Professional Documents
Culture Documents
Project Execution Document
Project Execution Document
1. Scope of Work
2. Project Timeline
3. Personnel
5. HSE Plan
6. Contractor Responsibilities
9. Emergency Plan
01 Off-site and Pre-Fabrication works o Fabricate concrete base offsite in line with project
specification.
o Weld base plates to Streetlight poles
o Complete all painting works
02 Site Preparation Removal of obstacle from planned installation area including, trees,
grass, etc.
03 Mobilize to site Manually move work tools and materials, this includes:
Personnel
PPEs
08 Housekeeping Ensure all work areas are clear of sharp objects and particles
09 Testing and Commissioning Confirm all Led lamps are working fine and Handover
2. PROJECT TIMELINE
Our typical project schedule onsite can be seen in the table below.
Site Preparation 1
Civil works 3
Electrical works 1
Estimated project duration is 13 working days. However, due to current measures set-out by
the Federal Government to combat the spread of COVID-19 Virus and the security situation
of the terrain, delivery time maybe longer due to market restrictions and curfew
3. PERSONNEL
A total of 6 personnel will be required to execute this project. 4 staff from Auxano team
and 2persons from the local community.
From our experience in previous projects within same community, we plan to have a mix of
our project team and local workforce for the execution of this project.
HSE Objectives
The objectives however are to comply with Shell HSSE and contract HSSE
requirements and prevent incidents while this activity is being executed.
o No harm to people, environment, and no leaks.
o Has a systematic approach to HSSE management designed to ensure compliance with
the law and to achieve continuous performance improvement
o Sets targets for improvement and measures, appraises, and reports performance.
o Engage effectively with neighbours and impacted communities
o Ensuring that hazards and risks associated the project are identified and managed to
ALARP.
o Educating the workers and public to the benefits of good house keeping o Ensuring
that staff competence is improved geared towards effective service delivery. o
Ensuring that personnel are issued with the right tools and equipment to execute jobs
safely.
o Set Key Performance Indicators (KPI) that will aid achieving Goal Zero.
HSE Target
• Conduct all took box meetings, site HSE meeting and induction courses for new
employees.
• 6.3. HELPERS
-Incompetency/working at height and L Erection of streetlight Use of PTW, proper JHA, toolbox
tripping hazard. poles talk and competent crew
/scaffolders
-Flying particles, line of fire and hot M Fabrication of internal Use of PTW, proper JHA and tool
surfaces and external bracing/ box talk, also use competent crew
changing of bolt and and avoid line of fire.
nut.
-Chemical inhalation L Use of Cement and Use of nose mask, and proper
Painting work supervision.
-Dust inhalation L Clearing of all waste Use of dust masks, hand gloves and
and tidying up of proper supervision
installation area
• 8. MATERIALS AND PERSONAL PROTECTIVE EQUIPMENT (PPE)
REQUIREMENTS
MATERIALS
• Trucks to convey prefabricated materials (concrete and galvanized poles) as well as
Solar All-in-one Lights to site
• Hiab/Loader vehicle to install concrete base and to erect streetlight poles
• Spanner
• Hex keys
• Screwdrivers
• Construction plum
• Shovel
• Digger
• Multimeter
PPEs
• Eye goggles
• Safety helmet
• Nose mask
• Safety shoe
• Coverall
• Hand glove (Cotton/leather / Rubber)
• 9. EMERGENCY PLAN
In the event of any minor fire incident, it would be put out using portable fire extinguishers, while major
fire incidents require more technical approach and trained fire fighters shall be invited to fight the fire.
In case of fire, workers are advised to act as follows:
Raise alarm to warn people in the vicinity
• Shut down power supply and remove any combustible materials near the fire, close doors
and window, but do not lock
• Fight fire with appropriate fire equipment if it is safe to do so
• Inform supervisor immediately
• Leave scene of incident and gather at the muster point at the sound of the alarm for roll
call
• Do not go back to work until you are told to do so.
All workers are to know the proper exits, corridors, and responsibilities of their section.
Each worker should know where to report upon evacuation and should stay there until roll call is taken
or a supervisory authority gives further instructions.
COVID-19 Emergency Response Generic Flowchart
• 10. GENERAL SITE HSE REQUIREMENTS
All staffs of AUXANO SOLAR NIG. LTD. shall have to adhere strictly to all HSE rules and
procedures on site. Among these rules are
- Risk assessment and toolbox talk shall be conducted before commencement of any
medium, high or extreme risk job task. This will ensure that workers become aware
of all aspects of the task, HSE implications and the role they are to play should
problem occur.
- Use PPEs provided for the task at hand.
- Obey all safety signs. No unauthorized persons shall have access into the work area.
- Obey Life Saving Rules.
- Observe and record UA/UC/NM. Monitor to ensure close out of items.
- Keep site clean and waste-bins. Waste shall be segregated properly.