Minutes of the Project Approval & Monitoring Committee (PAMC) meeting held under the

Chairpersonship of Secretary (Textiles) on 26 June 2023 at 4.00 PM in Room No. 162, Ministry of
Textiles, Udyog Bhawan, New Delhi to consider and approve the Craft Handloom Village Kunbi in
Goa State under National Handloom Development Programme (NHDP)-reg.

List of the participants is enclosed.

2. At the outset, Development Commissioner (Handicrafts & Handlooms) welcomed the


Chairman and the participants. She informed that the meeting has been convened to consider
and approve the proposal for setting-up of Craft Handloom Village at Kunbi in Goa State under
National Handloom Development Programme (NHDP).

3. Development Commissioner (Handicrafts & Handlooms) informed about the revised


Guidelines of NHDP issued on 12.05.2023, and the provision therein to develop Handloom
pockets on important tourist circuits as Craft Handloom Villages.

4. Goa Handicrafts, Rural and Small-Scale Industries Development Corporation (GHRSSIDC),


Department of Handicrafts, Textiles & Coir, Govt. of Goa (Implementing Agency) attended the
meeting through VC and made a presentation on the Kunbi Craft Handloom Village at Sanguem
Taluka, Goa in the presence of Principal Secretary (Finance) Goa, & WSC Mumbai, who joined
through VC.

5. Decision of PAMC: The PAMC approved the proposal for setting-up of Handloom Craft
Village Kunbi, at Sanguem Taluka, in Goa State with the total cost of Rs. 1738.69 Lakh consisting
of Govt. of India share Rs. 1000 lakh and State share of Rs. 738.69 lakh. The PAMC approved the
proposal with the following conditions:
i) Implementing Agency has to issue Tenders within one month and Work Orders within
three months for execution of the work related to the project.
ii) Funds due in 1st installment of GoI share will be released after issuance of Work Orders
by the Implementing Agency.
iii) Implementing Agency has to submit confirmation of convergence from Tribal and
Tourism departments of State Govt. for this project.
iv) The period of project implementation will be two years.
v) Implementing Agency has to submit sustainability plan of the project.

6. Intervention wise details of cost break-up is enclosed as annexure-A.

List of Participants:

1. Additional Secretary & Financial Advisor, Ministry of Textiles, New Delhi.


2. Development Commissioner (Handicrafts & Handlooms), Udyog Bhawan, New Delhi.
3. Principal Secretary (Finance), Govt. of Goa, Panaji.
4. Additional Development Commissioner for Handlooms, Udyog Bhawan, New Delhi.
5. Resident Commissioner Goa, Goa Sadan, 18 Amrita Shergil Marg, New Delhi - 110 003
6. Zonal Director (WZ), WSC, Mumbai.
7. Representative of Goa Handicrafts, Rural and Small-Scale Industries Development
Corporation (GHRSSIDC), (Implementing Agency)
8. Head of Office, WSC, Mumbai/HSC. Goa.
Annexure-A
Intervention wise cost break-up:
S.No. Particular GOI Share (in Rs.) State Govt. Share (in
Rs.)
Civil Work
1. Leveling 18,50,400/- -
2. Parking-Internal roads 4,81,100/- -
3. Parking-Storm water drains 2,97,150/- -
4. Entrance Avenue 22,11,000/- -
5. Showroom, Storage, Workroom, Display 3,18,44,400/- -
Rooms
6. Handloom, Coir and similar Craft Room 91,39,200/- -
7. Food Court 35,04,800/- -
8. Sewage Treatment 19,14,455/- -
9. Toilet Block 8,42,400/- -
10. Pathways and Paving 5,62,600/- -
12. PCC- Providing & laying cement concrete 12,53,265/- -
13. Providing and laying in design & pattern 26,98,540/- -
factory made PVC Rubber Moduled
14. Demolishing R.C.C. work including stacking - 2,97,554/-
of steel bars & disposal of unserviceable
15. Accommodation Unit - 2,04,98,100/-
16. Compound Wall - 28,30,400/-
17. Retaining Wall - 19,76,500/-
18. Security Office - 4,54,000/-
Electric, Water and Sewerage -
19. Electric External Service Connection - 30,99,595/-
20. Internal Electric Service Connection - 1,03,31,984/-
21. SITC of 11KV/0.433 KV Substation - 16,65,261/-
22. Water Supply - 33,06,235/-
23. Sewerage & Sanitation - 33,06,235/-
Other Items
24. Information Signages 10,23,390/- -
25. Entrance Gate- 03 Nos. 1,18,000/- -
26. Equipment Cost 1,89,42,420/- -
27. Interior Cost and Furniture 54,12,120/- -
Total (Excluding Tax & Contingencies) 8,20,95,240/ 4,77,65,865/-
Total (GOI + State Govt. Share) (A) 12,98,61,105/-
Add 18% GST (B) 2,33,74,998/-
Total (A) + (B) 15,32,36,103
Add Contingencies @3% © 45,97,083/-
RITES Charges @ 1.10% (D) 14,28,472/-
Service tax on RITES @18% (E) 2,57,125/-
Consultancy Fees @2% (F) 25,97,222/-
Total (G) = (B) + (C) + (D)+ (E) + (F) 16,21,16,006/-
Centage Charges @7.25% (H) 1,17,53,410/-
Grand Total (G) + (H) 17,38,69,417/-
Funding Pattern
GOI Share 10,00,00,000/-
State Govt. Share 7,38,69,417/-