Code Activity ES EF LS LF FF
ENA Earthworks, north abutment 0 5 0 5 0
ESA Earthworks, south abutment 5 9 15 19 10
CONN Construction, north abutment 5 19 5 19 0
CONS Construction, south abutment 19 31 19 31 0
COMN Compaction, north abutment 19 21 29 31 10
COMS Compaction, south abutment 31 33 31 33 0
RNB Road, north of bridge 21 23 33 35 12
RSB Road, south of bridge 33 35 33 35 0
PB Prefabricated bridge deck 0 18 12 30 12
TD Transport deck to site 18 20 30 32 12
EB Erect bridge deck 31 34 32 35 1
LBS Lay bridge surface 34 36 35 37 0
ICB Install crash barriers 34 35 36 37 2
L Landscape 35 36 36 37 1
2. Bar Chart
For the following activities, develop the bar chart/Gantt chart of the project
3. PERT Chart
For the following activities, draw the network diagram and calculate the expected time of completion of
the activities and the project
Act. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
H
F
B
J
A
C
G
E
I
D
3. PERT Chart
Code Predecessor O M P Expected Time
ENA - 4 5 7 5.17
ESA ENA 2 4 5 3.83
CONN ENA 12 14 15 13.83
CONS ESA, CONN 11 12 14 12.67
COMN CONN 1 2 3 2
COMS COMS, COMN 1 2 3 2
RNB COMN 1 2 3 2
RSB RNB, COMS 1 2 3 2
PB - 15 18 21 18
TD PB 1 2 4 2.17
EB TD, CONN, COMS, 2 3 4 3
COMN
LBS EB, RNB, RSB 1 2 4 2.17
LCB EB 1 1 2 1.17
L RNB, RSB 1 1 2 1.17