Other Types of NOC Requirements (E-NOC)

1. NOC for Using Own A/C System

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection
3. Letter from Building Owner requesting for NOC for Using Own A/C system

2. Design NOC for Shoring / Piling / Excavation NOC

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection

Required Drawings (Auto cad format only *.dwg)

i. Proposed Shoring / Piling / Excavation Layout with DLTM coordinates


ii. Proposed Shoring / Piling / Excavation cross section layout
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous

3. Design NOC for Other type of works

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection / Master Plan

Required Drawings (Auto cad format only *.dwg)

i. Proposed Scope of work layout with DLTM coordinates


ii. Proposed Scope of work cross section layout
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous

4. Construction NOC for Shoring / Piling / Excavation NOC

Required NOC documents (*.Pdf, *.Jpg)

Page 1 of 4 CONFIDENTIAL
Other Types of NOC Requirements (E-NOC)

1. Covering Letter (Project & Work description)


2. Site affection
3. Approved Design NOC with stamped drawings.

Required Drawings (Auto cad format only *.dwg)

i. Proposed Shoring / Piling / Excavation Layout with DLTM coordinates


ii. Proposed Shoring / Piling / Excavation cross section layout
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous
.
5. Construction NOC for Other type of works

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection / Master Plan
3. Approved Design NOC with stamped drawings.

Required Drawings (Auto cad format only *.dwg)

i. Proposed Scope of work layout with DLTM coordinates


ii. Proposed Scope of work cross section layout
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous

6. Construction NOC for Bore Logs / Soil Investigation

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection

Required Drawings (Auto cad format only *.dwg)

i. Proposed Bore Log location with DLTM coordinates


ii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iii. Miscellaneous

Page 2 of 4 CONFIDENTIAL
Other Types of NOC Requirements (E-NOC)

7. Construction NOC for Dewatering Works

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Master Plan

Required Drawings (Auto cad format only *.dwg)

i. Proposed dewatering layout with DLTM coordinates


ii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iii. Miscellaneous

8. Construction NOC for Fencing Works

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection Plan

Required Drawings (Auto cad format only *.dwg)

i. Proposed fencing and its foundation layout with DLTM coordinates


ii. Proposed fencing and its foundation cross section details
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous

9. Construction NOC for Site Mobilization Works

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project & Work description)


2. Site affection Plan

Required Drawings (Auto cad format only *.dwg)

i. Proposed scope of works layout with DLTM coordinates


ii. Proposed scope of works elevation detail / cross section details
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous
Page 3 of 4 CONFIDENTIAL
Other Types of NOC Requirements (E-NOC)

10. NOC for Utilizing EMPOWER’s Plot for Construction of Temporary Site Facilities/
Land Usage

Required NOC documents (*.Pdf, *.Jpg)

1. Covering Letter (Project description, Work description, Duration of usage & Area)
2. Site affection Plan

Required Drawings (Auto cad format only *.dwg)

i. Proposed scope of works layout with DLTM coordinates


ii. Proposed scope of works elevation detail / cross section details
iii. Superimposing of existing Empower services along with the proposed works and its horizontal, vertical
clearance.
iv. Miscellaneous

Page 4 of 4 CONFIDENTIAL