JOB STEPS:
1. Mobilization Of People, Equipment & Materials
2. Piling
3. Lowering of Steel cage Structure
4. Concreting
Contingency Plans. Standard PPE’s: First aid kit must be present at work site, Emergency contact
numbers to be in placed at job location
JSA Review Process. After the job has been completed, JSA leader should note: any hazards, which were
identified in the original JSA? In case of any new hazard indentified by any of the working team member
during the job, JSA review process should be carried on.
JSA JOB TITLE: Piling & Concreting Works for the construction of Foundations/Building
No:
S.N JOB STEP HAZARDS CONSEQUENCES CONTROL
O MEASURES
1 Mobilization Involvement of Personal Trained &
of equipment unskilled injury/Accident skilled staff to
& Materials personnel be authorized
for working
Ensure JSA
briefing &
Daily TBT to
all workforce
prior to
commence
activity
JSA JOB TITLE: Piling & Concreting Works for the construction of Foundations/Building
No:
S.N JOB STEP HAZARDS CONSEQUENCES CONTROL
O MEASURES
tripod, injure by tripod. Stand the
tripod properly,
tripod to be
fixed on
ground
properly.
Keep away all
unauthorized
people during
movement of
heavy
vehicle/equipm
ents
Be careful of
nearby live
areas
Ensure Close
HSE
monitoring
/supervision
Improper Entry of Barricade the
barricade unauthorised working area
person. properly
Fall of person in
Pile.
Sling broken, Fatal/injury due Ensure proper
load drop to load drop. & inspected
accessories
being used for
drilling
Ensure that
drilling bit is
properly fixed
with locking
pins
Keep away
during drilling
operation
working area
should
properly
barricaded
[Type text]
JSA JOB TITLE: Piling & Concreting Works for the construction of Foundations/Building
No:
S.N JOB STEP HAZARDS CONSEQUENCES CONTROL
O MEASURES
Noise Can cause Provide Ear
deafness & Plug
psychological
imbalance.
JSA JOB TITLE: Piling & Concreting Works for the construction of Foundations/Building
No:
S.N JOB STEP HAZARDS CONSEQUENCES CONTROL
O MEASURES
load barricaded
during lifting
operations
Poor Poor Ensure proper
Housekeeping. housekeeping can stacking of all
create unhygienic materials at
work place which work site
can leads to Maintain good
growth of insects. housekeeping
all the time
4 Concreting of Inappropriate Slip of tools can Use of
Piling PPE’s/Tools injure workmen appropriate
during concrete due to PPE’s during
work inappropriate ppe concrete
and tools. Ensure use of
Skin contact Skin contact with inspected tools
with concrete concrete can for the right
or other cause blisters, job
chemicals dead or hardened Availability of
skin. fresh water at
site
First aid box
should be in
place at site
5 Working at Poor visibility Tripping of Ensure proper
night shift at night hours workers due to lighting.
hours Poor visibility