Exhibit 01 - Application - Plan Set - 03-09-2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

GENERAL NOTES: EROSION AND SEDIMENT CONTROLS: DRAINAGE AND UTILITIES NOTES: INFILTRATION BASIN/SWALE NOTES:

1. THE CONTRACTOR SHALL NOTIFY "DIG-SAFE" [ 888.344.7233 ] AND VERIFY ALL THE FOLLOWING EROSION AND SEDIMENT CONTROL TECHNIQUES AND PROCEDURES ARE TO BE 1. ALL UNDERGROUND STRUCTURES, INCLUDING MANHOLES, CATCH BASINS, AREA 1. THE CONTRACTOR SHALL USE LIGHT EARTH MOVING EQUIPMENT TO EXCAVATE
UNDERGROUND UTILITIES PRIOR TO CONSTRUCTION. EMPLOYED TO PROTECT THE ADJACENT WETLANDS AND NEIGHBORING PROPERTIES AND DRAINS, THE PUMP STATION AND GREASE TRAP, SHALL BE DESIGNED TO THE BASIN TO MINIMIZE COMPACTION AND INFILTRATION CAPACITY OF THE SOILS
2. THE UNDERGROUND UTILITIES SHOWN ON THESE PLANS HAVE BEEN LOCATED BY ROADWAYS. WITHSTAND H-20 LOADING. BENEATH THE BASIN FLOOR AND ALONG THE SIDE SLOPES.
FIELD SURVEY AND EXISTING DRAWINGS. THIS ENGINEER MAKES NO GUARANTEE 2. ALL STORM DRAINAGE PIPING TO BE HIGH DENSITY POLYETHYLENE [HDPE, ADS 2. INITIAL BASIN EXCAVATION SHOULD BE CARRIED TO WITHIN 2 FEET OF THE FINAL
THAT THE UNDERGROUND UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN 1. PRIOR TO ANY SITE ACTIVITIES, SILT FENCE AND HAY BALES ARE TO BE PLACED WHERE N-12 OR APPROVED EQUAL] OR RCP CLASS IV CAPABLE OF WITHSTANDING H-20 ELEVATION OF THE BASIN FLOOR.
THE AREA EITHER IN USE OR ABANDONED. THE ENGINEER FURTHER DOES NOT SHOWN ON THESE PLANS. SILT FENCE/HAY BALE BARRIERS ARE TO TRAP SEDIMENT LOADING. MINIMUM CLEARANCE BETWEEN PROPOSED DRAINAGE PIPING AND 3. FINAL EXCAVATION TO THE FINISH GRADE AND CONSTRUCTION OF THE FOREBAY
WARRANT THAT THE UTILITIES SHOWN ARE IN THE EXACT LOCATION INDICATED TRANSPORTED BY RUN-OFF BEFORE IT IMPACTS THE WETLANDS OR LEAVES THE OTHER UTILITIES/STRUCTURES SHALL BE 18 INCHES VERTICALLY AND 4 FEET STONE FILTER SHALL NOT BE COMPLETED UNTIL ALL DISTURBED ARES WITHIN
ALTHOUGH THEY ARE LOCATED AS ACCURATELY AS POSSIBLE FROM THE CONSTRUCTION SITE. THESE SILT FENCES AND HAY BALES ARE TO BE INSPECTED HORIZONTALLY. THE MINIMUM COVER OF THE HDPE PIPE IS 1'-0" FOR H-20 LOADS, THE WATERSHED HAVE BEEN STABILIZED. BECAUSE SOME COMPACTION OF THE
INFORMATION AVAILABLE. PERIODICALLY AND REPAIRED / REPLACED AS NECESSARY DURING THE CONSTRUCTION THIS COVER IS MEASURED FROM THE PIPE OD TO THE TOP OF RIGID PAVEMENT. SOIL IS INEVITABLE DURING CONSTRUCTION, THE BASIN FLOOR SOILS SHALL BE
3. THESE SITE PLANS ARE BASED UPON AN ON-THE-GROUND TOPOGRAPHICAL PROJECT. INSPECTIONS OF THE EROSION CONTROLS ARE TO BE PERFORMED WEEKLY AND 3. THE MAINTENANCE OF ALL DRAINAGE STRUCTURES IS THE RESPONSIBILITY OF DEEPLY TILLED TO A DEPTH OF 12" AFTER FINAL GRADING IS COMPLETED.
SURVEY. NO ATTEMPT WAS MADE IN PREPARING THESE PLANS TO ASCERTAIN THE AFTER EVERY SIGNIFICANT PRECIPITATION EVENT [EXCEEDING 21" OF PRECIPITATION]. THE OWNER. 4. IMMEDIATELY AFTER THE BASIN CONSTRUCTION IS COMPLETED, STABILIZE THE
LOCATION OF NON-VISUALLY APPARENT SUBSURFACE UTILITIES AND 2. THE EROSION CONTROLS ARE TO BE IN PLACE PRIOR TO ANY EXCAVATION OR CLEARING OF 4. ALL CONSTRUCTION AND TESTING METHODS SHALL COMPLY WITH THE LOCAL BASIN FLOOR, SIDE SLOPES, AND ALL REMAINING DISTURBED AREAS AROUND THE
STRUCTURES OR CONDITIONS. THE SITE. AREAS OUTSIDE THE EROSION CONTROLS ARE NOT TO BE DISTURBED DURING RULES AND REGULATIONS. IN CASES WHERE THE DRAWINGS DIFFER FROM THESE BASIN WITH DENSE TURF BY SEEDING.
4. THESE PLAN HAVE BEEN PREPARED FOR THIS CLIENT AND THIS PROJECT. CONSTRUCTION. REGULATIONS, THE MOST RESTRICTIVE REQUIREMENT SHALL APPLY. 5. THE CONTRACTOR IS NOT TO DIRECT ANY RUNOFF INTO THE BASIN UNTIL THE
REPRODUCTION IN WHOLE OR IN PART FOR OTHER PURPOSES IS STRICTLY 3. SEDIMENT BUILDUP AT THE EROSION CONTROLS SHALL BE REMOVED ONE THE SEDIMENT 5. ALL DRAINAGE STRUCTURES AND DETAILS TO BE BE CONSTRUCTED AND BASIN BOTTOM AND SIDE SLOPES ARE FULLY STABILIZED.
PROHIBITED. VOLUME REACHES 21 THE HEIGHT OF THE HAY BALES. INSPECTED CONSISTENT WITH THE REQUIREMENTS OF THE LOCAL AUTHORITY. 6. THE CONTRACTOR IS RESPONSIBLE TO REMOVE ANY SEDIMENT WHICH ENTERS
5. THESE DRAWINGS SHALL NOT BE SCALED. IF CLARIFICATION OF INTENT IS 4. DIVERT RUNOFF FROM OFFSITE AND UNDISTURBED AREAS AWAY FROM CONSTRUCTION TO 6. THE CONTRACTOR SHALL INSPECT AND RESTORE / CLEAN ALL FACILITIES [INLETS, INTO THE BASIN DURING THE CONSTRUCTION PHASE.
REQUIRED, THE CONTRACTOR SHALL REQUEST CLARIFICATION PRIOR TO MINIMIZE SOIL EROSION AND SEDIMENTATION ON AND OFF-SITE. TEMPORARILY STABILIZE MANHOLES, BASINS, ETC] OF SEDIMENT AND DEBRIS PRIOR TO THE ENGINEER'S 7. BASIN SIDE SLOPES AND SEEDED AREAS NEAR THE BUILDING TO BE A MAXIMUM
CONTINUING HIS WORK. ALL HIGHLY ERODIBLE SOILS AND SLOPES IMMEDIATELY. ACCEPTANCE. OF 3:1. BASIN FLOOR AND SIDE SLOPES TO BE SEEDED WITH NEW ENGLAND
6. THE CONTRACTOR SHALL VISIT THE SITE PRIOR TO INITIATION OF THE WORK AND 5. LAND DISTURBANCE ACTIVITIES EXCEEDING TWO ACRES IN SIZE SHALLL NOT BE DISTURBED 7. PROPOSED GAS, ELECTRIC, WATER, TELEPHONE AND TELEVISION SERVICE WETLAND SEED MIX OR APPROVED EQUAL.
SHALL NOTIFY THE CIVIL ENGINEER OF RECORD AND THE OWNER OF ANY WITHOUT A SEQUENCING PLAN THAT REQUIRES STORMWATER CONTROLS TO BE INSTALLED LOCATIONS MUST BE COORDINATED WITH THE APPROPRIATE UTILITY COMPANY. 8. THE LOAM MATERIAL SHALL CONSIST OF 60 - 70 % WASHED SCREENED SAND, 20 -
DISCREPANCIES WITH THE SITE CONDITIONS OR PROPOSED CONSTRUCTION AND EXPOSED SOILS STABILIZED. AS DISTURBANCES BEYOND THE TWO ACRES CONTINUES. ALL CONSTRUCTION DETAILS TO BE CONSISTENT WITH UTILITY COMPANY 30 % TOPSOIL, AND 10 - 20 % ORGANIC MATTER. THE LOAM MATERIAL SHALL BE
IMMEDIATELY UPON DISCOVERY. A CONSTRUCTION PHASING PLAN, INCLUDING EROSION CONTROL AND SEDIMENT CONTROL STANDARDS AND REQUIREMENTS. MIXED TO A UNIFORM CONSISTENCY.
7. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING PROPOSED PLAN FOR EACH PHASE, SHALL BE SUBMITTED TO THE DEC PRIOR TO ANY CONSTRUCTION 8. CONTRACTOR TO PROVIDE EXCAVATION, BEDDING, BACKFILL AND COMPACTION 9. THE TOPSOIL SHALL BE NATURAL, FERTILE, FRIABLE, LOAM OR SANDY LOAM
CONSTRUCTION WITH EXISTING CONDITIONS. ON THE SITE. MASS CLEARINGS AND GRADING OF THE ENTIRE SITE SHOULD BE AVOIDED. FOR NATURAL GAS SERVICES. TYPICAL OF CULTIVATED TOPSOIL. THE TOPSOIL SHALL BE FREE OF SUB-SOIL,
8. THE CONTRACTOR SHALL BE RESPONSIBLE TO OBTAIN ALL REQUIRED PERMITS 6. SOIL STOCKPILES MUST BE STABILIZED OR COVERED AT THE END OF EACH WORKDAY. 9. ALL WATER MAINS AND WATER SERVICES SHALL HAVE A MINIMUM OF FIVE [5] FEET LARGE STONES, EARTH CLODS, STICKS, STUMPS, CLAY LUMPS, ROOTS, OR OTHER
AND LICENSES. STOCKPILE SIDE SLOPES SHALL NOT BE GREATER THAN 2:1. ALL STOCKPILES SHALL BE OF COVER. OBJECTIONABLE MATTER. TOPSOIL SHALL ALSO BE FREE OF NOXIOUS WEEDS,
9. ALL WORK SHALL CONFORM TO ALL LOCAL AND STATE REGULATORY AGENCIES SURROUNDED BY SEDIMENT CONTROLS. 10. ALL WATER MAIN INSTALLATIONS SHALL BE CLASS 52, CEMENT LINED DUCTILE AND SHALL HAD A PH FACTOR BETWEEN 6.0 AND 7.0.
AND UTILITY REQUIREMENTS. 7. DISTURBED AREAS REMAINING IDLE FOR MORE THAN 14 DAYS SHALL BE TEMPORARILY OR IRON PIPE. ALL WATER MAIN INSTALLATIONS SHALL BE PRESSURE TESTED AND
10. UPON ENTERING THE SITE, THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMANENTLY STABILIZED. CHLORINATED AFTER CONSTRUCTION PRIOR TO ACTIVATING THE SYSTEM.
EROSION CONTROL, DEWATERING AND SHALL UNDERTAKE ALL MEASURES TO 8. PERMANENT SEEDING SHALL BE UNDERTAKEN IN THE SPRING FROM MARCH THRU MAY, AND 11. HYDRANTS, GATE VALVES, FITTINGS, ETC. SHALL MEET THE REQUIREMENTS OF
PROTECT WETLANDS, THE DRAINAGE SYSTEMS, ADJACENT PROPERTIES AND IN LATE SUMMER AND EARLY FALL FROM AUGUST TO OCTOBER 15. DURING THE PEAK THE LOCAL AUTHORITY. THE CONTRACTOR SHALL CONSTRUCT THE WATER MAIN
STREETS FROM SILTATION, STORMWATER RUNOFF, AND DUST DURING THE SUMMER MONTHS AND IN THE FALL AFTER OCTOBER 15 AN APPROPRIATE TEMPORARY AND ITS APPURTENANCE WORK IN ACCORDANCE WITH THE LOCAL WATER LANDSCAPING NOTES:
ENTIRE PROJECT DURATION. MULCH AND/OR NON-ASPHALTIC SOIL TACKIFIER WITH WINTER RYE SHALL BE APPLIED. DEPARTMENT'S STANDARDS AND SPECIFICATIONS AND PAY FOR ALL ASSOCIATED
11. THE LIMIT OF WORK SHALL BE AS DESIGNATED ON THESE PLANS, AND/OR THE 9. ALL SLOPES STEEPER THAN 3:1, AS WELL AS PERIMETER DIKES, SEDIMENT BASINS OR FEES AS REQUIRED BY THE WATER DEPARTMENT. THE CONTRACTOR SHALL 1. REFER TO CIVIL PLANS FOR HARDSCAPE LAYOUT AND MATERIALS, UTILITIES,
EDGE OF PROPOSED GRADING AND/OR THE PROPERTY LINES IF NOT INDICATED TRAPS, AND EMBANKMENTS MUST, UPON COMPLETION, BE IMMEDIATELY STABILIZED WITH CONTACT THE WATER DEPARTMENT TO ENSURE PROPER INSPECTIONS OF WATER GRADING, EROSION CONTROLS, AND DRAINAGE.
OTHERWISE. SOD, SEED AND ANCHORED STRAW MULCH OR OTHER APPROVED STABILIZATION PIPING PRIOR TO BACKFILLING. 2. ALL DISTURBED AREAS SHALL RECEIVE LOAM AND SEED USING SEED MIX FOR
12. THE CONTRACTOR SHALL CLEARLY MARK THE LIMITS OF WORK PRIOR TO THE MEASURES. 12. ALL SEWER PIPE SHALL BE PVC SDR 35 UNLESS OTHERWISE STATED. COORDINATE GENERAL LAWN AREAS FOR AREAS CLOSE TO BUILDINGS PARKING AND DRIVE
START OF CONSTRUCTION. 10. TEMPORARY SEDIMENT TRAPPING DEVICES MUST NOT BE REMOVED I=UNTIL PERMANENT TESTING OF SEWER CONSTRUCTION WITH THE LOCAL AUTHORITY. LANES.
13. MATERIALS IMPORTED TO THE SITE SHALL BE FREE OF HAZARDOUS WASTE AND STABILIZATION IS ESTABLISHED IN ALL CONSTRUCTION AREAS ASSOCIATED WITH THE 13. ALL SEWER PIPE WITH LESS THAN 5' OF COVER UNDER PAVEMENT AND LESS THAN 3. ALL EXISTING TREES WITHIN THE LIMIT OF DISTURBANCE SHALL BE REMOVED
NOXIOUS MATERIALS, STORED AS DESIGNATED AND SHALL NOT HAMPER THE SITE PROJECT. SIMILARLY, STABILIZATION MUST BE ESTABLISHED PRIOR TO CONVERTING 4' OF COVER UNDER LOAMED AREAS SHALL BE INSULATED. INSULATION SHALL BE FOR DEVELOPMENT. TREES OUTSIDE OF THE LIMIT OF DISTURBANCE SHALL BE
ACTIVITIES. TEMPORARY SEDIMENT TRAPS/BASINS INTO PERMANENT [POST-CONSTRUCTION] 2" THICK POLYURETHANE INSULATION WITH PVC JACKET PLACED AROUND PIPE. PROTECTED.
14. MATERIALS EXPORTED FROM THE SITE SHALL BECOME THE PROPERTY OF THE STORMWATER MANAGEMENT FACILITIES. ALL FACILITIES USED FOR TEMPORARY MEASURES 14. A 10 FOOT MINIMUM EDGE TO EDGE HORIZONTAL SEPARATION SHALL BE 4. THE CONTRACTOR SHALL GRADE ALL AREAS OF THE SITE AS NEEDED TO
CONTRACTOR AND DISPOSED OF IN A LEGAL MANNER. SHALL BE CLEANED AND RE-STABLIZED PRIOR TO BEING PUT INTO FINAL OPERATION. PROVIDED BETWEEN ANY WATER AND SANITARY SEWER LINES. AN 18" INCH CREATE SMOOTH TRANSITIONS TO EXISTING AREAS OF THE SITE AS NEEDED
15. ALL NECESSARY POLICE DETAILS SHALL BE THE RESPONSIBILITY OF THE 11. ALL TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES SHALL BE REMOVED AFTER MINIMUM OUTSIDE TO OUTSIDE VERTICAL SEPARATION SHALL BE PROVIDED AT TO CREATE SMOOTH TRANSITIONS TO EXISTING GRADES AND DIRECT WATER
CONTRACTOR. THE CONTRACTOR SHALL COORDINATE DETAILS WITH THE LOCAL FINAL SITE STABILIZATION. DISTURBED SOIL AREAS RESULTING FROM THE REMOVAL OF ALL WATER/SANITARY SEWER CROSSINGS. AWAY FROM STRUCTURES.
POLICE DEPARTMENT. TEMPORARY MEASURES SHALL BE PERMANENTLY STABILIZED WITHIN 30 DAYS OF REMOVAL. 15. THE RELOCATION OF THE WATER AND SEWER SERVICES ALONG THE EAST END OF 5. ALL EXISTING UNDISTURBED LAWN AREAS SHALL BE OVER-SEEDED TO LIMIT
16. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING ALL EXISTING UTILITIES IN 12. TO REDUCE THE TRACKING OF SEDIMENT ONTO PUBLIC WAYS, PROVIDE A CRUSHED STONE THE PROPOSED ADDITION WILL REQUIRE CLOSE COORDINATION WITH THE OF DISTURBANCE (LOD) UNLESS OTHERWISE NOTED ON THE PLANS.
WORKING ORDER AND FREE FROM DAMAGE DURING THE ENTIRE DURATION OF FILTER AT THE DRIVE ENTRANCE. ALL CONSTRUCTION VEHICLES ENTERING AND LEAVING DEVENS UTILITIES DEPARTMENT TO MINIMIZE POTENTIAL IMPACTS ON ADJACENT 6. ALL PLANTING AREAS TO BE COVERED WITH A 6" MINIMUM DEPTH OF TOPSOIL.
THE PROJECT. ALL COSTS RELATED TO THE REPAIR OF DAMAGED UTILITIES SHALL THE SITE SHALL USE THE PROPOSED CONSTRUCTION ENTRANCE. PROPERTIES. THE NEW SEWER CONNECTIONS WILL REQUIRE A BYPASS PUMP 7. ALL NEW PLANTS SHALL BE HEALTHY, VIGOROUS AND WITHOUT BROKEN
BE THE RESPONSIBILITY OF THE CONTRACTOR. EXCAVATION REQUIRED WITHIN 13. PROPER MEASURES SHALL BE IMPLEMENTED BY THE CONTRACTOR IF DEWATERING IS STATION TO ENSURE SERVICE TO THE OTHER PROPERTIES. BRANCHES IN ACCORDANCE WITH ASNS.
THE PROXIMITY OF EXISTING UTILITY LINES SHALL BE DONE BY HAND. THE NECESSARY DURING CONSTRUCTION. THESE MEASURES SHALL INCLUDE DEWATERING 16. MECHANICAL AND FIRE PROTECTION ENGINEERS TO VERIFY DESIGN AND SIZES OF 8. DISTURBED AREAS OF GROUND AROUND THE DETENTION BASIN SHALL BE
CONTRACTOR SHALL REPAIR ANY DAMAGE TO EXISTING UTILITY LINES OR BAGS, TEMPORARY HAYBALES, SILT FENCES, SILT SOCKS AND/OR OTHER APPROVED PROPOSED WATER AND SEWER SERVICES TO SITE. HYDROSEEDED WITH A SHADE TOLERANT GRASS SEED.
STRUCTURES INCURRED DURING CONSTRUCTION AT NO ADDITIONAL COSTS TO DEVICES. THE DEWATERING SETUP SHALL BE APPROVED BY THE ENGINEER PRIOR TO 17. CONTRACTOR SHALL COORDINATE ALL ELECTRICAL WORK INCLUDING BUT NOT 9. INDIVIDUAL TREES SHALL RECEIVE A FIVE FOOT DIAMETER MULCH BED
THE OWNER. IMPLEMENTATION. LIMITED TO: CONDUIT CONSTRUCTION, MANHOLE CONSTRUCTION, UTILITY POLE AROUND EACH TREE AS SHOWN. BEDLINES FOR GROUPS OF PLANTINGS
17. THE CONTRACTOR SHALL UTILIZE ALL PRECAUTIONS AND MEASURES NECESSARY 14. THE CONTRACTOR SHALL REGULARLY INSPECT THE PERIMETER OF THE PROPERTY TO CONSTRUCTION, OVERHEAD WIRE RELOCATION, AND TRANSFORMER WITHIN A MULCH BED ARE AS INDICATED ON THE PLAN.
TO ENSURE THE SAFETY OF THE PUBLIC, ALL PERSONNEL AND PROPERTY DURING CLEAN UP LOOSE CONSTRUCTION DEBRIS BEFORE IT LEAVES THE SITE. CONSTRUCTION WITH THE POWER COMPANY. 10. THE CONTRACTOR SHALL GUARANTEE ALL PLANTS AND LAWN AREAS FOR ONE
CONSTRUCTION IN ACCORDANCE WITH OSHA STANDARDS, INCLUDING 15. THE CONTRACTOR IS RESPONSIBLE FOR THE INSPECTION AND MAINTENANCE DURING 18. SITE LIGHTING SPECIFICATIONS, CONDUIT LAYOUT AND CIRCUITRY FOR YEAR FROM ACCEPTANCE OF FINAL PLANTING.
BARRICADES, SAFETY LIGHTING, CONES, POLICE DETAILS, AND/OR FLAGMEN AS CONSTRUCTION OF ALL STORMWATER FACILITIES INSTALLED OR AFFECTED BY THE PROPOSED SITE LIGHTING SHALL BE PROVIDED BY THE PROJECT ELECTRICAL
NECESSARY. PROJECT. ANY SEDIMENT OR DEBRIS COLLECTED WITHIN THESE FACILITIES FROM THE ENGINEER.
18. ALL TRENCHING WORK WITHIN A ROADWAY SHALL BE COORDINATED WITH THE PROJECT WORK SHALL BE REMOVED PRIOR TO THE OWNER'S ACCEPTANCE. 19. WHERE MANUFACTURERS ARE SPECIFIED ON THESE DRAWINGS, APPROVED
PROPER LOCAL AND/OR STATE AGENCY. TRENCH SAFETY SHALL BE THE 16. STREET SWEEPING SHALL BE PERFORMED ON ADJACENT ROADS AND STREETS AS EQUALS MAY BE SUBSTITUTED UPON WRITTEN APPROVAL FROM THE CIVIL
RESPONSIBILITY OF THE CONTRACTOR DOING THE TRENCH WORK, INCLUDING ENGINEER OF RECORD. ALL AREAS DISTURBED DURING CONSTRUCTION TO RECIEVE A MINIMUM OF 6" OF LOAM
NECESSARY DURING THE PROJECT DURATION.
ANY LOCAL AND/OR STATE PERMITS REQUIRED FOR THE TRENCHWORK. 20. IF AN EXISTING UTILITY IS FOUND TO CONFLICT WITH THE PROPOSED WORK, OR AND SEEDED. LOAM SHALL BE A FERTILE, FRIABLE,MEDIUM TEXTURED SANDY LOAM
19. ALL TRENCHWORK WITHIN EXISTING PAVEMENT SHALL BE SAWCUT PER THE CONSTRUCTION SEQUENCING: EXISTING CONDITIONS DIFFER FROM THOSE SHOWN SUCH THAT THE WORK FREE OF MATERIALS TOXIC TO HEALTHY PLANT GROWTH.LOAM SHALL BE FREE OF
APPLICABLE DETAILS. TRENCHWORK BACKFILL AND COMPACTION SHALL HAVE CANNOT BE COMPLETED AS INTENDED, THE LOCATION, ELEVATION, AND SIZE OF STUMPS, ROOTS, STONES AND FREE OF OTHER EXTRANEOUS MATTER ONE INCH [1"]
MAXIMUM 8" LIFTS. THE CONTRACTOR SHALL BE REQUIRED TO REMOVE THE THE FOLLOWING EROSION CONTROL PRINCIPLES SHALL APPLY TO THE LAND GRADING AND THE UTILITY OR OTHER CONFLICT SHALL BE ACCURATELY DETERMINED BY THE OR GREATER IN DIAMETER.
PATCH AND REPAVE AFTER ONE COMPLETE 12-MONTH CYCLE IF SETTLEMENT CONSTRUCTION PHASES: CONTRACTOR WITHOUT DELAY, AND THE INFORMATION FURNISHED IN WRITING TO
OCCURS DUE TO INADEQUATE COMPACTION. CIVIL ENGINEER OF RECORD TO RESOLVE THE CONFLICT. ALL MIX TO BE AS PROVIDED BY ALLEN SEED OR APPROVED EQUIVALENT AT 5-7 LBS
20. SITE LAYOUT SURVEY REQUIRED FOR CONSTRUCTION WILL BE PROVIDED BY THE 1. STRIPPING OF VEGETATION, GRADING, OR OTHER SOIL DISTURBANCE SHALL BE DONE IN A 21. THE CONTRACTOR SHALL COORDINATE THE EXACT LOCATION OF NEW UTILITY PER ACRE IN ALL DISTURBED AREAS AS SHOWN ON THE PLANS: [ALL AREAS WITHIN 10
CONTRACTOR AND SHALL BE CONDUCTED BY A MASSACHUSETTS REGISTERED MANNER TO MINIMIZE SOIL EROSION. SERVICES, LOCATIONS AND ELEVATIONS WITH THE UTILITY COMPANIES AND THE FEET OF PARKING AND DRIVEWAYS AND 30 FEET OF THE BUILDING]
PROFESSIONAL LAND SURVEYOR. THE CONTRACTOR SHALL BE RESPONSIBLE FOR 2. WHENEVER FEASIBLE, NATURAL VEGETATION SHALL BE RETAINED AND PROTECTED. BUILDING DRAWINGS.
ESTABLISHING AND MAINTAINING ALL CONTROL POINTS AND BENCHMARKS 3. THE EXTENT OF THE AREA AND DURATION OF PERIOD WHICH THE AREA IS EXPOSED AND 22. THE CONTRACTOR IS RESPONSIBLE TO SUBMIT TESTING REPORTS, SHOP 25% IMPROVED PERENNIAL RYE
DURING CONSTRUCTION. FREE OF VEGETATION SHALL BE KEPT WITHIN PRACTICAL LIMITS. DRAWINGS AND PRODUCT SPECIFICATIONS TO THE CIVIL ENGINEER OF RECORD 25% IMPROVED ANNUAL RYE
21. CONSTRUCTION SHALL BE PERFORMED IN ACCORDANCE WITH LOCAL, STATE AND 4. TEMPORARY SEEDING, MULCHING, OR OTHER SUITABLE STABILIZATION MEASURES SHALL FOR MATERIALS, STRUCTURES, EQUIPMENT, RETAINING WALLS, ETC. FOR 25% CREEPING RED FESCUE
FEDERAL LAWS AND REGULATIONS REGARDING NOISE, VIBRATION, DUST, BE USED TO PROTECT EXPOSED CRITICAL AREAS DURING PROLONGED CONSTRUCTION OR APPROVAL PRIOR TO INSTALLATION. 16.5% TURF TYPE TALL FESCUE
SEDIMENTATION CONTAINMENT, TRENCHWORK AND ROADWAY WORK. OTHER LAND DISTURBANCE. 23. THE CONTRACTOR IS TO SUBMIT AS-BUILT PLANS IN ELECTRONIC CAD FORMAT TO 5% KENTUCKY BLUE GRASS 9885
22. SOLID WASTES SHALL BE COLLECTED AND STORED IN A SECURED DUMPSTER. 5. ALL SEDIMENT SHALL BE CONTAINED ONSITE AND REMOVED AS NECESSARY. CUT AND FILL THE OWNER AND CIVIL ENGINEER OF RECORD UPON COMPLETION OF THE 1% RED TOP
THE DUMPSTER SHALL MEET ALL LOCAL AND STATE SOLID WASTE MANAGEMENT SLOPES AND STOCKPILED MATERIALS SHALL BE PROTECTED USING SILT FENCE AND FILTER PROJECT. THE AS-BUILTS SHALL BE PREPARED AND CERTIFIED BY A MA LICENSED .5% COLONIAL BENTGRASS
REGULATIONS. LOGS TO PREVENT EROSION. SLOPES, ESPECIALLY DOWNGRADIENT OF PAVED AREAS, LAND SURVEYOR OR PROFESSIONAL ENGINEER.
23. THE CONTRACTOR SHALL RESTORE ALL SURFACES EQUAL TO THEIR ORIGINAL SHALL BE STABILIZED AS SOON AS POSSIBLE AND PROTECTED WITH PERMANENT EROSION ALL INFILTRATION/DETENTION BASINS TO BE SEED MIX "A": NEW ENGLAND
CONDITION AFTER CONSTRUCTION IS COMPLETE. AREAS NOT DISTURBED BY PROTECTION WHEN EROSION EXPOSURE PERIOD IS EXPECTED TO BE GREATER THAN OR CONSEVATION/WILDLIFE MIX- 25 LBS PER ACRE NURSE GRASS AND PERENNIAL RYE 5
CONSTRUCTION SHALL BE LEFT NATURAL. THE CONTRACTOR SHALL TAKE CARE EQUAL TO THREE MONTHS, AND TEMPORARY EROSION PROTECTION HAS BEEN LBS PER ACRE.
TO PREVENT DAMAGE TO SHRUBS, TREES AND OTHER LANDSCAPING AND/OR INCORPORATED PRIOR TO CONSTRUCTION.
NATURAL FEATURES. 6. PERMANENT EROSION PROTECTION SHALL BE ACCOMPLISHED BY SEEDING WITH GRASS OR Elymus virginicus
24. LEDGE OR BOULDER EXCAVATION IS ANTICIPATED FOR THIS SITE. THE OTHER MIXTURES AS SHOWN ON THESE PLANS. Schizachyrium scoparium
5 CUDWORTH ROAD SITE CONTRACTOR SHALL PROVIDE A UNIT COST PER CUBIC YARD FOR LEDGE AND/OR 7. TEMPORARY EROSION PROTECTION SHALL BE ACCOMPLISHED BY COVERING WITH EROSION Andrapagon gerardil
BOULDER REMOVAL. LEDGE AND/OR BOULDERS LESS THAN ONE CUBIC YARD IN PROTECTION MATERIALS AS REQUIRED BY THE ORDER OF CONDITIONS. Festuca rubra
SIZE WILL NOT BE CONSIDERED PAYABLE ROCK. 8. EXCEPT WHERE SPECIFIED SLOPE IS INDICATE ON THESE PLANS, FILL SLOPES SHALL BE Panicum virgatum
LIMITED TO A GRADE OF 2:1 [HORIZONTAL TO VERTICAL], CUT SLOPES AT 1.5:1 SHOULD BE Chamaecrista fesciculatata
NETTED WITH BIODEGRADABLE JUTE MESH OR EQUAL. Panicum clandestinum
Sorghastrum nutans
GRADING NOTES: Heliopsis helianthoides
Ascleplas syriaca
COMPACTION REQUIREMENTS: Eupatorium masculatum
Euthamia graminifolia
MINIMUM COMPACTION LOCATION Verbena hestata
Astar novae-angliea
95 % BELOW PAVED OR CONCRETE AREAS Soildago juncea

95 % TRENCH BEDDING MATERIALS ALL AREAS OUTSIDE OF 10 FEET OF PARKING AND DRIVEWAYS AND 30 FEET FROM THE
BUILDING SHALL RECEIVE SEED MIX "B": NEW ENGLAND NATIVE WARM SEASON GRASS
90 % BELOW LOAM AND SEED AREAS MIX- 23 LBS PER ACRE NURSE GRASS- AND ANNUAL RYE 5 LBS PER ACRE

1. ALL PERCENTAGES OF COMPACTION TESTING SHALL BE OF THE MAXIMUM DRY Elymus Virginicus
DENSITY AT THE OPTIMUM MOISTURE CONTENT AS DETERMINED AND Schizachyrium scoparium
CONTROLLED IN ACCORDANCE WITH ASTM D-1557, METHOD C. FIELD DENSITY Andrapagon gerardil
TESTS MUST BE MADE IN ACCORDANCE WITH ASTM D-1556 OR ASTM-2922. Sorghastrum nutans
Panicum virgatum
2. THE CONTRACTOR SHALL REFER TO THE ARCHITECTURAL PLANS AND Festuca rubra
SPECIFICATIONS FOR EARTHWORK AND COMPACTION REQUIREMENTS FOR ALL
SLABS AND BUILDING FOUNDATIONS.

3. SPRINKLER OR USE A WATER TRUCK AS NECESSARY TO APPLY WATER DURING


GRADING OPERATIONS IN ORDER TO MINIMIZE SEDIMENT TRANSPORT AND
MAINTAIN ACCEPTABLE AIR QUALITY CONDITIONS. REPETITIVE TREATMENTS
SHALL BE DONE AS NEEDED UNTIL THE GRADES ARE PAVED OR SEEDED.

4. ONCE THE PERIMETER EROSION CONTROL MEASURES HAVE BEEN IMPLEMENTED,


CUTTING AND EARTH PREPARATION SHALL COMMENCE FOR THE PROPOSED
CONSTRUCTION ENTRANCE.

5. DIVERSION BERMS AND SEDIMENT TRAPS SHALL BE CONSTRUCTED, AS NEEDED,


TO CAPTURE SILT LADEN RUNOFF FROM THE SITE.

6. SITE CLEARING AND GRUBBING CAN PROCEED UP TO THE LIMIT OF WORK. NO


ALTERATIONS SHALL TAKE PLACE OUTSIDE THE LIMIT OF WORK FOR THE PROJECT
WITHOUT PRIOR AUTHORIZATION FROM THE CIVIL ENGINEER OF RECORD AND THE
CONSERVATION AGENT.

7. PROCEED WITH ROUGH GRADING OF SUB-SOILS IN PREPARATION FOR GRAVEL


BASE COURSES.

8. ALL EARTHWORK AND SITE PREPARATION SHALL BE DONE IN STRICT


ACCORDANCE WITH THE RECOMMENDATIONS OF ANY SUBSURFACE
INVESTIGATION OR GEOTECHNICAL REPORTS PREPARED FOR THIS SITE.

9. 2" BINDER COURSE AND 121" FINISH COURSE OF BITUMINOUS PAVEMENT TO BE


INSTALLED ON SITE ON ALL PARKING AREAS. GRAVEL BASE CROSS-SECTION TO BE
PREPARED AND INSPECTED BY THE CIVIL ENGINEER OF RECORD PRIOR TO
PAVEMENT INSTALLATION.

10. THE CONTRACTOR SHALL ADJUST AND/OR CUT EXISTING PAVEMENT AS


NECESSARY TO ENSURE A SMOOTH FIT AND CONTINUOUS GRADE.

11. ALL AREAS DISTURBED DURING CONSTRUCTION SHALL RECIEVE A MINIMUM OF 6"
OF LOAM AND SEEDED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
WATERING ANY LOAMED AND SEEDED AREAS UNTIL LAWN GROWTH IS
ESTABLISHED AND APPROVED BY THE ENGINEER / OWNER.
APPROVED BY THE TOWN OF 12. CONTRACTOR TO PROVIDE A FINISH PAVEMENT SURFACE AND LAWN AREAS FREE
WEBSTER PLANNING BOARD: OF LOW SPOTS AND PONDING AREAS. THE CONTRACTOR SHALL ASSURE POSITIVE
DRAINAGE AWAY FROM ANY BUILDINGS FOR ALL NATURAL AND PAVED AREAS.
________________________________
________________________________
________________________________
________________________________
________________________________
________________________________
________________________________
DATE: _________________
N/F 554
TOWN OF WEBSTER
#23 CUDWORTH ROAD 552
PARCEL ID: 87-B-1

WF2 B107 546

N 88°-13'-06" E 908.76'
542.8 542.2 543.2
WF2 B106 55
WF2 B105

OHW
0

Eugene T. Sullivan, Inc.

OHW
542.4
WF2 B108
540.9 WF2 E WF E B104
EXISTING CONCRETE PADS,
EXISTING ELECTRICAL TO
548 Consulting Engineers
BE ABANDONED 6 230 Lowell Street - Suite 2A

OHW
PANELS ETC. TO BE REMOVED 54
Wilmington, MA 01887
WF2 B109 538.7
541.5
EXISTING GAS PIPE TO Phone: 978.657.6469

OHW
BE ABANDONED Fax: 978.657.8563
WF B103
Email: ETSPE@aol.com
533.1

OHW
540.8
WF1 INT CL6 E NO DATE REVISIONS
WF B102 E
537.5 G

OHW
530.9 WF B101
WF2 B110
531.4

OHW
527.7 WF B100

9'
82.9
WF1 INT CL5

OHW
540

OHW
7" E
WF1 INT CL4
522.2 CB [EX]:

43'-0
RIM= 538.39

OHW
538 SMH [EX]:
RIM= 537.27

18°-
538

540

OHW
546
WF1 INT CL3

S
515.4
CB [EX]:

OHW
8
53 RIM= 537.27

540
EXISTING LEDGE

544
OUTCROPPING

OHW
542
536

54
WF1 INT CL2

4
509.7

54
UP 9/19

2
54

HW
WF A127

O
507.4

546
505.5 4

HW
53

O
53
WF1 INT CL1 OHW
OHW DMH [EX]:

8
53 OHW

RIM= 537.09

53
WF A126 4

HW
OHW

O
6
OHW
OHW
OHW

505.0 53
OHW

X
505.9WF A128
OHW

HW
2

O
OHW
OHW
OHW

32
OHW

X
WF A129 E 5
UP 901
502.7

(1977
532
54 544
2

X
STONE ANTI-TRACKING

54
WF A125

(PLA CESTER WIDTH)


0
503.0 502.0
PAD [SEE DETAIL]

WOR ARIABLE
X
WF A124 WF A123
503.1 WV

53
538

N BO
0

(V
WF A122

X
15" INV.= 510.82

OK 4 OUNTY
538

X
WF A121 502.6

39, P
C
X
534

LAN AYOUT)
15" INV.= 505.97
WV
X

X
X

WF A120
X

536
X
X

108)
X

311 EXISTING CONTOUR

L
X

501.8

X
X

EXISTING CONCRETE WALLS


X

129 PROPOSED CONTOUR OR SPOT GRADE


X

AND PADS TO BE REMOVED. N/F


X

X
X

INFILL w/ASPHALT TO MATCH


X

ACCORD ELDER CARE

X
EXISTING 534 X X

NEW ASPHALT BERM


EXISTING EDGE OF #10 CUDWORTH ROAD

X
X
503.9
X

CB [EX]: PAVEMENT X

UNDERGROUND ELECTRIC CONDUIT

X
WF-A119 6" RIM= 513.75
X
PARCEL ID: 87-A-1-1 UE

CP
X

X
WF-A118

X
INV [IN]= 509.40 UTILITY POLE

X
P

52
51
502.1 DR INV [OUT]= 509.31 532 532

6
8
51

AI EXISTING DRAIN LINE

X
SUMP= 509.21

X
N EXISTING CHAIN LINK 532
6

X
[E

53
X FENCE TO BE REMOVED

52

0
] WV

52
WF-A117 PROPOSED DRAIN LINE

X
0
X

X
2
500.8

OHW
X
X

51

X
15

EXISTING PAVEMENT CATCH BASIN


X

4 EXISTING CONCRETE
"C

52
N 21

52

X
X
X

TO BE REMOVED
X

WV

8
PP

RAMP TO BE REMOVED

4
X

X
510

W
D DRAIN MANHOLE
DR

X
OH
X
510

X
X

530
AI
°-26

508

X
X

EXISTING SEWER PIPE


W
OH
[E

X
504
506
502

PROVIDE 12" FILTREXX


X

WF-A116
X]
'-37

SILT SOXX

532
X
S SEWER MANHOLE
W
OH

X
X
51
2

X
X
"W

X
X
X W
OH
X

W EXISTING WATER LINE


530

X
W WV
WATER GATE VALVE
OH
816

WF-A115 498.8 OHW


OHW

X
HYDRANT
OHW
OHW
.99'

OHW
OHW
OHW
OHW
OHW
OHW
OHW

GAS SERVICE

X
500.3 528 GV
WF-A114 GAS GATE VALVE

OHW
526 53
0 SMH [EX]:
524 12" FILTREXX SILT SOXX
RIM= 529.43
WF-A113 EXISTING EDGE OF

OHW
EXISTING TOWER AND FOUNDATION PAVEMENT 522
500.1 TO BE REMOVED
520
CB [EX]:

OHW
CB [EX]: RIM= 528.95
RIM= 516.80
.6
498

52
8
WF-A112 CB [EX]:
RIM= 527.85

DMH [EX]:
RIM= 527.71
498.1

WF-A111

WF-A110 526
498.5
UP 6/17

= 970.00'

OHW
WF-A109
498.3

OHW
L= 285.99' R
SMH [EX]:
RIM= 524.83

OHW
WF-A108

OHW
498.1

EX
IS
TI

OHW
NG
SE
WF-A107

W
ER
498.5

OHW
N/F

SE
RV
GREAT BAY LLC

I CE
#37 SUTTON ROAD

OHW
PARCEL ID: 86-D-1
WF-A106
498.3

OHW
OHW
WV
498.9
PREPARED FOR:

OHW
WF-A105
W
OH

CUDWORTH ROAD LLC

S 1°-49'-32" E 121.14'

OHW
133 PEARL STREET
W
OH

WV

496.7
OH
W
BOSTON, MA

OHW
WF-A104 OH
W

PROJECT:
OHW

W
OH

OHW
LOADING DOCK
496.8 OH
W

IMPROVEMENTS
WF-A103
OHW

5 CUDWORTH ROAD

OHW
W
OH

OHW
OHW
OHW OHW OHW
W
WEBSTER, AM
EXISTING CONCRETE TO
OH

OHW
BE REMOVED W
OH
OHW OHW
OHW OHW
OHW OHW
OHW
OHW
OHW OH
W
DRAWING:

OHW
496.5 OHW
OHW
OHW OHW
OHW OHW

WF-A102
OHW OHW OHW
OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW

OHW

OHW
495.5 S 88°-13'-06" W 787.61'
WF-A101

OHW
N/F
LELANITE CORP
#1 CUDWORTH ROAD
495.6 SCALE: 1" = 40'-0" PARCEL ID: 87-B-3
SCALE: 1" = 40'-0"
WF-A100
SBDH(F/H)
DATE: MARCH 6, 2020
20 0 20 40 80 DRAWING NUMBER
554

552

REQUIRED EXISTING PROPOSED

GAS
WF2 B107 546
MINIMUM LOT AREA 25,000 SF 671,845 SF ---

GAS
MINIMUM LOT FRONTAGE 50 FEET 788 FEET ---
WF2 B106 55

GAS
WF2 B105

OHW
0
" MINIMUM FRONT YARD 0 FEET 100 FEET ---
55'-0
544 MINIMUM SIDE YARD 0 FEET 65 FEET ---

GAS
175'-
0" Eugene T. Sullivan, Inc.

OHW
WF2 B108 MINIMUM REAR YARD 0 FEET 82 FEET ---

GAS
WF2 E WF E B104
548 65'-0
" MAXIMUM BUILDING HEIGHT 4 STORIES 2 STORIES --- Consulting Engineers
6 230 Lowell Street - Suite 2A

OHW
GAS
54

10'-0
MAXIMUM FLOOR AREA RATIO .50 .24 ---
Wilmington, MA 01887

"

GAS
WF2 B109
"
Phone: 978.657.6469

OHW
55'-0 Fax: 978.657.8563
WF B103

GAS
Email: ETSPE@aol.com

OHW
PROPERTY USES:

GAS
WF1 INT CL6 E NO DATE REVISIONS
WF B102 542

GAS

OHW
WF B101 THE EXISTING USES FOR THIS PROPERTY ARE OFFICE,
WAREHOUSING, AND MANUFACTURING WHICH ARE APPROVED

GAS
WF2 B110 540
USES IN THE INDUSTRIAL ZONING DISTRICT IN ACCORDANCE

OHW
WITH THE TABLE OF USE REGULATIONS OF THE TOWN OF

GAS
WF B100
WEBSTER ZONING BYLAWS.
WF1 INT CL5

GAS

OHW
540

GAS

OHW
538
EL

GAS
WF1 INT CL4
RAV
C T ED G AREA
PA

OHW
GAS
GE
538
COM TORA CRITERIA UNIT OF MEASURE REQUIRED
NEW ILER S

GAS
TRA 538 INDUSTRIAL USES 1 SPACE PER 1.5 EMPLOYEES 100 EMPLOYEES 67 SPACES

540

OHW
546

GAS
WF1 INT CL3
536 PARKING SPACES REQUIRED 67 SPACES

OHW
8

GAS
53

540

GAS
PROPOSED PARKING SPACES 79 SPACES

544

OHW
542
536

GAS
54
WF1 INT CL2

4
54

GAS
UP 9/19

2
54
536

HW
WF A127

GAS
546
4 534

HW
53

GAS
O
53
WF1 INT CL1 OHW
OHW

8
53 OHW

53
WF A126 4

HW

GAS
OHW

O
6
OHW
OHW
OHW

53
OHW

GAS
WF A128
OHW

HW
2

O
OHW
OHW
OHW

32
OHW

GAS
WF A129 E 5
UP 901

(1977
532
54 544

GAS
2 532
STONE ANTI-TRACKING

54
WF A125

(PLA CESTER WIDTH)


0

GAS
PAD [SEE DETAIL]

WOR ARIABLE
WF A124 WF A123
WV

53
538

N BO
GAS
0

(V
WF A122

OK 4 OUNTY
GAS
530
538 CCB
WF A121
532

528

GAS
39, P
CCB

C
526
534

GAS
524

LAN AYOUT)
528
WV
PROVIDE CONTINUOUS ASPHALT

522
WF A120 536

GAS
108)
BERM @ PERIMETER OF NEW PAVED AREAS 311 EXISTING CONTOUR

L
520
522
CCB CCB CCB

GAS
520 129 PROPOSED CONTOUR OR SPOT GRADE
NEW PAVED AREAS: AF OR
ARE E

GAS
534 NEW ASPHALT BERM
EXISTING EDGE OF CCB E D
3 21" BITUMINOUS ASPHALT PAVING PAV ORAG
TING R ST
PAVEMENT UNDERGROUND ELECTRIC CONDUIT

GAS
UE
CONSISTING OF 2" BINDER COURSE AND 1 21" EXIS TRAILE
WF-A119
WF-A118
FINISH COURSE OVER 12 COMPACTED UTILITY POLE

GAS
52
51

CCB
CCB
GRAVEL
532 BASE 532

6
8
51

518
532 EXISTING DRAIN LINE
6

GAS
53
9S

52

0
WV

52
WF-A117 PROPOSED DRAIN LINE

OHW
GAS
CCB
51
4 7S CATCH BASIN

52
52

GAS
WV

8
4
510

OH
W
D DRAIN MANHOLE
510

GAS
530
516

520
508

EXISTING SEWER PIPE


W
OH
504
506
502

WF-A116 PROVIDE 12" FILTREXX

GAS
SILT SOXX

532
S SEWER MANHOLE
W
OH
51

CCB
2

GAS
W
OH
W EXISTING WATER LINE
530

516

518
GAS
WV

GAS
W GAS

WATER GATE VALVE


OH

WF-A115 GAS
GAS

OHW
OHW GAS

GAS
HYDRANT
OHW

CCB
OHW
S
OHW
OHW
GA
OHW
OHW
S
OHW
OHW GA
OHW

GAS SERVICE

GAS
S
GA

528 GV

S
GA
514.75 GAS GATE VALVE
WF-A114

GAS
OHW
526 53

S
0

GA
524 12" FILTREXX SILT SOXX

GAS
S
WF-A113 EXISTING EDGE OF

GA
OHW
PAVEMENT 522 GAS GA
S

GAS
S
GA
GAS GAS GAS GAS GAS GAS GAS 520 GAS GAS GAS GAS

0'
GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS

100.0
S
GA

GAS
OHW
S
GA

GAS
GAS
52
8

GAS
WF-A112

GAS
GAS
GAS
9'-0" 8'-0" 8'-0" 8'-0"

GAS
WF-A111
VAN ACCESSIBLE

GAS
WF-A110 526

GAS
19'-0"

GAS
UP 6/17

OHW
GAS
WF-A109
6S

OHW
GAS
GASOHW
GAS
WF-A108 12S

OHW
OHW
WF-A107

OHW
9'-0" 8'-0" 8'-0" 8'-0"

OHW
VAN ACCESSIBLE
WF-A106

OHW
19'-0"

OHW
4S WV

PREPARED FOR:

OHW
WF-A105
8S OH
W

CUDWORTH ROAD LLC

OHW
133 PEARL STREET
W
OH

WV
OH
W
BOSTON, MA

OHW
WF-A104 OH
W
8'-0"

3P PROJECT:
OHW

W
OH

OHW
5' 3S 17S LOADING DOCK
82.7 20'-0" IMPROVEMENTS
W
OH

WF-A103
OHW

5 CUDWORTH ROAD

OHW
W
OH

WEBSTER, AM

65.00'
OHW OHW OHW
OHW
OHW W
OH

OHW
W
OH
OHW OHW
OHW OHW
OHW OHW
OHW
OHW
OHW OH
W
DRAWING:

OHW
OHW
OHW OHW
OHW OHW
OHW

WF-A102
OHW OHW OHW
OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW

OHW

OHW
WF-A101

OHW
SCALE: 1" = 40'-0" SCALE: 1" = 40'-0"
WF-A100

DATE: MARCH 6, 2020


20 0 20 40 80 DRAWING NUMBER
554

552

GAS
WF2 B107 546

GAS
WF2 B106 55

GAS
WF2 B105

OHW
0

544

GAS
Eugene T. Sullivan, Inc.

OHW
WF2 B108

GAS
WF2 E WF E B104
548 Consulting Engineers
6 230 Lowell Street - Suite 2A

OHW
GAS
54
Wilmington, MA 01887

GAS
WF2 B109 Phone: 978.657.6469

OHW
WF B103 Fax: 978.657.8563

GAS
Email: ETSPE@aol.com

OHW
GAS
WF1 INT CL6 E NO DATE REVISIONS
WF B102 542

GAS

OHW
WF B101

GAS
WF2 B110 540

OHW
GAS
WF B100
WF1 INT CL5

GAS

OHW
540

GAS

OHW
538

GAS
WF1 INT CL4
CB [EX]:
RIM= 538.39

OHW
GAS
538 SMH [EX]:
RIM= 537.27

GAS
538

540

OHW
546

GAS
WF1 INT CL3
536 CB [EX]:

OHW
8

GAS
53 RIM= 537.27

540

GAS
544

OHW
542
536

GAS
54
WF1 INT CL2

4
54

GAS
UP 9/19

2
54
536

HW
WF A127

GAS
546
4 534

HW
53

GAS
O
53
WF1 INT CL1 OHW
OHW DMH [EX]:

8
53 OHW

RIM= 537.09

53
WF A126 4

HW

GAS
OHW

O
6
OHW
OHW
OHW

53
OHW

GAS
WF A128
OHW

HW
2

O
OHW
OHW
OHW

32
OHW

GAS
WF A129 E 5
166'-8" LONG x 12" WIDE ZURN UP 901

(1977
532
54 544

GAS
2 532 Z882 PERMA TRENCH SYSTEM

54
WF A125 INV. [OUT]= 530.00

(PLA CESTER WIDTH)


0

GAS
WOR ARIABLE
WF A124 WF A123
WV

53
538

N BO
GAS
0

(V
WF A122
15" INV.= 510.82

OK 4 OUNTY
GAS
530
538
WF A121
532

528

GAS
39, P
C
526
534

GAS
524

LAN AYOUT)
15" INV.= 505.97 528
WV

522
WF A120 536

GAS
108)
311 EXISTING CONTOUR

L
520
522
9 ]

GAS
520 0.0 129 PROPOSED CONTOUR OR SPOT GRADE
', S=
00

GAS
534 2 NEW ASPHALT BERM
EXISTING EDGE OF =
[L
CB [EX]: PAVEMENT PE UNDERGROUND ELECTRIC CONDUIT

GAS
UE
WF-A119 6" RIM= 513.75 " HD
WF-A118 CP 12
INV [IN]= 509.40 UTILITY POLE

GAS
P

52
51
DR INV [OUT]= 509.31 532 532

6
8
51

AI SUMP= 509.21 518 EXISTING DRAIN LINE


N 532
6

GAS
[E

53
X

52

0
] WV

52
WF-A117 DMH-2: [N]: PROPOSED DRAIN LINE

OHW
GAS
RIM= 515.00
51
15

4 INV. [IN]= 511.25 CATCH BASIN


"C

52
52

GAS
INV. [OUT]= 511.25 CB-1: [N]: WV

8
PP

4
510

DMH-4: [N]: RIM= 529.00


W
D DRAIN MANHOLE
DR

OH

18" HDPE [L= 270', S= 0.0065]


510

GAS
RIM= 513.75

530
INV. = 520.00
AI

516

520
508

INV. [IN]= 509.50 12" HDP OH


W

EXISTING SEWER PIPE


E [L= 12
[E
504
506
502

WF-A116 0', S= 0
X]

GAS
INV. [OUT]= 509.00 .067]
8" HDPE

8" HDPE

532
S SEWER MANHOLE
[L= 30']

[L= 30']
W
OH
51

12" HDPE INV.= 511.75 INV.= 512.50 DMH-1: [N]:


2

GAS
DMH-3: [N]: RIM= 516.00
W
OH
W EXISTING WATER LINE
RIM= 513.50 INV. [IN]= 513.00 530

516

518
GAS
WV

GAS
GAS
INV. [IN]= 510.00 INV. [OUT]= 513.00
W

WATER GATE VALVE


OH

WF-A115 GAS

INV. [OUT]= 510.00 OHW


GAS

CDS-2025-5-C: [N]: OHW GAS

GAS
HYDRANT
OHW
OHW
S
OHW
GA
RIM= 514.50
OHW
OHW
OHW
S
OHW
OHW GA

INV. [IN]= 511.15 OHW

GAS SERVICE

GAS
S
GA

INV. [OUT]= 511.15 528 GV

S
GA
514.75 GAS GATE VALVE
WF-A114

GAS
OHW
526 53

S
0

GA
SMH [EX]: 12" FILTREXX SILT SOXX
524

GAS
RIM= 529.43

S
WF-A113 240' LONG x 12" WIDE ZURN Z882 EXISTING EDGE OF

GA
OHW
PERMA TRENCH SYSTEM. TOP OF PAVEMENT 522 GA
S
15" HDPE HEADER [INV.= 510.00]

18" HDPE HEADER [INV.= 511.00]

GAS

GAS
DRAIN ELEV.= 514.50
S
GA

S
GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS 520
GAS GAS GAS GAS GAS GAS

GA
CB [EX]:

GAS
OHW
GA
S
CB [EX]: RIM= 528.95
RIM= 516.80

GAS
GAS
126'-0"

52
8

GAS
WF-A112 CB [EX]:
RIM= 527.85

GAS
GAS
DMH [EX]:
SUBSURFACE INFILTRATION BASIN: RIM= 527.71
46'-6" WIDE x 126' LONG x 5'-0" DEEP

GAS
STONE TRENCH w/25- 40' LONG 48" DIA
PERFORATED HDPE PIPE WRAPPED

GAS
WF-A111 IN MIRAFI FABRIC.
BOTTOM OF STONE ELEV.= 506.00

GAS
48" PIPE INV.= 506.50

WF-A110 526

GAS
GAS
UP 6/17

OHW
46'-6"

GAS
WF-A109
6S

OHW
GAS
SMH [EX]:

GASOHW
RIM= 524.83

GAS
WF-A108 12S

OHW
EX
IS
TI

OHW
NG
SE
WF-A107

W
ER

OHW
SE
RV
I CE

OHW
WF-A106

OHW
OHW
4S WV

PREPARED FOR:

OHW
WF-A105
8S OH
W

CUDWORTH ROAD LLC

OHW
133 PEARL STREET
W
OH

WV
OH
W
BOSTON, MA

OHW
WF-A104 OH
W

3P PROJECT:
OHW

W
OH

OHW
3S 17S LOADING DOCK
IMPROVEMENTS
W
OH

WF-A103
OHW

5 CUDWORTH ROAD

OHW
W
OH

OHW
OHW
OHW OHW OHW
W
WEBSTER, AM
OH

OHW
W
OH
OHW OHW
OHW OHW
OHW OHW
OHW
OHW
OHW OH
W
DRAWING:

OHW
OHW
OHW OHW
OHW OHW
OHW

WF-A102
OHW OHW OHW
OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW OHW
OHW OHW OHW OHW OHW

OHW

OHW
WF-A101

OHW
SCALE: 1" = 40'-0" SCALE: 1" = 40'-0"
WF-A100

DATE: MARCH 6, 2020


20 0 20 40 80 DRAWING NUMBER
NOTES:
NOTES:
1. SANDY-LOAM AND/OR LOAMY-SAND TOPSOIL MATERIALS NOTES:
1. STONE ENTRANCES TO REMAIN UNTIL SHALL BE EXCAVATED FROM ALL PAVED AREAS PRIOR TO
SEE PLAN - 35' MINIMUM
INSTALLATION OF PAVEMENT SUB-BASE IS SUB-BASE INSTALLATION. 1. BERM TO BE CONSTRUCTED OF BITUMINOUS
TO BEGIN.
2" HEADWIDTH WOODEN STAKES 2. SUB-GRADE [EXISTING MATERIALS] SHALL CONSIST OF INERT CONCRETE WEARING SURFACE COURSE.
2. STONE SHALL BE REPLACED AS
REQUIRED TO ENSURE MUD REMOVAL. PLACED 10' ON CENTER MATERIAL THAT IS HARD, DURABLE STONE AND/OR COARSE 2. THE BITUMINOUS BERM MUST BE FOUNDED
3. SEE E.1 FOR LOCATIONS AND SAND, FREE FROM LOAM AND CLAY TO A DEPTH NOT LESS ENTIRELY ON THE BASE COURSE.
DIMENSIONS. THAN 4 FEET BELOW THE FINISH PAVEMENT SURFACE. 4" 12"
3. SUBGRADE FILL SHALL BE COMPACTED TO 95% COMPACTION.
R= 20' TYP. 12" DIAMETER FILTREXX SILT SOXX 4. PRIOR TO INSTALLING THE FINISH COURSE THE BINDER
121" TO 221" 12" THICK WASHED CRUSHED COURSE SURFACE SHALL BE SWEPT CLEAN BY A STREET
A STONE AGGREGATE ASTM SWEEPING MACHINE AND A TACK COAT SHALL BE INSTALLED
DESIGNATION C-33. TO A LEVEL APPROVED BY THE ENGINEER.
DRIVEWAY

6"
SEE PLAN
Eugene T. Sullivan, Inc.
1 1/2" TOP COURSE
1 1/2" TOP COURSE
2" BINDER COURSE Consulting Engineers
2" BINDER COURSE 230 Lowell Street - Suite 2A
12" PROCESSED GRAVEL Wilmington, MA 01887
(INSTALLED AND COMPACTED) 12" PROCESSED GRAVEL
IN TWO LAYERS) (INSTALLED AND COMPACTED) Phone: 978.657.6469
IN TWO LAYERS) Fax: 978.657.8563
6" COMPACTED GRAVEL BASE
[COMPACTE D TO 95 %]. COMPACTED SUITABLE Email: ETSPE@aol.com
PLAN VIEW SECTION A-A: SUBGRADE COMPACTED SUITABLE
NO DATE REVISIONS
SUBGRADE

MH FRAME AND COVER


LEBARON LK110 OR EQUAL. ADJUST TO REQUIRED
TYPE I CEMENT CONCRETE FRAME TO BE SET IN GRADE WITH A MINIMUM
MASONRY COLLAR. FULL BED OF MORTAR OF TWO COURSES, MAX.
OF 12", USING SEWER
LEBARON LF248-2 BRICK
CATCH BASIN FRAME
BRICKS SHALL BE USED
(3 FLANGE) AND GRATE.

MAX.
FOR GRADE ADJUSTMENTS

12"
FRAME TO BE SET IN
(2 COURSE MIN., 12" MAX.) FULL BED OF MORTAR

6" MIN. (TYP) MANHOLE TO MEET


2'-0" ASTM C478.
6" MIN. (TYP) STEEL REINFORCING
DIA.
TO MEET ASTM AND

3'-0" OR 4'-0"
8" AASHTO HS-20-44
FOR H-20 LOADING.
18"-24" 24" OR 48" SQ.
OPENING POLYPROPYLENE
CONICAL PRECAST REINFORCED MH STEPS
SECTIONS CONCRETE MH CONE
FLAT TOP ALTERNATE
REQUIRED FOR
8" MIN. SHALLOW STRUCTURES STANDARD BARREL
4'-0" DIAMETER (SEE ABOVE) SECTION
6'-0" DIA. @ DOUBLE GRATE CB's 5" MIN. 4'-0" DIA.
HEIGHT OF NORMAL WATER BUTYL RUBBER 1'-0"

COMBINATION OF 1, 2
3 OR 4 FT. LENGTHS
RISER SECTIONS LEVEL
PLUS 2" SEALANT (TYP) 8'-23
8"
CLEARANCE
(TYP)

VARY FROM 1'-4" 1"


1'-0"

94
OUTSIDE PIPE DIA.
REINFORCED
CONCRETE SECTIONS 4" 8'-0"
TO BE DESIGNED FOR MONOLITHIC PRECAST MIN.
BUTYL RUBBER
SUMP

A MIN. H-20 LOADING REINFORCED CONCRETE


4'-0"

JOINT SEALANT (TYP) 4,000 PSI MIN. BASE SECTION SHELF ELEVATION
COMPRESSIVE AT CROWN OF
5" MIN. STRENGTH HIGHEST PIPE
SNOUT STRUCTURE PIPE OUTSIDE DIA.
AS MANUFACTURED DIA. PLUS 2"
COMPACTED
BY NYLOPLAST
SUITABLE CONCRETE FILL
SUBGRADE
6"

8"
17
5" MIN. UNDISTURBED SOIL,

MIN.
LEDGE OR

4"
MONOLITHIC
COMPACTED
PRECAST
SUBGRADE
REINFORCED
CONCRETE BASE
8" MINIMUM COMPACTED
CRUSHED STONE [M2.01.4] BEDDING. 8" MINIMUM COMPACTED
CRUSHED STONE [M2.01.4] BEDDING.

PAVEMENT 95 % COMPACTED FILL 4 OZ. NON-WOVEN FILTER FABRIC


AROUND STONE PERIMETER.

8" MIN.
1"-2" DIAMETER
WASHED STONE.
ELEVATION = 511.00

6"
ELEVATION = 510.50

48" DIAMETER PERFORATED


HDPE PIPE [INV.= 507.50]

1'-0" 1'-0" 1'-0"

4'-0"

5'-0"
INVERT= 506.50
6"

ELEVATION= 506.00

BINDER AND FINISH


ASPHALT TO MATCH
EXISTING PAVEMENT
PW
W
6" 6"

PREPARED FOR:
FINAL BACKFILL

CUDWORTH ROAD LLC


133 PEARL STREET
BOSTON, MA
HDPE PIPE
INITIAL BACKFILL 6"-12" PROJECT:
ABOVE TOP OF PIPE
LOADING DOCK
PE R IMPROVEMENTS
P I TE
D= M E 5 CUDWORTH ROAD
A
DI 1/2" PIPE DIAMETER
WEBSTER, AM
6" GRAVEL BEDDING.

DRAWING:
NOTES:

EXISTING SOIL W= MAXIMUM TRENCH WIDTH


PW= MAXIMUM PAVING WIDTH = W + 1'-0"
NOTES: D= OUTSIDE DIAMETER
UNSHEATHED TRENCH: W= D+2' [3'-0" MIN.]
1. BEDDING AND INITIAL BACKFILL SHEATHED TRENCH: W= D+2'+ SHEATHING
MATERIALS TO BE CLEAN, HARD GRAVEL WIDTH:
4'-0" MIN. w/0 WALERS
w/ 85 % PASSING 38" SIEVE.
5'-0" MIN. w/WALERS
2. BEDDING LAYER TO BE 4" MINIMUM.
TRENCH BOX OR HYDRAULIC SHORING:
3. FINAL BACKFILL TO BE COMPACTED
W= D+2'+ [WALL SHIELD WIDTH +/- 8"] + 1' FOR SCALE: AS NOTED
GRAVEL PER PAVEMENT SECTIONS.
TRENCH BOX.
DATE: MARCH 6, 2020
DRAWING NUMBER

You might also like