Steel Structure Installation Progress Project Pangulir Gold CITEC Updated 03 Juli 2023
Steel Structure Installation Progress Project Pangulir Gold CITEC Updated 03 Juli 2023
(Kg) (Kg) % (Kg) (%) (Kg) (Kg) REASON FOR DELAY ERECTION
6 120 121 Crusher 20.293,19 17.440,89 85,94% 0,00 0,00% Completed - 17.440,89 Can not instal, waiting for civil work
9 140 140 Flotation 12.975,94 9.829,65 75,75% 0,00% Not ready 9.829,65 Can not install, waiting anchor to be installed
13 150 150 Roasting Dust Collection Section 8.140,00 0,00% Not ready
Can not instal, waiting for anchor to be
14 155 155 Conversion Section 18.493,91 2.239,07 12,11% 0,00% Not ready 2.239,07
installed
35 243 243 Oxygen Plant 10.230,33 5.919,69 57,86% 1.653,00 16,16% Completed 4.266,69 Installation on progress
41 373 373 Warehouse 13.270,10 10.237,00 77,14% 9.377,67 70,67% Completed 859,33 Installation on progress
42 218 218 Reagent Storage 34.283,24 32.272,33 94,13% 27.275,11 79,56% Completed 4.997,22 Installation on progress
43 219 219 Daily Reagent Shed 10.339,75 9.166,96 88,66% 7.994,22 77,32% Completed 1.172,74 Installation on progress
Can not instal, waiting for anchor to be
44 372 372 Workshop 47.970,27 40.087,05 83,57% 0,00% Not ready 40.087,05
installed
TOTAL WEIGHT (Kg) 2.049.182,90 250.213,90 12,21% 110.991,55 5,42% 102.869,23 36.353,12