Professional Documents
Culture Documents
Reaction
Reaction
Development length and lap length are two important terms in civil engineering. In this article, I will discuss the differences between
development length and lap length. Let’s get started.
What Is Development Length?
Development length is the length of bar required for transferring the stress into concrete. In simple words, the quantity of the rebar length
that is actually required to be embedded into the concrete to achieve the desired bond strength between concrete and steel by producing
required stress for the steel in that area.
• The formula for development is given below:
• Development length (Ld) = d x σs/τbd
Where
• d = Diameter of the bar.
• σs = Stress in the bar at the section considered as design load.
• τbd = Design bond stress.
In the below image, you can see some amount of rebar is left for future construction.
This extra rebar will be needed for tying bars of column. This extra length of rebar is called lap length.
Hope you all understood the difference between development length and lap length. If you have any questions, let me know in the
comments.
What Is Slab?
Slab is an important structural element generally constructed horizontally to provide flat surfaces such as roof, ceiling, floor, etc. Slabs
may be supported by RCC beams, columns, steel beams, etc. Basically, the depth of a slab is very small compared to its depth. There are
mainly two types of slabs, i.e one way slab and two way slab. In this article, I will discuss difference between one way slab & two way
slabs.
What Is One Way Slab?
One way slab is a slab which is supported by beams on the two opposite sides to carry the loads along one direction. In one way slab, the
ratio of longer span (l) to shorter span (b) is equal or greater than 2, i.e Longer span (l)/Shorter span (b) ≥ 2
Example:
Verandah slab is a type of one way slab, where the slab is spanning in the shorter direction with main reinforcement and the distribution
of reinforcement in the transverse direction.
One Way Slab Reinforcement Details:
In one way slab, as one side is larger than the other one, the maximum load will be conveyed by the larger side. Therefore it is important
to provide adequate support to this side.
To provide adequate support to the longer side, the main reinforcement bars are provided parallelly to the shorter side and the
distribution bars are provided on the longer side which won’t help in carrying the load.
In the above slab, Larger span/Shorter span = Lx/Ly = 4500/2000 = 2.5 Which is > 2.
So it is a one way slab. In this slab, the main reinforcement bars are provided on the shorter side and distribution bars are provided on the
longer side.
What Is Two Way Slab?
When a reinforced concrete slab is supported by beams on all the four sides and the loads are carried by the supports along with both
directions, it is known as two way slab. In two way slab, the ratio of longer span (l) to shorter span (b) is less than 2.
i.e Longer span (l)/Shorter span (b) < 2
These types of slabs are mostly used on the floor of multi-storey buildings.
Two Way Slab Reinforcement Details:
In two way slab, as the loads are carried in both directions (longer and shorter direction) main reinforcement bars are provided in both
directions.
The loads are carried by two sides are equal. Slab with reinforcement in both directions is more economical than one way reinforcement
slabs.
The loads are carried along one direction. The loads are carried along with both directions.
One Way Slab Two Way Slab
The ratio of Longer span to shorter span is equal or greater than 2. The ratio of Longer span to shorter span is less than
(i.e l/b ≥ 2). 2. (i.e l/b
Main reinforcement is provided only in one direction (Shorter Main reinforcement bars are provided in both
side). directions.
The deflected shape is cylindrical. The deflected shape is like a dish or saucer.
Apparatus
1. Steel test plate
2. Hydraulic jack and pump
3. Reaction beam or truss
4. Dial gauge
5. Pressure gauge
6. Excavation tools
7. Equipment for loading
8. Plumb bob, tripod, spirit level
Different Methods Of Plate Load Test
There are two different methods known for plate load tests.
1. Gravity loading platform method, and
2. Reaction truss method.
Let us learn these methods one by one in detail below.
1. Gravity Loading Platform Method
In this method, a platform is built on the top of a vertical post, resting on a platform. The load is applied on the platform with the help of
sandbags, stones, or concrete blocks.
When the load is applied on the platform, the test plate starts to settle down. That settlement is precisely measured using two sensitive
dial gauges, which are mounted on the independently supported datum bar. The total load is calculated and ultimate bearing capacity is
measured using the calculations and formulas.
This test is done at construction site before the concreting process. The slump test gives satisfactory results for the concrete mix of
medium to high workability and unfortunately, it does not give the correct indication of low workability, which may give zero slumps.
Apparatus For Slump Cone Test:
1. Mould or slump cone with a height of 300 mm, bottom diameter 200 mm, and top diameter 100 mm.
2. Standard tamping rod.
3. Non-porous base plate.
4. Measuring scale.
Procedure Of Slump Test (Step By Step):
1. First, clean the inner surface of the empty mould and then apply oil to it.
2. Set the mould on a horizontal non-porous and non-absorbent base plate.
3. Fill the mould fully by pouring freshly mixed concrete into three equal layers.
4. Stroke each layer 25 times with the standard tamping rod over the cross-section.
5. After stroking 25 times the top layer is struck off level, now lift the mould slowly in the vertical direction without disturbing the
concrete cone.
6. Use the measuring scale to measure the difference level between the height of the mould and the concrete sample.
7. The subsidence of concrete is known as the slump and the value of slump is measured in mm.
Types of Slump:
True Slump: The concrete mass after the test when slumps evenly all around without disintegration is called the true slump.
Shear Slump: When one-half of the concrete mass slide down the other is called the shear slump. This type of slump is obtained in a
lean concrete mix.
Collapse Slump: When the sample is collapsed due to adding excessive water, it is known as collapse slump.
Zero Slump: For very stiff or dry mixes it does not show any changes in the slump after removing the slump cone.
2. Pavements 20-30
The beam has a clear span of 5 meters consisting of two bottom layers (2 no.s of 20 mm dia and 2 no.s of 16 mm dia) and one top layer
(2 no.s of 12 mm dia).
It consists of 3 zones where zone 1 and zone 3 have 8 mm dia stirrups with a spacing of 150 mm & Zone 2 has 8 mm dia stirrups with a
spacing of 200 mm.
Clear Span of Beam = 5000 mm
Development Length Ld = 50d (assumption)
Clear Cover on any ends = 25 mm
Bottom – 2 no.s 20Ø and 2 no.s of 16Ø
Top – 2 no.s of 12Ø
Stirrups
Zone 1,3 = 8Ø @ 150mm clear cover
Zone 2 = 8Ø @ 200mm clear cover
Step 1 – Calculate Cutting Length Of Top Bar
Cutting length of top bar = Clear Span of Beam + Development length – Bend
Where bend for 45deg=1d, 90deg=2d, 135deg=3d
Cutting length = L + (2 x Ld) – (2 x 2d)
= 5000 + (2 x 50 x 12) – (2 x 2 x 12)
= 5000 + (2 x 50 x 12) – 50
= 6152 mm
Step 2 – Calculate Cutting Length Of Bottom Bar
For First Layer (20Ø):
Cutting length of bottom bar = Clear Span of Beam + Development length – Bend
Where bend for 45deg=1d, 90deg=2d, 135deg=3d
Cutting length = L + (2 x Ld) – (2 x 2d)
= 5000 + (2 x 50 x 20) – (2 x 2 x 20)
= 6920 mm
For Second Layer (16Φ):
Cutting length of bottom bar = Clear Span of Beam + Development length – Bend
Cutting length = L + (2 x Ld) – (2 x 2d)
= 5000 + (2 x 50 x 16) – (2 x 2 x 16)
= 6536 mm
Step 3 – Calculate Number of Stirrups
This beam has three zones where Zone 1 & 2 consist of 8 mm dia stirrups of 150 mm spacing and Zone 3 has 8 mm dia stirrups of 200
mm spacing.
First we need to calculate the length of each zone = L/3 = 5000/3 = 1666 mm
Number of stirrups required for Zone 1 = (Clear Span of beam/ Spacing of stirrups) + 1
= (1666/150)+1 = 12.10 ♎ 12 no.s
Number of stirrups required for Zone 3 = Same as Zone 1 = 12 no.s
Number of stirrups required for Zone 2 = (Clear Span of beam/ spacing Stirrups) – 1 = (1666/200) – 1 = 7 no.s
The reason for the “minus 1 “ is already zone 1 has end stirrup so we don’t need to again start from the new one. we just continue the
stirrups already existing with extra spacing.
Cutting length of stirrups:
Cross section of stirrups is
Width = 300 mm
Height = 500 mm
a is horizontal length of stirrup
= 300 – (2 x clear cover) – (2 x half of bar dia )
= 300 – (2 x 25) – ( 2 x 4)
= 242 mm
b is vertical length of stirrup
= 500 – (2 x clear cover) – (2 x half of bar dia)
= 500 – (2 x 25) – (2 x 4)
=442
Now calculate cutting length of stirrup
Cutting length = 2 x (a+b) + hook – bend
= 2 x ( 242 + 442) + (9d x 2) – (3d x2) – (2d x 3) [For 2 no. 135 bend (3dx2) & for 3 no. 90 bend (2dx3)]
= 2 x 684 + (9 x 8 x2) – (3 x 8 x 2) – (2 x 8 x3)
= 926 + 144 – 48 – 48
= 974 mm = 0.97 m
Calculate Weight Of Stirrups:
Total no. of stirrups = 12 + 12 + 7 = 31
Total length of stirrups = 0.97 x 31 = 30.19 m
Total weight of stirrups = d2xL/162 = 8 x8 x 30.19/162 = 12 kg
BBS Of Beam:
Top
12 2 6.152 12.30 10.93
Bar
Bottom
20 2 6.920 13.84 34.6
Bar
Bottom
16 2 6.536 13.07 20.91
Bar
But these are now backdated (not wrong), and we don’t use them today. Because No accurate values were specified if we use more bars
in a single member. Nowadays we are constructing 150+ floors building. It is now possible with our modern techniques, equipment, etc.
The estimation of steel becomes easier because of BBS.
Civil engineers who are working on site or freshers who are going to work at construction sites must know how to prepare bar bending
schedules. In this article, I will discuss some important things used in preparing bar bending schedule.
These are just basic things. In the future, I will come up with some other articles related to BBS such as BBS for beams, columns, slabs,
footings etc.
What Is Bar Bending Schedule?
Bar bending schedule commonly known as BBS is one of the most important terms in Civil Engineering. Because it plays a vital role in
building construction.
Like other building materials estimation of steel is also required for constructing a building and here BBS comes with an easy solution.
Bar bending schedule provides the reinforcement calculation and some other important details such as bar mark, bar diameter, bar shape,
cutting length, number of bars, the weight of bar, total weight of steel, etc, so that we can order the required amount of steel in advance.
Hook Length:
The hook is the extra length left at the 4th corner of a stirrup so that the stirrup retains its shape.
Generally, hook length is taken as 9d for one side.
Where d = Diameter of the bar.
The total length of stirrups = Total length of the bar + 2 x hook length (for two hooks)
= L + 2 x 9d
= L + 18d.
Where L = length of the bar for stirrup.
Bend Length:
The bar is bent at the column end to tie with the footings. This extra length for bend is called bend length.
Bend length is generally considered as 16 d
Bend Length = 16d
Development Length:
Development length is a vital point in bar bending schedule. Development length is the length of the bar required for transferring the
stress into the concrete.
In simple words, the quantity of the rebar length that is actually required to be embedded into the concrete to create the desired bond
strength between steel and concrete and furthermore to produce required stress for the steel in that area.
The formula for development is given below:
Development length (Ld) = d x σs/τbd
Where
d = Diameter of the bar.
σs = Stress in the bar at the section considered as the design load
τbd = Design bond stress.
Lap Length:
Lap length is an important term in BBS. Lap length is the overlapping length of two bars side by side which gives required design length.
In RCC structure if the length of a bar is not sufficiently available to make design length, lapping is done.
Suppose we need to build a 20 m tall building. But is there any 20 m bar available in the market? No, the maximum length of rebar is
usually 12 m, so we need to join two bars to get 20 m bar.
Lap length for tension members = 40d
Lap length for compression members = 50d.
d = Diameter of bars.
Look at the image below. You may be seen this on the terrace (top floor) of buildings. This extra rebar is left for future construction
purpose. I hope you understand this.
Crank Length:
Generally, bars are bent near the support at an angle of 45°. The angle of bend may also be 30° in shallow beams. The purpose of bend
near the support is firstly to resist the negative bending moment which occurs in the region of the support and secondly to resist the shear
force which is greater at the support.
Crank bars are mostly provided in slabs.
The length of hooks and the total length of a given steel reinforcement is achieved by the following method.
Difference Between Short Column And Long Column
There are different types of columns used in structures. In our previous article, we have already discussed that topic. In this article, I will
discuss the difference between short column and long column.
What is Short Column?
When the ratio of the effective length of a column to its least lateral dimension does not exceed 12, it is called short column.
1. The ratio of the effective length to its least lateral 1. The ratio of the effective length to its least lateral dimension
dimension is less than 12. is greater than 12.
2. The slenderness of short column is less than 12. 2. The slenderness of long column is greater than 12.
4. The load-carrying capacity of short column is 4. The load-carrying capacity is less compared to short column
greater than long column. of same cross-sectional area.
5. Stronger than long column and highly preferrable. 5. Weaker than short column and generally not preferred.
6. Short column is subjected to compressive stress. 6. Long column is subjected to buckling stress.
7. Mechanical failure mainly occurs due to shearing. 7. Long columns are liable to fail due to buckling.
Or You Can check out this article – What is 1.54 in Concrete Calculation?
Calculation For Cement
Formula, Cement = (Volume of dry concrete/a+b+c) × a
• = (1.54/a+b+c) × a = [(1.54/1+2+4)] × 1 = 0.22 cum
Now density of cement = 1440 kg/cu.m
• ∴ Volume of cement = 0.22 × 1440 =316.8 kg.
As we know, 1 bag of cement contains 50 kg of cement.
• ∴ Cement bags required = 316.8/50 = 6.33 bags.
Calculation For Sand
Formula, Sand = (Volume of dry concrete/a+b+c) × b
• = (1.54/a+b+c) × b = (1.54/1+2+4) × 2 = 0.44 cu.m.
Calculation For Aggregates
Formula, Aggregates = (Volume of dry concrete/a+b+c) × c
• = (1.54/a+b+c) ×c = (1.54/1+2+4) × 4 = 0.88 cu.m.
Calculation For Water Content
Let us assume the water-cement ratio of concrete is 0.45.
• w/c = 0.45
• Required water for 1 bag cement = 0.45 × 0.0353 = 0.0159 cu.m.
Where volume of 50 kg cement = 0.0353 cu.m
• 1 m3 water = 1000 Litre
Required water for 1 bag of cement=0.0159 × 1000 = 15.9 Litre.
∴ Required water for 6.33 bags cement = 6.33 × 15.9 = 101 Litre.
Summary
• Cement = 6.33 bags.
• Sand = 0.44 cum
• Aggregates = 0.88 cum
• Water = 101 litre.
Note: Yield of concrete is considered as 67% & Wastages of materials = 2%
You can use the same formula for different mix proportions such as 1:1.5:3 etc.
Here, we have used cubic meter unit but you can also calculate in cubic feet unit.
Following points should be remembered while calculating the quantity of cement, sand for plastering work.
1. For wall plastering, Cement : Sand = 1 : 6
2. For ceiling plastering, Cement : Sand = 1 : 4
3. Thickness of the plaster should be between 12-15 mm. If an additional coat is required, then do not do it in one go.
4. Use good quality cement & Sand.
5. Use a measuring box (not a head pan) for the site mix.
We will calculate cement and sand for 100 m2 plastering area in 1:6 ratio and thickness of 12 mm.
Cement Mortar Required:
Plastering thickness = 12 mm
= 12/1000 = 0.012m
Volume of cement mortar required = ( Plastering Area x thickness )
= 100 m2 x 0.012m = 1.2 m3
(This is wet volume of cement mortar (after mixing water), but we need dry volume. To get dry volume, consider 35% bulking of sand
and 20% wastage
= 1.2 m3 x (1+0.2+0.35) (Rather than 35% sand bulkage and 20% wastage, you can add 1.54 as constant)
= 1.86 m3
Cement : Sand = 1 : 6
Sum of ratio = (1+6) = 7
Cement Required
= 1.86 x 1/7 = 0.265 m3
= 0.265/0.0347 (0.0347 m3 = 1 bag = 50 kg cement)
= 7.66 bags = 8 bags
Sand required:
1.86 x 6/7
= 1.59 m3
Here we have calculated in Sq.m but you can also use Sq. ft.
Here we have calculated in Sq.m, but you can also calculate it in Sq.ft.
To use the brick calculator manually we need some data for calculating no. of bricks.
Required Data:
• Volume of the wall.
• Volume of a standard brick.
• Details of openings in the wall.
Let’s assume
Length of the wall = l = 4 m
Height of the wall = h = 3 m
Thickness of the wall = b = 200 mm = 0.2 m
Assuming that the wall has no openings.
Brick size = 190 mm x 90 mm x 90 mm (without mortar)
Volume of brick masonry in wall = lxhxb = 4 x 3 x 0.2 = 2.4 m 3
Volume of one brick with mortar = 0.2 x 0.1 x 0.1 = 0.002 m 3
Number of bricks = [Volume of brick masonry/volume of one brick]
= 2.4 / 0.002 = 1200 bricks.
Consider 5% wastage of bricks.
Thus, the number of bricks required for 1 cubic meter = 500
Example 2 (Brick Calculator In Feet Unit):
You can use the same brick calculator for different units. In this example, We will use the feet unit.
1. First, calculate the volume of the wall to be built:
Let us assume,
The length of the wall (l) = 10 feet.
The height of the wall (h) = 10 feet.
The thickness of the wall (b) = 200 mm = 0.656 feet.
Calculate the volume of the wall by multiplying the length, height, and thickness.
∴ Volume of the wall = l×h×b = 10×10×0.656 =65 Cu.F
2. Calculate the volume of one brick
We will use standard Indian bricks for the calculator.
The standard size of a brick (IS Standard) is 190 mm ×90 mm ×90 mm and
with the mortar joints, it becomes 200mm × 100 mm× 100 mm.
l = 200 mm= 0.656168 ft.
b = 100 mm =0.328084 ft.
h = 100 mm = 0.328084 ft.
∴ Volume of the brick = l× b×h = 0.656168× 0.328084× 0.328084 = 0.0706 Cu.F
3. To find out the total nos of brick divide the volume of the wall by the volume of the brick.
∴ No. of bricks required = 65.6/0.0706 = 929 no. of bricks.
Note:
1. Consider 5% wastage of bricks.
2. If the wall has any openings such as doors, windows, etc subtract the volume of the openings from the volume of the wall and then
divide it by the volume of brick.
I hope you have now learned how to calculate bricks using our manual brick calculator. Good luck.
1 90 to 40 100 100
80 65 – 85
63 25 – 60
40 0 -15
20 0–5
2 63 to 40 80 100
63 90 – 100
50 30 – 70
40 0 – 15
20 0–5
3 50 to 20 63 100
50 95 – 100
40 35 – 70
20 0 – 10
10 0–5
2. Screenings
The screenings are basically used for filling up the voids in the layer of coarse aggregates. Screenings include aggregates of smaller
sizes. The screenings are generally the same material as coarse aggregates used in water bound macadam.
The table below states the grading requirements of screenings for water bound macadam.
Grading Size of screenings Sieve size % By weight passing
10 mm 90 – 100
4.75 mm 10 – 30
B 10 mm 10 mm 100
4.75 mm 85 – 100
150 micron 10 – 30
3. Binding Materials
To avoid raveling of aggregates, fine grained materials such as kankar nodules or lime stone dust are used as binding materials for the
construction of water bound macadam.
When WBM is used as a surface course, the binding materials used in it should have a plasticity index between 4 to 9.
When and where crushable materials such as moorum or soft gravel are used as screenings, binding materials are not required.
WBM Road Construction Procedure
The following steps are adopted for the construction of WBM roads:
1. Preparing the foundation for receiving the WBM course
The foundation supporting the layer of WBM is either the subgrade or sub-base course. It is prepared to the required grade and camber.
It is cleaned of all the dust particles and loose materials present on it. The foundation, supporting the WBM, should be dried.
When the existing road is topped black, furrows are cut at an interval of 1m at an angle of 45 degrees to the centre line of carriageway.
2. Lateral confinement of aggregates
The aggregates in WBM are confined because if they are placed on the subgrade, there are possibilities that the aggregates may come out
due to the load of traffic. It is done by construction of shoulders of thickness similar to the thickness of the compacted layer of WBM
(7.5 cm).
3. Spreading coarse aggregates
The aggregates should be evenly and uniformly spread on the prepared base in the required amount. They may be spread manually or
mechanically. The thickness of the layers (compacted) of WBM constructed should not be more than 75 mm.
4. Rolling
Once the aggregates are spread evenly, the rollers are deployed to carry out the process of compaction. The rollers used shall be of 6 to
10 tonnes capacity. The compaction of aggregates should start from the edge of the surface. The aggregates are compacted partially then
the compaction is paused to permit the application of screenings
5. Application of screenings
After partial compaction of aggregates, screenings are applied so that the voids in the aggregates are filled completely. They are applied
gradually over the surface in three or more applications. Again after applying screenings, dry rolling is resumed so that they are
completely filled in the voids.
6. Sprinkling and grouting
The surface is sprinkled with water after applying the screenings. The surface is then swept and rolled so that the voids are completely
filled. If any voids are left empty, additional screenings may be applied.
7. Application of binding materials
After applying the screenings, binding materials are applied in thin layers. Two or more thin layers of binders are applied. After the
application of each layer of binding materials, water is sprinkled followed by compaction of layers by rollers of 6 to 10 tonnes capacity.
8. Setting and drying
After all the above mentioned processes, the layer of WBM is allowed to set overnight. Next day the road is inspected and if any voids
are empty, they are filled and compacted.
Advantages Of WBM Road
The advantages of WBM roads are as follows:
1. Initially, the construction of WBM road is cheaper.
2. Locally available materials are used.
3. No specially trained labours required.
4. If it is maintained properly, it can take up to 900 tonnes of traffic per day.
Disadvantages Of WBM Road
The disadvantages of WBM roads are as follows:
1. Higher maintenance cost.
2. It is permeable. So it causes softening of subsoil and may get damaged during the rainy season.
3. The life span of WBM roads is less.
4. It is not able to bear heavy traffic loads.
Purpose:
Dowel bars are used
1. To transfer the load from one slab to its adjacent slab such that two consecutive slabs move together and reduce impact loading
developed by the slabs by their independent movement.
2. To reduce joint faulting and corner cracking.
3. To improve the performance of pavement joints.
The size of dowel bars depends on the thickness of the pavement. Usually, these bars are 18 inches (460mm) long, 1.25 to 1.5 inches (32
to 38 mm) in diameter, and spaced 12 inches (305mm) apart. To protect the rods from corrosion they are either stainless steel or epoxy
coated.
Dowels must be placed parallel to the centerline. New channels must be cut so that at least one-half dowel can be on each side of the
joint or crack.
Assume,
Length of road = L = 5 km = 5000 m
Width of road = W = 6 m
Thickness of asphalt = H = 15 cm = 0.15 m
Quantity Of Asphalt Calculation:
The volume of asphalt = L x W x H
= 5000 x 6 x 0.15 = 4500 m3
Here, the density of asphalt is taken as 2330 kg/m3
Therefore, quantity of asphalt = Volume of asphalt x Density of asphalt
= 4500 x 2330 = 10485000 kg = 10485 tons
Cost of asphalt:
Suppose the cost of 1 ton asphalt is 6000 rs.
Cost of asphalt = 10485 x 6000 = 62910000 rs
Quantity Of Asphalt In Curved Road
Assume,
• Width of road = W = 6 m
• Thickness of asphalt = H = 15 cm = 0.15 m
Length of curved road = (π x R x θ)/180 = (3.14 x 10 x 100)/180 = 17.44 m
Volume of asphalt for curved road = Length x Width x Thickness
= L x W x H = 17.44 x 6 x 0.15 = 15.696 m 3
∴ Quantity of asphalt for curved road = Volume of asphalt x Density of asphalt
= 15.69 x 2330 = 36558 kg = 36.55 tons
Cost of asphalt:
Suppose the cost of 1 ton asphalt is 6000 rs.
Cost of asphalt = 36.55 x 6000 = 219300 rs
Note:
In case the area you are calculating has an irregular shape, divide it into several regularly-shaped sections, then calculate each of their
volume and asphalt requirements using the above method. Finally, sum them up together.
CONCRETE
The travel time of electronic pulses is measured when they travel from the transmitter to the receiver. The length of the path traveled by
pulses is divided by the travel time of pulses which gives the average velocity of wave propagation. The pulse velocity is correlated to
the strength of concrete. The higher the pulse velocity, the greater is the strength of concrete.
Objective
The objectives of rebound hammer test are as follows:-
1. To find out the compressive strength of concrete with suitable correlations between the compressive strength and rebound index.
2. To evaluate the uniformity of concrete.
3. To evaluate the quality of concrete on the basis of standard requirements.
4. To compare the quality of one element of concrete with the other element.
Principle Of Test
This test is based on the principle that the rebound of an elastic mass depends on the hardness of the concrete surface against which the
mass collides.
The rebound hammer comprises a plunger which is attached to a spring-driven metal mass. The plunger is held to a smooth concrete
surface. It is held at an angle of 90 degrees and firmly pressed at the concrete surface.
The metal mass controlled by a spring in the hammer rebounds when strikes concrete surface. The amount of rebound of the metal mass
is noted on a graduated scale which gives an indication of the compressive strength of concrete.
The strength of concrete is directly proportional to the hardness of the surface of the concrete. So the quality of concrete, in terms of its
compressive strength, is said to be better if the rebound is higher and vice versa.
Procedure
Before the commencement of the rebound hammer test, the rebound hammer which is to be used is calibrated against a steel test anvil
having a Brinell hardness number of 5000 MPa. Once the rebound hammer is calibrated and ready for use, the test is conducted.
To start with, the Swiss hammer is held at a right angle against the concrete structure. The Swiss hammer is then stroked against the
structure.
The hammer stroked at the structure bounces back with some amount of force which the reading is shown on the graduated scale given
on the rebound hammer itself and recorded.
On average 10 to 12 readings are taken to get better accuracy of results. Because sometimes the rebound number could be abnormally
high due to the presence of large aggregates immediately underneath the plunge or it may be too low due to some voids present beneath
the plunge of the hammer. So, it is advised to take at least 8 readings for more accurate results.
This test can be conducted on an element placed vertically or horizontally, keeping in mind that the rebound hammers should be placed
at 90 degrees to it.
The rebound value obtained from the test defines the quality of the concrete element or its compressive strength of it. Different rebound
values indicate the different quality of structure, as mentioned in the table below.
REBOUND NUMBER VALUE QUALITY OF CONCRETE ELEMENT
30 to 40 Good layer
20 to 30 Fair layer
Additional admixtures are always optional, but they do play an important role in enhancing the properties of concrete as per the
requirements.
All of the above mention ingredients are mixed in a definite proportion to form the final product, which is fresh concrete. Basically,
these proportions are selected in such a way that each set of proportions of materials in concrete determines a specific grade of concrete.
A specific grade of concrete represents a numeric value, which denotes the compressive strength of concrete, achieved after 28 days of
construction of a structure from that concrete.
i) Beam: Joint may be located at mid-span or over the center of the column in direction at right angles to the length of the beam.
ii) Columns: Joints should be located a few cm below its junction with the beam.
iii) Slab: Joints may be placed at mid-span or directly over the center of the beams, at right angles to the slab.
Formwork for construction joint should be placed at the end of each day’s work.
Before new concreting is started, the concrete surface of hardened concrete should be cleaned, roughened, saturated with water, and
applied cement grout. This will ensure proper bond between old and new concrete works. New concreting is started before the applied
grout on old surface attains initial set.
2. Expansion Joints:
These joints are provided to allow for expansion of the concrete, due to rise in temperature above the temperature during
construction. Expansion joints also permit the contraction of the element. Expansion joints in India are provided at an interval of 18 to
21 m. The open gap of this joint varies between 2 cm and 2.5 cm. Sometimes, to transfer load from one slab to the adjacent slab, dowel
bars are also used at suitable intervals at these joints.
3. Contraction Joints:
These types of concrete joints are provided to allow contraction of the concrete. Contraction joints are spaced closer than expansion
joints. These joints do not require any load transfer device as it can be achieved by the interlocking of aggregates. However, some
agencies recommend use to dowel bars fully bonded in concrete.
4. Warping:
Warping joints are provided to relieve stresses induced due to warping effect. These joints are also known as hinged joints.
Minimum Cover For Reinforcement in Cast-In-Place Concrete:
The clear cover is the distance between the outer surface of concrete to the nearest surface of reinforcing bar.
Clear cover varies in different conditions. The clear cover for cast-in-place concrete is given in the below table.
Minimum
Sl. No. Conditions cover
(inches)
A slight change in the amount of water causes much more differences in the strength of concrete.
If less water is used, the resultant concrete will be nearly dry, hard to place in the form and may create difficulties in compaction.
Besides this, with less water proper setting will not be guaranteed and thus the strength of concrete get reduced considerably.
On the other hand, if water is used more, it may develop larger voids and honey-combing in the set concrete, in this way decreasing its
density, durability, and strength.
Hence, water cement ratio attends an important role in producing concrete of required strength. The lower the ratio, the greater is the
strength of concrete.
Required Water-Cement Ratio ( British Standard Specifications):
1:2:4 0.58
1 : 1.5 : 3 0.51
1 : 1: 2 0.43
What Is Initial Setting Time Of Cement?
The time elapsed between when water is introduced to the cement and when the cement paste begins to lose its fluidity is known as the
initial setting time of cement.
Alternatively, it may be described as the period between adding water to the cement and the Vicat square needle penetrating a depth of
33-35 mm from the top (5 to 7 mm from the bottom) of the Vicat Apparatus’s mould.
What Is Final Setting Time Of Cement?
The interval between when water is introduced to the cement and when the cement paste has totally lost its fluidity is known as the final
setting time of cement.
The amount of time after the water has been added to the cement and the square needle has made an impression on the paste, while the
annular collar has failed to do so.
Apparatus Required
• Vicat’s apparatus: IS5513-1976 should be followed while using Vicat apparatus. It comprises a system to hold a 10 mm
diameter plunger and two additional needles that are free to fall into a mould filled with cement paste. The three needles’
penetration can be monitored using vertical graduations ranging from 0 mm to 50 mm.
• Balance: At a load of 1000 g, the allowed deviation in balance in use is 1.0 g. On a fresh balance, the permitted variance is
one-half of this figure. The reciprocal of the sensitivity must not be more than twice the permissible variation.
• Measuring cylinder stopwatch
• Glass plate
• Enamel tray
• Trowel
3. Setting Time:
Initial setting time should not be less than 30 minutes.
Final setting time should not be greater than 10 hours.
4. Required Curing Days:
Super sulfate cement – 7 days
Ordinary portland cement – 10 days
Cement with minerals and admixtures – 14 days.
5. Slump Value (IS-456):
Lightly reinforced concrete: 25 – 75 mm.
Heavily reinforced concrete: 75 – 100 mm.
Trench fill : 100 – 150 mm ( for in-situ & tremie).
6. Cube Samples:
1 – 5 m3 : 1 No.
6 – 15 m3 : 2 No..
16 – 30 m3 :3 No.
31 -50 m3 : 4 No.
Above 50 m3 : 4 + 1 no. of addition for each 50 m3.
The Formula D²L/162 Fully Derived:
To calculate the weight of steel bars you must use the formula D²L/162, but do you know where the formula D²L/162 came from? Okay,
no problem if you don’t know. In this article, I will share how to derive the formula D²L/162. So let’s start from the beginning.
The formula is D²L/162
Where,
D = Diameter of steel bar in millimeter
L = Length of steel bars in meter
Calculation Of The Formula D²L/162:
We know that,
Weight= Cross sectional area x Length x Density
For steel bar, this also remains same.
The weight of steel bars= Cross sectional area of steel bar x Length of steel bar x Density of steel bar.
That means,
W=AxLxρ
Where,
W = Weight of steel bars
A = Area = πD²/4
π (pi) = 3.14
D = Diameter of steel bar in millimeter
L = Length of steel bar in meter
ρ (Rho) = Density of steel bar = 7850 kg/m³
Therefore,
W = 3.14 x D²/4 x L x 7850
But there is two conflicting unit in the formula. Which is millimeter for D and meter for ρ (Rho).
So we need to convert either D or ρ to the same unit.
Let’s change the unit of D from millimeter to meter.
1 millimeter = 0.001 meter
Let’s put this into the formula,
W= 3.14 x {(D² x 0.001 x 0.001)/4} x L x 7850
= D²L/162
Following points should be remembered while calculating the quantity of cement, sand for plastering work.
1. For wall plastering, Cement : Sand = 1 : 6
2. For ceiling plastering, Cement : Sand = 1 : 4
3. Thickness of the plaster should be between 12-15 mm. If an additional coat is required, then do not do it in one go.
4. Use good quality cement & Sand.
5. Use a measuring box (not a head pan) for the site mix.
We will calculate cement and sand for 100 m2 plastering area in 1:6 ratio and thickness of 12 mm.
Cement Mortar Required:
Plastering thickness = 12 mm
= 12/1000 = 0.012m
Volume of cement mortar required = ( Plastering Area x thickness )
= 100 m2 x 0.012m = 1.2 m3
(This is wet volume of cement mortar (after mixing water), but we need dry volume. To get dry volume, consider 35% bulking of sand
and 20% wastage
= 1.2 m3 x (1+0.2+0.35) (Rather than 35% sand bulkage and 20% wastage, you can add 1.54 as constant)
= 1.86 m3
Cement : Sand = 1 : 6
Sum of ratio = (1+6) = 7
Cement Required
= 1.86 x 1/7 = 0.265 m3
= 0.265/0.0347 (0.0347 m3 = 1 bag = 50 kg cement)
= 7.66 bags = 8 bags
Sand required:
1.86 x 6/7
= 1.59 m3
Here we have calculated in Sq.m but you can also use Sq. ft.
Here we have calculated in Sq.m, but you can also calculate it in Sq.ft.
It is a combination of english bond and flemish bond. Facing of the wall is developed by using flemish bond and backing is developed by
using english bond. This type of bond can not be used in walls less than one and a half brick thickness. However, this bond gives better
and attractive looks.
b) Double Flemish Bond:
In this type of brick bonds, each course demonstrates the same appearance both in the front as well as back elevations (headers and
stretchers are laid in every course alternatively). Alternate headers and stretchers are used in every course.
This bond enables one brick wall to have flush and uniform faces on both sides. It gives a better appearance but comparatively weaker
than english bond.
Difference Between English Bond And Flemish Bond:
The difference between English bond and Flemish bond are as follows:
English bond is much stronger than flemish bond for the walls thicker more than 1½ brick.
Flemish bond shows more attractive and pleasing appearance of masonry work.
Flemish bond is economical as it uses broken brickbats, although it requires some extra mortar for additional joints.
Uses of flemish bond is a bit difficult than english bond. Flemish bond requires more skilled labour and supervision.
Stretcher Bond:
Stretcher bond is the simplest type of brick bond used for construction works. Sometimes it is also known as running bond.
In the arrangement of stretcher bond, all the bricks are laid as stretchers (as shown in fig).
No header is present in this bond, hence suitable reinforcement should always be provided for the construction of structural bondS.
Header Bond:
In this type of brick bond, all the bricks are placed as headers on the faces (as shown in fig). This bond is also known as the heading
bond.
The overlap is half the width of the brick and can be achieved by providing a three-quarter bat in each alternate course at quoins.
Header bond can be used in the construction of a curved structure, brick foundation,s etc.
What Is Formwork?
Formwork or shuttering is a temporary mold like arrangement of plates of different shapes, sizes, and materials used for the construction
of different concrete elements like columns, beams, walls, culverts, etc. In this article, we will discuss correct methods and period of
formwork removal i.e deshuttering.
Method And Period Of Removing Formwork:
The formwork should be constructed in such a manner that it is possible to remove the different components in the following order of
sequence:
1. Shuttering forming vertical faces of walls, beams, and columns sides (which bear no loads but are used only to retain the concrete)
should be removed first.
2. Shuttering forming soffit to slabs should be removed next.
3. Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.
Duration of time up to which the formwork should be kept in place depends upon many factors such as type of cement used, shape and
position of the member (whether the member is vertical, horizontal, or inclined) loads to be carried by the members and the temperature
of the air.
In general, rapid hardening cement, warm weather, and light loading conditions allow early removal of formwork.
Early release of formwork permits its reuse in other areas and this results in the economy by way of optimum utilization of material and
fast construction. At the same time, premature removal of formwork may prove to be dangerous and should not be allowed.
The formwork should, under no circumstances, be allowed to be removed until the concrete reaches a strength of at least twice the stress
to which the concrete may be subjected to the time of removal of formwork.
In normal conditions (where the air temperature is above 20°C and where ordinary Portland cement is used) the formwork may be struck
or removed after the expiry of the period indicated against respective members in the below table.
• Seal Coat
• Tack Coat
• Prime Coat
a. Seal Coat
Seal coat is provided directly on the top of surface course to make it watertight and to provide skid resistance to the surface. Mixture of
Emulsified asphalt, mineral fillers and water is used as seal coat material.
Fig 7: Seal Coat
b. Tack Coat
Tack coat is provided on the top of binder course to develop strong bond between the binder course and surface course. Asphalt
emulsion diluted with water is used as tack coat material.
c. Prime Coat
Prime coat is provided between base course and binder course to develop strong and water tight bong between them. Low viscous
cutback bitumen is sprayed on the top of base course as prime coat material.
• The surface dressing will provide a dust free wearing course over a granular base course that act similar to a water bound
macadam (WBM) or a wet mixed Macadam (WMM).
• The surface Dressing will help in providing impermeability for water percolation for the road surface
• Surface Dressing provide high friction for the riding surface
• This will provide a renewal coat for periodic maintenance of bituminous wearing surfaces.
• The surface dressing work involves the process of spraying of proper grade paving bitumen mainly VG-10 or the rapid setting
cationic emulsion. This is applied over an aggregate layer of appropriate size and gradation.
Surface dressing does not increase the structural strength and the riding quality of the pavement constructed.
Gap Graded Bitumen Mixes
The Stone Matrix Asphalt (SMA) is the most commonly used gap graded bituminous mixes. With the increasing traffic and the high
pressure of tires of the vehicles will give large stresses to the road pavement. The roads are subjected to overloading conditions in certain
cases. The stone matrix asphalt mix is tough, highly stable in structure and rut resistant asphalt mix. These systems rely on the stone to
stone contact that will facilitate in strength. The rich mortar used in the system will provide better durability.
The advantages of stone matrix asphalt mix are:
1. The selection of the materials i.e. aggregates, binder and the cellulose fiber.
2. Three trial gradations are involved to ensure stone to stone contact.
3. Optimum binder content is used for the all the gradation chosen
4. The binder drains down as well as the moisture susceptibility is evaluated.
The performance of the stone matrix asphalt mix pavement as studied by the US, based on the rutting effect seen in the road pavement.
The figure-5 below shows the rut depth caused for different ranges of the project conducted.
Fig.5: As per NCAT, the rutting performance of the stone matrix asphalt mix pavement constructed in the US
The performance of the SMA pavements that are constructed in India has performed well. Compared to bitumen concrete, the cost for
stone matrix asphalt mix has been found to be 25 to 30% higher. The increased cost of the SMA material is due to its composing
materials like cellulose fiber, modified binder, and the binder content. In the US, the life cycle study conducted showed that the stone
matrix asphalt mix is more cost effective in terms of performance and lesser maintenance.
For cube test two types of specimens either cubes of 15cm X 15cm X 15cm or 10cm X 10cm x 10cm depending upon the size of
aggregate are used. For most of the works cubical molds of size 15cm x 15cm x 15cm are commonly used.
This concrete is poured in the mold and appropriately tempered so as not to have any voids. After 24 hours, molds are removed, and test
specimens are put in water for curing. The top surface of these specimen should be made even and smooth. This is done by placing
cement paste and spreading smoothly on the whole area of the specimen.
These specimens are tested by compression testing machine after seven days curing or 28 days curing. Load should be applied gradually
at the rate of 140 kg/cm2 per minute till the Specimens fails. Load at the failure divided by area of specimen gives the compressive
strength of concrete.
Following are the procedure for testing the Compressive strength of Concrete Cubes
Apparatus for Concrete Cube Test
Compression testing machine
Preparation of Concrete Cube Specimen
The proportion and material for making these test specimens are from the same concrete used in the field.
Specimen
6 cubes of 15 cm size Mix. M15 or above
Mixing of Concrete for Cube Test
Mix the concrete either by hand or in a laboratory batch mixer
Hand Mixing
1. Mix the cement and fine aggregate on a watertight none-absorbent platform until the mixture is thoroughly blended and is of
uniform color.
2. Add the coarse aggregate and mix with cement and fine aggregate until the coarse aggregate is uniformly distributed throughout
the batch.
3. Add water and mix it until the concrete appears to be homogeneous and of the desired consistency.
Sampling of Cubes for Test
1. Clean the mounds and apply oil.
2. Fill the concrete in the molds in layers approximately 5 cm thick.
3. Compact each layer with not less than 35 strokes per layer using a tamping rod (steel bar 16mm diameter and 60cm long, bullet-
pointed at lower end).
4. Level the top surface and smoothen it with a trowel.
Curing of Cubes
The test specimens are stored in moist air for 24 hours and after this period the specimens are marked and removed from the molds and
kept submerged in clear freshwater until taken out prior to the test.
Precautions for Tests
The water for curing should be tested every 7 days and the temperature of the water must be at 27+-2oC.
Procedure for Concrete Cube Test
1. Remove the specimen from the water after specified curing time and wipe out excess water from the surface.
2. Take the dimension of the specimen to the nearest 0.2m
3. Clean the bearing surface of the testing machine
4. Place the specimen in the machine in such a manner that the load shall be applied to the opposite sides of the cube cast.
5. Align the specimen centrally on the base plate of the machine.
6. Rotate the movable portion gently by hand so that it touches the top surface of the specimen.
7. Apply the load gradually without shock and continuously at the rate of 140 kg/cm 2/minute till the specimen fails
8. Record the maximum load and note any unusual features in the type of failure.
Note:
Minimum three specimens should be tested at each selected age. If the strength of any specimen varies by more than 15 percent of
average strength, the results of such specimens should be rejected. The average of three specimens gives the crushing strength of
concrete. The strength requirements of concrete.
Calculations of Compressive Strength
Size of the cube =15cmx15cmx15cm
Area of the specimen (calculated from the mean size of the specimen )=225 cm 2
Characteristic compressive strength(f ck)at 7 days =
Expected maximum load =fck x area x f.s
Range to be selected is .......................
Similar calculation should be done for 28 day compressive strength
Maximum load applied =..........tones = .............N
Compressive strength = (Load in N/ Area in mm 2)=...............N/mm2
=............................N/mm2
Reports of Cube Test
1. Identification mark
2. Date of test
3. Age of specimen
4. Curing conditions, including date of manufacture of specimen
5. Appearance of fractured faces of concrete and the type of fracture if they are unusual
Results of Concrete Cube Test
Average compressive strength of the concrete cube = .............N/ mm 2 (at 7 days)
Average compressive strength of the concrete cube =.......... N/mm 2 (at 28 days)
Compressive Strength of Concrete at Various Ages
The strength of concrete increases with age. The table shows the strength of concrete at different ages in comparison with the strength at
28 days after casting.
Age Strength percent
1 day 16%
3 days 40%
7 days 65%
14 days 90%
28 days 99%
Compressive Strength of Different Grades of Concrete at 7 and 28 Days
Grade of Minimum compressive strength Specified characteristic compressive strength
Concrete N/mm2 at 7 days (N/mm2) at 28 days
M15 10 15
M20 13.5 20
M25 17 25
M30 20 30
M35 23.5 35
M40 27 40
M45 30 45
Some Facts on Concrete Strength Test
Why Compressive Strength Test of Concrete is Important?
The compressive strength of the concrete cube test provides an idea about all the characteristics of concrete. By this single test one judge
that whether Concreting has been done properly or not.
What is compressive strength of commonly used concrete?
Concrete compressive strength for general construction varies from 15 MPa (2200 psi) to 30 MPa (4400 psi) and higher in commercial
and industrial structures.
What is compressive strength after 7 days and 14 days?
Compressive strength achieved by concrete at 7 days is about 65% and at 14 days is about 90% of the target strength.
Which test is most suitable for concrete strength?
A concrete cube test or concrete cylinder test is generally carried out to assess the strength of concrete after 7 days, 14 days or 28 days of
casting.
What is the size of concrete cubes used for testing?
For cube test two types of specimens either cubes of 15cm X 15cm X 15cm or 10cm X 10cm x 10cm depending upon the size of
aggregate are used. For most of the works cubical molds of size 15cm x 15cm x 15cm are commonly used.
of fineness modulus.
Calculation of Fineness Modulus of Sand
Let us say the dry weight of sample = 1000gm After sieve analysis the values appeared are tabulated below.
Sieve size Weight retained (g) Cumulative weight retained(g) Cumulative percentage weight Retained (%)
4.75mm 0 0 0
Total 275
Therefore, fineness modulus of aggregate = (cumulative % retained) / 100 = (275/100) = 2.75 Fineness modulus of fine aggregate is
2.75. It means the average value of aggregate is in between the 2 nd sieve and 3rd sieve. It means the average aggregate size is in between
0.3mm to 0.6mm as shown in below figure.
Fineness modulus limits for various zones of sand according to IS 383-1970 are tabulated below.
Sieve size Weight retained(g) Cumulative weight retained (g) Cumulative % retained (g)
80mm 0 0 0
Sum = 717
Therefore, fineness modulus of coarse aggregates = sum (cumulative % retained) / 100 = (717/100) = 7.17 Fineness modulus of 7.17
means, the average size of particle of given coarse aggregate sample is in between 7 th and 8th sieves, that is between 10mm to 20mm.
1. To determine the compressive strength of the concrete by relating the rebound index and the compressive strength
2. To assess the uniformity of the concrete
3. To assess the quality of the concrete based on the standard specifications
4. To relate one concrete element with other in terms of quality
Rebound hammer test method can be used to differentiate the acceptable and questionable parts of the structure or to compare two
different structures based on strength.
Principle of Rebound Hammer Test
Rebound hammer test method is based on the principle that the rebound of an elastic mass depends on the hardness of the concrete
surface against which the mass strikes. The operation of the rebound hammer is shown in figure-1. When the plunger of rebound
hammer is pressed against the concrete surface, the spring controlled mass in the hammer rebounds. The amount of rebound of the mass
depends on the hardness of concrete surface. Thus, the hardness of concrete and rebound hammer reading can be correlated with
compressive strength of concrete. The rebound value is read off along a graduated scale and is designated as the
rebound number or rebound index. The compressive strength can be read directly from the graph provided on the body of the
hammer.
Procedure for Rebound Hammer Test
Procedure for rebound hammer test on concrete structure starts with calibration of the rebound hammer. For this, the rebound hammer is
tested against the test anvil made of steel having Brinell hardness number of about 5000 N/mm2. After the rebound hammer is tested for
accuracy on the test anvil, the rebound hammer is held at right angles to the surface of the concrete structure for taking the readings. The
test thus can be conducted horizontally on vertical surface and vertically upwards or downwards on horizontal surfaces as shown in
figure below If the rebound hammer is held at intermediate angle, the rebound number will be different for the same concrete.
Fig.2.Rebound Hammer Positions for Testing Concrete Structure
The impact energy required for the rebound hammer is different for different applications. Approximate Impact energy levels are
mentioned in the table-1 below for different applications.
Table-1: Impact Energy for Rebound Hammers for Different Applications As per IS: 13311(2)-1992
Approximate Impact Energy for Rebound
Sl.No Applications
Hammer in Nm
1. Type of Aggregate
2. Type of Cement
3. Surface and moisture condition of the concrete
4. Curing and Age of concrete
5. Carbonation of concrete surface
Type of Aggregate
The correlation between compressive strength of concrete and the rebound number will vary with the use of different aggregates.
Normal correlations in the results are obtained by the use of normal aggregates like gravels and crushed aggregates. The use of
lightweight aggregates in concrete will require special calibration to undergo the test.
Type of Cement
The concrete made of high alumina cement ought to have higher compressive strength compared to Ordinary portland cement. The use
of supersulphated cement in concrete decrease the compressive strength by 50% compared to that of OPC.
Type of Surface and Moisture Condition
The rebound hammer test work best for close texture concrete compared with open texture concrete. Concrete with high honeycombs
and no-fines concrete is not suitable to be tested by rebound hammer. The strength is overestimated by the test when testing floated or
trowelled surfaces when compared with moulded surfaces. Wet concrete surface if tested will give a lower strength value. This
underestimation of strength can go lower to 20% that of dry concrete.
Type of curing and age of concrete
As time passes, the relation between the strength and hardness of concrete will change. Curing conditions of concrete and their moisture
exposure conditions also affects this relationship. For concrete with an age between 3days to 90 days is exempted from the effect of age.
For greater aged concrete special calibrated curves is necessary.
Carbonation on Concrete Surface
A higher strength is estimated by the rebound hammer on a concrete that is subjected to carbonation. It is estimated to be 50% higher. So
the test have to be conducted by removing the carbonated layer and testing by rebound hammer over non-carbonated layer of
concrete.
Types of beams
The beams classes are as follows:
• Rectangular beam
• L-shape beam
• Circular shape beam
• T-shape beam
When a beam is designed with slab, called slab beam or Tee-beam, reinforcements are provided as shown in figure below. The beam is
generally designed as simple beam but additional reinforcement provided on top with slab to make it behave like a Tee-beam.
Reinforcement are provided to resist tensile stresses due to bending and shear in beams for singly reinforced sections.
In practice, for singly reinforced beams, two additional bars are provided in compression face of the beam so that stirrups can be tied
with bars. These additional reinforcement are of nominal diameter of 8mm or 10mm.
Doubly reinforced
when depth of section is restricted due to reasons such as architectural reasons, or basement floors, the beam section is designed as
doubly reinforced concrete beam.
These bars shall withstand compressive stresses and are provided with reinforcement in compression face.
Beams when subjected to torsion are provided additional longitudinal and shear reinforcement to resist bending and shear stresses
developed due to torsion.
• Minimum cover in beams must be 25 mm or shall not be less than the larger diameter of bar for all steel reinforcement
including links.
• Nominal cover specified in Table 16 and 16A of IS456-2000 should be used to satisfy the durability criteria.
Stirrups
this type of reinforcement act against shear force. Following are the types of stirrups provided in beams:
Fig.3: Types of stirrups in beams
Standard hooks and bends
Commonly, the provision of steel bar anchorage is in form of bends and hooks provided that straight length insufficient to develop bars.
Moreover, the anchorage value of bend of bar is taken as 4 times the diameter of bar for every 45 0 bend subjected to maximum of 16
times the diameter of bar.
Added to that, The specification for detailing of reinforcement in beams are given in cl.26.5.1 of IS 456 – 2000. Lastly, standard bends
and hooks required for reinforcing bars are shown in figure below.
Furthermore, cl.26.2 of IS 456 – 2000 gives the anchorage length required for main reinforcement in tension and compression.
Lastly, figure 5 shows typical details of curtailment of reinforcement in cantilever and continuous beams.
Fig.5: Typical Details of Reinforcement curtailment in beams
Development length (Ld)
Figure 6 provides details of necessary anchorage length for main reinforcement in tension and compression: