DQS251 - Piling - Spun Piles - Tutorial-Drwgs-Dec 2019 - pg11

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

CONFIDENTIAL AP/DEC2019/DQS251

UNIVERSITI TEKNOLOGI MARA


FINAL EXAMINATION

COURSE MEASUREMENT OF CONSTRUCTION WORKS IV

COURSE CODE DQS251

EXAMINATION DECEMBER 2019

TIME 3 HOURS

INSTRUCTIONS TO CANDIDATES

This question paper consists of one (1) question.

Answer the question in the Slip-sort Papers and Schedule Papers.

All measurement shall be in strict accordance with the principles laid down in the Malaysia
Standard Method of Measurement of Building Works (Second Edition) (SMM2).

Do not bring any material into the examination room unless permission is given by the
invigilator.

Please check to make sure that this examination pack consists of:

i) the Question Paper


ii) a six - page Appendix 1
iii) Slip-sort Papers - provided by the Faculty
iv) Schedule Papers - provided by the Faculty
v) an Answer Booklet's Cover - provided by the Faculty
vi) SMM2 - provided by the Faculty

Answer ALL questions in English.

DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO


This examination paperconsists of 2 printed pages
© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL
CONFIDENTIAL 2 AP/DEC 2019/DQS251

QUESTION 1

Based on the drawings and specification notes given in the drawing number
PUB/DQS251/1-6, prepare the followings:

a) Take off quantities for all spun piles using piling schedule.

b) Draft bill of quantities using slip sort for 500mm diameter spun piles only.

You are advised to read the specification notes in the drawings before proceeding with your
taking-off.
(100 marks)

END OF QUESTION PAPER

© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX 1(1) AP/DEC2019/DQS251

Notes

1. Take off all Pre-tensioned Spun Concrete Piles as shown in the drawings.

2. Ground water level established at 3.50m below original ground level on 04 February 2019.
3. 3 nos of boreholes were sunk on the site.

4. The works id about 400.00m from Sungai Tapah.

5. All piles is expected to start from ground level.


6. 1PA denotes as raking piles (1 in 5.6715) and the length is taken the same as 1P vertical piles.
7. The piles shall be supplied of 6.00m (initial pile) and 6.00m (extension pile)
8. 3 Nos. of pile from pile cap 1P shall be used as trial piles.
9. Based level:

1P- 86.00

2P-81.30

3P - 80.70

4P - 82.00

5P - 79.50

6P-76.35

7P - 74.70

8P - 75.00

9P - 73.00

10P- 81.75

PROJECT : DRAWING TITLE : SUBJECT DRAWN BY MONASH

CHECKED BY : NOR FAIZAH


CADANGAN MEMBINA DAN MENYIAPKAN NOTES FOR PILING WORKS MEASUREMENT OF DATE AS SHOWN
SEBUAH KOMPLEKS PENTADBIRAN NEGERI
CONSTRUCTION DATE DECEMBER 2019
MUKIM BAGAN DATUK
TEraOLOGI DAERAH BAGAN DATUK COURSE CODE WORKS IV DRAWING NO. :

PERAK DARUL RIDZUAN DQS251 PUB/DQS251/1

©Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX I (2) AP/DEC2019/DQS251

©Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX I (3) AP/DEC2019/DQS251

NOTES: g ROOF LEV.


5. DRIVING OF PILE SHALL BE BY HYDRAULIC HAMMER.
1. ALL PILE SHOULD BE OF APPROVED TYPE Of
-COLUMN TO DETAIL -COLUMN TO DETAIL DRIVING PILE MUST BE IN VERY CONTROL MANNER,
a & 350mm DIA. 400mm DIA. 4 500mm DIA. SPUN
CAREFULL OBSERVATION SHALL BE CARRIED OUT
PILE ; GRADE 80 PILES CLASS C. ON THE EXISTING STRUCTURES DUE TO PILE DRIVING
RNISH GRD LVL RNISH GRD LVL GRD LEVEL 2. PILES SHALL COMPLY WITH B.S. 8004 1986 BRITISH ACTIVITIES.
GRD LEVEL
mm STANDARD CODE OF PRACTICE FOR FOUNDATION
GROUND BEAM 1 GROUND BEAM 6. ALL WELD TO BE PENETRATED WELDS AND WELDING
AND MS 1314: PART 4 : 2004.
OF STEEL GRADE 50B TO B.S 4360 SHALL COMPLY
3. THE DESIGN WORKING LOAD FOR EACH PILE IS TAKEN WITH BS 5135.
i STUMP- -3T10 STUMP — -3TI0
AS 500 KN ( 50 TONNE). 7. ELECTRODES USED FOR ALL WELDING SHALL COMPLY
4. PILE TO BE TESe TILL TWICE ITS WORKING LOAD WITH BS 639,1976.
-6T20 B/W -6T20 B/W
OF 1000 KN (100 TONNE). BY MAINTAINED LOAD
Hu -50mm THK. LEAN
a -50mm THK. LEAN
TEST AFTER 28 DAYS DRIVEN OF PILE (FRICTION PILE).
8. ALL PILE JOINT SHALL BE PAINTED WITH EPOXY PAINT
FOR CORROSION PROTECTION.
i^r V3RD.,m,5KFLR. LEV.
CONCRETE CONCRETE

-0350 SPUN PILES TO -«50 SPUN PILES


BE DRIVEN36m LENGTH

0350-1P

-COLUMN TO DETAIL
-COLUMN TO DETAIL

RNISH GRD LVL ,,,..ip LEVEL


RNISH GRD LVL GRD LEVEL mm®
GROUND BEAM
GROUND BEAU

T12-200 c/c STUMP- r-5T12 a T12-200 c/c V2N0. FLR.LEV.


STUMP— r -5T12

-14T25
-13T25
-14T25 B/W

_50mm THK. LEAN £r 50mm THK. LEAN


T
CONCRETE
CONCRETE
-0400 SPUN PILES
-0350 SPUN PILES

035O-3P 04OO-4P
y 1ST. FLR. LEV.
VARIES ]_ GRD. LEV.
800 2000
50mm THK. LEAN
CONCRETE 400 , 600 600 . 400
I
0350 SPUN PILES

035O-2P 4' 44-} 4+-} ,450 Mir 450 MIN


8

2000
1
-H—
1
L.__
JXL
400 , 600 600 , 400
( 44)
^ i
44-} S CO
i
CO DvJ) OJI tX.1

44-}
4-+A. _ 4- - 4-+-y 400 | 600 1 600 I 400 4> TYPICAL COLUMN DETAILS
(NOT TO SCALE)
2000

PROJECT : DRAWING TITLE : SUBJECT DRAWN BY MONASH

CHECKED BY : NOR FAIZAH


CADANGAN MEMBINA DAN MENYIAPKAN PILE CAP DETAIL -1 MEASUREMENT OF DATE : 1 : 50
SEBUAH KOMPLEKS PENTADBIRAN NEGERI
UMjWERSITI MUKIM BAGAN DATUK
CONSTRUCTION DATE : DECEMBER 2019

TElOfOLOGI DAE RAH BAGAN DATUK COURSE CODE : WORKS IV DRAWING NO. :

PERAK DARUL RIDZUAN DQS251 PUB/DQS251/3

©Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX I (4) AP/DEC2019/DQS251

-COLUMN TO DETAIL -COLUMN TO DETAIL

RNISH GRD LVL RNISH GRD LVL GRD LEVEL


GRD LEVEL GRD LEVEL
GROUND BEAM GROUND BEAM

T12-200 c/c STUMP- -5T12 T12-200 c/c STUMP — -5T12 T12-200 c/c

-22T25
17T25 B/W t=f -22T25
-14T25 -19T25

50mm THK. LEAN


ry?«Egy^v:M.:r^r->.' BBMBBEBBMHBgB -50mm THK. LEAN spi -50mm THK. LEAN
CONCRETE
CONCRETE CONCRETE
0400 SPUN PILES -0400 SPUN PILES -0500 SPUN PILES

NOJESl
05OO-7P 1. ALL PILE SHOULD BE OF APPROVED TYPE OF
04OO-5P 04OO-6P
350mm DIA. 400mm DIA. 4 500mm DIA. SPUN
3200 PILE ; GRADE 80 PILES CLASS C.
400 200 400 600 , 600 . 400 ,200 400 2. PILES SHALL COMPLY WITH B.S. 8004 1986
2500 BRITISH STANDARD CODE OF PRACTICE FOR
400 , 850 850 , 400 3200 i i i i i i i FOUNDATION AND MS 1314: PART 4 : 2004.
400 1200 1200 400 3. THE DESIGN WORKING LOAD FOR EACH PILE
IS TAKEN AS 500 KN ( 50 TONNE).
4. PILE TO BE TESTED TILL TWICE ITS WORKING
LOAD OF 1000 KN (100 TONNE). BY MAINTAINED
4-i.L LOAD TEST AFTER 28 DAYS DRIVEN OF PILE
4-4} 44-} 4-+-} (FRICTION PILE).
5. DRIVING OF PILE SHALL BE BY HYDRAULIC HAMMER.
! DRIVING PILE MUST BE IN VERY CONTROL MANNER,
4-4--} —i— CAREFULL OBSERVATION SHALL BE CARRIED OUT ON
i THE EXISTING STRUCTURES DUE TO PILE DRIVING
ACTIVITIES.

4-4-} 4-4} 4-4} 6. ALL WELD TO BE PENETRATED WELDS AND WELDING


OF STEEL GRADE 50B TO B.S 4360 SHALL COMPLY
*4-> 44-} WITH BS 5135.

7. ELECTRODES USED FOR ALL WELDING SHALL COMPLY


WITH BS 639,1976.
400 600 600 400 8. ALL PILE JOINT SHALL BE PAINTED WITH EPOXY PAINT
FOR CORROSION PROTECTION.

PROJECT : DRAWING TITLE : SUBJECT DRAWN BY MONASH

CHECKED BY NOR FAIZAH


CADANGAN MEMBINA DAN MENYIAPKAN PILE CAP DETAIL - 2 MEASUREMENT OF DATE 1 : 50
SEBUAH KOMPLEKS PENTADBIRAN NEGERI
MUKIM BAGAN DATUK CONSTRUCTION DATE DECEMBER 2019

TEKMOLOOI DAE RAH BAGAN DATUK COURSE CODE WORKS IV DRAWING NO. :

PERAK DARUL RIDZUAN DQS251 PUB/DQS251/4

© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX I (5) AP/DEC2019/DQS251

-COLUMN TO DETAIL -COLUMN TO DETAIL -COLUMN TO DETAIL

RNISH GRD LVL RNISH GRD LVL RNISH GRD LVL GRD LEVEL
, GRD LEVEL GRD LEVEL
BEAM GROUND BEAM GROUND BEAM

STUMP — i—6T12 T12-2O0 c/c STU! -6T12 T12-200 c/c STUMP— -6T12 -T12-200 c/c
J.

Ml B I f=4^F? -30T25
-19T25
m -22T25
-19T25
-22T25 B/W

-50mm THK. LEAN j@ - WV^.W-T'.^ff. -50mm THK. LEAN -50mm THK. LEAN
ipl set
CONCRETE CONCRETE CONCRETE
-0500 SPUN PILES
-0500 SPUN PILES -0500 SPUN PILES

05OO-9P
0500-1 OP 05OO-8P
NOTES:
3200 1. ALL PILE SHOULD BE OF APPROVED TYPE OF
4400 3200 400 1200 1200 400 350mm DIA. 400mm DIA. 4 500mm DIA. SPUN
400 200. 400 400 1200 1200 400 PILE ; GRADE 80 PILES CLASS C.
400 200 400 600 600 , 600 600
2. PILES SHALL COMPLY WITH B.S. 8004 1986
TT BRITISH STANDARD CODE OF PRACTICE FOR
-k .k -k FOUNDATION AND MS 1314: PART 4 : 2004.
-k -k ^k ^k 44-} 4-+-} 4-4-} 3. THE DESIGN WORKING LOAD FOR EACH PILE
4-4} 44-} 4-4-} 4-+-} ^iy
r
V-L^
r
VJ_^
r IS TAKEN AS 500 KN ( 50 TONNE).
v Ls V_L^ ^.J_^
r r t 4. PILE TO BE TESTED TILL TWICE ITS WORKING
LOAD OF 1000 KN (100 TONNE). BY MAINTAINED
LOAD TEST AFTER 28 DAYS DRIVEN OF PILE
^k i /.u i ^k -k A -k (FRICTION PILE).
4-+-} —H— 4-4--} —l._ 4-+-} 44-} 4-+-} 4-4} 5. DRIVING OF PILE SHALL BE BY HYDRAULIC HAMMER.
v.lV
r 1 V i V v_Lv
r
v.L''
r
^Ls
t DRIVING PILE MUST BE IN VERY CONTROL MANNER,
CAREFUL! OBSERVATION SHALL BE CARRIED OUT ON
THE EXISTING STRUCTURES DUE TO PILE DRIVING
ACTIVITIES.
-k A* ^k ^k
4-4-} 4-4} 4-+-} 4-+-} -k .k -k
6. ALL WELD TO BE PENETRATED WELDS AND WELDING
OF STEEL GRADE 50B TO B.S 4360 SHALL COMPLY
v V V 4-+-} 4-4--} 4-4} WITH BS 5135.
V V V 7. ELECTRODES USED FOR ALL WELDING SHALL COMPLY
400 600 600 600 600 400 WITH BS 639,1976.
1200 1200 1200
8. ALL PILE JOINT SHALL BE PAINTED WITH EPOXY PAINT
FOR CORROSION PROTECTION.

PROJECT : DRAWING TITLE : SUBJECT : DRAWN BY : MONASH

CHECKED BY : NOR FAIZAH


CADANGAN MEMBINA DAN MENYIAPKAN
PILE CAP DETAIL - 3 MEASUREMENT OF DATE : 1 :50
SEBUAH KOMPLEKS PENTADBIRAN NEGERI
UMHVERBra MUKIM BAGAN DATUK CONSTRUCTION DATE : DECEMBER 2019

TE1MOL0OI DAERAH BAGAN DATUK COURSE CODE : WORKS IV DRAWING NO. :

PERAK DARUL RIDZUAN DQS251 PUB/DQS251/5

©Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL APPENDIX I (6) AP/DEC2019/DQS251

t'mm Thick

16mm Thick M.S.

DIIC PAD

10mm Thick Fillet sni , \ */1/ "\


V CUT OF LEVEL
\\ -4/
L
8
ELEVATION ^ .
.•c SOFFIT OF PILECAP
* . '« '
WTB • „"•.• *"«!'
*i •:;'.'. "s :>:" V
M
PLAN • •'. A

NOT TO SCALE
Pin 9f)0 r/r
* A
•. \1. •'•• 8
PILE SHOE DETAILS - CROSS FIN SHOE m

DETAIL 'Y'
(All dimensions are in mm) NOT TO SCALE ''"'"

4*'- .
Pile CO d s h t D
9Snmrn<a 9PIIN Pll F
16 10 350 WELD ED TO PLATE
350 350 50 .'• • • '• a •

400 400 16 50 10 400


500 500 16 50 10 500 UPPER PILE STEEL BAND
1 >.0mm THK. M.S PLATE AS FORMWORK
SEE DETAIL V
A • "0 RECEIVE IN-SITU CONCRETE PLUG
6mm THK. FILLET WELD All ROUND
V
END PLATE -^22 DEGRE DETAIL FOR PILE DOWEL BAR
END PLATE RQNFORCING BAND NOT TO SCALE
150 X 300 X 12.7

BUTT WELD ALL ROUND


UPPER PILE LOWER PILE STEEL BAND NOTES:
EFFECTIVE THROAT 9mm THK.
1. ALL PILE SHOULD BE OF APPROVED TYPE OF 350mm DIA.
A 400mm DIA 4 500mm DIA SPUN PILE ; GRADE 80
END PLATE PILES CLASS C.
DETAIL Z
2. PILES SHALL COMPLY WITH B.S. 8004 1986
SEE DETAIL ~Z NOT TO SCALE
BRITISH STANDARD CODE OF PRACTICE FOR FOUNDATION
AND MS 1314: PART 4 : 2004.

RQNFORCING BAND 3. THE DESIGN WORKING LOAD FOR EACH PILE IS TAKEN
150 X 300 X 12.7 AS 500 KN ( 50 TONNE).
4. PILE TO BE TESTED TILL TWICE ITS WORKING LOAD OF
r-250mm 0 SPUN PILE 1000 KN (100 TONNE). BY MAINTAINED LOAD TEST AFTER
28 DAYS DRIVEN OF PILE (FRICTION PILE).
LOWER PILE 5. DRIVING OF PILE SHALL BE BY HYDRAULIC HAMMER.
DRIVING PILE MUST BE IN VERY CONTROL MANNER, CAREFULL
OBSERVATION SHALL BE CARRIED OUT ON THE EXISTING
REINFORCING BAND STRUCTURES DUE TO PILE DRIVING ACTIVITIES.
150 X 300 X 12.7
6. ALL WELD TO BE PENETRATED WELDS AND WELDING OF
STEEL GRADE 50B TO B.S 4360 SHALL COMPLY WITH
BS 5135.

7. ELECTRODES USED FOR ALL WELDING SHALL COMPLY WITH


BS 639,1976.
SECTION A-A 8. ALL PILE JOINT SHALL BE PAINTED WITH EPOXY PAINT
DETAIL OF EXTENSION JOINT FOR CORROSION PROTECTION.
NOT TO SCALE
NOT TO SCALE

PROJECT : DRAWING TITLE : SUBJECT DRAWN BY : MONASH

CHECKED BY : NOR FAIZAH


CADANGAN MEMBINA DAN MENYIAPKAN
PILE CAP DETAIL - 4 MEASUREMENT OF DATE
SEBUAH KOMPLEKS PENTADBIRAN NEGERI : AS SHOWN
UMIVERSITII MUKIM BAGAN DATUK CONSTRUCTION DATE : DECEMBER 2019

Tekmologi DAE RAH BAGAN DATUK COURSE CODE : WORKS IV DRAWING NO. :

PERAK DARUL RIDZUAN DQS251 PUB/DQS251/6

©Hak Cipta Universiti Teknologi MARA CONFIDENTIAL

You might also like