List of Pending Activities (Ground Floor)

Progress - 05-May-2023

Sr. No. Area Pending Civil Activities Remarks

1 Plaster Couving (Walls) Will be done during Paintjob


2 Plaster of Columns 100% Completed
3 Floor Couving In Progress
4 Dispatch Room Floor Scratching/Finishing Polishing
5 Repairs in Floor & Edges of Wall Plasters
6 Light/IT Box in the Offices in Dispatch Room
7 Cable Tray for IT in Dispatch Room
8 Plaster Couving (Walls) Will be done during Paintjob
9 Plaster Work (Half Span & 1 Column Remaining) 100% Completed
10 Floor Scratching/Finishing Polishing
Finished Goods
11 Repair in Floor & Edges of Wall Plasters 100% Completed
12 Partitions for ETO have been decided to be done by Gypsum/Cement Board by Salman Khan Sb.
13 24" x 24" Exhaust Fan for the ETO
14 Plaster Couving (Walls) Will be done during Paintjob
15 Floor Scratching/Finishing Polishing
16 Repairs Edges of Wall Plaster 100% Completed
ETO
17 Cable Tray for Cabling 100% Completed
18 Installation of 32mm PPRC Air Pipe for ETO 100% Completed
19 HVAC passing through ETO Room should be completed in all respects (Glass Wool + Clothing) 100% Completed
20 Plaster Work (8 Columns Remaining) 75% Completed
21 Plaster Couving (Walls) - It's decided to be done by the Painter witht the Paint Job by Salman Khan Sb. Will be done during Paintjob
22 Floor Scratching/Finishing Polishing/Epoxy
23 Repairs Edges of Wall Plaster
Those HVAC Returns dropped with Walls in Packing Hall & Raw Material Stores would be concealed by
24
Packing Hall Cement Board/Gypsum Sheet. (Decided by Umair Sb & Salman Khan Sb.)
Those HVAC Retuens dropped in the corners would be concealed by the Standing Brick Masonry.
25
(Decided by Umair Sb & Salman Khan Sb.)
26 Cable Tray for Cabling 75% Completed
HVAC in Packing Hall need to be completed in all respects within 2 days starting from Saturday June 3rd,
27 100% Completed
2023.
28 Brick Work (1 Span Complete + All Spans Partial left for ducting)
29 Plaster Work (3 Spans Remaining)
30 Corridor 11' Floor Couving (1 Span only remaining)
31 Floor Scratching/Finishing Polishing/Epoxy
32 Repair work
33 Plaster Couving (Walls) Will be done during Paintjob
34 Material Entry Repair Works
35 Floor Scratching/Finishing Polishing/Epoxy
36 Plaster Couving (Walls) Will be done during Paintjob
37 Plaster Work (4 Columns Remaining)
38 Floor Scratching/Finishing Polishing/Epoxy
39 Buffers Repair work 75% Completed
The direction of the DoorFrames installed in last buffer opening in Assembly & IM required to be
40
changed. Mr. Adnan the door vendor will cut the existing DoorFrames & repalce them.
41 Partition Wall 4" needs to be provided in last common buffer.
42 Brick Work (1 Span of EM Exit only)
43 No Plaster for the Columns with HVAC Returns (Decided by Salman Khan Sb. & Umair Sb.)
44 Plaster Work (1 Span of Wall Remaining)
45 Plaster Work (17 Columns Remaining)
46 Plaster Couving (Walls) Will be done during Paintjob
47 Floor Couving (1 Span + Columns Bottoms remaining)
Assembly Hall
48 Floor Scratching/Finishing Polishing/Epoxy
49 Repair Work (Hatches in Walls)
50 Cable Tray for Cabling
Angle Supports need to applied to the HVAC Ducts tied with the Beam Drops. Nabeel Sb has to share the
51
size & design of Supports to Zia Sb. once the Ducts are finally clothed off.
52 Water & Air lines (50mm PPRC) need to be installed in Assembly Hall.
53 Plaster Work (12 Columns Remaining) 25% Completed
54 Plaster Couving (Walls) Will be done during Paintjob
Transit Warehouse
55 Floor Scratching/Finishing Polishing/Epoxy
56 Repair Works
57 Brick Work (1 Span + Crushers Rooms)
58 The wall of Crusher Rooms shall be of 9" (Hollow Wall as approved by Salman Khan Sb.)
There will be a Hatch (H: 4' x W: 3') with the floor in the midst of both the columns after the door (size
59 will be recommended by Zia Sb. after revieweing the size of Crusher Machines). The door will open
inside.
60 Plaster Work (1 Span of Wall Remaining + Crusher Rooms)
61 Plaster Work (20 Columns Remaining)
62 Floor Couving (4 Spans Remaining + 21 Columns Bottoms)
63 Injection Moulding Hall Slab Collar in Trenches 80% Completed
64 Slab Pouring for Trenches
65 Floor Scratching/Finishing Polishing/Epoxy
66 Repair Works
67 Cable Tray for Cabling (Partial) 50% Completed
68 Piping Works need to be commenced and completed ASAP.
The emergency exit in Injection Moulding shall of 8feet width & 8feet height. Leave the Door size
69 accurately and cover the rest of the span with the Brick Masonry. (Decided by Umair Sb. & Salman Khan
Sb.)
70 Plaster Work (1 Span of Wall Remaining)
Sr. No. Area Pending Civil Activities Remarks

71 Plaster Work (5 Columns Remaining)


72 Floor Border & Couving
73 Raw Material Store Plaster Couving (Walls) Will be done during Paintjob
74 Floor Scratching/Finishing Polishing
75 Repair Works
76 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
77 Plaster Work (6 Spans of wall Remaining) 50% Completed
78 Plaster Work (11 Columns Remaining)
79 Plaster Couving (Walls) Will be done during Paintjob
80 Packaging Material Store Floor Couving (Walls and Columns)
81 Floor Scratching/Finishing Polishing
82 Repair Works
83 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
84 Chips Flooring
85 Plaster Work (Walls)
86 Plaster Work (4 Columns Remaining)
87 Quarantine Section Plaster Couving (Walls) Will be done during Paintjob
88 Floor Couving
89 Floor Scratching/Finishing Polishing
90 Repair Works
91 Chips Flooring
92 Plaster Work (Walls)
93 Plaster Work (4 Columns Remaining)
94 Plaster Couving (Walls) Will be done during Paintjob
95 Floor Couving
Receiving Bay
96 Floor Scratching/Finishing Polishing
97 Repair Works
98 There will be an Exhaust (size shall be recommended by Umair Sb and Zia Sb.) opening in 20' main street.

99 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
100 Shutterinhg for Slab
101 Slab Pouring
102 MZ Floor Brick Work
103 Plaster
104 Repair Works
105 Brick Work (1 Span of Wall half heighted + 1 Span is on hold due to the Elevation) Discussion/Decision Required
106 Plaster Work (Walls)
107 Chips Flooring (Alternative Pattern) 100% Completed
108 Corridor 8' Plaster Couving (Walls) Will be done during Paintjob
109 Floor Border & Couving
110 Floor Scratching/Finishing Polishing
111 Repair Works
112 Chips Flooring (Alternative Pattern) 100% Completed
The top layer of black chip already poured in Executive Change Room would be scrapped off and would
113
be poured witht the White Chips.
114 Plaster Work (Walls)
Executive Change
115 Floor Border & Couving
116 Plaster Couving (Walls) Will be done during Paintjob
117 Floor Scratching/Finishing Polishing
118 Repair Works
119 Plaster Work (Walls)
120 Floor Border & Couving
121 Plaster Couving (Walls) Will be done during Paintjob
122 Office-1 Floor Scratching/Finishing Polishing
123 Repair Works
124 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
125 Black Chips in Office is okay but the Borders in and adjacent shall be poured with white chips.
126 Brick Work (1 Partition Remaining)
127 Plaster Work Remaining
128 Floor Border & Couving
Office-2
129 Plaster Couving (Walls) Will be done during Paintjob
130 Floor Scratching/Finishing Polishing
131 Repair Works
132 Brick Work (1 Front Span Remaining)
133 Plaster Work (Walls)
134 Flooring (Decision Yet to be made) Discussion/Decision Required
Reception
135 Plaster Couving (Walls) Will be done during Paintjob
136 Floor Couving
137 Reapair Works
138 Layout
139 Demarcation
140 Stairs Shuttering
141 Pouring
142 Finishing and Repair Works
143 Plaster Work (Walls)
144 Layout and Installation & Construction of Site Sewerage Network
145 Levelling, Dredging & Compaction of Outer Streets
146 External Building Pavement/Concreting of streets Discussion/Decision Required
147 Repair Works
RainWater Drain System & Rain Drain network around the building needs to be further discussed with
148 Discussion/Decision Required
the expert for the calculation of rainwater to be run off and to be taken care of.
149 Door Fixing for 3 Rooms 33% Completed
Sr. No. Area Pending Civil Activities Remarks

Exhaist (24" x 24") in Transformer Room near ATS partition & the same size hole needs to done in the
150
ATS Partition on the opposoite side so that the air flow may be maintained.
Electrical Rooms (Ground
12Watt Bulbs need to be provisoned to the Transformer/HT Panel Rooms energized by WAPDA & UPS
151 Floor)
both.
152 Flooring of Transformer Room 100% Completed
153 Flooring of ATS Room 100% Completed