Professional Documents
Culture Documents
Level 1.1
Level 1.1
GOOD LUCK !
1.
2. Write procedures of laying of rising main pipes in a water supply project. (10%)
Procedures of Laying of pipes
Setting out alignment of pipes
Excavation for laying of pipes and precautions to be observed
Handling, lowering, laying and jointing of pipes
Testing of pipe lines
Back filling and restoration to original surface
3.
4. Estimate the quantities of brickwork and plastering required in a wall 4 m long, 3 m high and
30 cm thick. Calculate also the cost if the rate of brickwork is 320.00birr per cu m and of
plastering is 8.50 birr per sq m. (20%)
Quantity of brickwork = L x B x H = 4 m x 3 m x .30 = 3.6 cu m. Quantity of plastering (two
faces) = 2 x Lx H = 2 x 4 m x 3 m = 24 sq m Cost of brickwork = 3.6 x 320.00= 1152.00 birr.
Cost of plastering = 24 x 8.50 = 204.00 birr
Total cost = 1152.00 +204.00 =1356.00birr.
5. Given 10m3 Concrete C – 20 Mechanical mixes with mix ratio 1:2:4. Assuming that 30%
shrinkage and 5% wastage and also take density of cement as 1400kg/m3.
a. Calculate the amount of cement required to make 10m3 of 1:2:4 concrete in kilograms
(10%)
b. Calculate the volume of sand in cubic meter (10%)
c. Calculate the volume of gravel (crushed stone) in cubic meter. (10%)