Assignment Schedulling (205263)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Assignment ( NAHVIN A/L SANGAR ) (205263)

HARIVARMAN RAJ RAJINIKANTH 205641

AoA and AoN

1. Single Span Bridge Project

For the following activities, do the following

a. Develop the Arrow diagram and Node diagram of the project


b. Do the necessary operations and determine the critical path in both diagrams
c. Fill in the `Relationship`, `ES`, `FS`, `LS`, `LF` and `FF` for each activity

Code Activity Dependence / Duration Relationship


Predecessor (days)
ENA Earthworks, north abutment - 5 ES
ESA Earthworks, south abutment ENA 4 FS
CONN Construction, north abutment ENA 14 FS
CONS Construction, south abutment ESA, CONN 12 FS
COMN Compaction, north abutment CONN 2 FS
COMS Compaction, south abutment CONS, COMN 2 FS
RNB Road, north of bridge COMN 2 FS
RSB Road, south of bridge RNB, COMS 2 FS
PB Prefabricated bridge deck - 18 FS
TD Transport deck to site PB 2 FS
EB Erect bridge deck TD, CONN, 3 FS
CONS, COMN
LBS Lay bridge surface EB, RNB, RSB 2 FS
ICB Install crash barriers EB 1 FS
L Landscape RNB, RSB 1 FS

Code Activity ES EF LS LF FF
ENA Earthworks, north abutment 0 5 0 5 0
ESA Earthworks, south abutment 5 9 15 19 10
CONN Construction, north abutment 5 19 5 19 0
CONS Construction, south abutment 19 31 19 31 0
COMN Compaction, north abutment 19 21 29 31 10
COMS Compaction, south abutment 31 33 31 33 0
RNB Road, north of bridge 21 23 33 35 12
RSB Road, south of bridge 33 35 33 35 0
PB Prefabricated bridge deck 0 18 12 30 12
TD Transport deck to site 18 20 30 32 12
EB Erect bridge deck 31 34 32 35 1
LBS Lay bridge surface 34 36 35 37 0
ICB Install crash barriers 34 35 36 37 2
L Landscape 35 36 36 37 1

2. Bar Chart

For the following activities, develop the bar chart/Gantt chart of the project

Activity Predecessor Duration (weeks)


A C,J 3
B F 2
C F 3
D C,I 4
E G 5
F H 4
G H 2
H - 3
I E,F 4
J B 2

3. PERT Chart

For the following activities, draw the network diagram and calculate the expected time of completion of
the activities and the project

Code Activity Dependence / o m p


Predecessor
ENA Earthworks, north abutment - 4 5 7
ESA Earthworks, south abutment ENA 2 4 5
CONN Construction, north abutment ENA 12 14 15
CONS Construction, south abutment ESA, CONN 11 12 14
COMN Compaction, north abutment CONN 1 2 3
COMS Compaction, south abutment CONS, COMN 1 2 3
RNB Road, north of bridge COMN 1 2 3
RSB Road, south of bridge RNB, COMS 1 2 3
PB Prefabricated bridge deck - 15 18 21
TD Transport deck to site PB 1 2 4
EB Erect bridge deck TD, CONN, 2 3 4
CONS, COMN
LBS Lay bridge surface EB, RNB, RSB 1 2 4
ICB Install crash barriers EB 1 1 2
L Landscape RNB, RSB 1 1 2
2. Bar Chart
Weeks

Act. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
H
F
B
J
A
C
G
E
I
D

3. PERT Chart
Code Predecessor O M P Expected Time
ENA - 4 5 7 5.17
ESA ENA 2 4 5 3.83
CONN ENA 12 14 15 13.83
CONS ESA, CONN 11 12 14 12.67
COMN CONN 1 2 3 2
COMS COMS, COMN 1 2 3 2
RNB COMN 1 2 3 2
RSB RNB, COMS 1 2 3 2
PB - 15 18 21 18
TD PB 1 2 4 2.17
EB TD, CONN, COMS, 2 3 4 3
COMN
LBS EB, RNB, RSB 1 2 4 2.17
LCB EB 1 1 2 1.17
L RNB, RSB 1 1 2 1.17