STEEL STRUCTURE INSTALLATION PROGRESS REPORT

PROJECT PANGULIR GOLD DEVELOPMENT


PT CIAWENINDO MITRA PERKASA
TAHUN 2023

MATERIAL ARRIVED IN INSTALLATION INSTALLATION UNINSTALLABLE REMAINING


SJR CITEC TOTAL QTY ANCHOR OUTSTANDING REMARK
NO BUILDING PANGULIR COMPLETED PROGRESS MATERIAL INSTALLATION
AREA NO AREA NO STATUS ANCHOR AREA

(Kg) (Kg) % (Kg) (%) (Kg) (Kg) REASON FOR DELAY ERECTION

Can not install, waiting anchor as AB/1'-1 to be


1 123 123-1 Conveyor Belt #1 10.604,47 10.360,93 97,70% 9.247,55 87,20% not completed yet as AB/1'-1 1.041,85 71,53
installed
Can not instal, waiting anchor as AB/1-2, 6-7
2 123 123-2 Conveyor Belt #2 15.221,87 14.795,69 97,20% 8.295,48 54,50% not completed yet as AB/1-2, 6-7 6.158,13 342,08
to be installed
Setting underground still progress. Waiting
3 123 123-3 Conveyor Belt #3 33.279,75 30.369,58 91,26% 12.178,36 36,59% Completed - - 18.191,22 material roof from Surabaya Vessel arrival in
Pangulir. Forecast instal start on 30 June 2023
Can not instal, waiting delivery material Beam
4 126 126 Transfer Tower 20.248,34 18.038,62 89,09% 12.611,20 62,28% Completed - 5.427,42
code B4 from KONKA Workshop. Qty 1 pcs
Can not instal, waiting delivery material
5 123 123 Emergency Reclaim Feed Bin 7.383,32 3.213,96 43,53% 0,00% Completed 3.213,96
coloumn from KONKA Workshop. Qty 1 pcs

6 120 121 Crusher 20.293,19 17.440,89 85,94% 0,00 0,00% Completed - 17.440,89 Can not instal, waiting for civil work

7 130 131 Grinding 184.000,00 0,00% Not ready

Can not instal, waiting delivery material


8 130 123-4 Conveyor Belt #4 12.862,15 11.665,24 90,69% 559,66 4,35% Completed - 11.105,58
coloumn from KONKA Workshop. Qty 2 pcs

9 140 140 Flotation 12.975,94 9.829,65 75,75% 0,00% Not ready 9.829,65 Can not install, waiting anchor to be installed

Flotation Concentrate Dewatering


10 146 146 125.000,00 0,00% Not ready
Circuit
11 147 147 Concentrate Thickening 2.733,65 0,00% Not ready

12 150 150 Roaster Blower Room 7.960,00 0,00% Not ready

13 150 150 Roasting Dust Collection Section 8.140,00 0,00% Not ready
Can not instal, waiting for anchor to be
14 155 155 Conversion Section 18.493,91 2.239,07 12,11% 0,00% Not ready 2.239,07
installed

15 155 155 Acid Storage 6.000,00 0,00% Not ready

16 155 155 Drying and Absorption 3.000,00 0,00% Not ready

17 160 160 Calcine Pretreatment Building 168.175,22 0,00% Not ready

18 164 164 Calcine Acid Wash 4.134,12 0,00% Not ready

19 167 167 Calcine Leaching 3.087,57 0,00% Not ready

20 169 169 Acid Leaching 1.027,11 0,00% Not ready


Can not install, waiting anchor as 2B-2C to be
21 170 170 Carbon in Leach 15.307,89 11.896,00 77,71% 10.584,29 69,14% not completed yet as 2B-2C 1.311,71
installed
Can not install, waiting anchor as 1B to be
22 171 171 Cil Feed Thickening 3.085,03 2.822,90 91,50% 926,27 30,02% not completed yet as 1B 1.896,63
installed
Elution & Electrowinning, Carbon
23 180 & 185 180 176.000,00 0,00% Not ready
Regeneration and Gold Room Area
Can not instal, waiting for anchor to be
24 193 Tails Thickening 2.912,39 2.751,09 94,46% 0,00% Not ready 2.751,09
installed
Can not instal, waiting for anchor to be
25 192 192 Tails Dewatering Circuit 171.113,46 366,20 0,21% 0,00% Not ready 366,20
installed

26 215 215 Flotation Reagent Circuit 69.000,00 0,00% Not ready


27 211 211 NaOH & NaCN & BLOWER 29.461,76 16.741,05 56,82% 10.288,74 34,92% Completed 6.452,31 Installation on progress
Waiting delivery material from KONKA
28 220 229 Mill Cooling Tower 1.584,16 0,00% Completed
workshop
Waiting delivery material from KONKA
29 229 229 Public Cooling Tower 1.199,80 0,00% Completed
workshop
Waiting delivery material from KONKA
30 223 223 Water Pond 2.973,75 0,00% Completed
workshop
Fresh Water Area for Raw Water
31 222 222 6.430,01 0,00% Not ready
Circuit
32 230 231 Piperacks 685.000,00 0,00% Not ready
Waiting delivery material from KONKA
33 232 232 Watertreatment Plant 9.046,41 0,00% Completed
workshop
34 233 233 Sewerage Treatment 805,69 0,00% Not ready

35 243 243 Oxygen Plant 10.230,33 5.919,69 57,86% 1.653,00 16,16% Completed 4.266,69 Installation on progress

36 242 242 Blower 5.993,45 0,00% Not ready

37 240 Flotation 7.000,00 0,00% Not ready


Waiting delivery material from KONKA
38 250 250 Fuel Service Area 3.000,00 0,00% Completed
workshop
39 263 262 SUB #2 1.154,80 0,00% Not ready

40 270 270 Office and LAB 61.000,00 0,00% Not ready

41 373 373 Warehouse 13.270,10 10.237,00 77,14% 9.377,67 70,67% Completed 859,33 Installation on progress

42 218 218 Reagent Storage 34.283,24 32.272,33 94,13% 27.275,11 79,56% Completed 4.997,22 Installation on progress

43 219 219 Daily Reagent Shed 10.339,75 9.166,96 88,66% 7.994,22 77,32% Completed 1.172,74 Installation on progress
Can not instal, waiting for anchor to be
44 372 372 Workshop 47.970,27 40.087,05 83,57% 0,00% Not ready 40.087,05
installed

45 123 123-6 Conveyor Belt 6 16.400,00 0,00% Not ready

TOTAL WEIGHT (Kg) 2.049.182,90 250.213,90 12,21% 110.991,55 5,42% 102.869,23 36.353,12

250.213,90 12,21% Material Arrived in Pangulir

Prepared by, 81967,32 110.991,55 5,42% Installation Completed

102.869,23 5,02% Uninstallable Material


Remaining Installation/Installation
Yaman Komaeni 36.353,12 1,77%
on Progress
PT. Ciawenindo Mitra Perkasa