Riyadh East - STP Classic Schedule Layout 09-Jan-23 11:24

Activity ID Activity Name Original Month


Duration
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Riyadh East - STP
A1310 EPC Duration 21m EPC Duration

Milestones 0m

Permits & Approvals 3m

Mobilization 2m

Design Works 5m

Procurement 13m

Long Lead Items 9m


Other Items 13m
Construction 15m

Phase 1 15m
Civil Works 7m
MEP & Instrumentation 6m
Power Supply 4m
Site Development 6m
Testing & Commissioning 3m
Handing Over 2m
Operation & Maintenance 24m

Training 2m

Level of Effort Critical Remaining Work Page 1 of 1 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation