STATION
Contract No.: MEW/C/5504-2020/2021
CLARIFICATION SHEET
Document Description: SAT PROCEDURE FOR VESDA SYSTEM Document No:-P5504MEW-SWK-10-SS-V-PPR-005
1 P5504MEW-SWK-10-SS-V-PPR-005 No comments
Page 1 of 1
Contract No. MEW/C/5504-2020/2021
Contractor HOT ENGINEERING AND CONSTRUCTION COMPANY Page 1 of 22
Client MINISTRY OF ELECTRICITY & WATER
DOCUMENT TITLE:
PROJECT TITLE:
REVISION LOG
INDEX
SL.No INDEX
DESCRIPTION
PAGE NO.
1. INTRODUCTION 04
2. CODES & STANDARDS 04
3. REFERENCES 04
4. DESCRIPTION 04
5. TEST EQUIPMENT 05
6. PROCEDURES 05
6.1 VISUAL INSPECTION 06
6.2 FUNCTIONAL TESTS 06
6.2.1 POWER UP & INITIALIZATION TEST 06
6.2.2 ALARM FUNCTION TEST 06
6.2.3 FAULT FUNCTION TEST 07
6.2.4 BATTERY BACK-UP TEST 07
7. CONCLUSION 07
8. SAT CHECKLISTS 08
8.1 EQUIPMENT CHECKLIST 08
8.2 VISUAL INSPECTION CHECKLIST 10
8.3 POWER UP & INITIALIZATION TEST CHECKLIST 12
8.4 ALARM FUNCTION TEST CHECKLIST 14
8.5 FAULT FUNCTION TEST CHECKLIST 16
8.6 BATTERY BACK-UP TEST CHECKLIST 18
APPENDIX – A TEST ATTENDANCE ROSTER 20
APPENDIX – B SITE ACCEPTANCE TEST (SAT) CERTIFICATE 21
APPENDIX – C PUNCH LIST 22
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 4 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
1. INTRODUCTION
This documented procedure has been established to ensure that all required tests and
inspections are carried out and documented for the acceptance of the VESDA system functioning
at site.
The scope includes the test procedures to be carried out after the installation and
commissioning of the VESDA system in SHUWAIK POWER STATION CONTROL BUILDING, and
verify the operations & functions of the VESDA system are in compliance with the project
requirements and specifications.
BS 5839 British standard for fire detection and alarm systems for buildings
3. REFERENCES
4. DESCRIPTION
The Site Acceptance Test (SAT) for the VESDA system shall be carried out in accordance with
the approved ITP. The testing shall be performed by the representative from the system vendor and
witnessed by the representatives from CONTRACTOR, CONSULTANT and MEW to ensure that the
system inspection & functionality at site in completed and satisfactory.
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 5 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Representatives/ attendees of all parties shall sign the test attendance rooster (Appendix A)
for record purpose.
5. TEST EQUIPMENT
The following test equipment shall be used for testing the VESDA system.
6. PROCEDURES
Site Acceptance test (SAT) shall be conducted after the installation and commissioning of the
VESDA system has been completed on-site as per the approved as built drawings (Refer Section 3).
The purpose of this inspection is to ensure that the installation of VESDA units, pipes and
wiring connections & terminations are completed successfully as per the approved as-built
drawings/documents (Refer section 3). This activity shall be performed in line with test descriptions
listed in the checklist (Section 8.1 and 8.2) and marked as completed upon the successful completion
of tests.
After the successful completion of visual inspection, the VESDA power supply unit shall be
energized with 230 VAC incoming power sources and battery power supply shall be
connected. The VESDA power supply unit will distribute 24 VDC power supply to the VESDA
Panel. The VESDA panel energizes and undergoes an initialization cycle prior entering into
its normal operating conditions.
During this stage, any fault detected shall be cleared and the functionality of the FACP shall
be verified as normal, prior proceeding for the functional test. This activity shall be performed
in line with test description listed in the checklist (Section 8.3) and marked as completed upon
the successful completion of tests.
This test is carried out to demonstrate that the alarm functions of the VESDA panel and
ensures the integrity of the pipes at event of smoke detection. This test is performed by
introducing sample smoke by using smoke canister into the sampling holes (preferably at the
last and first hole of the pipe) of each pipe individually. At the event of the smoke detection,
actual transport time (response time) of the alarm threshold levels (Alert, action, Fire-1 and
Fire-2) will be recorded and compared with the anticipated response time calculated by the
ASPIRE Installation Data Pack (Refer Datasheet Doc no. P5504MEW-SWK-10-SS-V-DAT-
012). Subsequently, the interfacing signals with the fire alarm control panel (FACP) will be
verified as per the cause & effect matrix (Refer Section 3). This activity shall be performed in
line with test descriptions listed in the checklist (Section 8.4) and marked as completed upon
the successful completion of tests.
Note: As per the manufacturer’s commissioning guidelines, the transport time of the actual
smoke detection may have a tolerance of more or less 20% compared to the data anticipated
by the ASPIRE Installation Data Pack.
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 7 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
This test is carried out to demonstrate the functions of VESDA system during fault conditions.
During this test, the fault conditions will be verified with the information visualized on the
panel’s display unit. Following, interfacing signals with the fire alarm control panel (FACP)
shall be verified as per the approved cause & effect matrix. This activity shall be performed in
line with test description listed in the checklist (Section 8.5) and marked as completed upon
the successful completion of tests.
This test is carried out to verify the supplied battery backup source is operational for the
VESDA system in the event of 230 VAC power supply failure. During this test, 230VAC power supply
failure will be disconnected and ensured that the system is operating under battery power supply
only, and the functionality of the VESDA panel shall be verified for the 24 hours standby condition
and 30 minutes alarm condition. This activity shall be performed in line with test description listed in
the checklist (Section 8.6) and marked as completed upon the successful completion of tests.
7. CONCLUSION
All required inspections and tests shall be carried as per the procedures (Refer Section 6). Upon
successful completion of each test, checklists for the same (Refer Section 7) shall be marked as
COMPLETED and signed by the authorized representatives from system vendor, HOTECC and
MEW. Upon the successful completion and verification of all test’s, the authorized representatives
from system vendor, HOTECC and MEW shall sign the SAT ACCEPTANCE CERTIFICATE (Refer
Appendix B). During the activity, any non-compliance points shall be noted in the punch List
(Appendix C), and the related actions shall be taken for punch point clearance.
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 8 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
8. SAT CHECKLISTS
Quantity (Nos)
S.No Equipment Description Manufacturer Remarks
Not
Ok
Ok
Vendor
Contractor
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 9 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 10 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
TAG NO:
LOCATION:
NOT
S. No Description OK Remarks
OK
Check and confirm the tag numbers and location for
1. the installed VESDA units approved as-built layout
drawing (Refer section 3).
Vendor
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 11 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Contractor
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 12 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
TAG NO:
LOCATION:
NOT
S. No Description OK Remarks
OK
Energize the VESDA power supply unit with 230 VAC
1. main incoming power supply and verify the 24 VDC
power is distributed to the VESDA panel.
REMARKS
Vendor
Contractor
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 13 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 14 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
TAG NO:
LOCATION:
NOT
S. No Description OK Remarks
OK
Simulate alarm signals by applying sample smoke using
1. smoke canister to at the first and last sampling holes (one
hole per test) for each pipe individually.
Alert
Test 1 Action
Fire 1/Fire
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 15 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Pipe No. 1 2 3 4
Test 1 Fire 2
Alert
Action /Pre-Alarm
Test 2
Fire 1/Fire
Fire 2
Vendor
Contractor
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 16 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
TAG NO:
LOCATION:
NOT
S. No Description OK Remarks
OK
Simulate AC Main Power fault by disconnecting AC power
1. supply and refer the fault LED is illuminated and
corresponding fault is visualized in display unit.
Vendor
Contractor
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 17 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 18 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
TAG NO:
LOCATION:
NOT
S. No Description OK Remarks
OK
Disconnect the 230 VAC Main power supply from the
1. VESDA power supply unit and make sure the VESDA
system is operating under battery supply unit
Check the panel display unit for fault information and fault
2.
LED is illuminated.
Check the Battery Voltage by using a multimeter when
230 VAC main is power off.
3.
V=________
Vendor
Contractor
Consultant
MEW
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND
MAINTENANCE FOR UPGRADATION OF FUEL SUPPLY Page 20 of 22
SYSTEM INFRASTRUCTURE WITHIN SHUWAIKH POWER
STATION
APPENDIX -A
Test Attendance Roster
Activity
Date
Location
APPENDIX -B
SITE ACCEPTANCE TEST (SAT) CERTIFICATE
This is to certify that the Site Acceptance Test for the VESDA system installed at SHUWAIK POWER
STATION CONTROL BUILDING have been successfully completed as per the approved Site
acceptance procedure P5504MEW-SWK-10-SS-V-PPR-005.
The system was found to be in accordance with the client purchase order requirements, applicable
specifications, procedures in accordance to approved project documents and drawings.
REMARKS:
NAME
DESIGNATION
SIGNATURE
DATE
Doc No : P5504MEW-SWK-10-SS-V-PPR-005
SAT PROCEDURE FOR VESDA SYSTEM
Rev. No. : 0
PROCUREMENT, CONSTRUCTION, COMMISSIONING AND MAINTENANCE
Page 22 of 22
FOR UPGRADATION OF FUEL SUPPLY SYSTEM INFRASTRUCTURE WITHIN
SHUWAIKH POWER STATION
APPENDIX-C
PUNCH LIST
SIGNATURE
S. ISSUED ACTION CLOSURE
DATE PUNCHLIST CATEGORY STATUS REMARKS
NO BY BY DATE
CONTRACTOR CONSULTANT MEW