List of Pending Activities (Ground Floor)

Progress - 06-June-2023

Sr. No. Area Pending Civil Activities Remarks

1 Plaster Couving (Walls) Will be done during Paintjob


3 Floor Couving In Progress
4 Floor Scratching/Finishing Polishing
Dispatch Room
5 Repairs in Floor & Edges of Wall Plasters 50% Completed
6 Light/IT Box in the Offices in Dispatch Room
7 Cable Tray for IT in Dispatch Room In Progress
8 Plaster Couving (Walls) Will be done during Paintjob
10 Floor Scratching/Finishing Polishing
Finished Goods
11 Repairs in Floor
13 24" x 24" Exhaust Fan for the ETO
14 Plaster Couving (Walls) Will be done during Paintjob
ETO
15 Floor Scratching/Finishing Polishing
22 Plaster Couving (Walls) - It's decided to be done by the Painter witht the Paint Job by Salman Khan Sb. Will be done during Paintjob
23 Floor Scratching/Finishing Polishing/Epoxy
24 Repairs Edges of Wall Plaster In Progress
Those HVAC Returns dropped with Walls in Packing Hall & Raw Material Stores would be concealed by
25
Cement Board/Gypsum Sheet. (Decided by Umair Sb & Salman Khan Sb.)
Those HVAC Retuens dropped in the corners would be concealed by the Standing Brick Masonry.
26
(Decided by Umair Sb & Salman Khan Sb.)
27 Cable Tray for Cabling 90% Completed
29 Brick Work (1 Span Complete + All Spans Partial left for ducting) 25% Completed
30 Plaster Work (3 Spans Remaining)
31 Corridor 11' Floor Couving (1 Span only remaining)
32 Floor Scratching/Finishing Polishing/Epoxy
33 Repair work
34 Plaster Couving (Walls) Will be done during Paintjob
35 Material Entry Repair Works
36 Floor Scratching/Finishing Polishing/Epoxy
37 Plaster Couving (Walls) Will be done during Paintjob
38 Plaster Work (4 Columns Remaining)
39 Floor Scratching/Finishing Polishing/Epoxy
40 Buffers Repair work 75% Completed
The direction of the DoorFrames installed in last buffer opening in Assembly & IM required to be
41
changed. Mr. Adnan the door vendor will cut the existing DoorFrames & repalce them.
42 Partition Wall 4" needs to be provided in last common buffer.
43 Brick Work (1 Span of EM Exit only)
44 No Plaster for the Columns with HVAC Returns (Decided by Salman Khan Sb. & Umair Sb.)
45 Plaster Work (1 Span of Wall Remaining)
46 Plaster Work (17 Columns Remaining)
47 Plaster Couving (Walls) Will be done during Paintjob
48 Floor Couving (1 Span + Columns Bottoms remaining)
Assembly Hall
49 Floor Scratching/Finishing Polishing/Epoxy
50 Repair Work (Hatches in Walls)
51 Cable Tray for Cabling 70% Completed
Angle Supports need to applied to the HVAC Ducts tied with the Beam Drops. Nabeel Sb has to share the
52 In Progress
size & design of Supports to Zia Sb. once the Ducts are finally clothed off.
53 Water & Air lines (50mm PPRC) need to be installed in Assembly Hall.
54 Plaster Work (12 Columns Remaining) 25% Completed
55 Plaster Couving (Walls) Will be done during Paintjob
Transit Warehouse
56 Floor Scratching/Finishing Polishing/Epoxy
57 Repair Works
58 Brick Work (1 Span + Crushers Rooms) In Progress
59 The wall of Crusher Rooms shall be of 9" (Hollow Wall as approved by Salman Khan Sb.)
There will be a Hatch (H: 4' x W: 3') with the floor in the midst of both the columns after the door (size
60 will be recommended by Zia Sb. after revieweing the size of Crusher Machines). The door will open
inside.
61 Plaster Work (1 Span of Wall Remaining + Crusher Rooms)
62 Plaster Work (20 Columns Remaining)
63 Floor Couving (4 Spans Remaining + 21 Columns Bottoms)
64 Injection Moulding Hall Slab Collar in Trenches 100% Completed
65 Slab Pouring for Trenches
66 Floor Scratching/Finishing Polishing/Epoxy
67 Repair Works
68 Cable Tray for Cabling (Partial) 90%
69 Piping Works need to be commenced and completed ASAP.
The emergency exit in Injection Moulding shall of 8feet width & 8feet height. Leave the Door size
70 accurately and cover the rest of the span with the Brick Masonry. (Decided by Umair Sb. & Salman Khan 25% Completed
Sb.)
71 Plaster Work (1 Span of Wall Remaining)
72 Plaster Work (5 Columns Remaining)
73 Floor Border & Couving
74 Raw Material Store Plaster Couving (Walls) Will be done during Paintjob
75 Floor Scratching/Finishing Polishing
76 Repair Works
77 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
78 Plaster Work (2 Spans of wall Remaining) 75% Completed
79 Plaster Work (11 Columns Remaining)
80 Plaster Couving (Walls) Will be done during Paintjob
81 Packaging Material Store Floor Couving (Walls and Columns)
Sr. No. Area Pending Civil Activities Remarks

82 Floor Scratching/Finishing Polishing


83 Repair Works
84 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
85 Chips Flooring
86 Plaster Work (Walls)
87 Plaster Work (4 Columns Remaining)
88 Quarantine Section Plaster Couving (Walls) Will be done during Paintjob
89 Floor Couving
90 Floor Scratching/Finishing Polishing
91 Repair Works
92 Chips Flooring
93 Plaster Work (Walls)
94 Plaster Work (4 Columns Remaining)
95 Plaster Couving (Walls) Will be done during Paintjob
96 Floor Couving
Receiving Bay
97 Floor Scratching/Finishing Polishing
98 Repair Works
99 There will be an Exhaust (size shall be recommended by Umair Sb and Zia Sb.) opening in 20' main street.

100 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
101 Shutterinhg for Slab
102 Slab Pouring
103 MZ Floor Brick Work
104 Plaster
105 Repair Works
106 Brick Work (1 Span of Wall half heighted + 1 Span is on hold due to the Elevation) Discussion/Decision Required
107 Plaster Work (Walls)
109 Plaster Couving (Walls) Will be done during Paintjob
Corridor 8'
110 Floor Border & Couving
111 Floor Scratching/Finishing Polishing
112 Repair Works
The top layer of black chip already poured in Executive Change Room would be scrapped off and would
114
be poured witht the White Chips.
115 Plaster Work (Walls)
116 Floor Border & Couving
117 Plaster Couving (Walls) Will be done during Paintjob
118 Floor Scratching/Finishing Polishing
119 Repair Works
120 Plaster Work (Walls)
121 Floor Border & Couving
122 Plaster Couving (Walls) Will be done during Paintjob
123 Office-1 Floor Scratching/Finishing Polishing
124 Repair Works
125 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
126 Black Chips in Office is okay but the Borders in and adjacent shall be poured with white chips.
127 Brick Work (1 Partition Remaining)
128 Plaster Work Remaining
129 Floor Border & Couving
Office-2
130 Plaster Couving (Walls) Will be done during Paintjob
131 Floor Scratching/Finishing Polishing
132 Repair Works
133 Brick Work (1 Front Span Remaining)
134 Plaster Work (Walls)
135 Flooring (Decision Yet to be made) Discussion/Decision Required
Reception
136 Plaster Couving (Walls) Will be done during Paintjob
137 Floor Couving
138 Reapair Works
139 Layout
140 Demarcation
141 Stairs Shuttering
142 Pouring
143 Finishing and Repair Works
144 Plaster Work (Walls) 55% Completed
145 Layout and Installation & Construction of Site Sewerage Network
146 Levelling, Dredging & Compaction of Outer Streets
147 External Building Pavement/Concreting of streets Discussion/Decision Required
148 Repair Works
RainWater Drain System & Rain Drain network around the building needs to be further discussed with
149 Discussion/Decision Required
the expert for the calculation of rainwater to be run off and to be taken care of.
150 Door Fixing for 3 Rooms 75% Completed
Exhaist (24" x 24") in Transformer Room near ATS partition & the same size hole needs to done in the
151 Electrical Rooms (Ground
ATS Partition on the opposoite side so that the air flow may be maintained.
Floor)
12Watt Bulbs need to be provisoned to the Transformer/HT Panel Rooms energized by WAPDA & UPS
152
both.