The document provides daily concrete pouring quantities for July 5th and 6th. On July 5th, 52 cubic meters of foundation concrete and 15 cubic meters of pedestal/wall concrete were poured. Works included ATM paving, road drainage for SPT, and local foundations. On July 6th, 16 cubic meters of foundation concrete was planned but actual pouring was 0 cubic meters. 0.5 cubic meters of pedestal/wall concrete was poured for DWT local foundations. Inspections were conducted for works including NT uditches, ATM sleepers, and local foundations.
The document provides daily concrete pouring quantities for July 5th and 6th. On July 5th, 52 cubic meters of foundation concrete and 15 cubic meters of pedestal/wall concrete were poured. Works included ATM paving, road drainage for SPT, and local foundations. On July 6th, 16 cubic meters of foundation concrete was planned but actual pouring was 0 cubic meters. 0.5 cubic meters of pedestal/wall concrete was poured for DWT local foundations. Inspections were conducted for works including NT uditches, ATM sleepers, and local foundations.
The document provides daily concrete pouring quantities for July 5th and 6th. On July 5th, 52 cubic meters of foundation concrete and 15 cubic meters of pedestal/wall concrete were poured. Works included ATM paving, road drainage for SPT, and local foundations. On July 6th, 16 cubic meters of foundation concrete was planned but actual pouring was 0 cubic meters. 0.5 cubic meters of pedestal/wall concrete was poured for DWT local foundations. Inspections were conducted for works including NT uditches, ATM sleepers, and local foundations.
The document provides daily concrete pouring quantities for July 5th and 6th. On July 5th, 52 cubic meters of foundation concrete and 15 cubic meters of pedestal/wall concrete were poured. Works included ATM paving, road drainage for SPT, and local foundations. On July 6th, 16 cubic meters of foundation concrete was planned but actual pouring was 0 cubic meters. 0.5 cubic meters of pedestal/wall concrete was poured for DWT local foundations. Inspections were conducted for works including NT uditches, ATM sleepers, and local foundations.
Date : 2023-07-05 (Wednesday) [ UNIT : ㎥ ] LEAN FOUNDATION PEDESTAL / WALL NO. ID NUMBER REMARKS PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL 1 ATM Paving Paving 3, 4 39.0 39.0 42.0 2 ATM Road Uditch Span 4 3.0 3.0 3 ATM Sleeper ASL 68, 69 5.0 5.0 5.0 4 SPT Road Drainage Span 5 6.0 6.0 6.0