Costing For VIP Toilet Participants 04-02-2019

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Kukokotoa Gharama za Kujenga Choo cha VIP cha Mlango Mmoja na Bafu

a) kuchimba shimo na kulijenga / Pit excavating and construction


Na Maelezo Kipimo Idadi Kiasi Jumla
1 Mawe / stones Safari/Trip 1 80,000 80,000
2 Mchanga / sand Toroli / push carts 1 15,000 15,000
3 Kokoto / gravels Toroli / push carts 30 700 21,000
4 Saruji / cement 50kg bags 4 20,000 80,000
5 Nondo / iron rods 12mm 2 20,000 40,000
6 Waya / binding wire rolls 1 3,000 3,000
7 miti au mirunda / wooden poles pcs 2 500 1,000
8 Kuchimba shimo / excavating 100x100x2100cm 1 30,000 30,000
9 Bomba / pipe pvc 0.5 15,000 7,500
Jumla ndogo / sub total Tsh 277,500

b) Kujenga kibanda cha choo na bafu / Construction of super structure


10 Matofali / bricks pcs 500 170 85,000
11 Mchanga / sand toroli / push carts 2 15,000 30,000
12 Saruji / cement 50kgs bags 3 20,000 60,000
13 Nondo / iron rods pcs 0.5 20,000 10,000
14 Mbao / timbers 2x2 inches 3 4,500 13,500
15 Mbao / timbers 2x4 inches 3 4,500 13,500
16 Bati / roofing sheets 6ft 4 16,000 64,000
17 Misumari ya mbao / timber nails kg of 4 inches 1 3,500 3,500
18 Misumari ya bati / roofing nails kgs 1 6,000 6,000
19 Waya wa Kenchi / wires for roof fasteningrolls 1 3,000 3,000
20 Milango / doors pcs 2 38,650 77,300
Jumla ndogo / sub total Tsh 365,800

Jumla kuu / grand total Tsh 643,300

Gharama ya fundi / masons fee Percentage 15% Tsh 96,495


Imekadiliwa kuwa / estimated at 100,000

JumlaYote 743,300

Mahitajiya Milango Miwili / requirements for making two doors

1 Mbao / timber pcs 8 4,500 36,000


2 Bati / roofing sheets 6 ft 2 16,000 32,000
3 Bawaba / hinges pcs 4 750 3,000
4 Komeo door stoppers pcs 4 700 2,800
5 Misumari / nails kgs 1 3,500 3,500
Jumla ndogo / sub total Tsh 77,300