Professional Documents
Culture Documents
Status of 1x660mw SGTPP Phase III Project Mechanical 30032023
Status of 1x660mw SGTPP Phase III Project Mechanical 30032023
Status of 1x660mw SGTPP Phase III Project Mechanical 30032023
C. ESP:.
D. TOTAL ERECTION OF BOILER (Non Pr. Parts + Pr. Parts +Rotary Parts + ESP):
F. Condenser-1:
Condenser-1, shell/box assembly completed.
Condenser-1, TSP generator side erection completed
G. Power House Erection & Fabrication:.
LP heater floor (BC bay between grids(8 to 11) at 8.5m elevation and AB bay between grids
(9 to 11) at 8.5m elevation structural erection and welding completed.
Placement of deck sheet for AB bay roof between grids (2 to 13) completed.
Fabrication February’23/Cumulative: 185.037 / 8009.125 MT.
Erection in February’23/Cumulative: 408.926 / 7025.013 MT.
H. Concreting:
Casting of silo slab at 12.05m elevation (320cum) completed.
Concreting of Vacuum pump house slab at 14.05m elevation completed.
Compressor foundation at the existing Compressor House completed.
I. Chimney:
Chimney shell casting crossed 100 mtr. height and presently achieved height of 116.450 mtr.
J. NDCT:
Completion of concreting of Cooling Tower Shell. 151.00 / 151.00mtr.
Fabrication of CT inlet pipe started.
K. CHP:
Grade slab of MCC 1 completed.
Fabrication of all columns of TP 22 completed and erection of forth tier started.
Fabrication of columns of conveyor 23AB (connection from existing unit) completed and 2
out of total 5 nos. of galleries completed.
Fabrication of all columns of TP 20 completed.
Concreting of 3nos of footing of TP25 completed. As on date all footings of TP 25
completed.
Temporary structures of TP 26 are started.
Fabrication February’23/Cumulative: 949.843 / 5315.176 MT.
Erection in February’23/Cumulative: 383.181 / 2026.948 MT.
L. TWT:
Raft casting of Wagon Tippler (1315 cum) completed.
M. 400kV Switchyard:
Stringing of 02 spans of quad moose conductor for GT Bay is completed.
12 nos. 400 KV CT erected out of total18 nos.
APH to wind box duct alignment( RHS) / sofa duct preassembly/ erection u/p
Lift Structure preassembly u/p & erection upto 6th tier completed