CITY OF ALAMINOS
Province of Pangasinan
BARANGAY BISOCOL
STATEMENT OF WORK ACCOMPLISHED
August 3, 2018
NAME OF PPOJECT: CONSTRUCTION OF ROAD SHOULDER AND LINE CANAL (PHASE III)
LOCATION: BRGY. BISOCOL, ALAMINOS CITY, PANGASINAN
PHYSICAL TARGET:
Accomplishment to Date
Item Number Description Quantity Unit Project Cost
Quantity Amount
I. Removal of Destruction ALL L.S. 6,210.00 ALL/L.S. 6,210.00
II. Excavation 36.24 CU.M. 18,375.00 36.24 18,375.00
III. Item 201 - Aggregate Base Course 8.23 CU.M. 6,311.16 8.23 6,311.16
IV. Masonry Works (Block Laying) 54.40 SQ.M. 20,835.94 54.40 20,835.94
V. Masonry Works (Plastering) 108.80 SQ.M. 27,063.75 108.80 27,063.75
VI Concrete Works 10.61 CU.M. 67,541.25 10.61 67,541.25
VII Reinforcing Steel Bars 612.08 KGS 41,055.00 612.08 41,055.00
TOTAL 187,392.10
Note : % of work accomplished : 100.00%
VERIFIED CORRECT: APPROVED FOR PAYMENT:
DALIO P. CABELEC
Project Engineer/Incharge
CONFORME:
ALCEL CONSTRUCTION
Contactor