
motors when the HYD. PUMP switch is in AUTO
Drill torque: 0 to Max. Continuous Potentiometer
Sets current limit in VDF during drilling and this sets the maximum
VDC 21 allowable drill pipe torque.
The torque is adjusted by setting the brake and adjusting DRILL
TORQUE pot. meter to increase or decrease
Torque: 0 to full scale Meter (0 – 10 VDC)
Displays drill pipe torque in ft lb.
VDC 22
In drilling mode torque is set by DRILL TORQUE pot. Meter and in
make-up mode by MAKE-UPCURRENT LIMIT pot.meter
RPM: 0 to 250 rpm Meter(0 – 10 VDC)
VDC 23 Displays drill pipe rotational speed in rpm. Rotational speed is
controlled by the THROTTLE control

IBOP
Prior to function testing, ascertain that, or perform a pressure test on
the upper and lower IBOP valves. First a 200-psi test (5 min), then
5.5 5,000 psi (5 min) and finally a 15,000-psi test (10 min), all done from
the bottom side.
Note: Ensure that the IBOP valves are rated for H2S service.
Check that the upper IBOP linkage is adjusted properly and the
5.6
valve opens and closes 100%.
Check the operation of the remote IBOP “OPEN / CLOSE” functions
5.7
and indications. Confirm the IBOP open operating timer at
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 7
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

approximately 30 seconds.

LINK TILT
Confirm the adjustment and setting of the four positions as per 4-39
of TDS service manual SM00856
Mouse hole position
5.8
Derrickman’s position
Well center
Drill down position
Confirm that the link tilt travel is set at acceptable speed, in order to
5.9
avoid injury.
Visually check that the link tilt is adjusted so it will clear the racking
5.10
board.
Check that the link tilt is adjusted so it will meet the mouse hole.
5.11 Adjustment can be done by pulling up or down of the mouse hole
position cable

TORQUE WRENCH
Verify that the torque wrench is adjusted and operating properly
5.12
Adjustment to be done by VARCO service engineers
Check that torque wrench is properly positioned in the vertical and
5.13
horizontal position.
Perform following handlings
Breaking out the saver sub
5.14 As per procedure 4-40 of TDS service manual SM00856
Minimum torque 42,000 lbs, maximum torque 46,000 ft lb
Making up the saver sub
5.15 As per procedure 4-42 of TDS service manual SM00856
Minimum torque 42,000 lbs, maximum torque 46,000 ft lb
Breaking out the lower IBOP
5.16 As per procedure 4-43 of TDS service manual SM00856
Minimum torque 42,000 ft lb, maximum torque 46,000 ft lb
Making up the lower IBOP
5.17 As per procedure 4-45 of TDS service manual SM00856
Minimum torque 42,000 ft lb, maximum torque 46,000 ft lb
Breaking out the upper IBOP
5.18 As per procedure 4-46 of TDS service manual SM00856
Minimum torque 42,000 ft lb, maximum torque 46,000 ft lb
Making up the upper IBOP
5.19 As per procedure 4-48 of TDS service manual SM00856
Minimum torque 42,000 ft lb, maximum torque 46,000 ft lb.

PIPE HANDLER ROTATION


Make sure the zero reference position is set correctly by rotating the
5.35
pipe handler a couple of revolutions.
Select “ROTATE” elevator “CW” (clockwise) and “CCW” (counter
5.36 clockwise) at various throttle settings. Observe the correct rotation
direction and the speed being proportional to the throttle setting.
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 8
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

DRILL MODE
Assign the Top Drive SCR, and all auxiliaries, after the purge cycle
select “DRILL MODE”, “FWD” and set the torque limit to
5.39
approximately 200 Amps, wait for 10 seconds. Then turn the throttle
on slowly. The top drive should rotate in the direction selected.
Turn the throttle off and reverse the direction of rotation (“REV”),
5.40 Turn the throttle on slowly. The top drive should rotate in the reverse
direction
Note! The following test should not be done before the rotary table
has been accepted.
Assign the Rotary Table AC motor, and all auxiliaries select “FWD”
after purge cycle, wait for 10 seconds. Then turn the throttle on
5.41
slowly. The rotary drive should rotate in the direction selected,
which should correspond with the direction of the top drive.
Turn the throttle off and reverse the direction of rotation for the rotary
5.42 (“REV”). Turn the throttle on slowly. The rotary drive should rotate
in the reverse direction
Set the top drive speed throttle to zero, actuate the top drive torque
5.43 throttle and adjust to 5,000 ft-lbs set point. Note that the value is
shown until 3 seconds after the throttle is no longer turned.
Apply the brake or have sufficient back up on the main shaft. Set
the top drive “DRILL / TORQUE UP / SPIN” switch in “DRILL” mode
5.44 and the top drive speed throttle to a low value. Verify that the value
as set in the item above when the motor is stalling. REPEAT this test
for the values 10,000 20,000 30,000 40,000 and 50,000 ft-lbs.

SPIN MODE
Set the top drive motor “REV / 0 / FWD” three selection switch in
“FWD” position.
Set the “DRILL / TORQUE UP / SPIN” to the spin position. Press
5.46
the “SPIN / TORQUE UP ACTIVATE” push button. The top drive
should start to rotate at approximately 25 rpm in the forward
direction.
Stop the spin in process:
By pressing the “SPIN / TORQUE UP ACTIVATE” once again,
5.47 By Changing the “DRILL / TORQUE UP / SPIN” switch to “DRILL”
By applying the brake.
By activating the emergency stop.
Set the top drive motor “REV / 0 / FWD” three selection switch in
“REV” position.
5.48 Set the “DRILL / TORQUE UP / SPIN” to the spin position. Press
the “SPIN / TORQUE UP” push button. The top drive should start to
rotate at approximately 25 rpm in the forward direction.
Stop the spin out process:
By pressing the “SPIN / TORQUE UP ACTIVATE” once again,
5.49 By Changing the “DRILL / TORQUE UP / SPIN” switch to “DRILL”
By applying the brake.
Activating the emergency stop
Verify that the spin in/out torque limiter is set to a value of
5.50
approximately 4,000 -5,000 ft-lbs.
TORQUE UP MODE
5.51 Check the operation of the pre-set make up torque limit setting:
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 9
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10

Give a quick push on the increase button, the actual setting will be
seen for 3 seconds on the drilling motor torque meter.
Press the increase / decrease button and note the change of the
torque setting on the top drive torque meter. Set the torque to
20,000 ft-lbs for the next test step.
5.52 Check the speed setting of the torque up and spin in speed.
Lower the top drive and make up on the joint by pressing the “SPIN /
TORQUE UP ACTIVATE” (Make up the connection to 20,000 ft-lbs)
5.53
Verify the correct sequence and the ramp up and ramp down time of
the toque-ing process. Break out the connection in reverse order
Make up on the joint by pressing the “SPIN / TORQUE UP
ACTIVATE” (Make up the connection to 20,000 ft-lbs) Abort the
5.54
process by pressing the “SPIN / TORQUE UP ACTIVATE” once
again
Note! Review all installation test documents and incorporate any
other checks as required.
5.55 Specify retest program on production site

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Top Drive
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 10
Client DAFORA SA Date 14-07-08 of
File Name 2006_Top Drive.doc Originator GW 10
Commissioning Check Sheet

Spin Torque
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2007_Spin Torque.doc Originator GW 4

Description: Spin Torque (Iron Roughneck)


Deutag Code: 2007
Manufacturer: NOV Type: ST-80
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The Spin Torq TS80 is a small Iron Roughneck and pipe spinner
combined that is mounted in a swiveling arrangement on the rig
floor. This set up does not require tracks and has a small footprint
on the rig floor.
The ST 80 is mounted on a swiveling pedestal and swinging of the
unit is done manually by the operator.
The hydraulic power comes from the main HPU in the structure of
the rig. Hoses for the ST80 come through the drill floor near the
pedestal and go up through the aft frame to the hydraulic manifold
of the unit. A ball valve is fitted in the supply line. Hydraulic
isolation must be done at the HPU.
The controls for extending/ retracting, lifting/lowering, make up
/break out, spin in and spin out are all manually operated.
The nominal size range is 4-1/2” to 8-1/2”: drill pipe from 3-1/2” to
5-1/2” and BHA’s up to 8-1/2”
Break out torque is 108.500 Nm and make up torque is 81.500
Nm.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Physically check for any transportation damage or deficiencies
3.2
after the unit has arrived on location
Commissioning Check Sheet

Spin Torque
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2007_Spin Torque.doc Originator GW 4

Verify if all buttons, switches and operating handles are clearly


3.3
identified and marked

Verify that all protection and safety covers have been installed and
3.4
are properly fastened
Verify if the hydraulic isolation valves are easy accessible and
3.5
functional. Operate the manual valves
Check that the hydraulic piping and hoses are secured and
3.6
sufficiently supported
When testing the HPU: inspect valves, hoses, piping and
3.7
connections for leaks
While “driving” the roughneck backwards and forwards ensure that
3.8
the all hoses and cable run freely
Slack off the locking bolts and test the swivel arrangement of the
3.9
ST 80. Ensure that all hoses and cable are free to follow.
Check the swivel locking mechanism. Apply the locking bolts and
3.10
test the “locked in position” condition
When swiveling the unit, check the level gauge on the top cover
3.11
for deviations
Review positioning of the ST 80 on the rig floor regarding the
3.12 rotary table and the mouse hole. The tilt angle for mouse hole
connections must be within the 3° and 7° range
Visually inspect the jaws and spinning wheels for damage,
3.13
conservation and general seating

4.0 Electrical Installation Verification.


4.1 Electrical wiring is complete
4.2 Instrumentation installation is complete
4.3 Test emergency stops
Check torque gauge and other control indications of the ST 80 on
4.4
the drillers panel

5.0 Cold Commissioning


Verify hydraulic supply pressure at the unit. Supply from the HPU
5.1 is 210 bar, the ST 80 requires minimum 140 bar (150 liter/min) and
maximum 170 bar (105 liter/min)
Apply hydraulic pressure to the unit and check that the controls
5.2
respond and that no air is trapped in the systems.
5.3 Operate the functions as per the control panel:
Back / Forward:
5.4 Operates the hydraulic cylinder under the jaws. Extends and
retracts the unit
UP / DOWN
5.5 Operates the hydraulic piston at the back of the roughneck. Lifts
and lowers the unit
TW – SW
5.6 Selector handle for operating the Torque Wrench or the Spinning
Wrench
Commissioning Check Sheet

Spin Torque
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2007_Spin Torque.doc Originator GW 4

Unclamp / Clamp
5.7
Operates the hydraulic cylinder for the clamp under the jaws
Break / Make
5.8 Operates the jaws with the rollers and clamps. Break will move
the jaws CCW, make will move the jaws CW16 / 04
Out / In
5.9 Operates the spinning wheels in the jaws. OUT spins CCW and
IN spins CW
From the VARCO manual:
Verify the ST- 80 meets the timing table presented below
1 Deployment with ST-80 under following conditions
a) Fully up(extended to work position)
b) Fully down (with ST80 extended to work position)
c) Fully forward (with adjust cylinder half extended
d) Fully backwards (with adjust cylinder half extended)
Jaws open and close
1 a) jaws from fully open to fully close
b) jaws from fully close to fully open
Spinners
1 a) spinning in 6-5/8” tool joint
b) spinning out a 5-1/2” tool joint
Torque Cylinders (torque setting at 20,000 ft/lbs
1 Make up, full stroke
Break out, full stroke
Total cycle time for a semi experienced operator
1 a) make up cycle
b) Break out cycle

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
Making up and breaking out connections with “ drill pipe
6.2 Set torque values and spin in, make up torque and check that the
unit acts on the preset torque values.
6.3 Make up / break out a connection in the rotary table
6.4 Make up / break out a connection in the mouse hole

Others:
Commissioning Check Sheet

Spin Torque
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-2008 of
File Name 2007_Spin Torque.doc Originator GW 4

Attachments:
Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch A.doc Originator GW 3

Description: Drillfloor Winch A (DS) Driller Side


Section: 2008
Manufacturer: EMCE Type: MC 309 ATEX
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Electric driven utility winch. Made by EMCE, type MC309
ATEX. Safe Working Load (SWL) is 5,100 kg. Line speed 0 –
20 m/min. cable diameter is 20 mm
Driven by electric motor, 690 V, 50 Hz, 1500 rpm with a rated
output of 22 kW through a planetary gear box with a ratio of 1 :
126. Total weight of the unit is 1340 kg
This is not a man riding winch and must not be used for moving
persons
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification.
1.2 (As and when required, such as API, NACE, IEEE, ANSI,
ATEX etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance
2.1 documentation, and confirm the unit has been released for
installation.
Review and amend the equipment acceptance and
2.2
performance tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and
procedural requirements have been satisfied prior to accessing
3.1
the equipment. This may include, but is not limited to, lockout /
tag out, ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Grade 8.8 or
3.2
higher foundation bolts must be used.
Perform a few trials without load before fitting the wire to check
the correct operation of the system
Fit the wire on the drum as described in section 5 of the EMCE
users manual
3.3 Review specification and certificate of winch wire and hook
Inspect securing wedge of cable on drum, hook, shackle, and
3.4
swivel for condition and operation
Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch A.doc Originator GW 3

Review installation of winch and the first pulley for an


acceptable fleet angle as per 3.1 of EMCE users manual
Inspect the following items for availability and / or proper
3.5
installation:
3.6 Drum guard
3.7 Level winding device.
3.8 Marking of SWL
3.9 Installation and working of emergency stop
Inspect all sheaves in the derrick for free rotation and possible
3.10
interference with other equipment and structures
Check that there will be at least 3 wire coils of rope on the drum
3.11
when the winch hook is in its lowest position

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers
4.1 are of the proper size, run correctly and secured in accordance
wit the relevant regulations.
Inspect the motor cable entries and the junction box cables
4.2 entries, for proper sealing and for correct termination. Also
verify that all terminal connections are tight.
4.3 Ensure that all cables have been checked for continuity
When running, check the motor for excessive noises, vibration
4.4
or high temperatures
4.5 Test the emergency stops of the winch
4.6 Test the functions on the remote panel of the winch

5.0 Cold Commissioning


Verify that the crankcase and gear box of the winch has been
5.1
filled with sufficient oil of good quality
5.2 Have winch bearings and other grease points been greased
Visually inspect the wire rope, is it undamaged and has it been
5.3 greased (preserved)
Non rotating wire, 20 mm.
5.4 Test operation of elect. automatic brake.
5.5 Verify that all winch sheaves have safety wires fitted
Inspect that the sheaves are sized for the wire and that all
5.6
sheave bearings have been greased.
Is there sufficient over view of the drill floor and in the
5.7 derrick when operating the winch
Make a few lifting trials with reduced load (up to 1,000 kg) to
5.8
check the correct operation of the brake and limits
Perform a load test with the maximum load (5100 kg). Lift the
5.9
load and apply the brakes. Maintain this load for 5 minutes.
GW

6.0 Hot Commissioning


Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch A.doc Originator GW 3

Repeat cold commissioning checks (after transportation to final


6.1
destination and before operation)
6.2 Start component and check operation mode (noise, vibration)

Others:

Attachments:
Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch B.doc Originator GW 3

Description: Drillfloor Winch B (ODS) Driller Side


Section: 2008
Manufacturer: EMCE Type: MC 309 ATEX
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Electric driven utility winch. Made by EMCE, type MC309
ATEX. Safe Working Load (SWL) is 5,100 kg. Line speed 0 –
20 m/min. cable diameter is 20 mm
Driven by electric motor, 690 V, 50 Hz, 1500 rpm with a rated
output of 22 kW through a planetary gear box with a ratio of 1 :
126. Total weight of the unit is 1340 kg
This is not a man riding winch and must not be used for moving
persons
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification.
1.2 (As and when required, such as API, NACE, IEEE, ANSI,
ATEX etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance
2.1 documentation, and confirm the unit has been released for
installation.
Review and amend the equipment acceptance and
2.2
performance tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and
procedural requirements have been satisfied prior to accessing
3.1
the equipment. This may include, but is not limited to, lockout /
tag out, ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Grade 8.8 or
3.2
higher foundation bolts must be used.
Perform a few trials without load before fitting the wire to check
the correct operation of the system
Fit the wire on the drum as described in section 5 of the EMCE
users manual
3.3 Review specification and certificate of winch wire and hook
Inspect securing wedge of cable on drum, hook, shackle, and
3.4
swivel for condition and operation
Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch B.doc Originator GW 3

Review installation of winch and the first pulley for an


acceptable fleet angle as per 3.1 of EMCE users manual
Inspect the following items for availability and / or proper
3.5
installation:
3.6 Drum guard
3.7 Level winding device.
3.8 Marking of SWL
3.9 Installation and working of emergency stop
Inspect all sheaves in the derrick for free rotation and possible
3.10
interference with other equipment and structures
Check that there will be at least 3 wire coils of rope on the drum
3.11
when the winch hook is in its lowest position

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers
4.1 are of the proper size, run correctly and secured in accordance
wit the relevant regulations.
Inspect the motor cable entries and the junction box cables
4.2 entries, for proper sealing and for correct termination. Also
verify that all terminal connections are tight.
4.3 Ensure that all cables have been checked for continuity
When running, check the motor for excessive noises, vibration
4.4
or high temperatures
4.5 Test the emergency stops of the winch
4.6 Test the functions on the remote panel of the winch

5.0 Cold Commissioning


Verify that the crankcase and gear box of the winch has been
5.1
filled with sufficient oil of good quality
5.2 Have winch bearings and other grease points been greased
Visually inspect the wire rope, is it undamaged and has it been
5.3 greased (preserved)
Non rotating wire, 20 mm.
5.4 Test operation of elect. automatic brake.
5.5 Verify that all winch sheaves have safety wires fitted
Inspect that the sheaves are sized for the wire and that all
5.6
sheave bearings have been greased.
Is there sufficient over view of the drill floor and in the
5.7 derrick when operating the winch
Make a few lifting trials with reduced load (up to 1,000 kg) to
5.8
check the correct operation of the brake and limits
Perform a load test with the maximum load (5100 kg). Lift the
5.9
load and apply the brakes. Maintain this load for 5 minutes.
GW

6.0 Hot Commissioning


Commissioning Check Sheet

Drillfloor Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA. Date 15-07-08 of
File Name 2008_Drillfloor Winch B.doc Originator GW 3

Repeat cold commissioning checks (after transportation to final


6.1
destination and before operation)
6.2 Start component and check operation mode (noise, vibration)

Others:

Attachments:
Commissioning Check Sheet
Manriding Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 00 1
Client DAFORA SA Date 15-07-2005 of
File Name 2008A_Manriding Winch.doc Originator G:W 3

Description: Manriding Winch


Section: 2008A
Manufacturer: EMCE Type: MR 30 FLG
Date: 02-2008 Serial No.:

ACCEPTANCE METHODE
Resources:
Time involved Date Signature
Air driven manriding winch. Made by EMCE, model MR 30 FLG.
Safe Working Load (SWL) is 150 kg. Line speed is 37 m/min, wire
rope is 10 mm. The winch is driven by an air motor of 1 kW. Air
pressure at the motor is 6 bar and an airflow of 50 ltr/sec is
required. A filter/oiler and reducer are fitted in the air supply line to
the winch.
Motor speed is 1870 rpm. Total weight of the unit is 210 kg.
The winch is equipped with an automatic band brake, an internal
automatic disc brake, a pneumatic load limiter and a slack wire
protection.
The winch is operated from a small portable panel that is
connected to the winch by a pneumatic multi-tube hose of approx.
5 meters long.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.
1.4 Check certification and specification of the wire rope

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Grade 8.8 or
3.2
higher foundation bolts must be used.
Perform a few trials without load before fitting the wire to check
3.3
the correct operation of the system
Inspect securing wedge of cable on drum, hook, shackle, and
3.4
swivel for condition and operation
Commissioning Check Sheet
Manriding Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 00 2
Client DAFORA SA Date 15-07-2005 of
File Name 2008A_Manriding Winch.doc Originator G:W 3

Fit the wire on the drum as described in section 5 of the EMCE


3.5
users manual
Review installation of winch and the first pulley for an acceptable
3.6
fleet angle as per 3.2 of EMCE users manual
Inspect the following items for availability and / or proper
3.7
installation:
3.8 Drum guard
3.9 Level winding device.
3.10 Marking of SWL
3.11 Test operation of the slack wire protection system
3.12 Test operation of the pneumatic load limiting system
3.13 Check installation and working of emergency stop
Inspect air supply line, ball valve, oiler / filter, reducer and all
3.14
connections for proper installation, operation and leaks
3.15 Confirm operation of the emergency brake lifting system
3.16 Check automatic operation of the air band brake
Check automatic operation of the internal disc brake (disconnect
3.17
air band brake for this)
Verify that there is a muffler fitted in the air exhaust system of the
3.18
air winch

4.0 Electrical Installation Verification.


Not Applicable

5.0 Cold Commissioning


Verify that the crankcase and gear box of the winch has been filled
5.1
with sufficient oil of good quality
5.2 Have winch bearings and other grease points been greased
Visually inspect the wire rope, is it undamaged and has it been
5.3 greased (preserved)
Non rotating wire, 10mm.
5.4 Check operation of air reducer and oiler.
Check oil drop rate of oiler in air supply line
Continuous operation : 3 – 5 drops / minute
5.5
Intermittent operation : 7 – 9 drops / minute
Very intermittent operation : 10 – 15 drops / minute
5.6 Verify that all winch sheaves have safety wires fitted
Inspect that the sheaves are sized for the wire and that all sheave
5.7
bearings have been greased.
Is there sufficient over view of the drill floor and in the derrick when
5.8
operating the winch
Test spring action of control lever, does it return to neutral position
5.9
once released
Make a few lifting trials with reduced load (approx80 kg) to check
5.10
the operation of the winch and braking system
Test the winch with the maximum load (150 kg) if allowed by the
5.11
load limiting system
Commissioning Check Sheet
Manriding Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 00 3
Client DAFORA SA Date 15-07-2005 of
File Name 2008A_Manriding Winch.doc Originator G:W 3

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
destination and before operation
Commissioning Check Sheet

Hydraulic Cathead
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2009_Hydraulic Cathead.doc Originator GW 3

Description: Hydraulic Cathead


Section: 2009
Manufacturer: Bentec Type: HC 31.5
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The hydraulic cathead is an hydraulic operated piston that is used
through a sheave and pulling wire for breaking out drill pipe
connections. Hydraulic pressure is from the main HPU. The unit
requires 100 liter/min with a pressure of 140 bars. The pulling wire
has a diameter of 22 mm. With a maximum line pull of 2 meters and
a line speed of 0.15 meter/sec, the operating pull is 31,500 lb
(140,000N)
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify that there is an emergency stop fitted which shut off the
3.2 hydraulic supply to the cylinder. The emergency stop should be
installed close to the operator handle.
3.3 Check hydraulic piping, hoses and hose connections.

3.5 Check wire rope clamps are properly bolted to drum flange
3.6 Check drum bearing has been greased
Activate hydraulic system, remove all air from the system and
3.9
confirm operation of controls from the drilling house
Verify correct position (open) of shut off valve on pressure, return
3.10
and drain lines
Commissioning Check Sheet

Hydraulic Cathead
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2009_Hydraulic Cathead.doc Originator GW 3

Verify correct position (open) of shut off valve on pressure, return


3.11
and drain lines

4.0 Electrical Installation Verification.


4.1 Electrical wiring is complete
4.2 Instrumentation installation is complete
4.3 Loop Check protocol is signed
Verify the controls and indication of the hydraulic cathead in the
4.4
drillers cabin

5.0 Cold Commissioning


Inspect pulling wire and proper installation in the dead man sheave.
5.1
The wire must have a fabricated eye, wire clamps are not allowed
Inspect welds and general arrangements of foundation and
5.2
fastenings
Check greasing of sheave pins and that both sheaves can be
5.3
manually turned
5.4 Confirm swiveling of pivot arm
Extend piston until fully stroked out, check hydraulic system for leaks
5.5
at maximum pressure (140 bars)
Inspect extended piston rod for damages. Visually inspect rod seals
for leakage
Retract the piston and maintain maximum pressure at retracted
5.6
position. Check for leaks
Fit pulling wire to a king post on the rig floor and perform a pull test.
5.7
Confirm read out of instrumentation in the drillers cabin

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Attachments:
Commissioning Check Sheet

Hydraulic Cathead
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2009_Hydraulic Cathead.doc Originator GW 3
Commissioning Check Sheet

Monkey Board Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 14-07-2008 of
File Name 2010-A_Monkey Board Air Hoist A.doc Originator G.W 3

Description: Monkey Board Hoist


Section: 2015
Manufacturer: JD Neuhaus Type: PROFI 1T1
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Electric operated hoist with a hand-held remote station for the
derrick man. This hoist is used to assist the derrickman in handling
drill pipe and drill collars.
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Verify that there is an emergency stop fitted which shut off the air
3.2 supply to the hoist. The emergency stop should be installed as close
as possible to the operator.
3.3 Inspect electrical cable support in the mast.
Confirm the proper installation and markings on the starter box and
3.4
junction boxes.
3.5 The SWL should be displayed.
3.6 All hoists must be certified.
3.7 Verify that a certified wire/chain is installed.
Review positioning of beams and hoists and confirm that oblique
3.8
lifting will not be required (is not allowed)
Commissioning Check Sheet

Monkey Board Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 14-07-2008 of
File Name 2010-A_Monkey Board Air Hoist A.doc Originator G.W 3

3.9 Confirm the system hoist capacity for the system.


Ensure that all components and fittings are securely mounted and
3.14
tightened. All shackles and fittings must be secured or lock-wired
Verify correct position (open) of shut off valve on pressure, return
3.15
and drain lines
Confirm connection and operation of remote control box of the air
3.16
hoists
3.17 The hoisting chains must be lubricated before starting operation

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


5.1
5.2 Confirm operation of the main switch and EM stop.
5.3 Confirm markings on the remote unit
5.4 Check operation of hand held control unit
Test operation of brake
5.5 (when operating hoist up/down with no load, chain must stop running
immediately after releasing control button)
Check direction of operation as per markings on hoist controls.
5.6
Up/down, fwd/aft
5.7 Check the overrun protection (hoist limit switch, page 19 of manual)
Activate or simulate the motor overload protection and confirm that
5.8
only the ‘down” motion can be initiated after activation.
5.9 Confirm operation of emergency stop in lifting and lowering mode
Make sure that the chain has enough length so the hook can reach
5.10
the working area

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Note: use of lubrication oil

Chain lubrication: motor oil


For bearings and gears: roller bearing grease, lithium sanopified
For motor preservation: non resinous and non sticking conserving oil
For motor cleaning: pure petroleum
Others:
Commissioning Check Sheet

Monkey Board Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 14-07-2008 of
File Name 2010-A_Monkey Board Air Hoist A.doc Originator G.W 3

Attachments:
Commissioning Check Sheet

Wireline Unit
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 17-07-2008 of
File Name 2010-Wireline Unit.doc Originator G.W 3

Description: Wireline Unit


Section: 2015
Manufacturer: Mathey Type: HR 5000 II
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Electric / hydraulic operated wireline unit with a rating of 25,000 feet capacity
of .092” wire. The unit is equipped with two brake bands with mechanical
brake lever. The 15 hp electric motor drives a hydraulic pump that delivers
2000 psi to the drive motor of the wire drum. The drive assembly is through
a chain and sprocket drive through a 3 speed transmission.
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As and when
1.2
required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and spare
parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and confirm


2.1
the unit has been released for installation.
Review and amend the equipment acceptance and performance tests. (As
2.2
required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment. This
3.1
may include, but is not limited to, lockout / tag out, ventilation, work permits
and safety barriers.
Verify that there is an emergency stop fitted which shut off the electric motor.
3.2
The emergency stop should be installed as close as possible to the operator.
Inspect the wireline unit, piping and aux. for possible damages due to
3.3
transport, installing etc.
Inspect the winch and the suitability of its location with regards to drill floor
3.4
operations and supporting sheaves in the mast.
Confirm the proper installation and markings on the starter box and junction
3.5
boxes.
Check for proper and secure mounting of the unit and its wire drum. Confirm
3.6
bolt torques and for tightness
Commissioning Check Sheet

Wireline Unit
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 17-07-2008 of
File Name 2010-Wireline Unit.doc Originator G.W 3

3.7 Check installation and functionality of the footage counter.


3.8 Check for secure installation of the line spooler and sheaves.
3.9 Check condition, lubrication and tension of the drive chain.
Confirm that a proper guard has been fitted over the chain drive and all
3.10
moving parts.
Check that an adequate guard has been fitted to protect the operator in the
3.11
event of a line fault, to prevent “whiplash” injuries to operating personnel
Check that the hydraulic safety (relief) valves are properly installed and with
3.12
seals intact

HYDRAULIC PUMP UNIT


Turn the motor / pump shaft by hand and ensure that the pump is running
3.13
freely.
Confirm that the hydraulic system strainers and filters are installed and clean
3.14
prior to power up the unit

HYDRAULIC OIL TANK


Inspect level gauge.
3.15
Is the tank equipped with a level sensor for alarm or trip function ?
Verify that there is a containment strip (dam) around the tank to prevent oil
3.16
spillage or leakage from becoming a safety or environmental hazard.
3.17 Inspect the size of the tank, the fill plug and the vent of the oil tank

4.0 Electrical Installation Verification.


4.1 Check that the electrical wiring is complete
Check that the electrical installation is complete with cable trays, supports
4.2
and cable clamps
Ensure that the cable glands of the terminal and junction boxes are properly
4.3
installed and that the cables are correctly terminated
Review electrical check sheets. Ensure that electrical cables have been
4.4
checked for continuity.
4.5 Test emergency stop of the unit

5.0 Cold Commissioning


The unit and all supporting equipment shall be connected, fully assembled
5.1 and adjusted in accordance with applicable installation drawings and
procedures. All equipment shall be permanently mounted.
All electrical systems shall be fully commissioned and installed
conform their legislative requirements. All cables and systems shall
5.2
be tested for continuity, electrical insulation (megger tested) and have
been released for service.
Check that all pump isolation valves are clear and open. Confirm for
5.3
correct settings of the pressure limit bypass valve.
Power up the system and verify that emergency stops are
5.4
operational.
5.5 Check for correct hydraulic operating supply, return and drain line
Commissioning Check Sheet

Wireline Unit
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 17-07-2008 of
File Name 2010-Wireline Unit.doc Originator G.W 3

pressures. Check the unit for leaks.


Operate the winch and its drum in both directions. Check for
abnormal sounds, excessive vibration, and for correct spooling of the
5.6
wire. Check that the operating handles returns to neutral when
released and confirm the operation of the footage counter.
Check that the RPM of the winch can be properly controlled with
5.7
smooth operation and acceleration at various speeds.
Check and test for proper operation of the brake. Ensure for safe and
5.8
proper adjustment of the brake.
5.9 Check operation of the wire spooler, footage counter and guidance sheaves
Carry out a thorough post operational inspection of the wire [survey]
5.10
line and its associated equipment upon completion of endurance test.

6.0 Hot Commissioning


Commissioning Check Sheet

Dead Line Anchor


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07--2008 of
File Name 2011_Dead Line Anchor.doc Originator GW 3

Description: Dead Line Anchor


Section: 2011
Manufacturer: BENTEC Type: DA-100-W-1 3/8”
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests as required.
Review the inspection reports of the NDT tests for the load bearing
2.3
areas and welds of the foundation.

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Inspect for proper mechanical and/or structural completion of the
dead line anchor and its associated equipment, supporting systems,
3.2 controls and integrated systems. This also includes the physical
interface with other systems and that all requirements and standards
are met.
Physically check the dead line anchor assembly for any
transportation damage prior to installation (after arrival on the
3.3
production site). Confirm that all preservatives have been removed
and that the assembly is in a clean, good condition.
Check the condition of the unit and drum for damage, cracks, and
3.4
ensure the groove profile is correct.
Ensure that the identification plate and marking of the dead line
3.5
anchor.
Check for proper and secure mounting of the dead line anchor
3.6 assembly. Particular attention must be given to the foundation, that
hold down bolts are properly torque and of correct grade, that nuts
Commissioning Check Sheet

Dead Line Anchor


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07--2008 of
File Name 2011_Dead Line Anchor.doc Originator GW 3

and bolts are properly locked, that the anchor dies are in a good
condition free of any damage, and that the grease points are
adequately protected and easy accessible.
Verify that guards are in place, that they have been installed
3.7
correctly and that they conform to specifications.
Check that the jumper bars are correctly and securely installed.
Jumper bars shall be fitted to avoid the cable jumping of the anchor
3.8
drum in the event of a sudden loss of hook load (typically three point
installations, including one on the top of the drum).
Check for properly and secure installation of the load cell. Ensure
3.9
that pins are in a good condition and securely locked.
3.10 Check for correct gap settings of the load cell.
Check the pressure integrity of the hose connections from the load
3.11 cell to the pressure switch. Check the condition of hoses and ensure
that they are not binding or damaged in any other way.
Ensure that the installed weight indicator is properly calibrated prior
3.12
to applying any loads.

4.0 Electrical Installation Verification.


Check that the cable installation to the load cell pressure switch is
4.1 correctly installed and well protected. Check for proper installation
and sealing of the junction box.

5.0 Commissioning
5.1 Ensure that all lubrication points have been properly lubricated.
When spooling on the drill line, ensure the wire is clear of any “hang-
5.2 up” points on the assembly. Make certain for proper fastening of
bars, guards and anchor points after installation of the drill line.
Perform a load test of the main drilling hoisting equipment as per
manufacturer’s recommended practice (or a pre-agreed load).
5.3 Check the operation of the dead line anchor, the load cell and the
weight indicator. Record the known weights against the assembly’s
calibrated load cell and weight indicator.
Carry out a thorough post operational inspection of the dead line
anchor assembly upon completion of endurance test. Check the
5.4
foundation and all bolts for proper tightness. Also confirm for proper
path of the drill line wire in the drum grooves.
5.5 Specify retest program on production site

Others:

Verify drill line is ready packed for transportation according to


Bentec packing standards

Attachments:
Commissioning Check Sheet

Dead Line Anchor


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07--2008 of
File Name 2011_Dead Line Anchor.doc Originator GW 3
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch DS.doc Originator GW 3

Description: Mast Telescoping Winch DS


Section: 2012
Manufacturer: DP Winch Type: 100BAX1L2D
Date: Serial No.: 15-5-00007

ACCEPTANCE METHODE
Resources:
Time involved Date Signature
The raising and lowering of the mast sections is done by two
hydraulic operated winches. These winches are named according
to their location: DS (driller side) and the other ODS (off driller
side). The wires, spooled on the drums of these winches, are
attached to the lower section of the mast through turn-down
sheaves, snatch blocks and shackles. The hydraulic power for
operating the winches is delivered by the main HPU and controls
of the winches is by a remote panel that can be plugged in at a
socket near the HPU. For monitoring loads, two suitcases each
with a load indicator gauge and a rotating recorder, are available
to be plugged.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2 and when required, such as API, NACE, IEEE, ANSI, DIN, ATEX
etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)
2.3 Review specification and certification of wire rope
Review certification of dead end shackles, snatch block and turn
2.4
down sheaves.

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Are the required
3.2 number and grade of bolts fitted 29 / 01 GW
As a minimum, grade 8.8 bolts must be fitted.
3.3 Confirm that the gear box has been filled with oil. Check level 29 / 01
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch DS.doc Originator GW 3

For a temperature range of 10 C to 120 C, a 85W 140 oil should


be used
29 / 01
Inspect hydraulic hoses and connections
3.4 Checked at GW
When pressure applied, check for leaks
115 bar
Check setting of internal hydraulic brake. This brake will set when 29 / 01
the hydraulic pressure is below 270 psi
3.5 GW
Note: brake will automatically set when winch control is in neutral
or in case of power failure
Before spooling the wire on the drum, run the winch in both 29 / 01
3.6 directions for approx. ½ hour and check for temperatures, GW
excessive noises or vibrations
Inspect dead end wedge of cable on drum. Confirm a secure
3.7
fastening of the wire.
When spooling the wire on the drum, confirm the right spool
3.8
direction and a compact installation without gaps.

4.0 Electrical Installation Verification.


Electrical wiring is complete
Instrumentation installation is complete
Test emergency stops on remote panels

5.0 Cold Commissioning


Check oil level in the winch. The level should be at the bottom of
5.1 29 / 01 GW
the fill / level plug
Plug in the remote control panel and confirm communication with
5.2 29 / 01 GW
the control valves of the winch
Visually inspect the sheaves and shackles in the mast. Confirm
5.3 that the sheave bearings have been greased and that safety slings
have been fitted where required.
When possible, rotate the winch and confirm signal return to the
5.4 29 / 01 GW
pressure indicator on the remote panel
For raising and lowering the mast, follow the instructions as per
5.5
Operations Manual

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
6.2 Start component and check operation mode (noise, vibration)

Others:

Attachments:
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch DS.doc Originator GW 3
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch ODS.doc Originator GW 3

Description: Mast Telescoping Winch ODS


Section: 2012
Manufacturer: DP Winch Type: 100BAX1R2D
Date: Serial No.: 15-6-00010

ACCEPTANCE METHODE
Resources:
Time involved Date Signature
The raising and lowering of the mast sections is done by two
hydraulic operated winches. These winches are named according
to their location: DS (driller side) and the other ODS (off driller
side). The wires, spooled on the drums of these winches, are
attached to the lower section of the mast through turn-down
sheaves, snatch blocks and shackles. The hydraulic power for
operating the winches is delivered by the main HPU and controls
of the winches is by a remote panel that can be plugged in at a
socket near the HPU. For monitoring loads, two suitcases each
with a load indicator gauge and a rotating recorder, are available
to be plugged.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2 and when required, such as API, NACE, IEEE, ANSI, DIN, ATEX
etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)
2.3 Review specification and certification of wire rope
Review certification of dead end shackles, snatch block and turn
2.4
down sheaves.

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Are the required
3.2 number and grade of bolts fitted 29 / 01 GW
As a minimum, grade 8.8 bolts must be fitted.
3.3 Confirm that the gear box has been filled with oil. Check level 29 / 01 GW
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch ODS.doc Originator GW 3

For a temperature range of 10 C to 120 C, a 85W 140 oil should


be used
29 / 01
Inspect hydraulic hoses and connections Checked at
3.4 GW
When pressure applied, check for leaks 115 bar
pressure
Check setting of internal hydraulic brake. This brake will set when 29 / 01
the hydraulic pressure is below 270 psi
3.5 GW
Note: brake will automatically set when winch control is in neutral
or in case of power failure
Before spooling the wire on the drum, run the winch in both 29 / 01
3.6 directions for approx. ½ hour and check for temperatures, GW
excessive noises or vibrations
Inspect dead end wedge of cable on drum. Confirm a secure
3.7
fastening of the wire.
When spooling the wire on the drum, confirm the right spool
3.8
direction and a compact installation without gaps.

4.0 Electrical Installation Verification.


Electrical wiring is complete
Instrumentation installation is complete
Test emergency stops on remote panels

5.0 Cold Commissioning


Check oil level in the winch. The level should be at the bottom of
5.1 29 / 01 GW
the fill / level plug
Plug in the remote control panel and confirm communication with
5.2 29 / 01 GW
the control valves of the winch
Visually inspect the sheaves and shackles in the mast. Confirm
5.3 that the sheave bearings have been greased and that safety slings
have been fitted where required.
When possible, rotate the winch and confirm signal return to the
5.4 29 / 01 GW
pressure indicator on the remote panel
For raising and lowering the mast, follow the instructions as per
5.5
Operations Manual

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
6.2 Start component and check operation mode (noise, vibration)

Others:
Commissioning Check Sheet

Mast Telescoping Winch


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2012_Mast Telescoping Winch ODS.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Catwalk Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2013_Catwalk Winch.doc Originator GW 3

Description: Catwalk Winch


Section: 2013
Manufacturer: EMCE Type: MC 303 E
Date: 01-2008 Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Electric driven utility winch. Made by EMCE, type MC303E ATEX.
Safe Working Load (SWL) is 1,000 kg. Line speed 9 m/min. cable
diameter is 10 mm
Driven by electric motor, 690 V, 50 Hz, 1500 rpm with a rated
output of 3 kW through a planetary gear box with a ratio of 1 : 178.
Total weight of the unit is 245 kg
This is not a man riding winch and must not be used for moving
persons
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, ATEX etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tag
out, ventilation, work permits and safety barriers.
Inspect foundation and mounting of the winch. Grade 8.8 or
3.2
higher foundation bolts must be used.
Perform a few trials without load before fitting the wire to check the
correct operation of the system
Fit the wire on the drum as described in section 5 of the EMCE
users manual
3.3 Review specification and certificate of winch wire and hook
Inspect securing wedge of cable on drum, hook, shackle, and
3.4
swivel for condition and operation
Review installation of winch and the first pulley for an acceptable
fleet angle as per 3.1 of EMCE users manual
Commissioning Check Sheet

Catwalk Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2013_Catwalk Winch.doc Originator GW 3

Inspect the following items for availability and / or proper


3.5
installation:
3.6 Drum guard
3.7 Level winding device.
3.8 Marking of SWL
3.9 Installation and working of emergency stop
Inspect all sheaves in the derrick for free rotation and possible
3.10
interference with other equipment and structures
Check that there will be at least 3 wire coils of rope on the drum
3.11
when the winch hook is in its lowest position

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers are
4.1 of the proper size, run correctly and secured in accordance wit the
relevant regulations.
Inspect the motor cable entries and the junction box cables
4.2 entries, for proper sealing and for correct termination. Also verify
that all terminal connections are tight.
4.3 Ensure that all cables have been checked for continuity
When running, check the motor for excessive noises, vibration or
4.4
high temperatures
4.5 Test the emergency stops of the winch
4.6 Test the functions on the remote panel of the winch

5.0 Cold Commissioning


Verify that the crankcase and gear box of the winch has been filled
5.1
with sufficient oil of good quality
5.2 Have winch bearings and other grease points been greased
Visually inspect the wire rope, is it undamaged and has it been
5.3 greased (preserved)
Non rotating wire, 10 mm.
5.4 Test operation of elect. automatic brake.
5.5 Verify that all winch sheaves have safety wires fitted
Inspect that the sheaves are sized for the wire and that all sheave
5.6
bearings have been greased.
Is there sufficient over view of the drill floor and in the derrick
5.7 when operating the winch
Make a few lifting trials with reduced load (up to 500 kg) to check
5.8
the correct operation of the brake and limits
Perform a load test with the maximum load (1,500 kg). Lift the load
5.9
and apply the brakes. Maintain this load for 5 minutes.

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)
Commissioning Check Sheet

Catwalk Winch
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2013_Catwalk Winch.doc Originator GW 3

6.2 Start component and check operation mode (noise, vibration)

Others:

Attachments:
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist A.doc Originator G.W 3

Description: BOP Air Hoist A


Section: 2015
Manufacturer: JD Neuhaus Type: EH-25
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Verify that there is an emergency stop fitted which shut off the air
3.2 supply to the hoist. The emergency stop should be installed as close
as possible to the operator.
3.3 The air hose connections should have ID of 1-1/2” minimum.
3.4 Confirm installation of a regulator and an oiler in air supply system
3.5 The SWL should be displayed.
3.6 All hoists must be certified.
3.7 Verify that a certified wire/chain is installed.
Review positioning of beams and hoists and confirm that oblique
3.8
lifting will not be required (is not allowed)
3.9 Confirm the system hoist capacity for the system. (BOP weights)
Ensure that all components and fittings are securely mounted and
3.14
tightened. Visually check stops at both side of trolley beams.
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist A.doc Originator G.W 3

Verify correct position (open) of shut off valve on pressure, return


3.15
and drain lines
Confirm connection and operation of remote control boxes for air
3.16
hoists
3.17 The hoisting chains must be lubricated before starting operation

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


5.1 Confirm available minimum air pressure of 6 bars.
5.2 Confirm operation of air regulator in air supply
Confirm oil filling of lubricator in air system (NO synthetic oils
5.3
allowed)
5.4 When operating, confirm oil lubrication of 15 drops per minute
Test operation of brake
5.5 (when operating hoist up/down with no load, chain must stop running
immediately after releasing control button)
Check direction of operation as per markings on hoist controls.
5.6
Up/down, fwd/aft
5.7 Check the overrun protection (hoist limit switch, page 19 of manual)
Activate or simulate the motor overload protection and confirm that
5.8
only the ‘down” motion can be initiated after activation.
5.9 Confirm operation of emergency stop in lifting and lowering mode
5.10 Make sure that the load hook can be lowered to the floor

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Note: use of lubrication oil


Oiler for motor lubrication; lubricating oil D, DIN 51502
Chain lubrication: motor oil
For bearings and gears: roller bearing grease, lithium sanopified
For motor preservation: non resinous and non sticking conserving oil
For motor cleaning: pure petroleum
Others:
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist A.doc Originator G.W 3

Attachments:
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist B.doc Originator G.W 3

Description: BOP Air Hoist B


Section: 2015
Manufacturer: JD Neuhaus Type: EH-25
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Verify that there is an emergency stop fitted which shut off the air
3.2 supply to the hoist. The emergency stop should be installed as close
as possible to the operator.
3.3 The air hose connections should have ID of 1-1/2” minimum.
3.4 Confirm installation of a regulator and an oiler in air supply system
3.5 The SWL should be displayed.
3.6 All hoists must be certified.
3.7 Verify that a certified wire/chain is installed.
Review positioning of beams and hoists and confirm that oblique
3.8
lifting will not be required (is not allowed)
3.9 Confirm the system hoist capacity for the system. (BOP weights)
Ensure that all components and fittings are securely mounted and
3.14
tightened. Visually check stops at both side of trolley beams.
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist B.doc Originator G.W 3

Verify correct position (open) of shut off valve on pressure, return


3.15
and drain lines
Confirm connection and operation of remote control boxes for air
3.16
hoists
3.17 The hoisting chains must be lubricated before starting operation

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


5.1 Confirm available minimum air pressure of 6 bars.
5.2 Confirm operation of air regulator in air supply
Confirm oil filling of lubricator in air system (NO synthetic oils
5.3
allowed)
5.4 When operating, confirm oil lubrication of 15 drops per minute
Test operation of brake
5.5 (when operating hoist up/down with no load, chain must stop running
immediately after releasing control button)
Check direction of operation as per markings on hoist controls.
5.6
Up/down, fwd/aft
5.7 Check the overrun protection (hoist limit switch, page 19 of manual)
Activate or simulate the motor overload protection and confirm that
5.8
only the ‘down” motion can be initiated after activation.
5.9 Confirm operation of emergency stop in lifting and lowering mode
5.10 Make sure that the load hook can be lowered to the floor

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Note: use of lubrication oil


Oiler for motor lubrication; lubricating oil D, DIN 51502
Chain lubrication: motor oil
For bearings and gears: roller bearing grease, lithium sanopified
For motor preservation: non resinous and non sticking conserving oil
For motor cleaning: pure petroleum
Others:
Commissioning Check Sheet

BOP Air Hoist


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2015_BOP Air Hoist B.doc Originator G.W 3

Attachments:
Commissioning Check Sheet

Crown Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 2016_Crown Block.doc Originator GW 3

Description: Crown Block


Section: 2016
Manufacturer: Bentec Type: CB-400-5-50-1 3/8
Date: 2008 Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Bentec has manufactured the crown block assembly. The assembly
has a total of 6 sheaves (including the fast line sheave). The
diameter of the sheaves is 50”. The sheaves are made to handle a
1-3/8” drill line. Load capacity of the crown block is 400 short tons
(363 metric tons) and the weight of the assembly is approx. 9500 kg
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1 02 / 02 GW
specification.
Review the system’s class authority and statutory certification. (As
1.2 02 / 02 GW
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
02 / 02 GW
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1 N/A GW
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2 N/A GW
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Inspect for proper mechanical and/or structural completion of the
crown block and its associated equipment, supporting systems. This
3.2
also includes the physical interface with other systems and that all
requirements and standards are met.
Visually check equal spacing of the sheaves and that bearing seals
3.3 29 / 01 GW
are in place
Check the condition of the sheaves for damage, cracks, and ensure
the sheave profile is correct. Ensure that the sheaves rotate freely
3.4 29 / 01 GW
and that they are without any wobble bearing wear. Also confirm for
equal spacing between the sheaves.
Check for proper and secure mounting of the crown block assembly.
Particular attention must be given to that all nuts and bolts are
3.5 29 / 01 GW
properly lock wired, and that the grease points are adequately
protected and easy accessible.
Commissioning Check Sheet

Crown Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 2016_Crown Block.doc Originator GW 3

Verify that guards are in place, that they have been installed
3.6
correctly.
Check crown platform for any deficiencies, Particular attention must
3.7 be given to that the platform’s handrails are in a good condition and 29 / 01 GW
safely installed.
Confirm that all preservatives have been removed and that the
3.8 29 / 01 GW
assembly is in a clean, good condition.
Check that the jumper bars are correctly and securely installed.
Jumper bars shall be fitted to avoid the cable jumping of the sheaves
3.9
in the event of a sudden loss of hook load (typically three point
installation, including one on the top of the sheaves).

4.0 Electrical Installation Verification.


Note! This general electrical installation verification describes
4.1 auxiliary switches and sensors in relation to the primary drilling
hoisting equipment.
Check the installation of the cables and proximity position switches
4.2
for the crown block assembly’s ton mile counters.
Check that clear indications are visible on drillers’ console showing
4.3
and confirming the ton miles.

5.0 Cold Commissioning


Ensure that grease have been added to the bearings of the crown
5.1 29 / 01 GW
block assembly (sheaves and grease manifold).
After installing the drill line, ensure that the drill line is clear of the
5.2
crown block guards and jumper bars.
After reeving of the drill line, very slowly hoist the primary drilling
5.3 hoisting equipment and constantly check to verify that the crown
sheaves reeves properly. The fleet angles must be minimal.
Proceed to hoist the equipment up to the crown. Watch for
5.4 interference between the drill line, crown block and service hoses /
loops. Solve any interference irregularities prior to continue the tests.
Once at the crown, slowly lower the hoisting equipment down and
5.5
continue to check for any irregularities.
Repeat the above two steps with slowly hoist the drilling hoisting
5.6 equipment to the crown, watching for any abnormalities. Lower the
equipment down.
In conjunction with the primary drilling hoisting equipment, verify and
5.7 test the anti-collision system (ZMS), crown saver and floor saver
functions prior to simulated RIH/POH operations.
Carry out an extended run and cycling test (simulate tripping) prior to
and after applying heavy load to the hoisting machinery. Operate the
hoisting equipment with different loads and check for smooth
5.8
operating of the crown block assembly. Check for excessive
temperature in the running gear (smell, smoke), if possible measure
temperature of bearings using an extendable probe.
Carry out a thorough post operational inspection of the crown block
assembly upon completion of endurance test. Check the foundation
bolts for proper tightness, to see if there is any indication of wear on
5.9
the sheaves and/or misalignment of the sheaves due to potential
bearing damage. Also confirm for proper path of the drill line wire
reaving.
Commissioning Check Sheet

Crown Block
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 2016_Crown Block.doc Originator GW 3

5.10 Specify retest program on production site

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Attachments:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.1.doc Originator GW 4

Description: Main Generator Sets No.1


Section: 3001
Manufacturer: Zeppelin/Caterpillar Type: CAT 3512 B
Engine No. 8RM00831
Date: Serial No.:
Generator No. 5SN00908

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Power generation is by three Caterpillar generator sets. Prime
mover is the Caterpillar type 3512B DITA SCAC engine.
Rating is 1.310 BkW @ 1500 RPM at a power factor of 0.8
The engine has 12 V cylinders, bore 170 mm and a stroke of 190
mm. The displacement is 51.8 liters and the compression rate is
14 : 1 Emission parameters of the engines is certified according to
European standards.
The engine is turbo charged with an after cooler. Fuel type is
Diesel

The generator is a free standing Caterpillar brushless type SR4B


with two bearings. Voltage is 690 V; 50 Hz, 3-phase at 1500 rpm.
The generator is rated at 1500 KVA with a power factor of 0.8.
Isolation class H, 155 C: Temperature rise is 105 C at an
ambiance temperature of 40 C
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Check that all indicators and valves are properly and correctly
3.1
labeled.
Confirm the security and tightness of all connections:
1. Fuel oil lines (internal lines, onboard tank)
3.2
2. Lubrication oil lines
3. Exhaust gas system lines
a) Verify ventilation dampers are operational prior to test run
3.3
b) Carry out a pre-commissioning check on the engine,
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.1.doc Originator GW 4

generator alignment and radiator shutter system.


c) Check the engine oil level, radiator water and fuel supply.
d) Check the operation of the heaters in the engine cooling
water system.
e) Check the tension of the fan belts.
f) Inspect the battery / air starter.
g) Check the spark arrestor installation.
Check the condition of all connection hoses and connection
3.4
bellows for chafing and deterioration.
3.5 Examine the exhaust pipe lagging for completeness.
Inspect the engine-mounted piping and the related piping system,
3.6
and confirm that all supports are properly installed.
Operate all engine-related valves and make sure they operate
3.7
freely.
Carry out a random check and verify the lash adjusters and
3.8 injectors are set in accordance with the manufacturer’s
instructions.
Move the fuel rack and confirm it is operating smoothly without
3.9
binding, and all the injector racks following correctly.
Carry out a random crankcase and top deck inspection and verify
3.10 all bolts / nuts are tight. Ensure no loose items are left in the sump
before charging the lubrication oil.
Obtain alignment readings of the generator flex coupler to the
3.11
engine flywheel.
Check that the starter motor exhaust ports are directed away from
3.12
personnel and from walk and passage ways.
Inspect the cooling water heating system: confirm that the heater
is working when the engine has been switched off: Temperature
range of thermostat is 18 – 60 C
Inspect the system and installation of the pre lubrication pump.
Test the system and record the oil pressure
3.13 INSTRUMENTATION
Test the following alarms:
1. High engine cooling water alarm.
2. High engine lubrication oil temperature.
3. Low engine cooling water pressure.
3.14 4. Low engine lubrication oil pressure.
5. Low engine fuel oil pressure.
6. Low engine start air pressure.
7. Low cooling water headertank.
8. Low lubrication oil level.
Test the following engine safety devices:
1. High engine cooling water temperature.
3.15 2. Low engine lubrication oil pressure.
9. Engine over-speed.
10. High crankcase pressure

4.0 Electrical Installation Verification.


Examine the cleanliness of the exterior / interior of the generator
4.1
set’s cabinet.
4.2 Verify whether all cables to the console are properly and securely
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.1.doc Originator GW 4

installed on the cable tray.


Confirm that the contactors, fuses and cables of control circuitry
4.3
are of the suitable type and rating.
Ensure that the junction boxes and terminal boxes and controls
4.4
are properly identified.
Ensure that the cable glands of the terminal and junction boxes
4.5
are properly installed and the cables correctly terminated.
4.6 Ensure that all electrical cables have been checked for continuity.

5.0 Commissioning
Verify that the mechanical preventative maintenance system has
5.1
been implemented and updated to suit the present installation.
Verify that the electrical preventative maintenance system has
5.2
been implemented and updated to suit the present installation.
5.3 Check the oil level in the governor.
5.4 Check the oil level in the engine sump.
Check the oil level in the air motor lubricator and confirm the
5.5
lubricator is set up correctly.
5.6 Check the cooling water level in the water header tank.
5.7 Confirm the engine cooling water has been adequately treated.
Check the daily fuel tank has been filled with sufficient clean diesel
5.8
fuel
Inspect the fuel lines to- and on the engine. Piping, hoses, filters
5.9
and connections: Supply and return hoses at the engines are ¾”
The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.10
installation drawing / procedure. All equipment shall be
permanently mounted.
All piping system systems shall be hydro tested, pickled,
5.11 passivated and / or flushed in accordance with the manufacturer’s
recommendations or otherwise required.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems
5.12
shall be tested for continuity, electrical integrity (megger tested)
and have been released for service.

LOAD TEST
5.11 See Bentec running test procedure in the attachment

Others:
Serial Numbers Gen-Set 1:
Generator:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.1.doc Originator GW 4

Engine:

Serial Numbers Gen-Set 2:


Generator:
Engine:

Serial Numbers Gen-Set 3:


Generator:
Engine:

Attachments:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.2.doc Originator GW 4

Description: Main Generator Sets No.2


Section: 3001
Manufacturer: Zeppelin/Caterpillar Type: CAT 3512 B
Engine No. 8RM00826
Date: Serial No.:
Generator No. 5SN00905

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Power generation is by three Caterpillar generator sets. Prime
mover is the Caterpillar type 3512B DITA SCAC engine.
Rating is 1.310 BkW @ 1500 RPM at a power factor of 0.8
The engine has 12 V cylinders, bore 170 mm and a stroke of 190
mm. The displacement is 51.8 liters and the compression rate is
14 : 1 Emission parameters of the engines is certified according to
European standards.
The engine is turbo charged with an after cooler. Fuel type is
Diesel

The generator is a free standing Caterpillar brushless type SR4B


with two bearings. Voltage is 690 V; 50 Hz, 3-phase at 1500 rpm.
The generator is rated at 1500 KVA with a power factor of 0.8.
Isolation class H, 155 C: Temperature rise is 105 C at an
ambiance temperature of 40 C
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Check that all indicators and valves are properly and correctly
3.1
labeled.
Confirm the security and tightness of all connections:
1. Fuel oil lines (internal lines, onboard tank)
3.2
2. Lubrication oil lines
3. Exhaust gas system lines
a) Verify ventilation dampers are operational prior to test run
3.3
b) Carry out a pre-commissioning check on the engine,
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.2.doc Originator GW 4

generator alignment and radiator shutter system.


c) Check the engine oil level, radiator water and fuel supply.
d) Check the operation of the heaters in the engine cooling
water system.
e) Check the tension of the fan belts.
f) Inspect the battery / air starter.
g) Check the spark arrestor installation.
Check the condition of all connection hoses and connection
3.4
bellows for chafing and deterioration.
3.5 Examine the exhaust pipe lagging for completeness.
Inspect the engine-mounted piping and the related piping system,
3.6
and confirm that all supports are properly installed.
Operate all engine-related valves and make sure they operate
3.7
freely.
Carry out a random check and verify the lash adjusters and
3.8 injectors are set in accordance with the manufacturer’s
instructions.
Move the fuel rack and confirm it is operating smoothly without
3.9
binding, and all the injector racks following correctly.
Carry out a random crankcase and top deck inspection and verify
3.10 all bolts / nuts are tight. Ensure no loose items are left in the sump
before charging the lubrication oil.
Obtain alignment readings of the generator flex coupler to the
3.11
engine flywheel.
Check that the starter motor exhaust ports are directed away from
3.12
personnel and from walk and passage ways.
Inspect the cooling water heating system: confirm that the heater
is working when the engine has been switched off: Temperature
range of thermostat is 18 – 60 C
Inspect the system and installation of the pre lubrication pump.
Test the system and record the oil pressure
3.13 INSTRUMENTATION
Test the following alarms:
1. High engine cooling water alarm.
2. High engine lubrication oil temperature.
3. Low engine cooling water pressure.
3.14 4. Low engine lubrication oil pressure.
5. Low engine fuel oil pressure.
6. Low engine start air pressure.
7. Low cooling water headertank.
8. Low lubrication oil level.
Test the following engine safety devices:
1. High engine cooling water temperature.
3.15 2. Low engine lubrication oil pressure.
9. Engine over-speed.
10. High crankcase pressure

4.0 Electrical Installation Verification.


Examine the cleanliness of the exterior / interior of the generator
4.1
set’s cabinet.
4.2 Verify whether all cables to the console are properly and securely
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.2.doc Originator GW 4

installed on the cable tray.


Confirm that the contactors, fuses and cables of control circuitry
4.3
are of the suitable type and rating.
Ensure that the junction boxes and terminal boxes and controls
4.4
are properly identified.
Ensure that the cable glands of the terminal and junction boxes
4.5
are properly installed and the cables correctly terminated.
4.6 Ensure that all electrical cables have been checked for continuity.

5.0 Commissioning
Verify that the mechanical preventative maintenance system has
5.1
been implemented and updated to suit the present installation.
Verify that the electrical preventative maintenance system has
5.2
been implemented and updated to suit the present installation.
5.3 Check the oil level in the governor.
5.4 Check the oil level in the engine sump.
Check the oil level in the air motor lubricator and confirm the
5.5
lubricator is set up correctly.
5.6 Check the cooling water level in the water header tank.
5.7 Confirm the engine cooling water has been adequately treated.
Check the daily fuel tank has been filled with sufficient clean diesel
5.8
fuel
Inspect the fuel lines to- and on the engine. Piping, hoses, filters
5.9
and connections: Supply and return hoses at the engines are ¾”
The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.10
installation drawing / procedure. All equipment shall be
permanently mounted.
All piping system systems shall be hydro tested, pickled,
5.11 passivated and / or flushed in accordance with the manufacturer’s
recommendations or otherwise required.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems
5.12
shall be tested for continuity, electrical integrity (megger tested)
and have been released for service.

LOAD TEST
5.11 See Bentec running test procedure in the attachment

Others:
Serial Numbers Gen-Set 1:
Generator:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.2.doc Originator GW 4

Engine:

Serial Numbers Gen-Set 2:


Generator:
Engine:

Serial Numbers Gen-Set 3:


Generator:
Engine:

Attachments:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.3.doc Originator GW 4

Description: Main Generator Sets No.3


Section: 3001
Manufacturer: Zeppelin/Caterpillar Type: CAT 3512 B
Engine No. 8RM00830
Date: Serial No.:
Generator No. 5SN00907

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Power generation is by three Caterpillar generator sets. Prime
mover is the Caterpillar type 3512B DITA SCAC engine.
Rating is 1.310 BkW @ 1500 RPM at a power factor of 0.8
The engine has 12 V cylinders, bore 170 mm and a stroke of 190
mm. The displacement is 51.8 liters and the compression rate is
14 : 1 Emission parameters of the engines is certified according to
European standards.
The engine is turbo charged with an after cooler. Fuel type is
Diesel

The generator is a free standing Caterpillar brushless type SR4B


with two bearings. Voltage is 690 V; 50 Hz, 3-phase at 1500 rpm.
The generator is rated at 1500 KVA with a power factor of 0.8.
Isolation class H, 155 C: Temperature rise is 105 C at an
ambiance temperature of 40 C
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Check that all indicators and valves are properly and correctly
3.1
labeled.
Confirm the security and tightness of all connections:
1. Fuel oil lines (internal lines, onboard tank)
3.2
2. Lubrication oil lines
3. Exhaust gas system lines
a) Verify ventilation dampers are operational prior to test run
3.3
b) Carry out a pre-commissioning check on the engine,
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.3.doc Originator GW 4

generator alignment and radiator shutter system.


c) Check the engine oil level, radiator water and fuel supply.
d) Check the operation of the heaters in the engine cooling
water system.
e) Check the tension of the fan belts.
f) Inspect the battery / air starter.
g) Check the spark arrestor installation.
Check the condition of all connection hoses and connection
3.4
bellows for chafing and deterioration.
3.5 Examine the exhaust pipe lagging for completeness.
Inspect the engine-mounted piping and the related piping system,
3.6
and confirm that all supports are properly installed.
Operate all engine-related valves and make sure they operate
3.7
freely.
Carry out a random check and verify the lash adjusters and
3.8 injectors are set in accordance with the manufacturer’s
instructions.
Move the fuel rack and confirm it is operating smoothly without
3.9
binding, and all the injector racks following correctly.
Carry out a random crankcase and top deck inspection and verify
3.10 all bolts / nuts are tight. Ensure no loose items are left in the sump
before charging the lubrication oil.
Obtain alignment readings of the generator flex coupler to the
3.11
engine flywheel.
Check that the starter motor exhaust ports are directed away from
3.12
personnel and from walk and passage ways.
Inspect the cooling water heating system: confirm that the heater
is working when the engine has been switched off: Temperature
range of thermostat is 18 – 60 C
Inspect the system and installation of the pre lubrication pump.
Test the system and record the oil pressure
3.13 INSTRUMENTATION
Test the following alarms:
1. High engine cooling water alarm.
2. High engine lubrication oil temperature.
3. Low engine cooling water pressure.
3.14 4. Low engine lubrication oil pressure.
5. Low engine fuel oil pressure.
6. Low engine start air pressure.
7. Low cooling water headertank.
8. Low lubrication oil level.
Test the following engine safety devices:
1. High engine cooling water temperature.
3.15 2. Low engine lubrication oil pressure.
9. Engine over-speed.
10. High crankcase pressure

4.0 Electrical Installation Verification.


Examine the cleanliness of the exterior / interior of the generator
4.1
set’s cabinet.
4.2 Verify whether all cables to the console are properly and securely
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.3.doc Originator GW 4

installed on the cable tray.


Confirm that the contactors, fuses and cables of control circuitry
4.3
are of the suitable type and rating.
Ensure that the junction boxes and terminal boxes and controls
4.4
are properly identified.
Ensure that the cable glands of the terminal and junction boxes
4.5
are properly installed and the cables correctly terminated.
4.6 Ensure that all electrical cables have been checked for continuity.

5.0 Commissioning
Verify that the mechanical preventative maintenance system has
5.1
been implemented and updated to suit the present installation.
Verify that the electrical preventative maintenance system has
5.2
been implemented and updated to suit the present installation.
5.3 Check the oil level in the governor.
5.4 Check the oil level in the engine sump.
Check the oil level in the air motor lubricator and confirm the
5.5
lubricator is set up correctly.
5.6 Check the cooling water level in the water header tank.
5.7 Confirm the engine cooling water has been adequately treated.
Check the daily fuel tank has been filled with sufficient clean diesel
5.8
fuel
Inspect the fuel lines to- and on the engine. Piping, hoses, filters
5.9
and connections: Supply and return hoses at the engines are ¾”
The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.10
installation drawing / procedure. All equipment shall be
permanently mounted.
All piping system systems shall be hydro tested, pickled,
5.11 passivated and / or flushed in accordance with the manufacturer’s
recommendations or otherwise required.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems
5.12
shall be tested for continuity, electrical integrity (megger tested)
and have been released for service.

LOAD TEST
5.11 See Bentec running test procedure in the attachment

Others:
Serial Numbers Gen-Set 1:
Generator:
Commissioning Check Sheet

Main Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15.047.2008 of
File Name 3001_Main Generator Set. No.3.doc Originator GW 4

Engine:

Serial Numbers Gen-Set 2:


Generator:
Engine:

Serial Numbers Gen-Set 3:


Generator:
Engine:

Attachments:
Commissioning Check Sheet

Emergency Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 00 1
Client DAFORA SA Date 15-07-2008 of
File Name 3001A_Emergency Generator.doc Originator GW 4

Description: Emergency Generator


Section: 3001A
Manufacturer: Caterpillar Type: C 15 ACERT
Engine No. FFJ00157
Date: Serial No.:
Generator No. L6B09142

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation,


2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Check that all indicators and valves are properly and correctly
3.1
labelled.
Confirm the security and tightness of all connections:
1. Fuel oil lines (internal lines, onboard tank)
3.2 02 / 02 GW
2. Lubrication oil lines
3. Exhaust gas system lines
a) Verify ventilation dampers are operational prior to test run
b) Carry out a pre-commissioning check on the engine,
generator alignment and radiator shutter system.
c) Check the engine oil level, radiator water and fuel supply.
3.3 d) Check the operation of the heaters in the engine cooling 02 / 02 GW
water system.
e) Check the tension of the fan belts.
f) Inspect the battery / air starter.
g) Check the spark arrestor installation……..Not Fitted
Check the condition of all connection hoses and connection
3.4 02 / 02 GW
bellows for chafing and deterioration.
3.5 Examine the exhaust pipe lagging for completeness. 02 / 02 GW
Commissioning Check Sheet

Emergency Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 00 2
Client DAFORA SA Date 15-07-2008 of
File Name 3001A_Emergency Generator.doc Originator GW 4

Inspect the engine-mounted piping and the related piping system,


3.6 02 / 02 GW
and confirm that all supports are properly installed.
Operate all engine-related valves and make sure they operate
3.7 02 / 02 GW
freely.
Carry out a random check and verify the lash adjusters and 02 / 02 Part
3.8 injectors are set in accordance with the manufacturer’s of pre-FAT GW
instructions. check
N/A
Move the fuel rack and confirm it is operating smoothly without
3.9 Electronic
binding, and all the injector racks following correctly.
control
Carry out a random crankcase and top deck inspection and verify 02 / 02 Part
3.10 all bolts / nuts are tight. Ensure no loose items are left in the sump of pre-FAT GW
before charging the lubrication oil. check
02 / 02 Part
Obtain alignment readings of the generator flex coupler to the
3.11 of pre-FAT GW
engine flywheel.
check
Check that the starter motor exhaust ports are directed away from
3.12 02 / 02 GW
personnel and from walk and passage ways.

3.13 INSTRUMENTATION
Test the following alarms:
1. High engine cooling water alarm.
2. High engine lubrication oil temperature.
3. Low engine cooling water pressure.
3.14 4. Low engine lubrication oil pressure.
5. Low engine fuel oil pressure.
6. Low engine start air pressure.
7. Low cooling water headertank.
8. Low lubrication oil level.
Test the following engine safety devices:
1. High engine cooling water temperature.
3.15 2. Low engine lubrication oil pressure.
9. Engine over-speed.
10. High crankcase pressure

4.0 Electrical Installation Verification.

Examine the cleanliness of the exterior / interior of the generator


4.1 02 / 02 GW
set’s cabinet.
Verify whether all cables to the console are properly and securely
4.2 02 / 02 GW
installed on the cable tray.
Confirm that the contactors, fuses and cables of control circuitry
4.3 02 / 02 GW
are of the suitable type and rating.
Ensure that the junction boxes and terminal boxes and controls
4.4 02 / 02 GW
are properly identified.
Ensure that the cable glands of the terminal and junction boxes
4.5 02 / 02 GW
are properly installed and the cables correctly terminated.
02 / 02 As
4.6 Ensure that all electrical cables have been checked for continuity. per E-check GW
sheets
Commissioning Check Sheet

Emergency Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 00 3
Client DAFORA SA Date 15-07-2008 of
File Name 3001A_Emergency Generator.doc Originator GW 4

5.0 Commissioning

Verify that the mechanical preventative maintenance system has Contractors


5.1
been implemented and updated to suit the present installation. policy
Verify that the electrical preventative maintenance system has Contractors
5.2
been implemented and updated to suit the present installation. policy
No governor,
5.3 Check the oil level in the governor. electronic
control
5.4 Check the oil level in the engine sump. 02 / 02 GW
Electric
Check the oil level in the air motor lubricator and confirm the
5.5 starting
lubricator is set up correctly.
system
5.6 Check the cooling water level in the water header tank. 02 / 02 GW
5.7 Confirm the engine cooling water has been adequately treated. 02 / 02 GW
The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
5.8
installation drawing / procedure. All equipment shall be
permanently mounted.
All piping system systems shall be hydro tested, pickled,
5.9 passivated and / or flushed in accordance with the manufacturer’s
recommendations or otherwise required.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems
5.10
shall be tested for continuity, electrical integrity (megger tested)
and have been released for service.
LOAD TEST
1. Run the engine @ 25% for 10 minutes

2. Run the engine @ 50% for 10 minutes


5.11
3. Run the engine @ 75% for 10 minutes

4. Run the engine @ 100% for 20 minutes

Perform a parallel running test as per BENTEC test method and


5.12
record the results on the Data Sheet.
5.13 Specify retest program on production site

Others:
Emergency GEN-Set compl. Serial No.:
Generator Serial No.
Motor Serial No.:

Attachments:
Commissioning Check Sheet

Emergency Generator Set


Rig 350 to Bentec AC Drilling Rig Rev. No. 00 4
Client DAFORA SA Date 15-07-2008 of
File Name 3001A_Emergency Generator.doc Originator GW 4
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6

Description: Air Compressor No.2, Air Receiver Tank, Air Dryer, Air Distribution
Section: 3003,3004,3005
Manufacturer: Friede (Atlas Copco) Type:
Date: Serial No.: See item others

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Air Compressor No.2
Type GA 45-150 E2 P/HAV
Serial No.
Motor rating 45 kw.
Capacity: 6.5 cub/meter/min @ 10 bar
The GA 45 type compressor is a single stage, oil injected screw
type compressor with an electrical driven motor. The compressors
are air cooled. The compressors are enclosed in a sound proof
enclosure. The control of the compressor is by the Atlas Copco
Electronicon II system, which is fitted in the right side door of the
enclosure.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.
1.4 Review certification of pressure relief valves
1.5 Review certification and pressure test reports of air vessels

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
3.2 Verify the compressor is properly positioned and fixed
Check ventilation system in the compressor room. There must be
3.3 sufficient ventilation to remove the generated heat and to prevent
an under pressure in the room
3.4 Test the operation of the automatic shutters in the ventilation
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6

system of the compressor room


Check that the automatic drain of the compressor is connected to
3.5
the oil-water separator
Check that the relief openings of the pressure relief valves on the
3.6
compressed air side are directed to a safe area.
Remove all transportation locks from the compressor.. Refer to
3.7
chapter 6.1 of the operations manual
Inspect air discharge piping from compressor to air drier and air
3.8
vessel. Operate all manual valves
3.
4.0 Electrical Installation Verification.
4.1 Electrical wiring is complete
4.2 Instrumentation installation is complete
Check that all equipment is in accordance with the requirements
4.3
for the areas in which the equipment operates.
Verify whether all cables to the electric motors and the starter
4.4
boxes are properly and securely installed on the cable tray.
Check that lock-out facilities are fitted on the motor starters and
4.5
that they are lined up for the use of pad locks

5.0 Cold Commissioning


Check oil level in the air separator. (GI) Can be checked in the
sight glass. Oil fill will be 14.1 liters
5.1
Note: when starting up, watch the oil level as it will change when
the oil piping will fill up.
Verify the setting of the Elektronikon II control system. For starting
up it should be set in the local control mode. When the air system
5.2
is completely installed, that can be changed to ‘remote control” or
LAN control
Before the first start, remove the un-loader and poor some oil
5.3
direct in the compressor. This should not be more than ¾ liter
Before the first start, remove the un-loader and poor some oil
5.4
direct in the compressor. This should not be more than ¾ liter
5.5 Test the emergency stop at the compressor control panel
5.6 Jog start the compressor and confirm direction of rotation.
Verify that all discharge valves are open at the compressor and at
5.7
the air vessel
Start the compressor and let it run unloaded for a few minutes.
5.8 Raise pressure and confirm unloading and loading of the
compressor as per setting of un loader valve
When more compressors are on line, test the sequence of starting
5.9
and “lead& slave” operation of the compressors
When running for en extended period, monitor the air temperature
5.10 and working of the air heat exchanger, oil level, water separator
and automatic drain valve and air filter warning system
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Air Drier Set. Made by Zander


Type KEN-MT 200-1400
Serial No.

The desiccant type air drier has two chambers filled with a reagent
material
Moist air is delivered to the first chamber by the compressor and
the air is led from the bottom up through the chamber where the
moist in the air is absorbed by the reagent material. The dry air is
led to the rig air system through an after filter. The absorbent
material in the other chamber is being regenerated by dry air that
flows in reverse direction through the chamber. The regeneration
and switch over of the chambers is an automatic, continuous
process.
3.0 Mechanical and / or Structural Completion Verification
Check the location of installation. There must be at least one
3.1
meter free space around and above the air drier
Inspect air piping to- and from the air drier. Operate all manual ball
3.2
valves, inlet, outlet and bypass
When pressure relief valves are fitted, check that the exhaust of
3.3
the valve is directed to a safe area
After connecting electricity: check the indications on the control
3.4 panel front. Diode powered lights indicate flow and status of the
chamber
Check that the silencer in the exhaust outlet is in good condition
3.5
and is properly fitted.
Check operation of the switch-over function and changing of
3.6
indication lights on the panel
When pressuring up the unit, watch the pressure gauge of the
3.7 active chamber come up and the pressure gauge of the
regenerating chamber fall to 0 bar.
All ball valves must be opened very slowly as rapid pressure
3.8 changes can course damage to the desiccant material and to the
drier unit
When the regenerating process proceeds, the pressure might rise
3.9
a bit but should never exceed 0.3 bars. (Staudruck)
3.10 Monitor the dew point on the digital display on the control panel.

Air pressure vessels.


2 x 1,000 liters. Max. allowable pressure is 16 bars
Serial No.

Two air vessels are installed in the air compressor room. These
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6

vessels have a capacity of 1,000 liter each and have a max.


allowable pressure of 16 bars.
A pressure relief valve is fitted to each vessel. A manual valve
with an automatic operated drain valve is fitted at the bottom of
each vessel. These drains are connected to the oil separator

3.0 Mechanical and / or Structural Completion Verification


3.1 Visually inspect air vessels and its fittings for damages
Operate all manual ball valves. Confirm that a pressure relief
3.2
valve is fitted
Check that the exhaust opening of the pressure relief valve is
3.3
directed to a safe area
3.4 Test the electrical operated automatic drain valve
3.5 Check that the drain valves are piped to the oil separator
When applying pressure to the vessel, check working of the
3.6
pressure gauge and check vessel and fittings for leaks.
Check that the Safe Working Load is displayed on the air pressure
3.7
vessels

Air Distribution System


The air distribution system on the rig comprises of piping, valves
and hoses. There are no additional air vessels fitted in the system
Via hoses from the air vessels in the compressor room, a valve
manifold is fitted at the DS of the lower rig structure. From there
the air consumers on the rig are connected.
3.0 Mechanical and / or Structural Completion Verification
Visually inspect all piping, hoses and hose connections, fittings
3.1
and valves in the rig air system,
3.2 Operate all valves and check for ease of operation
Test all air consumers on the rig for proper connections and flow
3.3
of compressed air.
Check that air hoses are fitted with approved couplings and that
3.4
safety wires are fitted

Oil / water Separator


Owemat type 6
The unit has a reservoir volume of 335 liters and must be filled
with 225 liters freshwater.
Two oil collecting tanks, each with a volume of 30 liters, are part of
the unit. In one of the chambers there are two filters installed,
one oleophilic pre filter with a volume of 9 liters and one
adsorption filter with a volume of 17 liters.
3.0 Mechanical and / or Structural Completion Verification
Check connections of the air compressor drains and the air vessel
3.1
drains to the pressure reducing chamber on top of the separator
Test the level indicator (5) in the top of the unit.
3.2 Open and turn over the top cover and check that the level indicator
extends out
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6

Fill up the unit with fresh water: page 16


1. Open the cover and check that the plastic bag has been
3.3 removed from the OEKOSORB filter
2. Fill op the dirt trap ( 3 Schmutzauffangbehalter) and the filter
house3. Stop filling up when water flows from the water outlet (8)
Checking of the oil outlet: page 22
1.With stabilized water level the adjustment ring of the oil outlet
must be 1 cm above the water level
3.4 2. As water will fill the filter elements, the level will degrease
3. Refill with fresh water and the unit is ready for use
Note: in the begin the water can be black(ish) This is normal and is
not a defect
Others:

Attachments:
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFURA SA Date 15-07-2008 of
File Name 3003, 3004, 3005 Air Compressor No.2.doc Originator GW 6
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6

Description: Air Compressor No.1, Air Receiver Tank, Air Dryer, Air Distribution
Section: 3003,3004,3005
Manufacturer: Friede (Atlas Copco) Type: GA 45
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
Air Compressor No.1
Type GA 45-150 E2 P/HAV
Serial No.
Motor rating 45 kw.
Capacity: 6.5 cub/meter/min @ 10 bar
The GA 45 type compressor is a single stage, oil injected screw
type compressor with an electrical driven motor. The compressors
are air cooled. The compressors are enclosed in a sound proof
enclosure. The control of the compressor is by the Atlas Copco
Electronicon II system, which is fitted in the right side door of the
enclosure.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.
1.4 Review certification of pressure relief valves
1.5 Review certification and pressure test reports of air vessels

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
3.2 Verify the compressor is properly positioned and fixed
Check ventilation system in the compressor room. There must be
3.3 sufficient ventilation to remove the generated heat and to prevent
an under pressure in the room
3.4 Test the operation of the automatic shutters in the ventilation
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6

system of the compressor room


Check that the automatic drain of the compressor is connected to
3.5
the oil-water separator
Check that the relief openings of the pressure relief valves on the
3.6
compressed air side are directed to a safe area.
Remove all transportation locks from the compressor.. Refer to
3.7
chapter 6.1 of the operations manual
Inspect air discharge piping from compressor to air drier and air
3.8
vessel. Operate all manual valves
3.
4.0 Electrical Installation Verification.
4.1 Electrical wiring is complete
4.2 Instrumentation installation is complete
Check that all equipment is in accordance with the requirements
4.3
for the areas in which the equipment operates.
Verify whether all cables to the electric motors and the starter
4.4
boxes are properly and securely installed on the cable tray.
Check that lock-out facilities are fitted on the motor starters and
4.5
that they are lined up for the use of pad locks

5.0 Cold Commissioning


Check oil level in the air separator. (GI) Can be checked in the
sight glass. Oil fill will be 14.1 liters
5.1
Note: when starting up, watch the oil level as it will change when
the oil piping will fill up.
Verify the setting of the Elektronikon II control system. For starting
up it should be set in the local control mode. When the air system
5.2
is completely installed, that can be changed to ‘remote control” or
LAN control
Before the first start, remove the un-loader and poor some oil
5.3
direct in the compressor. This should not be more than ¾ liter
Before the first start, remove the un-loader and poor some oil
5.4
direct in the compressor. This should not be more than ¾ liter
5.5 Test the emergency stop at the compressor control panel
5.6 Jog start the compressor and confirm direction of rotation.
Verify that all discharge valves are open at the compressor and at
5.7
the air vessel
Start the compressor and let it run unloaded for a few minutes.
5.8 Raise pressure and confirm unloading and loading of the
compressor as per setting of un loader valve
When more compressors are on line, test the sequence of starting
5.9
and “lead& slave” operation of the compressors
When running for en extended period, monitor the air temperature
5.10 and working of the air heat exchanger, oil level, water separator
and automatic drain valve and air filter warning system
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Air Drier Set. Made by Zander


Type KEN-MT 1150
Serial No. 08/52867 Built: 2008

The desiccant type air drier has two chambers filled with a reagent
material
Moist air is delivered to the first chamber by the compressor and
the air is led from the bottom up through the chamber where the
moist in the air is absorbed by the reagent material. The dry air is
led to the rig air system through an after filter. The absorbent
material in the other chamber is being regenerated by dry air that
flows in reverse direction through the chamber. The regeneration
and switch over of the chambers is an automatic, continuous
process.
3.0 Mechanical and / or Structural Completion Verification
Check the location of installation. There must be at least one
3.1
meter free space around and above the air drier
Inspect air piping to- and from the air drier. Operate all manual ball
3.2
valves, inlet, outlet and bypass
When pressure relief valves are fitted, check that the exhaust of
3.3
the valve is directed to a safe area
After connecting electricity: check the indications on the control
3.4 panel front. Diode powered lights indicate flow and status of the
chamber
Check that the silencer in the exhaust outlet is in good condition
3.5
and is properly fitted.
Check operation of the switch-over function and changing of
3.6
indication lights on the panel
When pressuring up the unit, watch the pressure gauge of the
3.7 active chamber come up and the pressure gauge of the
regenerating chamber fall to 0 bar.
All ball valves must be opened very slowly as rapid pressure
3.8 changes can course damage to the desiccant material and to the
drier unit
When the regenerating process proceeds, the pressure might rise
3.9
a bit but should never exceed 0.3 bars. (Staudruck)
3.10 Monitor the dew point on the digital display on the control panel.

Air pressure vessels.


2 x 1,000 liters. Max. allowable pressure is 16 bars
Serial No. 202457 & 202259

Two air vessels are installed in the air compressor room. These
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6

vessels have a capacity of 1,000 liter each and have a max.


allowable pressure of 16 bars.
A pressure relief valve is fitted to each vessel. A manual valve
with an automatic operated drain valve is fitted at the bottom of
each vessel. These drains are connected to the oil separator

3.0 Mechanical and / or Structural Completion Verification


3.1 Visually inspect air vessels and its fittings for damages
Operate all manual ball valves. Confirm that a pressure relief
3.2
valve is fitted
Check that the exhaust opening of the pressure relief valve is
3.3
directed to a safe area
3.4 Test the electrical operated automatic drain valve
3.5 Check that the drain valves are piped to the oil separator
When applying pressure to the vessel, check working of the
3.6
pressure gauge and check vessel and fittings for leaks.
Check that the Safe Working Load is displayed on the air pressure
3.7
vessels

Air Distribution System


The air distribution system on the rig comprises of piping, valves
and hoses. There are no additional air vessels fitted in the system
Via hoses from the air vessels in the compressor room, a valve
manifold is fitted at the DS of the lower rig structure. From there
the air consumers on the rig are connected.
3.0 Mechanical and / or Structural Completion Verification
Visually inspect all piping, hoses and hose connections, fittings
3.1
and valves in the rig air system,
3.2 Operate all valves and check for ease of operation
Test all air consumers on the rig for proper connections and flow
3.3
of compressed air.
Check that air hoses are fitted with approved couplings and that
3.4
safety wires are fitted

Oil / water Separator


Owemat type 6
The unit has a reservoir volume of 335 liters and must be filled
with 225 liters freshwater.
Two oil collecting tanks, each with a volume of 30 liters, are part of
the unit. In one of the chambers there are two filters installed,
one oleophilic pre filter with a volume of 9 liters and one
adsorption filter with a volume of 17 liters.
3.0 Mechanical and / or Structural Completion Verification
Check connections of the air compressor drains and the air vessel
3.1
drains to the pressure reducing chamber on top of the separator
Test the level indicator (5) in the top of the unit.
3.2 Open and turn over the top cover and check that the level indicator
extends out
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6

Fill up the unit with fresh water: page 16


1. Open the cover and check that the plastic bag has been
3.3 removed from the OEKOSORB filter
2. Fill op the dirt trap ( 3 Schmutzauffangbehalter) and the filter
house3. Stop filling up when water flows from the water outlet (8)
Checking of the oil outlet: page 22
1.With stabilized water level the adjustment ring of the oil outlet
must be 1 cm above the water level
3.4 2. As water will fill the filter elements, the level will degrease
3. Refill with fresh water and the unit is ready for use
Note: in the begin the water can be black(ish) This is normal and is
not a defect
Others:

Attachments:
Commissioning Check Sheet

Air Compressor System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 15-07-2008 of
File Name 3003,3004,3005_Air CompressorNo.1.doc Originator GW 6
Commissioning Check Sheet

Mud Tank System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 4000_Mud Tank System.doc Originator GW 4

Description: Mud Tank System


Section: 4000
200 cub.meter Active
Manufacturer: Bentec Type:
syst.
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The following tanks are part of the rig:
1 x shaker tank with the following compartments:
sand trap of 14.3 cub.meter
desander tank of 22.7 cub.meter
desilter tank of 22.6 cub.meter
1 x intermediate tank of 70 cub.meter
3 x reserve tank of 41 cub.meter each. Total reserve volume is
123 cub.meter
1 x suction / mixing tank of 70 cub.meter: suction compartment is
48 cub.meter and two mixing tanks of 11 cub.meter each

1 x hopper skid with two mixers, one E-shower and two mixing
pumps
Total tank capacity is 200 cub.meter
Included in the system: one desander pump, one desilter pump,
one vacuum degasser, 10 agitators, valves, piping, mud guns and
a triptank of 3.2 cub.meter and a strip tank of 400 liters.

1.0 Equipment Documentation, Completeness Verification


Review the manufacturer’s documentation, equipment data and
1.1
specification.
1.2 Review the system’s class authority and statutory certification.
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
2.2 Review and amend the equipment acceptance and performance tests

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Visually inspect all butterfly valves in the mud systems
3.2
Can valve handles turn freely
Commissioning Check Sheet

Mud Tank System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 4000_Mud Tank System.doc Originator GW 4

3.3 Operate all valve handles and check for ease of operation
Internal inspection of all tanks, check for debris and defects:
Shaker tank:
1. sand trap tank
2. desander compartment
3.4 3. desilter compartment
4. mud ditch from shaker tank to suction tank
5. mud guns and swivelling arrangements
6. Dump valves
7. Grating, ladders, hatches and hand rails
Internal inspection of all tanks, check for debris and defects:
The two compartments of the intermediate tank:
3.5 1. dump valves
2. mud guns and swivelling arrangements
3. grating, ladders, hatches and hand rails
Internal inspection of all tanks, check for debris and defects.
Suction tank / mixing tank
1. suction compartment
2. mixing compartment 1 (11 cub.meter)
3.6
3. mixing compartment 2 (11 cub.meter)
4. dump valves
5. mud guns and swivels
6. grating, hatches, ladders, hand rails
Inspect hopper skid for debris and defect:
1. one raised hopper platform
2. two ventury type hoppers
3. two mixing pumps,
4. emergency shower
5. PPE locker
6. piping, valves
7. grating, hand rails, hatches, ladders
Visually inspect the installation of mud monitoring equipment. Floats or
sensors
Verify that all auxiliary piping has been flushed and is free of
3.7
contamination and debris.

Night time checks:


Inspect all work areas in the tank section at night and ensure they are
3.22
adequately lit to enable safe operations.
Ensure each light is undamaged and when fitted in elevated position,
3.25
check that the safety sling is fitted.
Apply power to the Mud System lighting and ensure all units are
3.26
operating.

4.0 Electrical Installation Verification.


Inspect for proper electrical installation of instruments and equipment
4.1 connected to the mud system, its supporting system(s), controls and
integrated system(s).
Visually inspect all cabling, support in cable trays or conduits asnd
4.2
cable glands being suitable for zone 1 application
Commissioning Check Sheet

Mud Tank System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 4000_Mud Tank System.doc Originator GW 4

Check that starters of agitators, centrifugal pumps etc are identified


4.3
and marked
4.4 Check accessibility and marking of emergency stop buttons
4.5 Test communication system with drill floor

5.0 Cold Commissioning


Fill up one tank with fresh water and check for leakages of”
Dump valves, suction valves, equalizing valves, piping
Inspect bulk heads at the adjacent tanks for leakages
Line up one mixing pump and transfer the water to the next tank.
Pump from tank to tank testing suction/and discharge lines and valves
until all tanks and tank sections have been filled up and checked for
leakages. Tanks to be filled up and checked:
Suction tank/mixing tank
Shaker tank : sand trap
Desander compartment
Desilter compartment
Intermediate tank
Line up mixing pump and circulate via discharge line at the top side of
the tanks.
Test all valves in this system by opening them one by one and check
flow and stopping of flow when manually operating this lave.
Do this with all valve is the transfer line at all tanks
Open the valves to the mud guns one by one. Operate the swivels of
each mud gun and watch the flow of water from the nozzle
Number of mud guns:
Three (3) in the intermediate tank
One (1) in each mixing tank= total 2
Two (2)in the suction tank
One (1) in the shaker tank
One (1) in the degasser tank
Line up both mixing pumps and circulate via the mixing lines over both
mixing tanks. Test all valves in these lines at the pumps and at the
tanks
Pump through the mixers and check vacuum through the hoppers.
Test all valves in these lines.
Line up the desilter pump and pump water through the desilter unit.
Test the valves in the system
Monitor flow through the desilter unit and the return to the desilter tank
Line up the desander pump and pump through the desander unit. Test
the valves in the system
Monitor flow through the desanderunit and the returns to the desander
tank

06 Hot Commissioning
Mix mud and repeat the testing according to the cold commissioning
procedures
Commissioning Check Sheet

Mud Tank System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-2008 of
File Name 4000_Mud Tank System.doc Originator GW 4

Others:

Attachments:
Commissioning Check Sheet

Emergency Shower
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DARFORA AS Date 16-07-2007 of
File Name 4001E_Emergency Shower.doc Originator GW 3

Description: Emergency Shower


Section: 4001E
Manufacturer: BENTEC GmbH/Hughes Type: EXP-AH-5G/10G
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
1.2 Verify the visual inspection reports
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Review the manufacturer documentation, equipment data and
2.1
specification.
Evaluate the manufacturer’s factory acceptance documentation, and
2.2
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.3
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


GENERAL
Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
3.2 Verify that the complete unit is not damaged during transportation
3.3 Verify the free movement of the main valve
Verify and ensure that the unit is properly connected to the supply
3.3
line
3.4 Verify the correct connection of the water line of 1 ¼” male coupling
Verify if the main valve of the shower operates smoothly and is not
3.5
sticking
Verify if the valve of the hand shower is operating smoothly and is
3.6
not sticking
Verify if the safety shower is located according the safety plan
3.7 drawing 1-97.98-1021067 in the south corner of the mud mixing
area.
Verify if the base plate is correctly fastened and that proper bolts are
3.8
used
Commissioning Check Sheet

Emergency Shower
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DARFORA AS Date 16-07-2007 of
File Name 4001E_Emergency Shower.doc Originator GW 3

4.0 Electrical Installation Verification.


Verify the correct installation of the wire for the heater
Verify the correct installation of the power cables (entering from the
4.1
bottom side or from the side)
Verify that conductivity test are performed on the supply cables and
4.2
on the earthing wire
4.3 Verify the correct installation of the earthing wire

5.0 Cold Commissioning


Verify that the mechanical preventive maintenance system has been
5.1
implemented and updated to suit the present installation.
Verify that the electrical preventive maintenance system has been
5.2
implemented and updated to suit the present installation.
Test the safety shower by conducting the following procedure:
5.3
Open shower and verify if water is sprayed properly
Function test the heating element:
• Ensure that the electrical supply is connected
• Connect a clamp meter to the power cables
• Turn thermostat all the way down n(no current should be
measured
5.4
• Turn the thermostat slowly up till switching point (measure
current)
• Turn set point a bit below the switching point and observe
heating of the water and the automatic switch off of the
thermostat

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Data and Details.

Others:
Commissioning Check Sheet

Emergency Shower
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DARFORA AS Date 16-07-2007 of
File Name 4001E_Emergency Shower.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Mud Agitator
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 4003_Mud Agitator No.1 doc.doc Originator GW 3

Description: Mud Agitator No.1, D = 900mm, Shaker Tank


Section: 4003
Manufacturer: Bentec Type: MAG 7,5 H
Date of manufac. 2008 Serial No.: 8851842 / 3

ACCEPTANCE METHOD
No.2, Desiltertank 8551842 / 4. No.3, 8851842 / 2. No.4, Suctiotank 8851841 / 1.
No.5, Suctiontank 88511842 / 9. No.6, Mix.II 8851841 / 2. No.7, Mix I 8851841 /
Resources: 3. No.8, Interm 1 8851842 / 7. No.9, 8851842 / 8. No.10, Interm 2 8851842 / 10.
No. 11, Interm 2 8851842 / 5. No.12, Interm 3 8851842 / 1. No.13 Interm. 3
8851842 / 6
: Time involved Date Signature
The mud agitators are used to maintain movement and internal flow of
the mud in the mud tanks, and thus maintain a homogeneous mixture
and prevent solidifying of the mud.
A mud agitator consists of a few components:
A paddle on a agitator shaft driven by an electrical motor via a gear box
On this rig there are a total of 10 agitators fitted. There are a total of 13
agitators installed in the mud system. All agitators are similar
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As and
1.2
when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance tests.
2.2
(As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment. This
3.1
may include, but is not limited to, lockout / tag-out, ventilation, work
permits and safety barriers.
Inspect fastenings and foundation bolts of the agitators on top of the
3.2 29 / 01 GW
mud tanks
Inspect the oil level in the gear box of the agitator.
3.3 29 / 01 GW
Filling requires approx. 10 liters of good quality gear oil
29 / 01
No vent
Check available oil dip stick and aeration plug in gear box. Confirm that plug
3.4 GW
the aeration opening is not restricted or blocked. fitted. No
dip stick
available
Commissioning Check Sheet

Mud Agitator
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 4003_Mud Agitator No.1 doc.doc Originator GW 3

3.5 Rotate agitator motor by hand 29 / 01 GW


Inspect positioning of paddle in the mud tank. The paddle should be in
3.6 the center of the tank and there should be 500 mm between the paddle 29 / 01 GW
and the tank bottom
Manually rotate the paddle in both directions and feel the back lash of
3.7 the gear box. 29 / 01 GW
Check agitator shaft for straightness
3.8 Inspect the shaft bearing for signs of oil leakage. 29 / 01 GW
Confirm that there is no interference from ladders, reach rods, bulk
3.9 heads or other objects and that the flow of mud in the tank will not be 29 / 01 GW
obstructed.

4.0 Electrical Installation Verification.


4.1 Electrical wiring is complete see motor check sheet
4.2 Instrumentation installation is complete
Check that all equipment is in accordance with the requirements for the
4.3
areas in which the equipment operates.
Verify whether all cables to the electric motors and the starter boxes are
4.4
properly and securely installed on the cable tray.
Ensure that the junction boxes, terminal boxes and controls are properly
4.5
identified and marked
Check that lock-out facilities are fitted on the motor starters and that they
4.6
are lined up for the use of pad locks
Individual emergency stops are not fitted. Test the general emergency
stop (trip) of the whole mud cleaning plant

5.0 Cold Commissioning


Start the agitator and check rotation. Confirm that the agitator paddle
5.1 and shaft are not swinging and rotate smoothly
Record Amperes of the motor
When the tank is filled with water or mud, run the agitator for a number
5.2
of hours (minimum 2 hours)
Check the temperature of motor and gearbox
5.3
Record Amperes of the motor
5.4 Note for excessive noises, leakages, vibrations etc
Witness the swirl of the fluid in the tank and ensure that the flow of the
5.5
fluid is unrestricted and forceful
Check that there is no air intake (aeration) of the fluid. This would
indicate a wrong positioning of the paddle.

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Mud Agitator
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 4003_Mud Agitator No.1 doc.doc Originator GW 3

Remarks
01 Ventplugs to be fitted in the gear boxes 29 / 01 GW
02 Paddle of agitator No.1 not yet fitted 29 / 01 GW
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump A.doc Originator GW 3

Description: Charging Pump A


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-6 X 5-14-30-1000-50

Date: 07-2008 Serial No.: M 91262

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 6 X 5 X 14
with a 13” impeller installed

The pump is fitted with a 30 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
3.3 15 / 01 GW
handles can be moved open & close
3.4 Open suction strainer, inspect internals and cover seal
15 / 01
Pump must
3.5 Verify that there is sufficient space for maintenance. GW
be removed
for that
3.6 Before filling with water or medium assure the pipe cleaning protocol
3.7 Check lubrication if applicable
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump A.doc Originator GW 3

3.8 Remove coupling and check free rotation by hand 15 / 01 GW


Check that all foundation bolts and flange bolts are fitted and
3.9 15 / 01 GW
secured
3.10 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump A.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump B.doc Originator GW 3

Description: Charging Pump B


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-6 X 5-14-30-1000-50

Date: 07-2008 Serial No.: M 91263

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 6 X 5 X 14
with a 13” impeller installed

The pump is fitted with a 30 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
3.3 15 / 01 GW
handles can be moved open & close
3.4 Open suction strainer, inspect internals and cover seal
15 / 01
Pump must
3.5 Verify that there is sufficient space for maintenance. GW
be removed
for that
3.6 Before filling with water or medium assure the pipe cleaning protocol
3.7 Check lubrication if applicable
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump B.doc Originator GW 3

3.8 Remove coupling and check free rotation by hand 15 / 01 GW


Check that all foundation bolts and flange bolts are fitted and
3.9 15 / 01 GW
secured
3.10 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump B.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump C.doc Originator GW 3

Description: Charging Pump C


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-6 X 5-14-30-1000-50

Date: 07-2008 Serial No.: M 91264

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 6 X 5 X 14
with a 13” impeller installed

The pump is fitted with a 30 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
3.3 15 / 01 GW
handles can be moved open & close
3.4 Open suction strainer, inspect internals and cover seal
15 / 01
Pump must
3.5 Verify that there is sufficient space for maintenance. GW
be removed
for that
3.6 Before filling with water or medium assure the pipe cleaning protocol
3.7 Check lubrication if applicable
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump C.doc Originator GW 3

3.8 Remove coupling and check free rotation by hand 15 / 01 GW


Check that all foundation bolts and flange bolts are fitted and
3.9 15 / 01 GW
secured
3.10 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Mud Charging Pump


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-0708 of
File Name 4004_Charge Pump C.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Desander Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desander Pump.doc Originator GW 3

Description: Desander Pump


Section: 4004
Manufacturer: BENTEC GmbH Type: 8 x 6 x 14

Date: Serial No.: M 91260

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 6 X 5 X 14
with a 12.5” impeller installed

The pump is fitted with a 75 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
15 / 01 GW
handles can be moved open & close
3.3 Verify that there is sufficient space for maintenance. 15 / 01 GW
3.4 Before filling with water or medium assure the pipe cleaning protocol
3.5 Check lubrication if applicable
3.6 Remove coupling and check free rotation by hand 15 / 01 GW
3.7 Check that all foundation bolts and flange bolts are fitted and 15 / 01 GW
Commissioning Check Sheet

Desander Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desander Pump.doc Originator GW 3

secured
3.8 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:
Commissioning Check Sheet

Desander Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desander Pump.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Desilter Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desilter Pump.doc Originator GW 3

Description: Desilter Pump


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-8x6-14-75-1500-50

Date: 08-2007 Serial No.: M 91261

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 8 x 6 x 14
with a 12.5” impeller installed

The pump is fitted with a 75 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
15 / 01 GW
handles can be moved open & close
3.3 Verify that there is sufficient space for maintenance. 15 / 01 GW
3.4 Before filling with water or medium assure the pipe cleaning protocol
3.5 Check lubrication if applicable
3.6 Remove coupling and check free rotation by hand 15 / 01 GW
Check that all foundation bolts and flange bolts are fitted and
3.7 15 / 01 GW
secured
Commissioning Check Sheet

Desilter Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desilter Pump.doc Originator GW 3

3.8 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Attachments:
Commissioning Check Sheet

Desilter Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 4004_Desilter Pump.doc Originator GW 3
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump A.doc Originator GW 3

Description: Mixing Pump A


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-8x6- 14 - 90-1500-50

Date: 04 / 08 Serial No.: M 89492

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 8 x 6 x 14
with a 13” impeller installed

The pump is fitted with a 90 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
15 / 01 GW
handles can be moved open & close
3.3 Verify that there is sufficient space for maintenance. 15 / 01 GW
3.4 Before filling with water or medium assure the pipe cleaning protocol
3.5 Check lubrication if applicable
3.6 Remove coupling and check free rotation by hand 15 / 01 GW
Check that all foundation bolts and flange bolts are fitted and 15 / 01
3.7 GW
secured See note
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump A.doc Originator GW 3

3.8 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Bolts and nuts of the discharge flange connection missing and / or


01 15 / 01 GW
not torqued up

Attachments:
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump A.doc Originator GW 3
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump B.doc Originator GW 3

Description: Mixing Pump B


Section: 4004
Manufacturer: BENTEC GmbH Type: LCPU-8x6- 14 - 90-1500-50

Date: 04 / 08 Serial No.: M 89493

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 8 x 6 x 14
with a 13” impeller installed

The pump is fitted with a 90 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 15 / 01 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
15 / 01 GW
handles can be moved open & close
3.3 Verify that there is sufficient space for maintenance. 15 / 01 GW
3.4 Before filling with water or medium assure the pipe cleaning protocol
3.5 Check lubrication if applicable
3.6 Remove coupling and check free rotation by hand 15 / 01 GW
Check that all foundation bolts and flange bolts are fitted and 15 / 01
3.7 GW
secured See note
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump B.doc Originator GW 3

3.8 Check that all moving parts are protected by proper guards 15 / 01 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


5.1 With tanks filled with water, operate valves and fill up the pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the pits.
Run the pump for one hour while circulating over the pits
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Bolts and nuts of the discharge flange connection missing and / or


01 15 / 01 GW
not torqued up

Attachments:
Commissioning Check Sheet

Mixing Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-0/-2008 of
File Name 4004_Mixing Pump B.doc Originator GW 3
Commissioning Check Sheet

Triptank Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-07-2008 of
File Name 4004_Triptank Pump.doc Originator GW 3

Description: Triptank Pump


Section: 4004
LCPU-3 x 2-12.5-18.5-1500-
Manufacturer: BENTEC GmbH Type: 50
Date: 07-2007 Serial No.: M 93417

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
A Mission Magnum low pressure centrifugal pump: type 3 x 2 x 13
with a 12.5” impeller installed

The pump is fitted with a 18.5 kW electric motor


1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Evaluate the manufacturer’s factory acceptance documentation, and


2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
Verify the pump is properly positioned suction and discharge flange
3.2 02 / 02 GW
are free of stress
Check that suction and discharge valves are fitted and that all valve
02 / 02 GW
handles can be moved open & close
3.3 Verify that there is sufficient space for maintenance. 02 / 02 GW
3.4 Before filling with water or medium assure the pipe cleaning protocol
3.5 Check lubrication if applicable 02 / 02 GW
3.6 Remove coupling and check free rotation by hand 02 / 02 GW
Check that all foundation bolts and flange bolts are fitted and
3.7 02 / 02 GW
secured
Commissioning Check Sheet

Triptank Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-07-2008 of
File Name 4004_Triptank Pump.doc Originator GW 3

3.8 Check that all moving parts are protected by proper guards 02 / 02 GW

Electrical Installation Verification.


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
4.1
This may include, but is not limited to, lockout / tagout, ventilation,
work permits and safety barriers.
4.2 Electrical wiring is complete see motor check sheet
4.3 Instrumentation installation is complete
4.4 Check tag plate on motor for proper application of the electric motor
Inspect motor starter consoles for proper location, connection and
4.5
marking
4.6 Jog start the motor and check for direction of rotation

5.0 Cold Commissioning


With the trip tank filled with water, operate valves and fill up the
5.1
pump.
5.2 Remove air and inspect pump & piping for leaks
5.3 Close discharge valve and start pump
5.4 Record discharge pressure and Amperes.
Inspect sealing area, check for leaks, vibration of noises
Open discharge valve and record pressure and Amperes
Note: difference in Amperes with closed and open discharge valve
should be more that 10%
Check flow of water when pumping through the mud lines back to
5.5
the trip tank.
Run the pump for one hour while circulating over the trip tank
Check temperatures
5.6
Vibration and noises
Monitor amperes and pressures

6.0 Hot Commissioning


Repeat cold commissioning checks (after transportation to final
6.1
destination and before operation)

Others:

Attachments:
Commissioning Check Sheet

Triptank Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-07-2008 of
File Name 4004_Triptank Pump.doc Originator GW 3
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.1.doc Originator GW 3

Description: Shale Shaker No.1


Section: 4008, 4008C, 4009, 4010
Manufacturer: MI Swaco Type: Mongoose PT
Date: 2008 Serial No.: MPB 159

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The Mongoose PT shale shaker is designed for pre-tensioned
screens with a wedge mounted system. There are four (4) pre-
tensioned screens and eight (8)wedges, four per side on the
shaker basket. The screens are placed on the screen bed and the
wedges are driven between each screen edge and support bars
on the shaker sidewalls. The screen bed is slightly crowded at the
center coursing the screen frames to bow when the wedges are
forced in place
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tag
out, ventilation, work permits and safety barriers.
3.2 Manually operate valves and gates in the flow system
Check mud flow system: open gates to the mud trough and to the
3.3
dump system
Visually inspect the shaker inlet header and operate the gates and
3.4
gate valves in the system
Inspect the connected pipe work and valves for damages and
3.5
proper connections
3.7 Inspect the foundation mounts or springs
Before starting, remove the transportation brackets (4) and bolts at
3.8 the foundation springs.
These should be stored for re-use
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.1.doc Originator GW 3

4.0 Electrical Installation Verification.


Verify that the installation of the system / equipment conforms to
4.1
the relevant installation drawings and manufacturer’s procedures.
Check that the installation material and techniques are suitable for
4.2
the environment and hazardous area application.
Verify whether all cables to the electric motors and the starter
4.3 boxes are properly and securely installed in the cable trays,
ladders or hangers.
Inspect starters for pumps and agitator motors. All must be
4.4
identified and marked
4.5 Visually check the earting wires of electric motors
Ensure that all electrical cables and the motor electrical integrity
4.6
have been verified by means of an insulation test.
4.7 Check lock-out facility at the starter box of the shaker
Test the general power trip (E-stop) of the entire mud
4.8
cleaning/processing plant
Check the direction of rotation of the electric motor. (5.1 in
4.9
operation manual)

5.0 Cold Commissioning


5.1 Inspect feed header box and operate gates and gate valves
Test the deck angle adjustment of the shaker. Should be from 3
5.2
degrees up to 3 degrees down. This must be done manually
Confirm that all grease points are operable and have been
5.3
greased before starting the performance test.
Inspect and operate the screen clamping arrangements. This is
5.3
done with eight (8) wedges per shaker
Jog start the shaker and check for excessive noises. Watch the
mounting springs and confirm that the shaker can move freely.

6.0 Hot Commissioning


Repeat the cold commissioning steps
In conjunction with the main mud pump tests, or by other means,
6.3 pump water down the return line and through the flow line and
over the shakers.
Operate the gates in the mud trough and check efficiency of the
6.4
system
6.8 Ensure the flow can be distributed evenly between the shakers.

Others:
Serialnumber Shaker 1:
Serialnumber Shaker 2:
Serialnumber Mud Cleaner:
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.1.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.2.doc Originator GW 3

Description: Shale Shaker No.2


Section: 4008, 4008C, 4009, 4010
Manufacturer: MI Swaco Type: Mongoose PT
Date: Serial No.: MPB 160

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The Mongoose PT shale shaker is designed for pre-tensioned
screens with a wedge mounted system. There are four (4) pre-
tensioned screens and eight (8)wedges, four per side on the
shaker basket. The screens are placed on the screen bed and the
wedges are driven between each screen edge and support bars
on the shaker sidewalls. The screen bed is slightly crowded at the
center coursing the screen frames to bow when the wedges are
forced in place
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tag
out, ventilation, work permits and safety barriers.
3.2 Manually operate valves and gates in the flow system
Check mud flow system: open gates to the mud trough and to the
3.3
dump system
Visually inspect the shaker inlet header and operate the gates and
3.4
gate valves in the system
Inspect the connected pipe work and valves for damages and
3.5
proper connections
3.7 Inspect the foundation mounts or springs
Before starting, remove the transportation brackets (4) and bolts at
3.8 the foundation springs.
These should be stored for re-use
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.2.doc Originator GW 3

4.0 Electrical Installation Verification.


Verify that the installation of the system / equipment conforms to
4.1
the relevant installation drawings and manufacturer’s procedures.
Check that the installation material and techniques are suitable for
4.2
the environment and hazardous area application.
Verify whether all cables to the electric motors and the starter
4.3 boxes are properly and securely installed in the cable trays,
ladders or hangers.
Inspect starters for pumps and agitator motors. All must be
4.4
identified and marked
4.5 Visually check the earting wires of electric motors
Ensure that all electrical cables and the motor electrical integrity
4.6
have been verified by means of an insulation test.
4.7 Check lock-out facility at the starter box of the shaker
Test the general power trip (E-stop) of the entire mud
4.8
cleaning/processing plant
Check the direction of rotation of the electric motor. (5.1 in
4.9
operation manual)

5.0 Cold Commissioning


5.1 Inspect feed header box and operate gates and gate valves
Test the deck angle adjustment of the shaker. Should be from 3
5.2
degrees up to 3 degrees down. This must be done manually
Confirm that all grease points are operable and have been
5.3
greased before starting the performance test.
Inspect and operate the screen clamping arrangements. This is
5.3
done with eight (8) wedges per shaker
Jog start the shaker and check for excessive noises. Watch the
mounting springs and confirm that the shaker can move freely.

6.0 Hot Commissioning


Repeat the cold commissioning steps
In conjunction with the main mud pump tests, or by other means,
6.3 pump water down the return line and through the flow line and
over the shakers.
Operate the gates in the mud trough and check efficiency of the
6.4
system
6.8 Ensure the flow can be distributed evenly between the shakers.

Others:
Serialnumber Shaker 1:
Serialnumber Shaker 2:
Serialnumber Mud Cleaner:
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-07-2008 of
File Name 4008_Shale Shaker No.2.doc Originator GW 3

Attachments:
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 16-07-2008 of
File Name 4008A_Mud Cleaner.doc Originator GW 3

Description: Mud Cleaner


Section: 4008, 4008C, 4009, 4010
Manufacturer: MI Swaco Type: Mongoose PT
Date: 2008 Serial No.: MPB 152

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The basics of the mud cleaner is a foundation of a shale shaker
fitted with a desilter unit and a desander unit on top. The purpose
of this setup is to concentrate on a small volume of the mud
circulation so that much finer screening can be done with the mud
cleaner than with the primary shakers which must handle the
entire circulating volume.
The capacity of the type 6T4 D-silter is 900 gpm
The capacity of the 212 type D-sander is 1,000 gpm
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tag
out, ventilation, work permits and safety barriers.
3.2 Manually operate valves and gates in the flow system
Check mud flow system: open gates to the mud trough and to the
3.3
dump system
Visually inspect the shaker, D-sander and D-silter for damage due
3.4
to transport or installation
Inspect the connected pipe work and valves for damages and
3.5
proper connections
Check that pressure gauges have been fitted to the headers and
3.6
that they are in a good condition
3.7 Inspect the foundation mounts or springs
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 16-07-2008 of
File Name 4008A_Mud Cleaner.doc Originator GW 3

Before starting, remove the transportation brackets (4) and bolts at


3.8 the foundation springs.
These should be stored for re-use
The clones of desilter/desander should be measured to handle
3.9 125 to 150% of the circulating volume. Check pump capacities for
this

4.0 Electrical Installation Verification.


Verify that the installation of the system / equipment conforms to
4.1
the relevant installation drawings and manufacturer’s procedures.
Check that the installation material and techniques are suitable for
4.2
the environment and hazardous area application.
Verify whether all cables to the electric motors and the starter
4.3 boxes are properly and securely installed in the cable trays,
ladders or hangers.
Inspect starters for pumps and agitator motors. All must be
4.4
identified and marked
4.5 Visually check the earting wires of electric motors
Ensure that all electrical cables and the motor electrical integrity
4.6
have been verified by means of an insulation test.
4.7 Check lock-out facility at the starter box of the shaker
Test the general power trip (E-stop) of the entire mud
4.8
cleaning/processing plant
Check the direction of rotation of the electric motor. (5.1 in
4.9
operation manual)

5.0 Cold Commissioning


5.1 Inspect feed header box and operate gates and gate valves
Test the deck angle adjustment of the shaker. Should be from 3
5.2
degrees up to 3 degrees down. This must be done manually
Confirm that all grease points are operable and have been
5.3
greased before starting the performance test.
Inspect and operate the screen clamping arrangements. This is
5.3
done with eight (8) wedges per shaker
Jog start the shaker and check for excessive noises. Watch the
mounting springs and confirm that the shaker can move freely.
D-sander
Fill up the degasser- and desilter tank and start the desander
pump with closed discharge valve. Check for leaks and record
pressure. Should be in the 3.2 bar region
Open the discharge valve and admit water to the desander unit.
Record pressure in the inlet header.
Check for leaks in the piping system. Feel the nozzle of the cone
and check for vacuum or discharge.
5.4 Monitor fluid return to the tank
D-silter
Fill up the degasser- and desilter tank and start the desilter pump
with closed discharge valve. Check for leaks and record pressure.
Should be in the 3.2 bar region
Commissioning Check Sheet

Shale Shaker Package


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 16-07-2008 of
File Name 4008A_Mud Cleaner.doc Originator GW 3

Open the discharge valve and admit fluid to the desilter unit
Check for leaks in the piping system. Feel the nozzle of the cone
and check for vacuum or discharge
Monitor fluid return back to the tank

6.0 Hot Commissioning


Repeat the cold commissioning steps
In conjunction with the main mud pump tests, or by other means,
6.3 pump water down the return line and through the flow line and
over the shakers.
Operate the gates in the mud trough and check efficiency of the
6.4
system
6.8 Ensure the flow can be distributed evenly between the shakers.

Others:
Serialnumber Shaker 1:
Serialnumber Shaker 2:
Serialnumber Mud Cleaner:

Attachments:
Commissioning Check Sheet

Mud Gas Separator


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client Darfora Date 07-08-2008 of
File Name Mud Gas Separator Originator GW 2

Description: Mud Gas Separator


Section: 4011
Manufacturer: Bentec Type: Poor Boy type
Date of
2008 Serial No.:
manufacture:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The Bentec Mud Gas Separator has a diameter of 48 “, an 8 “ mud
return line which creates the liquid mud seal of approx. 5‘ and a 8”
vent line. The vent line is not fitted in the mast but is secured with
a number of steel wires at 4 locations. The exhaust opening of the
vent line is approx 5 meters above the drill floor. A 6” butterfly
valve is fitted in the drain pipe at the bottom of the vessel.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
19 / 08 GW
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
19 / 08
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.
Spare parts GW
is N/A

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
3.2 Inspect unit for possible transportation damage 19 / 08 GW
Make a visual internal inspection of the vessel. Check for any 19 / 08
3.3
debris an that all openings are open
GW
When installed on its location, check for level seating of the 19 / 08
3.4
assembly
GW
Check for proper securing of the vent pipe. Inspect level 19 / 08
3.5
installation, steel wires, mountings and turn buckles.
GW
Visual inspect nuts and bolts in all flanges; 48” body flange, return 19 / 08
3.6
line, vent line, drain line and choke line
GW
3.7 Manually operate the 6” butterfly valve in the drain line. 19 / 08 GW
Visually inspect the Weco union of the choke connection: threads, 19 / 08
3.8
sealing surfaces and seal ring.
GW
Commissioning Check Sheet

Mud Gas Separator


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client Darfora Date 07-08-2008 of
File Name Mud Gas Separator Originator GW 2

Inspect installation of the mud return line and measure liquid mud
3.9
seal. Should be a minimum of 5 ‘
19 / 08 GW
Inspect choke line from choke manifold to mud gas separator inlet. Not fitted
3.10
Should be a high pressure piping
GW
yet
3.11 This choke line must be well supported and secured. Not fitted GW

4.0 Electrical Installation Verification.


N/A

5.0 Cold Commissioning


When all systems are hooked up: pump water through the choke
5.1 manifold and fill up the mud gas separator until water flows
through the return line back to the pit

Attachments:
Commissioning Check Sheet

Vacuum Degasser
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name 4012_Vacuum Degasser.doc Originator GW 3

Description: Vacuum Degasser


Section: 4012
Manufacturer: Bentec Type: DMD 1 - 250
Date: 2008 Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
This vacuum degasser acts as a separator of drilling fluid and
entrapped gas.
Drilling fluid is pumped to the degasser from the shaker tank
through the decentralization tube, where the fluid is pumped
through small openings and is devided into small particles. A
vacuum pump maintains a vacuum in the degasser vessel and the
entrapped gas is separated from the fluid. The vacuum pump
pumps the gas through the separator (5) and fluid particles are
collected in the separator vessel. This vessel must be regularly
drained. The gas free drilling fluid goes to another tank and is
ready for re-use.
Technical details:
Length: 4.7 meter. Wide: 1.1 meter. Height: 2.4 meter. Weight:
2500 kg
Max. circulation rate is 250 cub.meter/hour (4166 l/min.) with a
max. specific gravity of 2.4 kg/liter. The capacity of the pump must
be between 150 – 1500 l/min.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Verify the installation of the systems / equipment conforms to the
3.4
relevant installation drawings and manufacturer’s procedures.
3.5 Inspect the degasser, pipe work and valves for possible transport-
Commissioning Check Sheet

Vacuum Degasser
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name 4012_Vacuum Degasser.doc Originator GW 3

and installation damage.


Check that the vacuum pump has been filled up with the correct
3.6
grade of oil. Check oil level
Confirm that the V-belt and drive are in a good condition and
3.7
properly aligned.
3.8 Check that the degasser is securely mounted on the tank.
Exercise all manual valves and verify there is no binding and the
3.9
valves are easily accessible.
Check that the vacuum / pressure gauge has been fitted and that it
3.10
is in an undamaged condition
Operate the float mechanism and confirm the operation of the 3-
3.11
way valve
Review the positioning of the degasser in the tank. The inlet of the
3.12 degasser requires to be submersed for at least 8” to maintain
suction.
Check that the gas exhaust line vents at a safe location. Visually
3.13
inspect this line and its connections.

4.0 Electrical Installation Verification.


Verify that the installation of the system / equipment conforms to
4.1
the relevant installation drawings and manufacturer’s procedures.
Check that the installation material and techniques are suitable for
4.2
the environment and hazardous area application.
Verify whether all cables to the electric motors and the starter
4.3 boxes are properly and securely installed in the cable trays,
ladders or hangers.
Inspect the earthing wire of the electrical motor of the vacuum
4.4
pump
4.5 Check the starter box of the unit for markings and accessibility
4.5 Jog start the compressor motor and check rotation.

5.0 Cold Commissioning


Fill up the shaker tank with the suction pipe of the degasser.
5.1
Ensure that the suction opening is submersed.
Check the vacuum gauge, this gauge should indicate nearly zero
5.2
pressure.
Start the vacuum pump and check suction –and discharge piping
5.3
and valves of the vacuum pump system for leaks.
Confirm that the 3-way valve is closed as long as the fluid level in
5.4
the degasser is low.
Watch the vacuum gauge on the degasser shell, the unit should fill
5.5
up with fluid now.
When fluid comes out of the outlet piping, confirm sufficient flow
5.6
and watch the operation of the internal float and 3-way valve
Run degasser for some time (60 + minutes) and check
5.7
performance, temperatures, vibrations and other parameters.

6.0 Hot Commissioning


Commissioning Check Sheet

Vacuum Degasser
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name 4012_Vacuum Degasser.doc Originator GW 3

Repeat cold commissioning procedures with weighted mud in the


6.1
tanks

Remarks:
Commissioning Check Sheet

Fuel Distribution System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-2008 of
File Name Fuel Distribution System Originator GW 3

Description: Fuel Distribution System


Section: 5002
Manufacturer: BENTEC GmbH Type:
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The fuel distribution system starts with the four (4) fuel storage
tanks. The tanks are connected by a fuel hose to the fuel distribution
container. In this container there are two pumps which via a valve
manifold, can fill up the engine day tank or via a hose and a hand
held nozzle, can fill up small containers and the tank of the
emergency generator.
Solenoid valves and flow counters are fitted in the discharge of the
fuel oil distribution pumps.
An control panel, with fuel tank monitoring is fitted in the distribution
container. The system has been developed for automatic operation
of pump- and tank switch over operation. The three storage tanks
and the engine day tank have been made of steel and have double
walls. Leak alarms, based on maintaining a vacuum between the
two walls, are fitted at each tank. Filling capacity of a storage tank is
approx. 20,000 litres.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
1.3 Check that all relevant instruction manuals, workshop manuals and
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation, and
2.1
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification

Ensure all relevant personal protection equipment and procedural


requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
The fuel oil system and associated components shall be installed,
connected, fully assembled and adjusted in accordance with the
3.2
applicable installation drawing or procedure. All equipment shall be
permanently mounted.
Commissioning Check Sheet

Fuel Distribution System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-2008 of
File Name Fuel Distribution System Originator GW 3

All piping shall be hydro tested to 1-½ times design working


3.3
pressure.
Walk the system and check for adequate pipe hangers, hangers
3.4
bolted up tight, completeness, welding quality and system tightness.
Exercise the manual valves and verify there is no binding or other
3.5
problems.
3.6 Verify that all valves are properly labelled.
Inspect the hoses and quick disconnect couplings of the connections
3.7
at the tanks and at the distribution container.
Open the steel box at the frame of the storage tank and remove the
3.8 fire extinguisher. Check the unit for condition and last inspection
day
Open the steel box at the frame of the storage tank and inspect the
3.9
contents for condition
Operate all manual valves at the two fuel transfer pumps in the
3.10
distribution container
3.11 Manually rotate both pumps
Visually inspect the QD coupling and hose from the distribution
3.12
container to the engine skid
Confirm that electricity is connected and that the pump, tanks and
3.13
control / monitor panels in the distribution container, are live
Test the vacuum leak detectors of the storage tanks and of the
3.14
engine day tank

4.0 Electrical Installation Verification.


GENERAL
Verify whether all cables to the fuel oil system equipment and the
4.1 starter boxes are properly and securely installed on the cable tray or
fixed in another proper way.
Confirm that the contactors, fuses and cables of the equipment and
4.2
its control circuitry are of the suitable type and rating.
Are the junction boxes and terminal boxes and controls properly
4.3
identified?
Ensure that the cable glands of the terminal and junction boxes are
4.4
properly installed and the cables correctly terminated.
4.5 Check that each tank and container is properly bonded
4.6 Jog start both pumps and confirm direction of rotation
4.7 Test the emergency stop at the fuel control cubicle
Test the emergency stop at the transfer pump starter box in the
4.8
distribution container

5.0 Cold Commissioning


Ensure operation of the solenoid valve in the pump discharge when
5.1
starting the pump
Verify operation of the storage tank monitoring cubicle: temperatures
and levels
5.2
Verify operation of the engine day tank monitoring system,
temperature and level
Commissioning Check Sheet

Fuel Distribution System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-2008 of
File Name Fuel Distribution System Originator GW 3

Test automatic pumping system of the transfer pumps to the engine


5.3 day tank. These pumps will start when simulating low level in day
tank
Test automatic stopping of transfer pump when the day tank is at the
5.4
pre-designed level
Test automatic tank switch over function of pump suction. This can
5.5
be done by simulating a low level in the active storage tank.
When pumping or filling, check hoses, connection, piping and both
5.6
fuel flow counters

6.0 Hot Commissioning


Monitor automatic operation of the fuel distribution system

Attachments:
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Description: Mud Pump A (No. 1)


Section: 9001
Manufacturer: EWECO Type: E-1600
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
EWECO Triplex pump
Size 7” x 12”. Max. SPM 120
Rated HP = 1,600. Max rated pressure = 5,000 psi
Serial No. 16002507 and 16002607
Gear ratio: 4.4688 : 1
Liner size pressure GPM at 120 SPM
7” 3620 720
6-1/2” 4198 621
6” 4927 529
5-1/2” 5000 444
5” 5000 367
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Review the manufacturer documentation, equipment data and


2.1
specification.
Evaluate the manufacturer’s factory acceptance documentation, and
2.2
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.3
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


GENERAL
Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Check that the installation has been carried out according to the
3.2
factory instructions. Check for any transportation damage.
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Remove drain plug (18) from crankcase and drain any moisture
3.3
Fill up crankcase with EP gear oil (185 USG = 685 ltr)
Start external oil pump and make sure the pump is operating and
3.4
pumping oil through all the internal lube lines.
Open the side inspection covers and confirm oil lubrication of cross
3.5
heads and guides with external oil pump running
Check installation of discharge pulsation dampener. Discharge
3.6 dampener to be charged with approx. 1000 psi (1/3 of anticipated
working pressure) of Nitrogen
Check installation of suction dampener and strainer. Suction
3.7
dampener to be initially charged with 15 psi compressed air.
Fill the liner piston cooling tank with fresh water, It is recommended
3.8 that soluble oil be added to the cooling water.

Check that the H.P. relief valve is piped to the pits. The relief line
3.9
must be sloped down and be well supported.
Confirm that suction filters have been fitted and that covers and
3.10
seals are tight
Operate all valves in the system and confirm they are free to operate
3.11
and correctly labeled.
3.12 Visually inspect the installation and sitting of drive belts.
3.13 Check that covers are fitted around all couplings and moving parts
3.14 Check availability and closing of pony rod well covers.
Confirm the size and pressure rating of the installed liners. Must be
3.15
compatible with setting of pop off valve.

High Pressure Mud Piping


Review pressure test documents of high pressure mud pipe
3.16 sections. For 5,000 psi system the proof testing must be done at
7,500 psi
Visually inspect high pressure piping from the pump to the drill floor.
3.17 Piping must be well secured, properly supported and without
threaded connections
3.18 Inspect jumper hoses for condition and record certification data.
Confirm proper installation of safety wires and wire clamps on hoses
3.19
and structure
Witness pressure testing of high pressure mud lines and hoses. A
3.20
system pressure test of 5,000 psi is recommended.

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers are
4.1 of the proper size, run correctly and secured in accordance wit the
relevant regulations.
Inspect the motor cable and junction box cables entries, for proper
4.2 sealing and for correct termination. Verify that all terminal
connections are tight, if not already confirmed previously.
4.3 Ensure that all electrical cables have been checked for continuity.
Start the AC motor cooling fan and confirm the correct direction of
4.4
rotation. Minimum air flow is 1.4 cub.meter/sec
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Confirm correct direction of rotation for:


Charge pumps
4.5
External lubrication pump
Liner cooling pump
Remove the AC motor inspection cover and check that there is no
4.6
debris in the motor.
4.7 Confirm operation of anti-condensation heater in the AC motor.
Ensure the purge cycle is completed before the main AC motor
4.8
assignment is enabled.
Assign the drive motor and open the hand throttle slightly, check the
4.9
motor rotation.
Verify that upon AC blower loss an alarm is initiated, but the
assignment and controls remains available and an alarm sound, until
4.10 the throttle is cycled through “0”, then the power should not come
back to the AC motors. (As per the European standard EN 50016,
the unit will shut down at loss of purging).
Verify the correct operation of the motor’s ‘Lockout’ switch.
4.11
Test emergency stop systems of the electrical motors
When running, check motor for excessive noises, vibrations and
4.12
temperature

5.0 Cold Commissioning


Note liner size and setting of discharge relief valve.
5.1
Note: 10 % above maximum liner working pressure
Line up suction of pump from a filled up tank. Water can be used for
5.2
this test
Line up the discharge lines and hoses to the standpipe manifold on
the rig floor
5.3 Note: for this test the choke on the standpipe manifold should be
used. The return from this choke must go back to the suction tank
via hoses or chicksan’s. This return line must be well secured.
Confirm that pressure gauges and pressure monitoring systems are
5.4 connected and operational. During the test run the pressure
indications must be compared and adjusted when required.
Controls and indications in the drillers cabin must be operational.
5.5 During this testing the pumps must be controlled and monitored from
the drillers cabin.

6.0 Hot Commissioning


The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
6.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems shall
6.2
be tested for continuity, electrical integrity (megger tested) and have
been released for service.
Line up the mud charge pump.
6.3
Fully open the suction valves at the mud pump
Open the discharge valve at the pump, the valves to the stand pipe
6.4
manifold and the valves to the mud choke
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Ensure that the valve in the standpipe to the derrick is closed


Fully open the mud choke and confirm an open return back to the
6.5
suction tank
Start the mud pump and run idle for 30 minutes at 30 SPM and
6.6
without pressure. Witness returns back to the suction tank
Monitor pump and motors for noise, vibrations, temperatures and
6.7
pressures
Confirm proper operation and flows of liner wash pump and external
6.8
oil pump
Verify that charge pump delivery at correct pressure. During
6.9
pumping there must always be a positive pressure.
Verify that stroke counters are operational and read-backs at drillers
6.10
console and auto choke panel are correct.
6.11 Stop pump after 30 minutes and prepare for duration testing.

ENDURANCE TESTING. Fill in appendix II


6.12 Start pump and run at 60 strokes and 1,500 psi for a 30 minutes
6.13 Increase pressure to 2,500 psi and run for 30 minutes
Increase strokes to 80 and set pressure to maximum for liner size
6.14
and run for 30 minutes (set at 320 bar)
6.15 Increase strokes to 120 and run for 30 minutes (set at 150 bar)

Stop the mud pump and visually check for metal particle in the sump
6.16
(magnetic plug).
6.17 Take an oil sample and sent it in for analyzing.
.
Remarks:

Appendix I
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Jack shaft bearings


Cross Slides

eccentrics

Main
S/N =
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump A.doc Originator G.W 6

Appendix II
Mud Pump No.1 Endurance test.

Times / Left Right Motor Crankcase SPM Pump AC Real power


minutes hand hand bearing oil temp / output Motor consumption
main main temperature pressure pressure Amps
bearing bearing
temp temp T P
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Description: Mud Pump B (No. 2)


Section: 9001
Manufacturer: EWECO Type: E-1600
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
EWECO Triplex pump
Size 7” x 12”. Max. SPM 120
Rated HP = 1,600. Max rated pressure = 5,000 psi
Serial No. 16002507 and 16002607
Gear ratio: 4.4688 : 1
Liner size pressure GPM at 120 SPM
7” 3620 720
6-1/2” 4198 621
6” 4927 529
5-1/2” 5000 444
5” 5000 367
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Review the manufacturer documentation, equipment data and


2.1
specification.
Evaluate the manufacturer’s factory acceptance documentation, and
2.2
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.3
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


GENERAL
Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Check that the installation has been carried out according to the
3.2
factory instructions. Check for any transportation damage.
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Remove drain plug (18) from crankcase and drain any moisture
3.3
Fill up crankcase with EP gear oil (185 USG = 685 ltr)
Start external oil pump and make sure the pump is operating and
3.4
pumping oil through all the internal lube lines.
Open the side inspection covers and confirm oil lubrication of cross
3.5
heads and guides with external oil pump running
Check installation of discharge pulsation dampener. Discharge
3.6 dampener to be charged with approx. 1000 psi (1/3 of anticipated
working pressure) of Nitrogen
Check installation of suction dampener and strainer. Suction
3.7
dampener to be initially charged with 15 psi compressed air.
Fill the liner piston cooling tank with fresh water, It is recommended
3.8 that soluble oil be added to the cooling water.

Check that the H.P. relief valve is piped to the pits. The relief line
3.9
must be sloped down and be well supported.
Confirm that suction filters have been fitted and that covers and
3.10
seals are tight
Operate all valves in the system and confirm they are free to operate
3.11
and correctly labeled.
3.12 Visually inspect the installation and sitting of drive belts.
3.13 Check that covers are fitted around all couplings and moving parts
3.14 Check availability and closing of pony rod well covers.
Confirm the size and pressure rating of the installed liners. Must be
3.15
compatible with setting of pop off valve.

High Pressure Mud Piping


Review pressure test documents of high pressure mud pipe
3.16 sections. For 5,000 psi system the proof testing must be done at
7,500 psi
Visually inspect high pressure piping from the pump to the drill floor.
3.17 Piping must be well secured, properly supported and without
threaded connections
3.18 Inspect jumper hoses for condition and record certification data.
Confirm proper installation of safety wires and wire clamps on hoses
3.19
and structure
Witness pressure testing of high pressure mud lines and hoses. A
3.20
system pressure test of 5,000 psi is recommended.

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers are
4.1 of the proper size, run correctly and secured in accordance wit the
relevant regulations.
Inspect the motor cable and junction box cables entries, for proper
4.2 sealing and for correct termination. Verify that all terminal
connections are tight, if not already confirmed previously.
4.3 Ensure that all electrical cables have been checked for continuity.
Start the AC motor cooling fan and confirm the correct direction of
4.4
rotation. Minimum air flow is 1.4 cub.meter/sec
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Confirm correct direction of rotation for:


Charge pumps
4.5
External lubrication pump
Liner cooling pump
Remove the AC motor inspection cover and check that there is no
4.6
debris in the motor.
4.7 Confirm operation of anti-condensation heater in the AC motor.
Ensure the purge cycle is completed before the main AC motor
4.8
assignment is enabled.
Assign the drive motor and open the hand throttle slightly, check the
4.9
motor rotation.
Verify that upon AC blower loss an alarm is initiated, but the
assignment and controls remains available and an alarm sound, until
4.10 the throttle is cycled through “0”, then the power should not come
back to the AC motors. (As per the European standard EN 50016,
the unit will shut down at loss of purging).
Verify the correct operation of the motor’s ‘Lockout’ switch.
4.11
Test emergency stop systems of the electrical motors
When running, check motor for excessive noises, vibrations and
4.12
temperature

5.0 Cold Commissioning


Note liner size and setting of discharge relief valve.
5.1
Note: 10 % above maximum liner working pressure
Line up suction of pump from a filled up tank. Water can be used for
5.2
this test
Line up the discharge lines and hoses to the standpipe manifold on
the rig floor
5.3 Note: for this test the choke on the standpipe manifold should be
used. The return from this choke must go back to the suction tank
via hoses or chicksan’s. This return line must be well secured.
Confirm that pressure gauges and pressure monitoring systems are
5.4 connected and operational. During the test run the pressure
indications must be compared and adjusted when required.
Controls and indications in the drillers cabin must be operational.
5.5 During this testing the pumps must be controlled and monitored from
the drillers cabin.

6.0 Hot Commissioning


The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
6.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems shall
6.2
be tested for continuity, electrical integrity (megger tested) and have
been released for service.
Line up the mud charge pump.
6.3
Fully open the suction valves at the mud pump
Open the discharge valve at the pump, the valves to the stand pipe
6.4
manifold and the valves to the mud choke
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Ensure that the valve in the standpipe to the derrick is closed


Fully open the mud choke and confirm an open return back to the
6.5
suction tank
Start the mud pump and run idle for 30 minutes at 30 SPM and
6.6
without pressure. Witness returns back to the suction tank
Monitor pump and motors for noise, vibrations, temperatures and
6.7
pressures
Confirm proper operation and flows of liner wash pump and external
6.8
oil pump
Verify that charge pump delivery at correct pressure. During
6.9
pumping there must always be a positive pressure.
Verify that stroke counters are operational and read-backs at drillers
6.10
console and auto choke panel are correct.
6.11 Stop pump after 30 minutes and prepare for duration testing.

ENDURANCE TESTING. Fill in appendix II


6.12 Start pump and run at 60 strokes and 1,500 psi for a 30 minutes
6.13 Increase pressure to 2,500 psi and run for 30 minutes
Increase strokes to 80 and set pressure to maximum for liner size
6.14
and run for 30 minutes (set at 320 bar)
6.15 Increase strokes to 120 and run for 30 minutes (set at 150 bar)

Stop the mud pump and visually check for metal particle in the sump
6.16
(magnetic plug).
6.17 Take an oil sample and sent it in for analyzing.
.
Remarks:

Appendix I
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Jack shaft bearings


Cross Slides

eccentrics

Main
S/N =
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump B.doc Originator G.W 6

Appendix II
Mud Pump No.1 Endurance test.

Times / Left Right Motor Crankcase SPM Pump AC Real power


minutes hand hand bearing oil temp / output Motor consumption
main main temperature pressure pressure Amps
bearing bearing
temp temp T P
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

Description: Mud Pump C (No. 3)


Section: 9001
Manufacturer: EWECO Type: E-1600
Date: Serial No.:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
EWECO Triplex pump
Size 7” x 12”. Max. SPM 120
Rated HP = 1,600. Max rated pressure = 5,000 psi
Serial No. 16002507 and 16002607
Gear ratio: 4.4688 : 1
Liner size pressure GPM at 120 SPM
7” 3620 720
6-1/2” 4198 621
6” 4927 529
5-1/2” 5000 444
5” 5000 367
1.0 Equipment Documentation, Completeness Verification

Review the manufacturer’s documentation, equipment data and


1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, etc.)
Check that all relevant instruction manuals, workshop manuals and
1.3
spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.

Review the manufacturer documentation, equipment data and


2.1
specification.
Evaluate the manufacturer’s factory acceptance documentation, and
2.2
confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.3
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


GENERAL
Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the equipment.
3.1
This may include, but is not limited to, lockout / tag out, ventilation,
work permits and safety barriers.
Check that the installation has been carried out according to the
3.2
factory instructions. Check for any transportation damage.
3.3 Remove drain plug (18) from crankcase and drain any moisture
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

Fill up crankcase with EP gear oil (185 USG = 685 ltr)


Start external oil pump and make sure the pump is operating and
3.4
pumping oil through all the internal lube lines.
Open the side inspection covers and confirm oil lubrication of cross
3.5
heads and guides with external oil pump running
Check installation of discharge pulsation dampener. Discharge
3.6 dampener to be charged with approx. 1000 psi (1/3 of anticipated
working pressure) of Nitrogen
Check installation of suction dampener and strainer. Suction
3.7
dampener to be initially charged with 15 psi compressed air.
Fill the liner piston cooling tank with fresh water, It is recommended
3.8 that soluble oil be added to the cooling water.

Check that the H.P. relief valve is piped to the pits. The relief line
3.9
must be sloped down and be well supported.
Confirm that suction filters have been fitted and that covers and
3.10
seals are tight
Operate all valves in the system and confirm they are free to operate
3.11
and correctly labeled.
3.12 Visually inspect the installation and sitting of drive belts.
3.13 Check that covers are fitted around all couplings and moving parts
3.14 Check availability and closing of pony rod well covers.
Confirm the size and pressure rating of the installed liners. Must be
3.15
compatible with setting of pop off valve.

High Pressure Mud Piping


Review pressure test documents of high pressure mud pipe
3.16 sections. For 5,000 psi system the proof testing must be done at
7,500 psi
Visually inspect high pressure piping from the pump to the drill floor.
3.17 Piping must be well secured, properly supported and without
threaded connections
3.18 Inspect jumper hoses for condition and record certification data.
Confirm proper installation of safety wires and wire clamps on hoses
3.19
and structure
Witness pressure testing of high pressure mud lines and hoses. A
3.20
system pressure test of 5,000 psi is recommended.

4.0 Electrical Installation Verification.


Verify that the supply cables to the AC motors and the blowers are
4.1 of the proper size, run correctly and secured in accordance wit the
relevant regulations.
Inspect the motor cable and junction box cables entries, for proper
4.2 sealing and for correct termination. Verify that all terminal
connections are tight, if not already confirmed previously.
4.3 Ensure that all electrical cables have been checked for continuity.
Start the AC motor cooling fan and confirm the correct direction of
4.4
rotation. Minimum air flow is 1.4 cub.meter/sec
Confirm correct direction of rotation for:
4.5
Charge pumps
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

External lubrication pump


Liner cooling pump
Remove the AC motor inspection cover and check that there is no
4.6
debris in the motor.
4.7 Confirm operation of anti-condensation heater in the AC motor.
Ensure the purge cycle is completed before the main AC motor
4.8
assignment is enabled.
Assign the drive motor and open the hand throttle slightly, check the
4.9
motor rotation.
Verify that upon AC blower loss an alarm is initiated, but the
assignment and controls remains available and an alarm sound, until
4.10 the throttle is cycled through “0”, then the power should not come
back to the AC motors. (As per the European standard EN 50016,
the unit will shut down at loss of purging).
Verify the correct operation of the motor’s ‘Lockout’ switch.
4.11
Test emergency stop systems of the electrical motors
When running, check motor for excessive noises, vibrations and
4.12
temperature

5.0 Cold Commissioning


Note liner size and setting of discharge relief valve.
5.1
Note: 10 % above maximum liner working pressure
Line up suction of pump from a filled up tank. Water can be used for
5.2
this test
Line up the discharge lines and hoses to the standpipe manifold on
the rig floor
5.3 Note: for this test the choke on the standpipe manifold should be
used. The return from this choke must go back to the suction tank
via hoses or chicksan’s. This return line must be well secured.
Confirm that pressure gauges and pressure monitoring systems are
5.4 connected and operational. During the test run the pressure
indications must be compared and adjusted when required.
Controls and indications in the drillers cabin must be operational.
5.5 During this testing the pumps must be controlled and monitored from
the drillers cabin.

6.0 Hot Commissioning


The unit and all associated assemblies shall be connected, fully
assembled and adjusted in accordance with their applicable
6.1
installation drawing / procedure. All equipment shall be permanently
mounted.
All electrical systems shall be fully commissioned, and installed
conform their legislative requirements. All cables and systems shall
6.2
be tested for continuity, electrical integrity (megger tested) and have
been released for service.
Line up the mud charge pump.
6.3
Fully open the suction valves at the mud pump
Open the discharge valve at the pump, the valves to the stand pipe
6.4 manifold and the valves to the mud choke
Ensure that the valve in the standpipe to the derrick is closed
Fully open the mud choke and confirm an open return back to the
6.5
suction tank
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 4
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

Start the mud pump and run idle for 30 minutes at 30 SPM and
6.6
without pressure. Witness returns back to the suction tank
Monitor pump and motors for noise, vibrations, temperatures and
6.7
pressures
Confirm proper operation and flows of liner wash pump and external
6.8
oil pump
Verify that charge pump delivery at correct pressure. During
6.9
pumping there must always be a positive pressure.
Verify that stroke counters are operational and read-backs at drillers
6.10
console and auto choke panel are correct.
6.11 Stop pump after 30 minutes and prepare for duration testing.

ENDURANCE TESTING. Fill in appendix II


6.12 Start pump and run at 60 strokes and 1,500 psi for a 30 minutes
6.13 Increase pressure to 2,500 psi and run for 30 minutes
Increase strokes to 80 and set pressure to maximum for liner size
6.14
and run for 30 minutes (set at 320 bar)
6.15 Increase strokes to 120 and run for 30 minutes (set at 150 bar)

Stop the mud pump and visually check for metal particle in the sump
6.16
(magnetic plug).
6.17 Take an oil sample and sent it in for analyzing.
.
Remarks:

Appendix I
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 5
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

Jack shaft bearings


Cross Slides

eccentrics

Main
S/N =
Commissioning Check Sheet

Mud Pump
Rig 350 to Bentec AC Drilling Rig Rev. No. 01 6
Client DAFORA SA Date 15-07-08 of
File Name 9001_Mud Pump C.doc Originator G.W 6

Appendix II
Mud Pump No.1 Endurance test.

Times / Left Right Motor Crankcase SPM Pump AC Real power


minutes hand hand bearing oil temp / output Motor consumption
main main temperature pressure pressure Amps
bearing bearing
temp temp T P
Commissioning Check Sheet

Gas Detection System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 1
Client Euro Rig No.5 Date 06-08-2008 of
File Name 11003 Gas Detection System Originator GW 3

Description: Gas Detection System


Section: 11003
Manufacturer: Honeywell Analytics AG Type: Touchpoint 4
Date of
2008 Serial No.:
manutacture:

ACCEPTANCE METHOD
Resources:
Time involved Date Signature
The Zareba Touchpoint 4 gas detection system is made by
Honeywell Analytics. The system can be equipped with up to four
Zareba Sensepoint gas sensors for explosive gas CH 4 or for
H2S. The system works independent and can be adjusted and
calibrated according to requirements.
Components of the system on this rig are: Three sensors to
detect 0 – 10%0 CH4. As per standard these sensors will be fitted
at the Bell Nipple, Shaker Header box and one location to be
selected (mud tanks or degasser outlet)
One integrated monitor unit
One alarm / flash light
One acoustic alarm
One calibration unit
All these components are of thre Eex D version.
1.0 Equipment Documentation, Completeness Verification
Review the manufacturer’s documentation, equipment data and
1.1
specification.
Review the system’s class authority and statutory certification. (As
1.2
and when required, such as API, NACE, IEEE, ANSI, DIN etc.)
1.3 Check that all relevant instruction manuals, workshop manuals
and spare parts manuals are on file onboard the installation.

2.0 Factory Acceptance Test & Site Acceptance Test.


Evaluate the manufacturer’s factory acceptance documentation,
2.1
and confirm the unit has been released for installation.
Review and amend the equipment acceptance and performance
2.2
tests. (As required)

3.0 Mechanical and / or Structural Completion Verification


Ensure all relevant personal protection equipment and procedural
requirements have been satisfied prior to accessing the
3.1
equipment. This may include, but is not limited to, lockout / tagout,
ventilation, work permits and safety barriers.
Inspect the monitoring unit and gas sensors for possible
3.2
transportation damage
Inspect the positioning of the monitoring unit and review the proper
3.3
fitting and support.
Inspect the positioning of the sensors ( 3 locations) and review the
3.4
proper fitting and support.
Commissioning Check Sheet

Gas Detection System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 2
Client Euro Rig No.5 Date 06-08-2008 of
File Name 11003 Gas Detection System Originator GW 3

Are the sensors protected against impact and / or mechanical


3.5
damage
Check wiring of the sensors to the monitoring unit. Must be fitted
3.6
in proper cable trays.
Confirm that the work area of the sensors is not obstructed by
3.7
objects or structures.
3.8 Check installation and wiring of the alarm / flash light
3.9 Check installation and wiring of the acoustic alarm
Confirm that one calibration unit is part of the delivery and that this
3.10
unit is available on the spot.
3.11 Confirm that test gas and a test canister holder are available

4.0 Electrical Installation Verification.


4.1 Check that the electrical wiring is complete
4.2 Instrumentation installation is complete
Check that all equipment is in accordance with the requirements
4.3 for the areas in which the equipment operates. All components
must be Eex D
Ensure that the cable glands of the terminal and junction boxes
4.4
are properly installed and that the cables are correctly terminated
4.5 Ensure that all electrical cables have been checked for continuity.
Confirm electric supply of 265 V AC at 50/60 Hz. This will be
4.6
internally converted into 16 – 32 V DC:
4.7 When connected, check power available indication (green)
Test the Test / Accept / Reset button and check indication lights
Green : power available
4.8
Red: alarm
Yellow: failure

5.0 Cold Commissioning


5.1 Set LEL at set point (depending on test gas mix)
5.2 Activate each of the sensors by using the test gas canister.
Watch the display at the monitoring unit. The alarm must be
triggered at the set value
5.3
Alarm 1 at 20% LEL
Alarm 2 at 40% LEL
5.4 Watch maximal reading at the display, should be 100%
When test gas has been removed the level should drop till the
5.5
alarm setting. Alarm should be de-activated
5.6 Reset the unit and watch ready (or active) indication on the display
During alarm, check the working of the flash light and the audible
5.7
alarm

6.0 Hot Commissioning


6.1 Repeat cold commissioning checks (after transportation to final
Commissioning Check Sheet

Gas Detection System


Rig 350 to Bentec AC Drilling Rig Rev. No. 01 3
Client Euro Rig No.5 Date 06-08-2008 of
File Name 11003 Gas Detection System Originator GW 3

destination and before operation)

Others:

Attachments:
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

8. Commissioning Time Table

To be developed prior start of commissioning activities

11
Status Mechanical Commissioning

Date: 02.02.2009
Originator: G. Wijdenes
Rig: Bentec 350t AC Land Drilling Rig
Client: DARFORA SA

No. Section Description Status Remarks

1 1001 A Rig Structure %


2 1000,10001N Derrick and Substructure 0%
3 1001 Mast Telescoping System 0%
4 1111 Casing Stabbing Board 0%
5 2001 Draw Works 40 % JJJJ
6 2001 Rotary Table 0%
7 2002-E Power Slip 0%
8 2003 Traveling Block 25 % JJ
9 2004-A Drill Line Reel 0%
10 2005 Hydraulic Power Unit 60 % JJJJJJ
11 2006 Top Drive 0%
12 2007 Spin Torque 0%
13 2008 Drill Floor Winch A 0%
14 2008 Drill Floor Winch B 0%
15 2008-A Man Riding Winch 0%
16 2009 Hydraulic Cathead 0%
17 2010 Derrick Man Air Hoist 50 % JJJJJ
18 2010-A Wireline Unit 0%
19 2011 Dead Line Anchor 0%
20 2012 Mast Telescoping Winch A 50 % JJJJJ
21 2012 Mast Telescoping Winch B 50 % JJJJJ
22 2013 Catwalk Winch 0%
23 2015 BOP Air Hoist A 0%
24 2015 BOP Air Hoist B 0%
25 2016 Crown Block 25 % JJ
26 3001 Main Generator set No.1 0%
27 3001 Main Generator set No.2 0%
28 3001 Main Generator set No.3 0%
29 3001-A Emergency Generator 40 % JJJJ
30 3003,3004,3005 Air Comprssor System No.1 0%
31 3003,3004,3005 Air Compressor System No.2 0%
32 4000 Mud Tank System 20 % JJ
33 4001-E Emergency Shower 0%
34 4003 Agitator, 01 25 % JJ
35 4003 Agitator 02 25 % JJ
36 4003 Agitator 03 25 % JJ
37 4003 Agitator 04 25 % JJ
38 4003 Agitator 05 25 % JJ
39 4003 Agitator 06 25 % JJ
40 4003 Agitator 07 25 % JJ
41 4003 Agitator 08 25 % JJ
42 4003 Agitator 09 25 % JJ
4003 Agitator 10 25 % JJ
4003 Agitator 11 25 % JJ
4003 Agitator 12 25 % JJ
43 4003 Agitator 13 25 % JJ
44 4004 Low Pressure Centrifugal Pump, Charge Pump A 25 % JJ
45 4004 Low Pressure Centrifugal Pump, Charge Pump B 25 % JJ
46 4004 Low Pressure Centrifugal Pump, Charge Pump C 25 % JJ
47 4004 Low Pressure Centrifugal Pump, Desander Pump 25 % JJ
48 4004 Low Pressure Centrifugal Pump, Desilter Pump 25 % JJ

You might also like