Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

AIAA 94-3065

ARIANE 5 MPS Igniter


Subsystem - Design
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

Approach and Development


Phase Results
M. Santilli
EUROPROPULSION (F)
A. Fontana
BPD Difesa e Spazio (I)

30th AIANASMEISAWASEE Joint


Propulsion Conference
June 27-29, 1994 / Indianapolis, IN
~r permission to copy or republish, contact the American Institute of Aeronautics and Astronautics
370 L'Enfant Promenade, S.W., Washington, D.C. 20024
diameter (656 m n is the flange maximum main difference is that the contrast
diameter). is not realized by the metallic
projection of the two items to be
assembled, but by means of a suitable
circular metallic ring, which has the
function to block any possible
movement of the items in the axial
direction.
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

Pig. 1 - Assembled igniter

The final configuration was chosen


after a trade off among different
configurations, being strict Pig. 2 - Lock-wire junction
requirements imposed at design level
as far as geometric dimensions and This ring is made up of two bands to
igniter assembling sequence are be inserted, one by one, in a suitable
concerned. In particular, as to the window realized on the igniter flange,
integration, the most logical solution thus realizing the junction between
seemed to be a bolt junction the main basket and the flange. The
(configuration referred to as 'Bolts most important advantage obtained with
configuration'), in which the junction this type of junction is the increase
-./ of the main igniter metallic case and of the contrast area respect to the
the flange was accomplished by means traditional 'bayonet junction'. The
of 40 bolts. This solution was increased contact area, in fact,
rejected because of the thermal allows to distribute the interface
protection cold bonding, necessary to loads and to reduce the local stresses
cover the bolt junction after the of the material, thus resulting in
final assembling; the reliability of higher safety factors during the
this particular operation was not in functioning. Furthermore, the ring is
accordance with the final reliability not a critical item because it is
goal of the ARIANE 5 igniter. submitted to compression loads only.
Stress analyses (later on confirmed by The main charge case (see Fig. 3 ) has
hydraulic tests) and the above a cylindrical shell threaded to a
mentioned problems in the thermal hemispherical dome in which five
protection application led to the regularly spaced holes (450 respect to
design of the present configuration the longitudinal axis) are the seats
(referred to as 'Lock-wire', Fig. 2 ) . for the outlet carbon-phenolic
This junction was utilized for the nozzles.
first time by BPD on military The intermediate case is very similar
applications (torpedo) and it may be but smaller in size: it is threaded to
considered similar to the 'bayonet the igniter flange. Like in the main
junction': in fact, its functioning is igniter, five small holes are machined
based on the same logic, i.e. in the dome representing the seat for
"metallic contrast between two the carbon-phenolic nozzles.
different items capable of maintaining The pyrotechnic cylindrical basket,
themselves in proper position". The threaded to the body, has a flat
^i
2
ARIANE 5 MPS P230 - IGNITION SYSTEM

M. Santilli', A. Fontana**

Abstract reliable, and safe ignition of t h e w


relevant launcher (in a two-booster
This paper deals with the steps launcher this ignition must be
performed to develop the ARIANE 5 MPS simultaneous as far as possible):
P 2 3 0 igniter. In a solid propellant
rocket motor, a satisfactory therefore, the igniter is required for
attainment of equilibrium chamber a high mass flow-rate of gases to
pressure and gas flow is dependent on reach the stated rise of temperature
several factors, among which its and pressure, so as to respect the
design characteristics, motor allowable maximum delay between the
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

propellant grain surface ignitability 'Fire" command and the ignition of


within well defined instants of time each of the two MPS boosters.
and heat transfer phenomena are of In order to fulfil these stringent
primary importance. In order to reach functional requirements, the Ariane 5
a frozen configuration fulfilling the
requirements (usually a combination of Igniter is made up of the following
igniter and vehicle requirements), chain of components:
specific pre-development, development
and qualification tests are entailed. no 2 IFOCs (Through Bulkhead
These tests, currently performed at Initiators)
BPD Difesa G Spazio facilities and
aiming to guarantee the high required no 1 Fyrotechnic Igniter
reliability goal are
I mainly
environmental (i. e. leak, thermal and no 1 Igniter Initiator (also
humidity cycles, vibrations and X-Ray) referred to as Intermediate Igniter)
and after firing (previous ones plus
ballistic and structural analysis) no 1 Main Igniter
tests. The methodology used to analyze
the experimental results is based upon in which an Igniter Initiatoi- of
a comparison between these results and reduced size was added to the Ariane 3-
performance predictions, carried out
in terms of chamber pressure and mass and Ariane 4 configurations because it
flow rate data. As expected, the tests can be easily ignited by a small
performed up to now have shown a good charge of pellets placed in the
compliance between predicted Pyrotechnic Igniter; in this way a
performances and experimental results. great reliability and reproducibility
of performances are assured.
Experiences in large solid propellant
General motors (Shuttle, Titan) confirm that
this configuration is the best.
The ignition system of the Ariane 5
MPS P 2 3 0 booster was defined taking
into account the experience acquired Chosen c o n f i a u r a t m
during the development of the previous
Ariane 3 and Ariane 4 ignition The Ariane 5 igniter final
systems. The main duty of each igniter configuration is shown in Fig. 1
is to provide a reproducible, (assembled). It consists of four main
components: a main charge case, an
* EUROPROPULSION - F 921 SO SURESNES (F) intermediate case, the pyrotechnic
System engineer body and basket and the igniter
'* BPD DIfesi & Spnzio - COLLEFERRO (I) flange. The overall dimensions are
Propulsion group engineer 1181 mm in length and 469.5 mm in

1
motor and ignitei- level). That's why,
as far as tests, checks, technologies

-
and approach to the design are
concerned, the qualification phase
will be carried out on the basis of
the same logical principles of the
development one.

Referenceg

Parker, K.H., Wenogard, J. and


Summerfield, M., "The ignition
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

transient in solid propellant


rocket motors", A I P A Paper 64-126,
Solid Proellant Rocket Conference,
Palo Alto, C, Jan. 1964
Erinton, E.C. Kilminster,
J.C. , "Space Shuttle SRM
Development", A I A A Paper 79-1136
Sutton, G.P., "Rocket propulsion
elements", 1996, Wiley
Interscience.
"MPS P230 Technical
specif ication ,
" P.5-ST-1120000-
0609-EUP
more reliable ignition of the attainment of the correct amount of
intermediate igniter. discharged mass flow rate towards the
Once the preliminary firing tests MPS propellant grain (star and
performed, a relevant change of the cylinder shaped): only in this case a
configuration was made by introducing correct and simultaneous ignition can
.*/
a fiber glass external support for be reached, so as to avoid problems
the propellant grain (liner): in of thrust imbalance at ignition.
order to inhibite the rear surface of This target could be reached first of
the propellant grains facing the all by building two limit cases for
thermal protection (so as to prevent the igniter discharged mass flow. The
the hot gases and flames from resulting gabarit shows two curves:
reaching this surface, thus starting an 'upper curve , which
its burning before the complete represents, for each instant of
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

COmbustiOn), to assure a reliable time, the highest value of the


joint between the propellant and the mass flow rate to be discharged;
thermal protection and to prevent higher values would result in
from a too high propellant radial dangerous motor overpressure;
shrinkage after the casting, this a 'lower curve', which represents,
special resin reinforced by for each instant of time, the
fiberglass was designed as the smallest value of the mass flow
interface between the thermal rate to be discharged; smaller
protection and the pi-opellant. values would result in no
Furthermore, this solution allows the ignition.
reduction of the efforts to be These two curves, report.ed in Fig. 4.
exerted in ordert to extract the were obtained by performing a
mandrel after the propellant casting statistical analysis of the
phase, thus reducing also possible parameters which are known to affect
damages on the propellant grain the performances: the propellant
surface (advantages in terms of costs geometry (represented by the
during the industrialization phase). combustion surface), the propellant
At present, the described burning rate and characteristic
~~ ~

configuration fulfils the velocity (and the relevant efficiency


requirements imposed by the MPS on the characteristic velocity), the
Technical specification and Igniter propellant density, erosion
Techincal Specification, above all phenomena, firing temperature, delay
given in terms of: of time at ignition and s o on, were
thrust gabarit, i.e. the igniter taken into account at their nominal
must succeed in firing the MPS value (average values of BPD
booster within well def ined database) and a relevant dispersion
instants of time, at which the (30) was also calculated. If n is the
thrust must reach well defined number of the parameters, 2n+l runs
values; of the ballistic code employed at BPD
mass flow rate gabarit, which to analyze transient phenomena were
represents the mount of mass performed: a first run with all the
(minimum and maximum) to be parameters at their nominal value,
discharged in order to fulfil the the other 2n by varying all the
previous requirement. parameters one by one at their
maximum value (nominal + 3 0 ) and
minimum value (nominal - 30). In this
Ballistic behaviow way, a *Ami+' and a ,Ami-, were
obtained as the output of each
As previously stated, one of the most ballistic run, then they were grouped
important requirement to be fulfilled together on the basis of simple
at igniter level, concerns the statistical formulas in order to

4
W
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

Pig. 3 - Igniter exploded v i e w

bottom with five parallel holes for and then machined to the final
the outlet (through the same number thickness and shape.
of small graphyte nozzles) of the The intermediate and main igniter
combustion gases. On the pyrotechnic propellant grains are star shaped (30
body, 5 holes are machined, 2 for the and 25 tips respectively), designed
I F O C s and 3 for the instrumentation. in order to assure the suitable
The igniter flange has an ellipsoidal burning surface for the required mas:
d
shape in order to withstand in a flow rate, to reduce the sliver phase
suitable way the loads of both the of the combustion, to have a
igniter and MPS. In addition to the sufficient structural resistance
junction with the main igniter case, under the chosen internal pressure
it is also connected with the booster and the specific environmental
by means of 4 0 bolts; the tightness conditions. The chosen propellant is
is assured by 2 O-rings. a HTPB polymer (binder) with a high
All these components are made up of amount of aluminium, ammonium
commercial steels with high perchlorate as oxidizer.
characteristics from a stress The pyrotechnic charge is made up of
corrosion point of view (moreover, BKN03 pellets, randomly disposed
they are also zinc-plated for a inside a polyethilene bag placed
thickness of 13 microns), internally inside the basket; a plastic grid
and externally insulated by a keeps the pellets separated from the
variable thickness of thermal discharging nozzles. These nozzles,
protection (an EPDM based rubber once accomplished by machining the
filled with aramidic fibers), in thermal protection to the desired
order to withstand the thermal loads discharging area, are now made up of
during the igniter and the booster graphyte inserts. in order to
functioning. The application is made guarantee a more correct flow of the
with pre-molded layers glued conkustion gases and, thus, a higher
together by vulcanization 'in situ' reproducibilty of performances and a

3
The post firing analysis is carried After these operations, the new
out by making a comparison between obtained values of the ballistic
the predicted and the experimental parameters are taken into account to
pressure curves. increase the available database: new
mean values and dispersions are made,
upon them the next predictions will
u
be based.
m

1' m e r m a l Drotection behaviour

Thermal protections were designed on


1: the basis of BPD know-how and taking
into account the results of the
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

experimental tests. The thickness of


..
0

the external and internal layers was


.
I I
. " an
reduced at various times. Post firing
-I

analyses performed after B1 and M1


Fig. 6 -
Intermediate igniter firing tests showed that the maximum
pressure vs time curve ablated thickness is, on the main
igniter external surface, 358 of the
original one (before firing); this
means that large areas of the applied
thermal protection remains virgin.
At present, even though the thichness
is still oversize, further reductions
are not foreseen, because the gain in
weight is negligible with respect to
the high impacts to face in order to
improve the configuration.

A suitable test plan was made in


order to develop the final
Pig. 7 - Main igniter pressure vs configuration, pointing out the
time curve safety margins relevant to the
following main functions:
Of course, slight differences are to provide a mass flow rate vs
always present and thus the time in accordance with the
parameters from 1 to 3 are employed requirements set forth in the
to obtain the best matching of the Technical Specification;
curves: the scale factor is employed to assure the structural integrity
to tune the pressure during the of the whole motor.
steady phase, the flame spreading The ignition ballistic performances
during the rising phase, the time were analyzed by means of firing
delay is obtained to adjust the tests, while the metallic case
timing. These parameters are strictly structural integrity was checked by
joint one to the other, so that means of:
changing one of them causes the hydraulic burst test, performed on
change of them all: of course this one igniter only. The minimum
loop is generally converging to the pressure value requested to
final solution. validate the item was set to

6
obtain the final * A m + ' and 'Am-' to intermediate igniter and the main
be added or subtracted to the igniter.
nominal mass flow rate (output of the The pyrotechnic igniter has an
impulsive trend: in fact it reaches
the maximum value of the pressure
(ranging from 160 to 200 b a r ) W
generally after 3 4 ms.
The intermediate and the main
igniter, both charged with a star
shaped grain, show the typical
pressure trend of such a grain
configuration: after a very steep
rising phase, in which the most
significant points are 10% of
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

.. ** .n 8.
-lM
.m >. .s ..
111

Pig. 4 Mass flow rate gabarit !a


m
nominal run).
In the above shown Fig. 4 the mass
flow rate gabarit is reported
1:
together with an experimental curve,
in order to show the compliance
i: 0

between the requirement and the m


obtained result.
The attainment of such a compliance
was possible on the basis of a tuning
.DI om om
....
em 0- 0- ow

of the ballistic parameters employed Pig. 5 - Pyrotechnic igniter pressure


to carry out the predictions and the vs time curve
post firing analysis. In more ..&
details, analyses concerning each Pmax and 90% of P , T , ~ X , the maximum
firing test include: pressure is reached (generally after
ballistic predictions; a time ranging from 30 to 40 ms for
post-firing analysis: the intemediate igniter and from 90
database updating. to 110 ms for the main igniter); this
The main parameters (the ones which maximum ranges from 110 to 140 bar
may vary from one firing to the for the intei-mediate igniter and from
other), taken into account in order 85 to 105 bai- f o r the main igniter.
to carry out the ball istic Soon after a steady phase takes
predictions in terms of pressure, place, until the beginning of the
are: tail off phase (S5+120 ms and 330+430
1. burning rate scale fact.or,s.f.: ms respectively for the intermediate
2. flame spreading, f.s.: and the main igniter).
3. time delay, Td; Predictions, based on the Pn,ax, 10%
4 . characteristic velocity Pinax, 90% Pmax. tail off pressure and
efficiency, qc*; the relevant instants of time, are
5. throat diameter; carried out by employing the actual
6 . firing temperature. value of the above reported 6
Figures from 5 to 7 show the typical parameters and their dispersion (ID,
pressure vs . time curves respectively except for the temperature, on which
for the pyrotechnic igniter, the no dispersion is given), so as to
obtained the above mentioned ranges.
PI “ l s r = s . f. X MEOP For the pyrotechnic igniter, the test
where s.f. is the requested ultimate sequence can be summarized as
safety factor. follows :
Success criteria for this test are: before firinq
no structural failure occurs up to 1. Natural Frequency research
4 burst pressure. 2. Transport vibrations
3 . Natural Frequency research
L€Ax 4 . Sinusoidal vibrations
Aim of this test is to verify that 5. Natural Frequency research
the fixed leak rates are sufficiently 6. Random vibration
small to guarantee the sealing I. Natural Frequency research
function during all the phases of the gfter f a
igniter life. The items or interfaces 1. Natural Frequency research
to be tested are protection plugs 2 . Sinusoidal vibrations
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

(the pyrotechnic igniter is 3. Natural Frequency research

-
transported separately from the main 4 . Random vibrations
igniter and thus it is replaced by 5. Natural Frequency research
these plugs), the nozzle diaphragms, For the intermediate, and main
the IFOC/pyrotechnic body I igniters, the test sequence can be
pyrotechnic body/flange and summarized as follows:
flange/main basket interfaces.
Success criteria are: 1. Natural Frequency research
no leak rate higher than the 2 . Transport vibrations
required one is measured. 3 . Natural Frequency research
after fir-
Vibrations 1. Natural Frequency research
Vibration tests are performed in 2. Sinusoidal vibrations
order to prove the item capability to 3 . Natural Frequency research
withstand the dynamic: loads (induced 4. Random vibrations
on the igniter during the various 5 . Natural Frequency research
phases of its operative life) without These vibrations are performed within
performance or material degradation. well defined frequency bands and
The items under investigation are: giving, along the excitation axis,
the pyrotechnic ignitei- (assembled suitable peak accelerations and
with IFOCs and pressure sweeping rates (in the case of random
transducers). vibrations the acceleration spectral
the intermediate igniter is tested density is given); amplification
assembled on the actual flange, in factors are then calculated as the
two different configurations: ratio between the input g-peaks and
transport configuartion (without the output ones (along the three
pyrotechnic igniter, which is axes). Resonance frequencies were
transported separately) and before found around 90 and 500 Hz, while the
and aftex- firing test maximum amplification factor turned
configuration (assembled with out to be 20 (obtained when the input
completely instrumented and the output axis are the same, in
pyrotechnic charge); all the other cases amplification
the main igniter is tested in two factors are lower).
different configurations: Success criteria of these tests are:
transport configudrtion (without no rupture occurs in the metallic
pyrotechnic igniter, which is parts or in the propellant grain;
transported separately) and before output signals (in terms of g-
and after firing test peak) must not be. greater or
configuration (assembled with equal to the dimensioning static
completely instrumented flange). loads;

9
no crack increase in the metallic
parts or in the propellant grain S a l t foa test
is detected; This test is performed on all the
no unbonding increase between metallic parts in order to verify the
thermal protection and case (or behaviour of the zinc superficia:
nozzles) is detected. treatment, which must be able t o w
prevent the base metal from getting
mermal cvcles attacked by extreme environments,
Thermal cycles are performed in order which are likely to be found in
to verify the material behaviour (in French Guyana.
particular all the bondings) , Success criteria are:
physical damages and degradation of no corrosion attack at the base '

performances when the igniter is metal is detected;


submitted to a temperature variation. no failure of structural parts due
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

In more details, thermal cycles are to stress corrosion occurs.


carried out by using two conditioned
chambers (each of them has a Visual/dimensional insDection8
continuous recording device for Each sub-assembly, before being
temperature vs time), the first assembled, is carefully examined to
regulated at 0 2 3 T and the other at determine the dimensions, the quality
+40+3 O C . Two complete cycles 0+40 OC of the activities carried out by the
over a period of 4 5 houi-s are operators, the use of proper material
performed. P. minor group of igniters and the visible defects or any other
undergoes thermal shocks, during imperfection.
which two complete cycles -20+40 O C
over a period of 4 8 hours are BadioaraDhic test (X-ravl
performed. Each sub-assembly, in order to verify
Success criteria are: the internal interfaces and sub-
no unbonding between metallic assembly status, undergoes
parts/thermal protect ion is radiographic inspections. A technique
detected ; capable of showing possible interna!
no unbonding between propellant grain defects or unbonding betweer.-
grain/thermal protection is metallic parts/thermal protection and
detected ; thermal protection/propellant grain
no rupture in the propellant gi-air, is employed.
is detected.

Humiditv cvcles Conclusiou


Humidity cycles are performed in
order to verify material behaviour, The ARIANE 5 MPS P230 ignition system
physical damages and degradation of has been completely developed. After
performances when the igniter is a Critical Design Review, the
submitted to extreme environments, development phase has come to an end,
which are likely to be found in while the qualification phase is
French Guyana. The test conditions about to start at igniter level only
are: temperature 30uCS0C, 1-elative (tests to be performed in EPD). The
humidity 9 5 % 5 % , time 2 4 h, 1 cycle logical principles underlining the
only. design, tests and checks performed
Success criteria are: during the pre-development and
no corrosion attack at the development phases, the employed
metallic parts is detected; technologies and production cycles
no unbonding between propellant proved to be successfull, on the
grain/thermal protection is basis of the obtained results
detected. (compliance with the requirements at

10 'ci
to verify, from a reliability X-ray inspections;
point of view, the behaviour of visual inspections.
the ignition system;
to make the final tuning of those
parameters, whose influence on the Test descriDtiQQ
.-, performances is great;
to perform tests and checks proof t e s t .
already performed during the As above reported, tests are
previous phases, according to a performed by the metallic part
slightly modified logic: tests and supplier in order to detect possible
checks which showed a low impact cracks in the steel; these tests are
on the performances will be performed, after the forging
reduced. operation, with Ultra Sound system,
Of course, during this phase, only able to detect a well defined minimum
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

slight modifications to the crack size; after the final machining


configutation are likely to be made, piercing 1iquids and X-ray
without altering the general design. inspections are performed in order to
The qualification phase of the detect possible superficial cracks.
igniter, to be performed at BPD The proof acceptance test is
plants. will give the go-ahead for performed only on the metallic parts.
the full scale qualification tests, Aim of this test is to check the
to be performed the next year on at. mechanical properties of the item
least two motors. These full scale under investigation, in order to meet
tests complete the whole the relevant functional requirement,
qualification phase of both the motor which states that the igniter must
and the igniter. withstand the mechanical loads
induced by its and MPS functioning.
This test is performed by
Tests and checks pressurizing each metallic sub-
assembly with emulsified water up to
During the pre-development and the the proof pressure, which is:
development phases, the following P ~ > r v >=f S . f . X MEOP
tests and inspections were carried where s.f. i s the requested safety
out before and after each firing factor and the MEOP is defined
test : according to the propellant grain
tests performed by the metallic configuration. This pressure is kept
part supplier to detect possible for a holding time of 120,180 sec.
defects of the steel; Success criteria for this test are:
hydraulic test; no leak is detected up to proof
dimensional inspect ions, in order pressure;
to verify the geometric compliance no permanent deformation greater
with the design requirements than 0.2% is detected up to proof

-
(before and after hydraulic and/or pressure.
burst test);
environmental tests (thermal and Burst test
humidity cycles, salt fog test, Aim of this test, is to verify that
vibrations), some Of them the mechanical properties of the item
performed before and after the under investigation fulfil the
firing test; requirement on the ultimate safety
8 leak tests, in oredr to verify the factor.
tightness requirement after the This test is performed by
assembling phase and the case pressurizing each metallic sub-
behaviour before and after firing assembly up to the burst pressure,
vibration tests. which is:

8
2xMEOP. wher MEOP stands for ballistic code, already employed for
Maximum Expected Operating P.RI?.NE 3 and f.RIANE 4 igniters, was
Pressure; definitively tuned.
hydraulic acceptance test for each
igniter sub-component, by means of
proof test at a pressure of pevelopment Dhase
1.3xMEOP; u
pre-firing vibration test (random The aim of this phase was:
and sinusoidal fi-equencies, plus to submit all the sub-components ,
natural frequency research), to all the structural, ballistic
simulating the acoustic loads and environmental tests above
induced by the motor functioning described. Firing tests at
(booster MPS P230 plus WLCAIN different temperatures were
motor) ; performed once again in order to
Ultra sound, piercing liquids and evaluate the effects of a
Downloaded by VIRGINIA TECHNICAL UNIVERSITY on November 11, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.1994-3065

Rx inspections. temperature variation (coupled


Besides, in order to simulate all the with a variation of the nozzle
stresses induced during the transpoi-t throat diameter plus the variation
and the storage phases,. each igniter of the propellant bur,ning rate) on
of the development phase iindei-went the ballist ic performances,
the following tests: expecially on the mass flow rate,
thermal cycles; whose values must fall inside the
humidity cycles; well defined range set forth in
salt fog tests; the Technical Specification;
transport vibrations. to analyze the results of each
The capability of t.he igniter to seal test in comparison with both the
the whole struct,ure was proved by ballistic performance predictions
means of: and the outcomes of the structural
leak tests (to be performed before analysis;
and after firing). to make all the possible
The main goals of the test plan were modifications to the design. In
attained in three different st.eps, fact, during this phase, th6
i.e. the pre-development, the configuration was not yet f r o z e n , U
development and the qualification thus, once the ballistic.
phases (still in progress). structural and thermo-ablative
critical points individuated, they
were one by one re-designed;
Pre-develoDment phase to fix all the aspects relevant to
the industrialization phase of the
The aim of this phase was the igniter and in particular to make
analysis of the requirements imposed the maximum effort to finalize the
by the applicable Technical objective costs to be reached;
Specification, the pi-eliminary design to investigate the igniter
of all the components with the behaviour on full scale tests, in
relevant ballistic and structural which the igniter itself is fired
calculations and a preliminary with the MPS P230 booster, thus
testing of the chosen configuration. checking the behaviour of the
In particular, firing tests performed interface.
at different temperatures plus post
firing test analyses aimed to verify
the ballistic characteristics and the Qualification Dh ase
behaviour of the components submitted
to the loads induced during the The aim of this phase is:
burning phase of the igniter. The

You might also like