Progress - 05-May-2023
99 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
100 Shutterinhg for Slab
101 Slab Pouring
102 MZ Floor Brick Work
103 Plaster
104 Repair Works
105 Brick Work (1 Span of Wall half heighted + 1 Span is on hold due to the Elevation) Discussion/Decision Required
106 Plaster Work (Walls)
107 Chips Flooring (Alternative Pattern) 100% Completed
108 Corridor 8' Plaster Couving (Walls) Will be done during Paintjob
109 Floor Border & Couving
110 Floor Scratching/Finishing Polishing
111 Repair Works
112 Chips Flooring (Alternative Pattern) 100% Completed
The top layer of black chip already poured in Executive Change Room would be scrapped off and would
113
be poured witht the White Chips.
114 Plaster Work (Walls)
Executive Change
115 Floor Border & Couving
116 Plaster Couving (Walls) Will be done during Paintjob
117 Floor Scratching/Finishing Polishing
118 Repair Works
119 Plaster Work (Walls)
120 Floor Border & Couving
121 Plaster Couving (Walls) Will be done during Paintjob
122 Office-1 Floor Scratching/Finishing Polishing
123 Repair Works
124 3/4" PVC pipe to be buried under floor while filling the border for A/C drain.
125 Black Chips in Office is okay but the Borders in and adjacent shall be poured with white chips.
126 Brick Work (1 Partition Remaining)
127 Plaster Work Remaining
128 Floor Border & Couving
Office-2
129 Plaster Couving (Walls) Will be done during Paintjob
130 Floor Scratching/Finishing Polishing
131 Repair Works
132 Brick Work (1 Front Span Remaining)
133 Plaster Work (Walls)
134 Flooring (Decision Yet to be made) Discussion/Decision Required
Reception
135 Plaster Couving (Walls) Will be done during Paintjob
136 Floor Couving
137 Reapair Works
138 Layout
139 Demarcation
140 Stairs Shuttering
141 Pouring
142 Finishing and Repair Works
143 Plaster Work (Walls)
144 Layout and Installation & Construction of Site Sewerage Network
145 Levelling, Dredging & Compaction of Outer Streets
146 External Building Pavement/Concreting of streets Discussion/Decision Required
147 Repair Works
RainWater Drain System & Rain Drain network around the building needs to be further discussed with
148 Discussion/Decision Required
the expert for the calculation of rainwater to be run off and to be taken care of.
149 Door Fixing for 3 Rooms 33% Completed
Sr. No. Area Pending Civil Activities Remarks
Exhaist (24" x 24") in Transformer Room near ATS partition & the same size hole needs to done in the
150
ATS Partition on the opposoite side so that the air flow may be maintained.
Electrical Rooms (Ground
12Watt Bulbs need to be provisoned to the Transformer/HT Panel Rooms energized by WAPDA & UPS
151 Floor)
both.
152 Flooring of Transformer Room 100% Completed
153 Flooring of ATS Room 100% Completed