General Technical Information

SF6 Gas-insulated Switchgear


Field Testing of GIS Type ELK

Content
1. Introduction

2. Mechanical operation tests on circuit-breakers, discon-


nectors and earthing switches

3. Measurement of the resistance of the main circuit

4. Moisture content and purity measurement

5. Checks and verifications


5.1 Correct wiring
5.2 Proper function of the local control
5.3 Verifying of current transformers
5.4 Verifying of voltage transformers
5.5 Earthing

6. High-voltage tests on the main circuit

7. References

1. Introduction 2. Mechanical operation tests on circuit-breakers,


The tests and checks performed on ABB Gas-insulated Sub- disconnectors and earthing switches
stations (GIS) type ELK after installation on site are in line with Mechanical operation tests are performed in the factory.
following standards:
– – IEC 62271-203 [1] In addition, a number of checks are made on site after instal-
– – IEEE C 37.122 [2] lation of the GIS.

Field tests are performed on the completely assembled GIS For circuit-breakers these tests consist of:
or subassemblies thereof to check the correct operation and –– Check of pump control
the dielectric strength of the equipment before putting into –– Check of blocking mechanisms
service. –– Check of switching times
–– Check of position indicator
Test methods and procedures are defined in internal ABB
testing instruction manuals. The test sequence is appropriate For disconnector and earthing switches these consist of:
and adequately defined. –– Check of correct adjustment and indicator position
–– CO-operations of drive motors
After successful field testing an acceptance certificate will be
issued. Results will be used as reference in future maintenance work.
3. Measurement of the resistance of the main circuit 5.3 Verifying of current transformers
Resistance checks are performed during installation of the Current transformers are checked by current impulses for cor-
GIS according to the progress of assembly. The purpose of rect polarity. If agreed upon, also measurement of ratio and
these measurements is to verify proper alignment of the main magnetic characteristic may be performed.
circuit contacts.
This test is done in mounted position using the insulated
The resistance readings do not show individual components, earthing switches for current injection. A special testing facility
but several components connected in series. has to be provided.

5.4 Verifying of voltage transformers

© Copyright ABB. 1HC0007012 E01 / AD12


4. Moisture content and purity measurement Voltage transformers are checked for correct polarity by
After proper evacuation the newly assembled GIS-plant will be means of voltage impulses.
filled with SF6-gas being in accordance with IEC 60376 [4].
Measurement of ratio is performed during the high-voltage
The SF 6-gas of the sealed assembly will be tested to assure test or prior by means of primary voltage injection.
the moisture content is below the level specified by ABB.
These measurements will be made on all gas compartments. 5.5 Earthing
Since the moisture migration from the interior metal and The GIS earthing connections will be checked.
insulating surfaces may take considerable time, the moisture
content is shall be measured when the equilibrium state is
established. 6. High-voltage tests on the main circuit
An appropriate selection of high-voltage tests is normally car-
All gas compartments are to be measured concerning the ried out after completion of the tests as described in chapters
content of SF 6 and its purity. The gas should contain at least 2 to 5.
97% pure SF 6. The measured values have to be recorded in
the respective forms, which are important as a reference for Their purpose and the procedures are described in detail in
later measurements of gas quality. the General Technical Information „High-voltage on-site Test-
ing of GIS Type ELK“ [3].

5. Checks and verifications


5.1 Correct wiring 7. References
It is verified that the wiring conforms with the wiring diagram [1] IEC 62271-203, Gas-insulated metal-enclosed switchgear
and the prescribed requirements. for rated voltage above 52 kV

5.2 Proper function of the local control [2] ANSI C 37.122, IEEE Guide for gas-insulated substations
Each bay is checked for all the functions the local control cu-
bicle is intended for. This includes testing of alarms, metering [3] ABB publication, 1HC0007011 E01, High-voltage on-site
equipment, switching operations, mechanical and electrical Testing of GIS Type ELK
blockings, as well as verifying correct supply with auxiliary and
control voltage. [4] IEC 60376, Specification of technical grade sulfur hexa-
flouride (SF6) for use in electrical equipment
The interlocking is checked according to the interlocking list
provided.