Cost Estimate Khupi
tonne.
(i) Surfaced Road 2.60
km
tonne.
(ii) Unsurfaced Gravelled Road 3.20
km
tonne.
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. 6.30
km
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees,
2.1 including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable
material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.)
Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps
2.3 of trees cut earlier and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned up to a lead of 1000 metres including removal and disposal
of top organic soil not exceeding 150 mm in thickness.)
1000
B In mud mortar numbe 235.00
rs
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 264.00
B In Mud mortar cum 56.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 9.00
Removing all type of hume pipes and stacking within a lead of 1000 metres including
(ix)
earthwork and dismantling of masonry works.
A Up to 600 mm dia metre 97.00
B Above 600 mm to 900 mm dia metre 131.00
C Above 900 mm metre 224.00
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of
2.5 dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately)
I By Manual Means
A Bituminous courses cum 450.00
B Granular courses cum 334.00
II By Mechanical Means
A Bituminous course cum 233.00
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including
posts, foundation concrete, back filling of pit by manual means including disposal of
2.11 metre 29.00
dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately. )
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including
2.12 disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and metre 77.00
unserviceable material separately under supervision of concerned department)
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of
sewer gutter 1500 mm dia under the supervision of concerned department including disposal
2.13 metre 107.00
with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable
material separately but excluding earth excavation and dismantling of masonry works.)
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles
including excavation and dismantling of foundation concrete and lines under the supervision
2.14 each 105.00
of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking
the serviceable and unserviceable material separately)
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means
3.1 including loading in truck for carrying of cut earth to embankment site with all lifts and lead cum 102.00
upto1000 metres.)
Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual
3.2 means including loading in a truck and carrying of excavated material to embankment site cum 141.00
with in all lifts and leads upto 1000 metres )
Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by
mechanical means including cutting and pushing the earth to site of embankment upto a
3.3 cum 154.00
distance of 100 metres (average lead50 metres), including trimming bottom and side slopes
in accordance with requirements of lines, grades and cross sections.)
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in
ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site
3.4 cum 259.00
of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom
and side slopes in accordance with the requirements of lines, grades and cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of
3.5 cum 174.00
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000 metres )
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000
metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity
3.6 including cutting and loading in tippers, trimming bottom and side slopes, in accordance with cum 45.00
requirements of lines, grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m)
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto
1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum
3.7 bucket capacity including cutting and loading in tippers, transporting to embankment site cum 59.00
within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting
prohibited) with rock breakers including breaking rock, loading in tippers and disposal
3.8
within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance
with requirements of lines, grades and cross sections.)
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of
3.9 cum 230.00
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000 metres )
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9
cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and
3.10 cum 50.00
lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements
of lines, grades and cross sections.)
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil
3.11 including excavation, loading and disposal upto 1000 metres lead but excluding replacement cum 45.00
by suitable soil which shall be paid separately as per clause 305.)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of explosives and blasting accessories in
3.12 properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, sqm 131.00
loading in tipper by a front end loader and disposing of the material with all lifts and lead
upto 1000 m, all as specified in clause No. 303)
Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of
top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading
3.21 cum 92.00
and re-laying after taking the borrow earth to maintain fertility of the agricultural field,
finishing it to the required levels and satisfaction of the farmer.)
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on
3.22 embankment slope, verges or other locations shown on the drawing or as directed by the sqm 30.00
engineer including preparation of ground, fetching of rods and watering)
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and
placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate
3.23 sqm 99.00
of0.23 litres per sqm and laying and fixing jute netting, including watering for 3 months all as
per clause 308)
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area
0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause
3.24
301 and 309. Excavated material to be used in embankment within a lead of50 metres
(average lead 25 metres))
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as
3.25
per approved design and to the requirement of clause 301 to 309. Excavated material to be
used in embankment at site.)
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm
3.28 metre 130.00
with aggregates conforming to table 300-4, excavated material to be utilised in roadway )
Construction of Rock fill Embankment (Construction of rock fill embankment with broken
hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick
3.31 cum 52.00
including filling of surface voids with stone spalls, blinding top layer with granular material,
rolled with vibratory road roller, all complete as per clause 313)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by
3.32 (i) mechanical means including cutting and trimming of side slopes and disposing of excavated cum 104.00
earth with all lifts and lead upto 1000 metres)
Depositing of excavated earth on the barren valley side. (Excavation in soil in hilly area by
3.32 (ii) mechanical means including cutting and trimming of side slopes and disposing of excavated cum 60.00
earth on the Barren Valley side)
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.
(Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means
3.33 (i) cum 155.00
including cutting and trimming of slopes and disposal of cut material with all lift and lead
upto 1000 metres )
Disposal of excavated earth on the barren valley side. (Excavation in hilly area in ordinary
3.33 (ii) rock not requiring blasting by mechanical means including cutting and trimming of slopes and cum 92.00
disposal of excavated earth on the barren valley side)
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard
3.34 rock requiring blasting, by mechanical means including trimming of slopes and disposal of cut cum 219.00
material with all lifts and lead upto 1000 metres.)
Excavation in Hilly Areas in Soil by Manual Means (Excavation in soil in Hilly Area by Manual
Means including cutting and trimming of side slopes and disposing of excavated earth with a
3.35 (i) A cum 94.00
lift upto 1.5 m and a lead upto 20 m as per drawing and Technical Specification Clause
1603.1)
Deduct for quantum of earthwork of all types disposal directly by throwing into the valley
3.35 (i) B without involving any lead and lift (Ordinary and Hard Soil/Hard Shale, Soil containing shingle cum 35.00
or small size boulders.
Excavation in Hilly Area in Ordinary Rock by Manual Means (Excavation in Ordinary Rock using
3.35 (ii) A Manual Means including loading in a truck and carrying of excavated material to embankment cum 206.00
site with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2.)
Deduct for quantum of earthwork of all types disposal directly by throwing into the valley
3.35 (ii) B cum 57.00
without involving any lead and lift. (Ordinary and Hard Rock)
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading
A
in uniform layers with motor grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per clause 401 )
Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of granular
sub-base by providing coarse graded material, spreading in uniform layers with motor grader
4.2
on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting
with vibratory roller to achieve the desired density, complete as per clause 401)
Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade
on a prepared surface, pulverising, mixing the spread soil in place with rotavator with 3 %
4.3 slaked lime having minimum content of 70% of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density to form a layer of improved
sub grade)
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime with minimum
4.4 cum 639.00
content of 70% of CaO, grading with motor grader and compacting with the road roller at
OMC to achieve at least 98%of the max dry density to form a layer of sub base.)
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub
grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place
4.5 cum 677.00
with rotavator, grading with the motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)
Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of
specific sizes to water bound macadam specification including spreading in uniform
4.9 thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade
and camber, applying and brooming requisite type of screening/ binding Materials to fill up
the interstices of coarse aggregate, watering and compacting to the required density.)
A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1359.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1613.90
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1622.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1746.00
(c) Using Screening Type-B (11.2mm Agg.) cum 1842.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1622.00
(b) Using Screening Type-B (11.2mm Agg.) cum 1842.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1296.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1550.11
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1558.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1682.00
(c) Using Screening Type-B (11.2mm Agg.) cum 1778.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1558.00
(b) Using Screening Type-B (11.2mm Agg.) cum 1778.00
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in
4.10 table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at cum 204.00
a lead of L km., laying and compacting the same as sub base/ base course, constructed as
WBM to clause 404 except the use of screening or binding Material.)
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen
over cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by
4.11 sqm 23.00
a bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10
sqm by a mechanical gritter and rolling the surface as per clause 506.3.8)
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to
wet mix macadam specification including premixing the Material with water at OMC in
4.12 mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers cum 1349.00
with paver in sub- base / base course on well prepared surface and compacting with
vibratory roller to achieve the desired density.)
Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of
Median and Island above road level with approved material deposited at site from roadway
4.13 cum 194.00
cutting and excavation for drain and foundation of other structures, spread, graded and
compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median
4.14 and Island above road level with approved material brought from borrow pits, spread, sloped cum 214.00
and compacted as per clause 407)
4.15 Construction of Shoulders (A. Earthen Shoulders)
Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared
4.17 surface by hauling vehicles, spreading and mixing with a motor grader, watering and
compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base)
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface
5.1 of granular Base including clearing of road surface and spraying primer at the rate of 0.60 sqm 25.00
kg/sqm using mechanical means.)
5.2 Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor
at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with sqm 9.00
mechanical broom.
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of
5.3 specified grading premixed with bituminous binder, transported to site, laid over a previously
prepared surface with paver finisher to the required grade, level and alignment and rolled as
per clauses 501.6 and 501.7 to achieve the desired compaction)
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared
base consisting of a two layer composite construction of compacted crushed coarse
aggregates using motor grader for aggregates. key stone chips spreader may be used with
5.5 sqm 263.00
application of bituminous binder after each layer, and with key aggregates placed on top of
the second layer to serve as a Base conforming to the line, grades and cross-section
specified, the compacted layer thickness being 75 mm)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by
5.6 weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction
as per MoRTH specification clause No. 507 complete in all respects.)
Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix
5.7 and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification
clause No. 508 complete in all respects)
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve
5.10
as wearing course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and
grades.)
Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate
(i) sqm 291.00
capacity not less than 75 tonnes/hour .
(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 126.00
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of
appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-
graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm
5.11 (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to sqm 147.00
the required line, grade and level to serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10
tonne capacity, and finishing to required level and grade. )
Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the
5.12
specified levels, grade and cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 48.00
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate
(ii) capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and sqm 146.00
penetration bitumen of suitable grade.)
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved
sources confirming to the physical requirement, specified in the respective specified clauses,
including royalties, fees rents, collection, transportation, stacking and testing and measured
in cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates
5.13 cum
for stone crushing given in chapter 1may be adopted, if found economical. In case for supply
of aggregates at site are not available, nearest crusher site may be ascertained. Loading and
un-loading charges and cost of carriage may be added to these rates to arrive at the cost at
site.)
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving
grade bitumen meeting the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm
5.14 sqm 390.00
nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface when the temperature of surfaces
not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per
clause 515.)
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates,
portland cement filler, bituminous emulsion and water on a road surface including cleaning
5.15
of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to provide
even riding surface)
added 1.In case it is decided by the engineer to blind the fog spray, the following may be added sqm 4.00
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous
cold mix on prepared base consisting of a mixture of unheated mineral aggregate and
5.18
emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and levels.)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 8481.00
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 8371.00
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 6421.00
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 6273.00
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines,
5.19 cum 6409.00
levels, grades and cross sections as per the drawings including mixing in a plant of suitable
type and capacity, transporting, laying, compacting and finishing.)
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such
as natural rubber or crumb rubber or any other polymer found compatible with bitumen and
which allows properties given in clause 521.3 and IRC: SP: 53 blending of modifier with
5.20 tonne
bitumen to be done either at the refinery or at the site plant capable of producing the
modified binder to be delivered in drums which shall be agitated in melted condition using
suitable device before use to ensure uniform dispersion.)
Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress
absorbing membrane over a cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed
(i) sqm 48.00
at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum
per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a
stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed
(ii) sqm 66.00
at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum
per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to
conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 %
(Providing and laying a single coat of a stress absorbing membrane over a cracked road
surface, with crack width above 9 mm and cracked area above 50 % after cleaning with a
(iii) mechanical broom, using modified binder complying with clause 521, sprayed at the rate of sqm 87.00
15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm,
sweeping the surface for uniform spread of aggregates and surface finished to conform to
clause 902.)
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion
binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver
5.22
finisher, rolled with a pneumatic tyred roller initially and finished with a smooth steel wheel
roller, all as per clause 519.3)
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base
over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per table 600-1, cement content not to be less
6.1 cum 2501.00
than 150 kg/ cum, optimum moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching
plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10
tonnes vibratory roller, finishing and curing.)
Rolled Cement Concrete Base (Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding
25 mm with minimum, aggregate cement ratio15:1 and minimum cement content of 200
6.3 kg/cum, aggregate gradation to be as per table 600-4 after blending, mixing in batching cum 2863.00
plant at optimum moisture content, transporting to site, laying with a paver with electronic
sensor, compacting with 8-10 tonnes smooth wheeled vibratory roller to achieve, the
designed flexural strength, finishing and curing.)
Transition section between rigid and flexible pavement (Due to change in the properties of
materials and type of construction, a gradual changeover from rigid pavement to flexible
pavement is desirable to avoid any damage at the butting joint. After provision of an
6.4
expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10
cm over a length of 3 m towards the flexible pavement. The deficiency of thickness caused
due to tapering of the slab should be made up by the asphaltic layers.)
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade
8.1 foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone
laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)
Printing new letter and figures of any shade (Printing new letter and figures of any shade
8.3
with synthetic enamel paint black or any other approved colour to give an even shade)
cm
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be height
(i) 0.60
counted as half ) per
letter
cm
height
(ii) English and Roman 0.40
per
letter
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting
direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick
8.5 sqm 1965.00
with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed foundation with M15 grade
cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing)
Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing
and erecting direction and place identification retro- reflectorised sign asper IRC :67 made of
encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting,
8.6 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x sqm 3000.00
75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation
with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per
approved drawing)
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface
8.8 sqm 51.00
with synthetic enamel paint in all shades on new plastered concrete surfaces)
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved
8.9 sqm 48.00
brand on steel surface after through cleaning of surface to give an even shade)
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved
8.10 sqm 54.00
brand on wood surface after through cleaning of surface to give an even shade)
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines,
dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint
8.11
conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust
and other foreign matter, demarcation at site and traffic control )
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes,
arrows etc on roads in two coats on old work with ready mixed road marking paint confirming
8.12
to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control )
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design
8.14
as per IRC:8-1980, fixing in position including painting and printing etc)
(i) 5th kilometre stone (precast) each 2200.00
(ii) Ordinary Kilometer stone (Precast) each 1300.00
(iii) Hectometer stone (Precast) each 360.00
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design
8.16 each 330.00
as per IRC:25-1967, fixed in position including finishing and lettering but excluding painting)
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire
fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th
8.17 metre 219.00
post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal
wires, fixed with GI staples, turn buckles etc complete as per clause 807 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire
fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th
8.18 metre 372.00
post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807 )
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre
high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with
8.19 0.40 metre embedded in M15 grade cement concrete, corner, end and every 10th post to be metre 512.00
strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm
(Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium
8.20 metre 2185.00
weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing
and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical
8.21 metre 1755.00
posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre
to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to bridge structures and medians, constructed
with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25
8.22 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed
to the structure on which it is built and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the
approved drawing and at locations directed by the Engineer, all as specified)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam
crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
B centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be metre 3482.00
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm
long complete as per clause 810)
Road Traffic Signals electrically operated (Since it is a ready made item commercially
produced and erected by specialised firm in the electrical and electronic field, rate may be
8.24
taken based on market enquiry from firms specialised in this field and ISI certified for the
approved design and drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety
barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50
kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom
for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center
8.25 to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 metre 2790.00
m apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x
900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination
and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and cement concrete.)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of
standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
8.27
both sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium
vapour lamp and fixed firmly in concrete foundation.)
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct,
300 mm dia, across the road (new construction), extending from drain to drain in cuts and
toe of slope to toe of slope in fills, constructing head walls at both ends, providing a
minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded
8.29
on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of
pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row
ducts, joints to be made leak proof, invert level of duct to be above higher than ground level
to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100
mm, die cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense
8.35 reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of each 579.00
60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part
4:1973)
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of
8.36 low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a each 1428.00
height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)
Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-
8.38 20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to sqm
control speed, marked with white strips of road marking paint.)
High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole
lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with
wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted
with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage,
suitable winching arrangement for safe working load of 750 kg and high powered electrically
driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable,
8.40 lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top
of the mast, all complete as per approved design and drawings This is a specialised work and
is generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this
work is required to be worked out based on approved design, drawings and estimate of the
lowest tender. A separate contract for this work is concluded as the contractors for road and
bridge works generally donot undertake such jobs.)
With Bricks (Construction of a permanent type barricade made with brick work in mud
C mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted each 14017.00
with yellow and white strips)
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag
8.46 each 318.00
600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)
CHAPTER-9
PIPE CULVERTS
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40
9.1 mm nominal size mechanically mixed, placed in foundation and compacted by vibration cum 3325.00
including curing for 14 days.)
Laying Reinforced Cement Concrete Pipe NP2/prestrssed concrete pipe on first class bedding
in single row . (Laying Reinforced cement concrete pipe NP2/prestrssed concrete pipe for
9.2 culverts on first class bedding of granular material in single row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets . )
A 1000 mm dia metre 4820.00
B 1200 mm dia metre 4400.00
Laying Reinforced Cement Concrete Pipe NP 2 /prestrssed concrete pipe on first class
bedding in double row . (Laying Reinforced cement concrete pipe NP2 /prestrssed concrete
9.3 pipe for culverts on first class bedding of granular material in double row including fixing
collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets . )
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of
these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers
10.1 cum 75.00
not exceeding 250 mm and compacting with plate compactor or power rammers to restore
the original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
10.2 irregularities on shoulder to the design level by adding fresh approved soil and compacting it sqm 52.00
with appropriate equipment.)
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder
10.3 sqm 18.00
surface to achieve the approved level and compacting with plate compactor)
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of
all failed material, trimming of completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the sides and base of excavation as per clause
10.4 sqm 125.00
503, back filling the pot holes with hot bituminous material as per clause 511, compacting,
trimming and finishing the surface to form a smooth continuous surface, all as per clause
3004.2)
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all
failed material, trimming of completed excavation to provide firm vertical faces, cleaning
10.5 of surface, painting of tack coat on the sides and base of excavation as per clause 503, back
filling the pot holes with hot bituminous material as per clause 504, compacting, trimming
and finishing the surface to form a smooth continuous surface, all as per clause 3004.2)
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % sqm
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock
10.13 requiring blasting for 50% of the boulders and disposal of the same on the valley side with cum 95.00
Bulldozer D 50)
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165
10.14 cum 3.00
Hp and disposing it on the valley side)
Maintenance of WBM Road (Maintenance of WBM road including filling up of pot holes, ruts
10.15 and rectifying corrugated surface, damaged edges and ravelling as per technical specification sqm 110.00
clause 1906).
Maintenance of Hume Pipe (Maintenance of Hume Pipe Culvert by way of Cleaning, Clearing,
10.16 Erosion repair, repairs to cracks, parapet wall and protection work as per drawing and each 772.00
technical specification Clasue 1908)
Maintenance of Culverts Slab type (Maintenance of Slab type Culvert by way of Cleaning,
10.17 Clearing, Erosion repair, repairs to cracks, parapet wall and protection work as per drawing each 1592.00
and technical specification Clasue 1908).
Maintenance of Road signs (Maintenance of Road signs by way of cleaning and repainting of
10.19 mandatory/regulatory/cautionary/informatory and place identifications sign board as per km 771.00
drawings and technical specifications Clause 1910).
10.20 Cutting of branches of trees shrubs and trimming of grass and weeds
Cutting of branches of tress and shrubs from the road way or with in R.O.W. including per
(i) 62.00
disposal of wood and leaves to suitable location as per technical specification Clause 1914. tree
Cutting of shrubs from the road way or with in R.O.W. and disposal of shrubs to suitable per
(ii) 4.00
location as per technical specification Clause 1914. shrub
Triming of grass and weeds from the shoulders/berms and disposing off the same to suitable
(iii) sqm 1.00
locations as per technical specifications Clause 1914.
White washing of parapet walls of CD work and tree trunks (White washing two coats on
10.21 parapet walls and tree trunks including preparation of surface by cleaning scraping etc. as sqm 12.00
per technical specifications Clause 1915)
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard
11.1 manure or/ and good earth in required thickness (cost of sludge, farm- yard manure or/and cum 13.00
good earth to be paid for separately))
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance
11.2 of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed)
(i) In rows 15 cm apart in either direction sqm 21.00
(ii) In rows 7.5 cm apart in either direction sqm 37.00
Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns
including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs
11.3 sqm 21.00
grass roots and planting at 15 cm apart, including supplying and spreading of farm yard
manure at rate of 0.18 cum per 100 sqm)
Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine
grassing including ploughing, dressing including breaking of clods, removal of rubbish,
11.5 sqm 24.00
dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of
farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 182.00
Planting of Trees and their Maintenance for one Year (Planting of trees by the road side
(Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with
11.9 each 2324.00
decayed farm yard/sludge mannure, planting the saplings, backfilling the trench, watering,
fixing the tree guard and maintaining the plants for one year)
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil
(Renovation lawns including, weeding, forking the ground, top dressing with forked soil,
11.10 watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn, sqm 11.00
free from weeds, and fit for moving and disposal of rubbish as directed, including supplying
good earth, if needed but excluding the cost of well decayed farm yard manure)
Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard
11.11 manure, from any available source, approved by the engineer in charge including screening cum 131.00
and stacking)
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and
height 1.2 metres, above ground and 0.20 metre below ground (Half brick circular tree
guard, in 2nd class brick, internal diametre 1.25 metres, and height 1.2 metres, above
11.14 each 1743.00
ground and 0.20 metre below ground, bottom two courses laid dry, and top three courses in
cement mortar 1:6 ( 1 cement 6 sand) and the intermediate courses being in dry honey
comb masonry, as per design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry
11.15 lengthwise, including excavation, refilling, consolidation, with a hand packing and metre 36.00
spreading nearly surplus earth within a lead of 50 metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making
tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to
11.16 each 183.00
permit sun and air, (supplied by the department at stock issue rate) including providing
and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums
(Making tree guard 53 cm dia and 2 metres high as per design from empty bitumen drums,
11.17 slit suitably to permit sun and air, ( supplied by the department at stock issue rate) each 355.00
including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using
angles, square bars, tees and channel grills, grating frames, gates and tree guards of any
11.18 size and design etc. including cost of screens and welding rods or bolts and nuts complete quintal 6986.00
fixed in position but without the cost of excavation and concrete for fixing which will be paid
separately)
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high
above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to each
11.19 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm dia and 30 mm long tree 1780.00
bolts including painting two coats with paint of approved brand over a coat of priming, guard
complete in all respects.)
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre each
11.20 square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm tree 3060.00
and steel wire3 mm dia welded and fabricated as per design in two halves bolted together) guard
CHAPTER-12
FOUNDATIONS
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 73.00
(ii) 3 m to 6 m depth cum 94.00
(iii) Above 6 m depth cum 125.00
B Mechanical Means
(i) Depth upto 3 m cum 40.00
(ii) Depth 3 m to 6 m cum 59.00
(iii) Depth above 6m cum 71.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 80.00
B Mechanical Means cum 66.00
III Hard rock ( requiring blasting )
A Manual Means cum 310.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 366.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 340.00
B Mechanical Means cum 91.00
VI Back Filling in Marshy Foundation Pits cum 269.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate
12.2
may be taken as per items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 718.00
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with
12.4 crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and cum 3706.00
compacted by vibration including curing for 14 days.)
Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and
12.5 cum 5487.00
plastering, as per drawing and technical specifications
12.6 A Cement mortar1:3 (1cement :3 sand) cum 3652.00
B Cement mortar1:2 (1cement :2 sand) cum 4591.00
C Cement mortar1:4 (1cement :4 sand) cum 3030.00
D Cement mortar1:6 (1cement :6 sand) cum 2413.00
Stone masonry work in cement mortar 1:3 in foundation complete as per drawing and
12.7
Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 3126.00
(b) Random Rubble Masonry cum 2350.00
Plain/Reinforced cement concrete in open foundation complete as per drawing and
12.8
technical specifications
A PCC Grade M15 cum 3350.00
B PCC Grade M20 cum 3830.00
C RCC Grade M20
Case I Using concrete mixer cum 4951.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4808.00
D PCC Grade M25
Case I Using concrete Mixer cum 5279.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5141.00
E RCC Grade M25
Case I Using concrete Mixer cum 5405.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4000.00
F PCC Grade M30
Case I Using Concrete Mixer cum 5316.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5174.00
G RCC Grade M30
Case I Using Concrete Mixer cum 5420.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5280.00
H RCC Grade M35
Case I Using Concrete Mixer cum 5520.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4250.00
Providing and constructing temporary island 16 m diameter for construction of well
12.9
foundation for 8m dia. Well.
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 34808.00
B Assuming depth of water 4.0 m and height of island 4.5 m. each 221243.00
Providing and constructing one span service road to reach island location from one pier
C metre 1530.00
location to another pier location
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation
12.10 tonne 64000.00
complete as per drawing and technical specification.
Plain/Reinforced cement concrete, in well foundation complete as per drawing and
12.11
technical specification
A Well curb
(i) RCC M20 Grade
Case I Using concrete mixer cum 5713.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5549.00
(ii) RCC M25 Grade
Case I Using concrete mixer cum 6252.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6216.00
(iii) RCC M35 Grade
Case I Using concrete mixer cum 6433.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5100.00
B Well steining
(I) PCC M15 Grade cum 4462.00
(ii) PCC M20 Grade cum 5110.00
(iii) RCC M20 Grade
Case I Using concrete mixer cum 5237.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5086.00
(iv) PCC M25 Grade
Case I Using concrete mixer cum 5597.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5451.00
(v) RCC M25 Grade
Case I Using concrete mixer cum 5731.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5698.00
(vi) PCC M30 Grade
Case I Using concrete mixer cum 5651.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5499.00
(vii) RCC M30 Grade
Case I Using concrete mixer cum 5762.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4470.00
(viii) RCC M35 Grade
Case I Using concrete mixer cum 5897.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5870.00
(ix) RCC M40 Grade 5942.00
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 5361.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5109.00
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 5622.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4250.00
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 5672.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5421.00
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 5790.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5536.00
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 5131.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4889.00
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 5379.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4100.00
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 5428.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5186.00
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 4056.00
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 4645.00
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 5089.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4955.00
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 5137.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4999.00
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 4900.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4757.00
(ii) RCC Grade M25
Case I Using concrete Mixer cum 5405.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5265.00
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 5420.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5279.00
(iv) RCC Grade M35
Case I Using Concrete Mixer cum 5520.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4250.00
(v) RCC M40 Grade cum 5605.00
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all
12.12 types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 2688.00
(ii) Beyond 3m upto 10m depth metre 3839.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 5071.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 9511.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 11413.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 22596.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 27115.00
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 3845.00
(ii) Beyond 3m upto 10m depth metre 9192.00
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 12141.00
meter
b Add for dewatering @ 5% of cost, if required. metre 12748.00
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 22773.00
meter
b Add 5% of cost for dewatering of the cost, if required metre 29890.00
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 28467.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 54105.00
meter
b Add 5% of cost for dewatering, if required metre 68172.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 64926.00
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 13033.00
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 13167.00
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all
12.13 types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 8033.00
(ii) Beyond 3m upto 10m depth metre 5469.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 7222.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 13546.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 16255.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 32182.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 38618.00
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all
12.14 types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 4990.00
(ii) Beyond 3m upto 10m depth metre 6151.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 8124.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 15240.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 18288.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 5357.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 6428.00
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all
12.15 types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5052.00
(ii) Beyond 3m upto 10m depth metre 6754.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 8921.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 16734.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 20080.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 39756.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 47707.00
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through
all types of strata namely sandy soil, clayey soil and rock as shown against each case,
12.16
complete as per drawing and technical specifications. Depth of sinking is reckoned from bed
level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 6072.00
(ii) Beyond 3m upto 10m depth metre 7130.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 9416.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 17662.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 21194.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 41961.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 50354.00
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 13971.00
(ii) Beyond 3m upto 10m depth metre 11030.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 14566.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 27321.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 32785.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 64910.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 77892.00
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through
all types of strata namely sandy soil, clayey soil and rock as shown against each case,
12.18
complete as per drawing and technical specifications. Depth of sinking is reckoned from bed
level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 28882.00
(ii) Beyond 3m upto 10m depth metre 32461.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 42870.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 80414.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 96497.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 191052.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 229262.00
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of
12.19 strata namely sandy soil, clayey soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 6545.00
(ii) Beyond 3m upto 10m depth metre 7061.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 9326.00
meter
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 17494.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 20993.00
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
a metre 41564.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 49876.00
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing
12.23 and technical specifications and removal of excavated earth with all lifts and lead upto 1000 metre 5576.00
m. (Pile diameter-750 mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing
12.24 and technical specifications and removal of excavated earth with all lifts and lead upto 1000 metre 9085.00
m. (Pile diameter-1000 mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing
12.25 and technical specifications and removal of excavated earth with all lifts and lead upto 1000 metre 11562.00
m. (Pile diameter-1200 mm)
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per
12.26 metre 4543.00
drawing and & Technical Specification (Pile diameter - 750 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
12.27 metre 7159.00
drawing and & Technical Specification (Pile diameter - 1000 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
12.28 metre 10472.00
drawing and & Technical Specification (Pile diameter - 1200 mm)
12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
(a) Initial and routine load test tonne 300.00
(b) Lateral load test tonne 5000.00
Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical
12.38
Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 4908.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 4787.00
B RCC Grade M25
(i) Using concrete mixer. cum 5392.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5273.00
C RCC Grade M30
(i) Using concrete mixer. cum 5454.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5333.00
D RCC Grade M35
(i) Using concrete mixer. cum 5582.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5463.00
12.39 Levelling course for Pile cap cum 4042.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as 55593.00
12.40 tonne
per drawing and technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as
12.41 tonne 55783.00
per drawing and technical specification
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as
13.1 cum 5585.00
per drawing and technical specifications
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical
13.2 sqm 32.00
specifications
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
13.3 sqm 75.00
specifications
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and
13.4
Technical Specifications
A Random Rubble Masonry cum 3131.00
B Coursed rubble masonry (first sort ) cum 3216.00
C Ashlar masonry ( first sort ) cum 3951.00
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical
13.5
specifications
A PCC Grade M15
(p) Height upto 5m cum 3520.00
B PCC Grade M20
(p) Height upto 5m cum 4050.00
C PCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 5597.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5451.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5801.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5649.00
(r) Height above 10m
Case I Using concrete Mixer cum 6055.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5897.00
D PCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 5651.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5499.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5857.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5699.00
(r) Height above 10m
Case I Using concrete Mixer cum 6114.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5949.00
E RCC Grade M20
(p) Height upto 5m
Case I Using concrete Mixer cum 5237.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4020.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5428.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5271.00
(r) Height above 10m
Case I Using concrete Mixer cum 5666.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5503.00
F RCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 5731.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4400.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5919.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4550.00
(r) Height above 10m
Case I Using concrete Mixer cum 6200.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6038.00
G RCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 5762.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5612.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5924.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5770.00
(r) Height above 10m
Case I Using concrete Mixer cum 6154.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5995.00
H RCC Grade M35
(p) Height upto 5m
Case I Using concrete Mixer cum 5897.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5870.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 6025.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4650.00
(r) Height above 10m
Case I Using concrete Mixer cum 6218.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6191.00
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
13.6 tonne 45000.00
drawing and technical specifications
Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per
13.7 tonne 55298.00
drawing and technical specification
Back filling behind abutment, wing wall and return wall complete as per drawing and
13.9
Technical specification
A Granular material cum 700.00
B Sandy material cum 896.00
Providing and laying of Filter media with granular materials/stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size towards
13.10 cum 850.00
the wall and provided over the entire surface behind abutment, wing wall and return wall to
the full height compacted to a firm condition complete as per drawing and technical
specification.
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing tonne
13.11 conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete capaci 1468.00
including all accessories as per drawing and Technical Specifications. ty
Supplying, fitting and fixing in position true to line and level forged steel roller bearing tonne
13.12 conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete capaci 1292.00
including all accessories as per drawing and Technical Specifications. ty
Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE
tonne
surface sliding on stainless steel complete including all accessories as per drawing and
13.13 capaci 2754.00
Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of
ty
MoRTH Specifications.
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming cubic
13.14 to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all centim 1.00
accessories as per drawing and Technical Specifications. etre
Supplying, fitting and fixing in position true to line and level sliding plate bearing with tonne
13.15 stainless steel plate sliding on stainless steel plate with mild steel matrix complete including capaci 223.00
all accessories as per drawing and Technical Specifications. ty
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of
a metal piston supported by a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating tonne
13.16 surface, completre assembly to be of cast steel/fabricated structural steel, metal and capaci 295.00
elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to ty
BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing
and approved technical specifications.
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per
14.1
drawing and Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5654.00
(q) Height 5m to 10m cum 5890.00
(r) Height above 10m cum 6126.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 5890.00
(q) Height 5m to 10m cum 6126.00
(r) Height above 10m cum 6361.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5489.00
(q) Height 5m to 10m cum 5717.00
(r) Height above 10m cum 5946.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 5717.00
(q) Height 5m to 10m cum 5946.00
(r) Height above 10m cum 6175.00
B RCC Grade M25
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6213.00
(q) Height 5m to 10m cum 6472.00
(r) Height above 10m cum 6731.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6472.00
(q) Height 5m to 10m cum 6731.00
(r) Height above 10m cum 6990.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6054.00
(q) Height 5m to 10m cum 6306.00
(r) Height above 10m cum 6559.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6306.00
(q) Height 5m to 10m cum 6559.00
(r) Height above 10m cum 6811.00
C RCC Grade M 30
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6301.00
(q) Height 5m to 10m cum 6563.00
(r) Height above 10m cum 6826.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6563.00
(q) Height 5m to 10m cum 6826.00
(r) Height above 10m cum 7088.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6125.00
(q) Height 5m to 10m cum 5000.00
(r) Height above 10m cum 6636.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6381.00
(q) Height 5m to 10m cum 6636.00
(r) Height above 10m cum 6891.00
D RCC/PSC Grade M35
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6341.00
(q) Height 5m to 10m cum 6609.00
(r) Height above 10m cum 6878.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6609.00
(q) Height 5m to 10m cum 6878.00
(r) Height above 10m cum 7147.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7415.00
(q) Height 5m to 10m cum 7953.00
(r) Height above 10m cum 8490.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6167.00
(q) Height 5m to 10m cum 6428.00
(r) Height above 10m cum 5200.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6428.00
(q) Height 5m to 10m cum 6689.00
(r) Height above 10m cum 6950.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7212.00
(q) Height 5m to 10m cum 7734.00
(r) Height above 10m cum 8257.00
E PSC Grade M-40
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6692.00
(q) Height 5m to 10m cum 6971.00
(r) Height above 10m cum 7250.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6971.00
(q) Height 5m to 10m cum 7250.00
(r) Height above 10m cum 7528.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6380.00
(q) Height 5m to 10m cum 6650.00
(r) Height above 10m cum 5650.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6650.00
(q) Height 5m to 10m cum 6921.00
(r) Height above 10m cum 7191.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7461.00
(q) Height 5m to 10m cum 8002.00
(r) Height above 10m cum 8543.00
F PSC Grade M-45
(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
(p) Height upto 5m cum 6609.00
(q) Height 5m to 10m cum 6893.00
(r) Height above 10m cum 5650.00
For I-beam & slab including launching of precast girders by launching truss upto 40 m span,
(ii)
21-31% of cost of concrete.
(p) Height upto 5m cum 6893.00
(q) Height 5m to 10m cum 7178.00
(r) Height above 10m cum 7463.00
For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost
(iii)
of concrete.
(p) Height upto 5m cum 7748.00
(q) Height 5m to 10m cum 8318.00
(r) Height above 10m cum 8887.00
G PSC Grade M-50
For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost
(i)
of concrete
(p) Height upto 5m cum 7971.00
(q) Height 5m to 10m cum 8561.00
(r) Height above 10m cum 9152.00
H PSC Grade M- 55
For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost
(i)
of concrete
(p) Height upto 5m cum 8409.00
(q) Height 5m to 10m cum 9032.00
(r) Height above 10m cum 9655.19
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as
14.2 tonne 45000.00
per drawing and technical specifications
High tensile steel wires/strands including all accessories for stressing, stressing operations
14.3 tonne 84000.00
and grouting complete as per drawing and Technical Specifications
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
14.4 cum 9373.00
complete as per drawing and Technical Specifications
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of
deck slab excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid surface with bitumen precoated fine
14.5 sqm 271.00
grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and
at an approximate spacing of 10 cm center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over
mastic surface, all complete as per clause 515.)
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true
to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre
14.6 metre 1549.00
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre
14.7 metre 1506.00
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.
Providing, fitting and fixing mild steel railing complete as per drawing and Technical
14.8 metre 2919.00
Specification
14.9 Drainage Spouts complete as per drawing and Technical specification each 530.00
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10 cum 4056.00
specification
Reinforced cement concrete approach slab including reinforcement and formwork complete
14.11 cum 6250.00
as per drawing and Technical specification
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-
14.15 rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been
made and included in chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to
14.16 unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, metre 61.00
efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm,
covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per
14.17 IS: 2062, placed symmetrical to centre line of the joint, resting freely over the top surface metre 1027.00
of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c
along the centre line of the plate, all as specified in clause 2604.)
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for
(iii) fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement metre 204.00
upto 20 mm, covered with sealant complete as per drawing and technical specifications.
Providing and filling joint sealing compound as per drawings and technical specifications with
(iv) metre 15.00
coarse sand and 6% bitumen by weight
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal
movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a
14.19 closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic metre 2734.00
plug to consist of polymer modified bitumen binder, carefully selected single size aggregate
of 12.5 mm nominal size and a heat resistant foam caulking/backer rod, all as per approved
drawings and specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm, complete as per approved drawings and
14.20 metre 10000.00
standard specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation and
clause 2606 of MoRTH specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel
armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a
14.21 preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into metre 14623.00
the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm
and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and
14.22 metre 15270.00
standard specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion
joint including anchorage catering to a horizontal movement beyond 70 mm and upto
14.23 140mm, complete as per approved drawings and standard specifications to be installed by metre 250827.00
the manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion
joint catering to a horizontal movement beyond 140mm and upto 210mm, complete as per
14.24 approved drawings and standard specifications to be installed by the manufacturer/supplier metre 277233.00
or their authorised representative ensuring compliance to the manufacturer's instructions for
installation.)
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour with stone
15.1 boulders weighing not less than 40 kg each complete as per drawing and Technical
specification.
A Boulder laid dry without wire crates. cum 961.00
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh
15.2 cum 1671.00
(weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing
not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement
15.3 concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cum 4302.00
cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media including boulder
15.4 apron laid dry in front of toe of embankment complete as per drawing and Technical
specifications
A Stone/Boulder cum 880.00
B Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 cum 4302.00
Providing and laying Filter material underneath pitching in slopes complete as per drawing
15.5 cum 960.00
and Technical specification
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of
dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix
if cement concrete block have been used for pitching . Rates for toe wall can be adopted
15.7
from respective clauses depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and given in respective
chapters.)
Providing and laying Flooring complete as per drawing and Technical specifications laid over
15.8
cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 3797.00
B Cement Concrete blocks Grade M15 cum 5666.00
15.9 Dry rubble Flooring cum 1000.00
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 3126.00
B Cement concrete Grade M15 cum 4218.00
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders
15.11 cum 800.00
weighing not less than 40 kg beyond curtain wall.
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for
retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5
m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
15.12 having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating cum 1500.00
conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100
mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm
galvanised steel wire)
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing
and constructing gabain structures for erosion control, river training works and protection
works with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile
15.13 cum 2500.00
strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with
boulders with least dimension of 200 mm, all loose ends to be securely tied with 4 mm
galvanised steel wire.)
CHAPTER-16
REPAIR AND REHABILITATION
Removal of existing cement concrete wearing coat including its disposal complete as per
Technical specification without causing any detrimental effect to any part of the bridge
16.1 sqm 82.00
structure and removal of dismantled material with all lifts and lead upto 1000m(Thickness 75
mm)
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid
16.2 sqm 62.00
over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m.
Guniting concrete surface with cement mortar applied with compressor after cleaning
16.3 sqm 790.00
surface and spraying with epoxy complete as per Technical specification
Providing and inserting nipples with approved fixing compound after drilling holes for
16.4 grouting as per Technical specifications including subsequent cutting/removal and sealing of each 88.00
the hole as necessary of nipples after completion of grouting with Cement/Epoxy
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete
mixture mechanically with compressed air under pressure, comprising of cement, sand,
coarse aggregates, water and quick setting compound in the proportion as per clause
16.9 sqm 264.00
2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012
respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than
2000 kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6.
Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for
16.10 sqm 86.00
replacement of spalled concrete
16.11 Eproxy bonding of new concrete to old concrete sqm 112.00
16.17 Replacement of Expansion Joints complete as per drawings metre 1984.00
16.18 Replacement of damaged concrete railing. metre 141.00
16.19 Replacement of crash barrier. metre 236.00
16.20 Replacement of damaged mild steel railing metre 122.00
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade
16.21 by cutting and trimming the damaged portion to a regular shape, cleaning the area to be metre 158.00
repaired thoroughly, applying cement concrete after erection of proper form work.)
16.22 Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) metre 106.00
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 240.00
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to
Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
PACKAGE B - COMPARATIVEABSTRACT OF COST (REVISED ESTIMATE)
Length = 20.04 Km
Item. SoR
Description
No. Ref Unit Quantity Rate Amount
8.01 12.1 Earthwork in excavation for foundation of structures as per drawings and Technical Specifications Clause
No.304.
I) Ordinary soil
A) Manual Means
(i) upto 3 m depth cu.m #REF! 121.00 #REF!
WELL FOUNDATION
8.02 12.11 Providing, placing,compacting and curing plain/ Reinforced cement concrete in well foundations with all lift
and leads complete as per MoRT&H tech. Specification .
A) Well curb : M-35 grade cu.m #REF! 9209.00 #REF!
B) Weel Staining : M-30 grade cu.m #REF! 8262.00 #REF!
C) Bottom Plug : M-25 grade cu.m #REF! 7890.00 #REF!
D) Intermediate Plug : M-25 grade cu.m #REF! 7541.00 #REF!
E)Top Plug : M-25 grade cu.m #REF! 7230.00 #REF!
F) Well Cap : M-35 grade cu.m #REF! 7904.00 #REF!
8.03 12.10 Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per
drawing and technical specification. MT #REF! 104806.00 #REF!
8.04 12.13 Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is rekonewed from bed level.
Depth below bed level upto 3.0 M Rm #REF! 11500.00 #REF!
Beyond 3m upto 10m depth Rm #REF! 7769.00 #REF!
Beyond 10m upto 20m Rm #REF! 10260.00 #REF!
8.05 12.12 Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications.Depth of sinking is rekonewed from bed level.
Depth below bed level upto 3.0 M Rm #REF! 3909.00 #REF!
Beyond 3m upto 10m depth Rm #REF! 5521.00 #REF!
Beyond 10m upto 20m Rm #REF! 7292.00 #REF!
Bill 8- 41
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee
Dolo)''(Khupi Segment , Length = 9+200 km)
BILL OF QUANTITIES & COST ESTIMATE
Bill No. 8. MINOR BRIDGES
Item. SoR
Description
No. Ref Unit Quantity Rate Amount
8.06 12.21 Sand filling in wells complete as per drawing and technical specifications cum #REF! 958.00 #REF!
8.07 12.40 Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per
drawing and technical specifications MT #REF! 78187.00 #REF!
8.08 13.5 Plain/Reinforcedcement concrete, in sub structure complete as per drawing and technical specification
G. RCC Grade M30
p) Height upto 5m
case-I Using concrete Mixer
cu.m #REF! 8262.00 #REF!
8.09 13.6 Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical
specifications MT #REF! 78328.00 #REF!
8.10 13.14 Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and
Technical Specifications.
cu.cm #REF! 1.00 #REF!
8.11 13.10 Providing and laying of filter media with stone crushed aggregates satisfying the requirements laid down in
clause 2504.2.2 of MoRT&H specifications to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface behind abutment,wing
wall,return wall,portal wall and box wall to the full height compacted to confirm to afirm condition with all lift
& lead as per Drawing and MoRT&H tech. Specification clause 2200 & 710.1.4 of IRC:78
cu.m #REF! 2122.00 #REF!
8.12 13.8 Providing Weep Holes in abutment, wing wall, return wall,portal walls, median walls and box walls with
100mm dia AC pipe,extending through the full width of the structure with slope of 1V:20H towards drawing
force,with all lift & lead as per Drawing and MoRT&H tech. Specification clause 2706 & 2200.
No. #REF! 140.00 #REF!
8.13 14.1 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing
and Technical Specification
A RCC M20 Grade
(q) Height 5m to 10m cum #REF! 8512.00 #REF!
8.14 14.2 a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and
technical specifications MT #REF! 79602.00 #REF!
Bill 8- 42
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee
Dolo)''(Khupi Segment , Length = 9+200 km)
BILL OF QUANTITIES & COST ESTIMATE
Bill No. 8. MINOR BRIDGES
Item. SoR
Description
No. Ref Unit Quantity Rate Amount
8.15 14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum
horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
m #REF! 16813.00 #REF!
8.16 14.4 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per
drawing and Technical Specifications cum #REF! 13360.00 #REF!
8.17 14.6 Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and
grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved
drawings and technical specifications.
m #REF! 2196.00 #REF!
8.18 14.10 PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
specification cu.m #REF! 5955.00 #REF!
8.19 14.11 Reinforced cement concrete approach slab including reinforcement and formwork complete as per
drawing and Technical specification cu.m #REF! 11462.00 #REF!
8.20 14.9 Drainage Spouts complete as per drawing and Technical specification Nos. #REF! 1109.00 #REF!
8.21 15.4 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications
i.) Stone/Boulder
cu.m #REF! 1128.00 #REF!
8.22 15.5 Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical
specification cu.m #REF! 2303.00 #REF!
8.23 15.2 Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm
dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10%
extra for laps and joints laid with stone boulders weighing not less than 40 kg each.)
cu.m #REF! 1886.00 #REF!
Total : #REF!
Bill 8- 43
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment,
Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''
(Khupi Segment , Length = 9+200 km)
INPUT
Total ABS- 45
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
GENERAL ABSTRACT OF COST
Length = 9.200 Km
Bill Cost
Item of works and Sub-Heads Unit Quantity
No (Rs. lakhs)
1 SITE CLEARANCE Km 9.200 8.355
2 EARTH WORK
Clearance of land slides in soil Cum 4082.4 4.123
Earthen Shoulder Cum 3509.8 9.757
Sub Total = 13.880
3 BASE / SUB BASE COURSES (350 mm) Km 9.200 293.261
4 BITUMINOUS COURSES (80 mm) DBM & BC Km 9.200 124.498
5 CULVERTS (18 nos.)
a) RCC Slab Culverts (1.5 m span) Nos. 10
b) RCC Slab Culverts (2.0 m span) Nos. 6 193.626
c) RCC Slab Culverts (3.0 m span) Nos. 2
6 DRAINAGE AND PROTECTIVE WORKS
a) Longitudinal Drains Mtr. 8200 137.757
b) R R Masonary Breast Wall Mtr. 245 44.899
c) R R Masonary Retaining wall Mtr. 260 64.085
TRAFFIC SIGNS, MARKINGS AND OTHER ROAD
7 Km 9.2 21.793
APPURTENANCES
Superintending Engineer
Executive Engineer Office of the Chief Engineer Highway
Naharlagun Highway Division, Nirjuli (WZ)
PWD ,Arunachal Pradesh PWD , AP , Itanagar.
ABS- 46
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item. SoR
Description Unit Quantity Rate Amount (Rs.)
No. Ref
1.01 2.3 Clearing and Grubbing Road Land .
(Clearing and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned up to a lead of 1000 metres including removal
and disposal of top organic soil not exceeding 150 mm in thickness.)
Item. SoR
Description Unit Quantity Rate Amount (Rs.)
No. Ref
C) Prestressed / Reinforced cement concrete grade M-20 & above Cum 15.000 1508.000 22620.000
(iii) Dismantling Stone Masonry
B) Rubble stone masonry in cement mortar. Cum 277.500 407.000 112942.500
(ix) Removing all type of hume pipes and stacking within a lead of 1000 metres
including earthwork and dismantling of masonry works.
B) Above 600 mm to 900 mm dia m 60 312.000 18720.000
Total (Rs.) : 8 35 522.10
Bill 1- 48
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment,
Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
BILL OF QUANTITIES & COST ESTIMATE
Bill No. 2. EARTH WORK
Item. SoR
Description Unit Quantity Rate Amount (Rs.)
No. Ref
2.01 10.12 Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12,
(i) 180 HP and disposal of the same on the valley side cu.m 4082.400 101.00 412322.40
2.02 3.18 Construction of Subgrade and Earthen Shoulders
(Construction of subgrade and earthen shoulders with approved material
obtained from borrow pits with all lifts & leads, transporting to site, spreading,
grading to required slope and compacted to meet requirement of table No. 300-
2)
cu.m 3509.800 278.00 975724.40
Total : 13 88 046.80
Bill 2- 49
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to
Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Bill 3- 50
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment,
Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item.
Ref Description Unit Quantity Rate Amount
No.
4.01 5.1 Prime coat
(Providing and applying primer coat with bitumen emulsion on prepared
surface of granular Base including clearing of road surface and spraying
primer at the rate of 0.60 kg/sqm using mechanical means.)
sq.m 36225.000 41.00 1485225.00
4.02 5.2 Tack Coat
(Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom.)
sq.m 36225.000 15.00 543375.00
4.03 5.9 Surface Dressing (Providing and laying surface dressing as wearing
course in single coat using crushed stone aggregates of specified size on
a layer of bituminous binder laid on prepared surface and rolling with 8-10
tonne smooth wheeled steel roller)
(ii) Case -I :-19 mm nominal chipping size - 1st Coat sq.m 36225.000 143.84 5210604.00
(ii) Case -I :-19 mm nominal chipping size - 2nd Coat sq.m 36225.000 143.84 5210604.00
Total : 12449808.00
Bill 4- 51
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Se
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item SoR
Description of Item Unit Quantity Rate
No. Ref
A. SLAB CULVERT
5.01 12.1(B) Excavation for Structures (Earth work in excavation of foundation of structures
(i) as per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth Cum 1731.060 186.00
5.02 12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration including curing for 14 Cum 114.410 6578.00
days.)
5.03 12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing
and technical specifications
III) PCC Grade M20 Cum 1677.512 8771.00
Case-I, Using Concrete Mixer
5.04 12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing
and technical specifications
IV) RCC Grade M20 Cum 76.172 9083.00
Case-I, Using Concrete Mixer
Bill 5- 52
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Se
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item SoR
Description of Item Unit Quantity Rate
No. Ref
5.05 13.10 Providing and laying filter media behind box structure, wing wall, retaining wall
and return wall complete as per drawings and Technical Specifications Section
305 and 2500. Cum 478.725 2711.00
5.06 13.8 Providing & fixing weep holes in head wall, return wall, wing wall and retaining
wall complete as per drawings and Technical Specifications Clause 2706. Nos. 324.000 176.00
5.07 13.6 Providing & fixing in position HYSD (TMT) reinforcement bars in foundations,
substructures, box strucutre complete as per drawings and Technical MT 14.904 99102.00
Specifications Section 1600.
5.08 14.9 Providing and fixing in position drainage spouts complete as per drawings
and Technical Specifications Clause 2705. Nos. 36.000 1412.00
Sub - Total
Bill 5- 53
o Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Amount
###
321977.16
752588.98
14713457.75
691870.28
Bill 5- 54
o Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Amount
1297822.66
57024.00
1477016.21
50832.00
19362589.04
Bill 5- 55
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Se
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item.
Ref Description Unit Quantity Rate
No.
A. Longitudinal open Drains
6.01 12.1 B (i) Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.) cum 2583.000 82.00
6.03 12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing
and technical specifications
A) PCC Grade M15 cum 1640.000 7876.00
6.03 12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing
and technical specifications
B) PCC Grade M20 cum 73.800 8771.00
Sub - Total
Bill 6- 56
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Se
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item.
Ref Description Unit Quantity Rate
No.
B. RR masonry Breast Wall
6.06 12.1 B (i) Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.) cum 507.150 82.00
6.07 12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm nominal size mechanically mixed,
placed in foundation and compacted by vibration including curing for 14 days.) cum 132.300 6578.00
6.08 12.7 Stone masonry work in cement mortar 1:3 in foundation complete as per drawing
and Technical Specification
(b) Random Rubble Masonry cum 577.710 5351.00
6.09 13.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per
Technical specifications Sqm 815.850 177.40
6.10 13.8 Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing
wall/return wall with 100 mm dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce. Complete as per drawing No. 245.000 176.00
and Technical specifications
6.11 13.10 Providing and laying filter media behind box structure, wing wall, retaining wall and
return wall complete as per drawings and Technical Specifications Section 305
and 2500. Sqm 110.250 2711.00
Sub - Total
Bill 6- 57
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Se
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item.
Ref Description Unit Quantity Rate
No.
B. RR masonry Retaining wall
6.12 12.1 B (i) Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.) cum 593.500 82.00
6.13 12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm nominal size mechanically mixed,
placed in foundation and compacted by vibration including curing for 14 days.)
cum 59.350 6578.00
6.14 12.7 Stone masonry work in cement mortar 1:3 in foundation complete as per drawing
and Technical Specification
(b) Random Rubble Masonry cum 993.163 5351.00
6.15 13.8 Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing
wall/return wall with 100 mm dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce. Complete as per drawing
and Technical specifications No. 420.000 176.00
6.16 13.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per
Technical specifications Sqm 983.388 177.40
6.17 13.10 Providing and laying filter media behind box structure, wing wall, retaining wall and
return wall complete as per drawings and Technical Specifications Section 305
and 2500. cum 150.000 2711.00
Sub - Total
Total for Draiange and Protective Works
Bill 6- 58
o Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Amount
211806.00
12916640.00
647299.80
137 75 745.80
Bill 6- 59
o Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Amount
41586.30
870269.40
3091326.21
144731.79
43120.00
298887.75
44 89 921.45
Bill 6- 60
o Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Amount
48667.00
390404.30
5314412.54
73920.00
174453.07
406650.00
64 08 506.90
246 74 174.15
Bill 6- 61
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde
to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Item.
Ref Description Unit Quantity Rate Amount
No.
7.01 8.14 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard
design as per IRC:8-1980, fixing in position including painting and printing etc)
i) 5th km stones No. 1 5107.00 5107.00
ii) Km stones No. 8 3099.00 24792.00
iii) Hectometer stones No. 37 858.00 31746.00
7.03 8.13 Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads
on Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5
mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be
level, uniform and free from streaks and holes.) sq.m 1860.000 764.000 1421040.00
7.04 8.6 Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing
and erecting direction and place identification retro- reflectorised sign asper IRC :67 made
of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post
75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed
foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground
sq.m 30 5683.000 170490.00
level as per approved drawing)
7.06 8.35 Road Markers/Road Stud with Lense Reflector (Providing and fixing of
road stud 100x 100 mm, die cast in aluminium, resistant to corrosive effect of
salt and grit, fitted with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973)
each 640 822.00 526080.00
Total : 2179255.00
Bill 7- 62
Annexure 1
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Seg
, Length = 9+200 km)
Annexure 1 - DETAILS OF MEASUREMENT
Item
Descriptions Unit No. Length Width Ht/Th Area
No.
1 2 3 4 5 6 7 8
Bill NO. 1. SITE CLEARANCE AND DISMANTLING
Clearing and Grubbing of
1.01 Road land Hct 1.000 9200.000 8.00
1.02 Cutting of Trees
a) Girth from 300mm to 600mm
No.
b) Girth from 600mm to 900mm
No.
c) Girth from 900mm to 1800mm
No.
Dismantling of existing
1.02 structures
a) Plain/Reinforced cement
concrete structures
i) PCC M-10 & M-15
Culverts cum 10 5.00 0.150
Total
ii) RCC M-20 and above
Culverts cum 10 5.00 0.300
Total
b) Stone Masonary
Culverts cum 10 1.500 5.00 3.000
Return wall cum 10 3.500 0.600 2.500
Total
c) Ordinary KM Stone No.
d) Removal of Hume Pipes
B) Above 600 mm to 900 mm
dia m 8.000 7.500
Bill NO. 2. EARTHWORK
Clearance of land slides in
soil and ordinary rock by a
2.01 bull-dozer D 80 A-12, Cum 60 7.200 4.200 4.500
180 HP and disposal of the
same on the valley side
Construction of Shoulders
2.02 Cum 6614.800
from borrow area
i Granular Shoulder Cum 2.000 9200.0 1.125 0.150
ii Earthen Shoulder
Anx 1.- 63
Annexure 1
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Seg
, Length = 9+200 km)
Annexure 1 - DETAILS OF MEASUREMENT
Item
Descriptions Unit No. Length Width Ht/Th Area
No.
1 2 3 4 5 6 7 8
Bill NO .3. GRANULAR SUB-BASE & BASE COURSE (Non - Bituminous)
3.01 Preparation of Subgrade
Total Subgrade Quantity for
cum
500mm depth
Subgarde area Sqm 9200.000 x 6.000
3.02 GSB cum
Ref Annexure 6
3.03 Wet Mix Macadam cum
Bill No. 4. BITUMINOUS SURFACE COURSE
4.01 Primer Coat sqm
4.02 Tack Coat sqm
Ref Annexure 6
4.03 DBM cum
4.04 BC cum
Bill No. 5. CROSS DRAINAGE WORKS
5.01 Slab Culverts Refer Annexure 5
Bill No. 6.PROTECTION WORKS
6.01 Kerb and Channel Drain Refer Annexure 2
6.02 RR Masonry Breast Wall Refer Annexure 3
6.03 PCC Retaining Wall Refer Annexure 4
Anx 1.- 64
Annexure 1
Quantity
9
D DISMANTLING
7.360
285
45
15
7.500
7.500
15.000
15.000
225.000
52.500
277.500
60.000
4082.400
6614.800
3105.000
3509.800
Anx 1.- 65
Annexure 1
Quantity
9
BASE COURSE (Non - Bituminous)
6614.800
55200.000
2936.640
5390.246
OURSE
36225.000
36225.000
36225.000
1091.580
S
1
8
37
1840.000
20.000
1860.000
30.00
640.00
###
###
Anx 1.- 66
ANNEXURE 2
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment,
Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Annexure 2 :
Cost Analyisis of rate for PCC Kerb and Channel Drain
Size = 0.6 m top width
1 Excavation:
1 1.00 0.90 0.35 0.315
82.00 0.315 Rs. 25.830 2583.000 ₹ 211,806.00
cum 1 0.200
cum 7876.00 Total 0.200 Rs. 1,575.200 1640.000 ₹ 12,916,640.00
3 Supprting Stone
PCC Grade M20
Bottom Slab = cum 1 0.10 0.30 0.300 0.0090
cum 8771.00 0.0090 Rs. 78.94 73.800 ₹ 647,299.80
Anx 2.- 67
ANNEXURE 3
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua
Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
6 13.10 Filter Media Filling cum 2711.00 0.450 1219.950 110.250 298887.75
Anx 3.- 68
ANNEXURE 4
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to
Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length = 9+200 km)
1 Eartwork in Excavati cum 82.000 1.450 118.900 2.663 218.325 3.038 249.075 593.500 48667.00
2 PCC 1:3:6 cum 6578.000 0.145 953.810 0.266 1751.393 0.304 1998.068 59.350 390404.30
3 Stone Msonry cum 5351.000 2.327 12453.115 4.123 22059.498 5.803 31052.522 993.163 5314412.54
4 Weep Hole No. 176.000 1.000 176.000 2.000 352.000 2.000 352.000 420.000 73920.00
5 Plastering sqm 177.400 3.037 538.752 3.862 685.039 4.892 867.899 983.388 174453.07
6 Filter Media Filling cum 2711.000 0.360 975.960 0.600 1626.600 0.900 2439.900 150.000 406650.00
Total per m 15216.54 Total per m 26692.85 Total per m 36959.46 6408506.90
Total for Total for 60
Total for 100 m 1521653.64 2669285.45 2217567.81
100 m m
Anx 4.- 69
Annexure 6
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass
on Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
Annexure 6 : Earthwork Quantities
Quantity Generated from MX Road.
Total Qntty. = 16137.410 Cum
Add 10% for widening at curve & Passing place = 1613.741 Cum
Total = 17751.151 Cum ###
ORDINARY SOIL = 10403.563 Cum
Add 10% for widening at curve & Passing place = 1040.356 Cum ###
Total = 11443.919 Cum ###
ORDINARY ROCK = 4558.269 Cum
Add 10% for widening at curve & Passing place = 455.827 Cum ###
Total = 5014.096 Cum ###
HARD ROCK = 1175.784 Cum
dd 10% for widening at curve & Passing place= = 117.578 Cum
Total = 1293.362 Cum
Filling = 7430.668 Cum
dd 10% for widening at curve & Passing place= = 743.067 Cum
Total = 8173.735 Cum
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
Anx 6- 42
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
380.0 1.30 0.543 29.080 15.994 8.724 4.362 16.180
400.0 2.15 0.706 34.520 18.986 10.356 5.178 12.490
420.0 1.83 0.574 39.800 21.890 11.940 5.970 12.800
440.0 2.13 1.207 39.610 21.786 11.883 5.942 17.810
460.0 2.14 1.053 42.690 23.480 12.807 6.404 22.600
480.0 1.64 1.036 37.740 20.757 11.322 5.661 20.890
500.0 2.15 1.067 37.830 20.807 11.349 5.675 21.030
520.0 1.56 0.372 37.030 20.367 11.109 5.555 14.390
540.0 2.15 0.651 37.060 20.383 11.118 5.559 10.230
560.0 1.39 0.596 35.440 19.492 10.632 5.316 12.470
580.0 2.00 1.241 33.960 18.678 10.188 5.094 18.370
600.0 1.80 0.916 38.060 20.933 11.418 5.709 21.570
620.0 1.68 0.917 34.830 19.157 10.449 5.225 18.330
640.0 1.64 0.640 33.200 18.260 9.960 4.980 15.570
660.0 1.37 0.972 30.090 16.550 9.027 4.514 16.120
680.0 1.69 0.911 30.580 18.348 6.116 6.116 18.830
700.0 2.08 0.760 37.720 22.632 7.544 7.544 16.710
720.0 1.24 0.976 33.260 19.956 6.652 6.652 17.360
740.0 1.59 0.835 28.350 17.010 5.670 5.670 18.110
760.0 1.44 1.210 30.350 18.210 6.070 6.070 20.450
780.0 2.03 1.009 34.770 20.862 6.954 6.954 22.190
800.0 1.54 0.310 35.730 21.438 7.146 7.146 13.190
820.0 2.02 0.671 35.570 21.342 7.114 7.114 9.810
840.0 1.38 1.022 34.020 20.412 6.804 6.804 16.930
860.0 2.14 0.859 35.280 21.168 7.056 7.056 18.810
880.0 1.74 1.077 38.850 23.310 7.770 7.770 19.360
900.0 1.67 0.704 34.120 20.472 6.824 6.824 17.810
920.0 1.30 0.794 29.680 17.808 5.936 5.936 14.980
940.0 1.93 0.425 32.220 19.332 6.444 6.444 12.190
960.0 1.49 0.512 34.120 20.472 6.824 6.824 9.370
980.0 1.52 0.512 30.110 18.066 6.022 6.022 10.240
1000.0 1.81 0.847 33.380 20.028 6.676 6.676 13.590
1020.0 1.34 0.514 31.500 18.900 6.300 6.300 13.610
1040.0 1.67 1.287 30.080 18.048 6.016 6.016 18.010
1060.0 1.50 0.332 31.690 19.014 6.338 6.338 16.190
1080.0 1.76 0.334 32.610 19.566 6.522 6.522 6.660
Anx 6- 43
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
1100.0 1.49 0.465 32.540 19.524 6.508 6.508 7.990
1120.0 1.50 0.303 29.920 17.952 5.984 5.984 7.680
1140.0 1.60 1.234 30.980 18.588 6.196 6.196 15.370
1160.0 2.15 0.901 37.430 22.458 7.486 7.486 21.350
1180.0 1.75 1.033 38.970 23.382 7.794 7.794 19.340
1200.0 2.16 1.004 39.130 23.478 7.826 7.826 20.370
1220.0 1.36 0.721 35.220 17.610 10.566 7.044 17.250
1240.0 2.22 1.119 35.780 17.890 10.734 7.156 18.400
1260.0 1.82 1.299 40.400 20.200 12.120 8.080 24.180
1280.0 2.19 1.094 40.130 20.065 12.039 8.026 23.930
1300.0 2.07 1.189 42.610 21.305 12.783 8.522 22.830
1320.0 2.21 0.663 42.770 21.385 12.831 8.554 18.520
1340.0 1.65 0.524 38.590 19.295 11.577 7.718 11.870
1360.0 2.08 0.595 37.350 18.675 11.205 7.470 11.190
1380.0 1.55 0.496 36.340 18.170 10.902 7.268 10.910
1400.0 1.23 0.980 27.760 15.268 8.328 4.164 14.760
1420.0 2.15 1.248 33.750 18.563 10.125 5.063 22.280
1440.0 1.66 0.862 38.040 20.922 11.412 5.706 21.100
1460.0 1.36 1.016 30.190 16.605 9.057 4.529 18.780
1480.0 2.05 1.159 34.120 18.766 10.236 5.118 21.750
1500.0 2.19 1.004 42.360 23.298 12.708 6.354 21.630
1520.0 1.77 0.442 39.540 21.747 11.862 5.931 14.460
1540.0 1.91 0.431 36.740 20.207 11.022 5.511 8.730
1560.0 1.76 1.009 36.660 20.163 10.998 5.499 14.400
1580.0 2.14 1.239 38.940 21.417 11.682 5.841 22.480
1600.0 1.78 0.465 39.110 21.511 11.733 5.867 17.040
1620.0 2.14 0.977 39.130 21.522 11.739 5.870 14.420
1640.0 2.11 0.963 42.510 23.381 12.753 6.377 19.400
1660.0 2.18 0.515 42.950 23.623 12.885 6.443 14.780
1680.0 2.16 0.711 43.390 23.865 13.017 6.509 12.260
1700.0 1.95 0.491 41.090 20.545 12.327 8.218 12.020
1720.0 1.71 1.231 36.570 18.285 10.971 7.314 17.220
1740.0 2.08 1.029 37.850 28.388 7.570 1.893 22.600
1760.0 1.44 0.953 35.240 26.430 7.048 1.762 19.820
1780.0 1.86 0.537 33.040 24.780 6.608 1.652 14.900
1800.0 1.77 1.053 36.340 27.255 7.268 1.817 15.900
Anx 6- 44
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
1820.0 1.95 0.432 37.280 27.960 7.456 1.864 14.850
1840.0 1.99 1.028 39.470 29.603 7.894 1.974 14.600
1860.0 1.46 0.685 34.570 25.928 6.914 1.729 17.130
1880.0 1.62 0.622 30.880 23.160 6.176 1.544 13.070
1900.0 1.75 1.032 33.760 25.320 6.752 1.688 16.540
1920.0 1.54 0.704 32.900 24.675 6.580 1.645 17.360
1940.0 1.78 0.576 33.140 24.855 6.628 1.657 12.800
1960.0 1.24 0.985 30.190 22.643 6.038 1.510 15.610
1980.0 1.27 0.729 25.100 18.825 5.020 1.255 17.140
2000.0 1.85 0.334 31.210 23.408 6.242 1.561 10.630
2020.0 1.26 0.928 31.100 23.325 6.220 1.555 12.620
2040.0 1.39 0.713 26.480 19.860 5.296 1.324 16.410
2060.0 1.90 0.962 32.920 24.690 6.584 1.646 16.750
2080.0 1.72 0.869 36.240 27.180 7.248 1.812 18.310
2100.0 2.14 0.925 38.670 29.003 7.734 1.934 17.940
2120.0 1.98 0.643 41.200 30.900 8.240 2.060 15.680
2140.0 2.13 0.883 41.030 30.773 8.206 2.052 15.260
2160.0 1.68 0.365 38.080 28.560 7.616 1.904 12.480
2180.0 1.94 1.277 36.250 27.188 7.250 1.813 16.420
2200.0 1.54 1.182 34.820 26.115 6.964 1.741 24.590
2220.0 2.00 0.445 35.400 26.550 7.080 1.770 16.270
2240.0 2.20 0.851 41.960 31.470 8.392 2.098 12.960
2260.0 1.87 0.431 40.600 30.450 8.120 2.030 12.820
2280.0 1.91 0.548 37.790 28.343 7.558 1.890 9.790
2300.0 2.15 1.163 40.600 30.450 8.120 2.030 17.110
2320.0 1.40 1.112 35.420 23.023 10.626 1.771 22.750
2340.0 1.72 0.706 31.190 20.274 9.357 1.560 18.180
2360.0 1.49 0.423 32.150 20.898 9.645 1.608 11.290
2380.0 1.32 0.705 28.150 18.298 8.445 1.408 11.280
2400.0 1.53 1.058 28.570 18.571 8.571 1.429 17.630
2420.0 2.22 0.970 37.490 24.369 11.247 1.875 20.280
2440.0 2.13 1.275 43.480 28.262 13.044 2.174 22.450
2460.0 1.82 0.967 39.520 25.688 11.856 1.976 22.420
2480.0 1.41 0.544 32.240 20.956 9.672 1.612 15.110
2500.0 1.66 0.907 30.610 19.897 9.183 1.531 14.510
2520.0 1.76 1.074 34.200 22.230 10.260 1.710 19.810
Anx 6- 45
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
2540.0 2.20 0.932 39.660 25.779 11.898 1.983 20.060
2560.0 1.84 0.827 40.370 26.241 12.111 2.019 17.590
2580.0 2.07 1.205 39.090 25.409 11.727 1.955 20.320
2600.0 1.43 0.373 34.990 22.744 10.497 1.750 15.780
2620.0 1.80 0.323 32.290 20.989 9.687 1.615 6.960
2640.0 1.28 0.723 30.870 20.066 9.261 1.544 10.460
2660.0 1.98 0.377 32.610 21.197 9.783 1.631 11.000
2680.0 1.24 0.674 32.220 20.943 9.666 1.611 10.510
2700.0 1.76 0.456 29.990 19.494 8.997 1.500 11.300
2720.0 1.75 0.489 35.050 22.783 10.515 1.753 9.450
2740.0 1.99 1.160 37.440 24.336 11.232 1.872 16.490
2760.0 1.77 1.271 37.660 24.479 11.298 1.883 24.310
2780.0 1.41 0.837 31.820 20.683 9.546 1.591 21.080
2800.0 2.13 1.037 35.370 22.991 10.611 1.769 18.740
2820.0 1.40 0.673 35.280 22.932 10.584 1.764 17.100
2840.0 1.62 0.403 30.210 19.637 9.063 1.511 10.760
2860.0 2.08 0.851 37.010 24.057 11.103 1.851 12.540
2880.0 1.46 1.099 35.380 22.997 10.614 1.769 19.500
2900.0 1.97 1.039 34.230 22.250 10.269 1.712 21.380
2920.0 2.10 1.277 40.700 26.455 12.210 2.035 23.160
2940.0 1.49 1.044 35.940 23.361 10.782 1.797 23.210
2960.0 2.13 1.191 36.190 23.524 10.857 1.810 22.350
2980.0 1.53 0.519 36.560 23.764 10.968 1.828 17.100
3000.0 2.16 0.567 36.880 23.972 11.064 1.844 10.860
3020.0 1.91 1.291 40.720 26.468 12.216 2.036 18.580
3040.0 1.44 0.529 33.510 21.782 10.053 1.676 18.200
3060.0 2.04 0.345 34.800 22.620 10.440 1.740 8.740
3080.0 1.52 1.223 35.560 23.114 10.668 1.778 15.680
3100.0 1.67 1.174 31.890 20.729 9.567 1.595 23.970
3120.0 1.52 0.599 31.930 20.755 9.579 1.597 17.730
3140.0 1.89 0.423 34.130 22.185 10.239 1.707 10.220
3160.0 1.81 0.313 37.060 24.089 11.118 1.853 7.360
3180.0 2.18 0.523 39.950 27.965 9.988 1.998 8.360
3200.0 1.29 0.868 34.720 24.304 8.680 1.736 13.910
3220.0 2.12 1.281 34.120 23.884 8.530 1.706 21.490
3240.0 1.25 0.848 33.710 23.597 8.428 1.686 21.290
Anx 6- 46
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
3260.0 1.66 0.361 29.060 20.342 7.265 1.453 12.090
3280.0 2.13 0.599 37.840 26.488 9.460 1.892 9.600
3300.0 1.84 0.432 39.650 27.755 9.913 1.983 10.310
3320.0 1.55 1.123 33.870 23.709 8.468 1.694 15.550
3340.0 2.15 1.261 36.970 25.879 9.243 1.849 23.840
3360.0 1.41 0.992 35.590 24.913 8.898 1.780 22.530
3380.0 1.98 1.028 33.900 23.730 8.475 1.695 20.200
3400.0 2.14 0.811 41.190 28.833 10.298 2.060 18.390
3420.0 2.05 1.048 41.910 29.337 10.478 2.096 18.590
3440.0 1.42 1.105 34.740 24.318 8.685 1.737 21.530
3460.0 1.67 1.056 30.960 21.672 7.740 1.548 21.610
3480.0 1.48 0.689 31.560 22.092 7.890 1.578 17.450
3500.0 1.82 0.814 33.040 23.128 8.260 1.652 15.030
3520.0 1.94 0.718 37.590 26.313 9.398 1.880 15.320
3540.0 1.91 0.525 38.520 26.964 9.630 1.926 12.430
3560.0 1.45 0.642 33.670 23.569 8.418 1.684 11.670
3580.0 1.84 0.689 32.940 23.058 8.235 1.647 13.310
3600.0 1.42 1.091 32.630 22.841 8.158 1.632 17.800
3620.0 1.36 1.205 27.800 19.460 6.950 1.390 22.960
3640.0 1.94 1.056 33.020 23.114 8.255 1.651 22.610
3660.0 1.90 0.646 38.410 26.887 9.603 1.921 17.020
3680.0 1.59 0.785 34.910 24.437 8.728 1.746 14.310
3700.0 1.25 1.187 28.440 19.908 7.110 1.422 19.720
3720.0 1.93 1.139 31.830 22.281 7.958 1.592 23.260
3740.0 1.91 0.801 38.410 26.887 9.603 1.921 19.400
3760.0 1.47 1.163 33.800 23.660 8.450 1.690 19.640
3780.0 1.88 1.256 33.560 23.492 8.390 1.678 24.190
3800.0 1.43 1.243 33.110 23.177 8.278 1.656 24.990
3820.0 2.20 0.422 36.280 25.396 9.070 1.814 16.650
3840.0 1.48 1.105 36.810 25.767 9.203 1.841 15.270
3860.0 2.11 0.580 35.920 25.144 8.980 1.796 16.850
3880.0 1.96 0.448 40.760 28.532 10.190 2.038 10.280
3900.0 2.20 0.346 41.670 29.169 10.418 2.084 7.940
3920.0 1.36 0.674 35.580 24.906 8.895 1.779 10.200
3940.0 1.78 1.235 31.350 21.945 7.838 1.568 19.090
3960.0 1.35 0.541 31.320 21.924 7.830 1.566 17.760
Anx 6- 47
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
3980.0 2.19 0.574 35.440 24.808 8.860 1.772 11.150
4000.0 1.59 0.961 37.820 26.474 9.455 1.891 15.350
4020.0 2.14 0.589 37.320 26.124 9.330 1.866 15.500
4040.0 2.15 1.058 42.900 30.030 10.725 2.145 16.470
4060.0 1.40 1.028 35.520 24.864 8.880 1.776 20.860
4080.0 1.29 1.267 26.960 18.872 6.740 1.348 22.950
4100.0 1.84 0.472 31.300 21.910 7.825 1.565 17.390
4120.0 1.78 1.162 36.220 25.354 9.055 1.811 16.340
4140.0 1.64 0.491 34.200 23.940 8.550 1.710 16.530
4160.0 1.40 1.288 30.340 21.238 7.585 1.517 17.790
4180.0 1.26 0.777 26.530 18.571 6.633 1.327 20.650
4200.0 1.69 0.748 29.490 20.643 7.373 1.475 15.250
4220.0 1.57 1.252 32.660 21.229 9.798 1.633 20.000
4240.0 1.68 1.079 32.500 21.125 9.750 1.625 23.310
4260.0 1.33 0.696 30.070 19.546 9.021 1.504 17.750
4280.0 1.96 1.231 32.920 21.398 9.876 1.646 19.270
4300.0 1.36 0.580 33.190 21.574 9.957 1.660 18.110
4320.0 1.85 1.064 32.010 20.807 9.603 1.601 16.440
4340.0 2.02 1.044 38.670 25.136 11.601 1.934 21.080
4360.0 1.88 0.357 39.000 25.350 11.700 1.950 14.010
4380.0 1.86 1.156 37.360 24.284 11.208 1.868 15.130
4400.0 1.89 1.066 37.460 24.349 11.238 1.873 22.220
4420.0 1.36 1.296 32.490 21.119 9.747 1.625 23.620
4440.0 1.98 0.323 33.400 21.710 10.020 1.670 16.190
4460.0 1.54 0.594 35.170 22.861 10.551 1.759 9.170
4480.0 2.17 0.751 37.090 24.109 11.127 1.855 13.450
4500.0 1.84 0.313 40.130 26.085 12.039 2.007 10.640
4520.0 1.39 1.094 32.360 21.034 9.708 1.618 14.070
4540.0 1.78 1.093 31.760 20.644 9.528 1.588 21.870
4560.0 1.34 0.790 31.230 20.300 9.369 1.562 18.830
4580.0 1.90 0.384 32.450 21.093 9.735 1.623 11.740
4600.0 1.91 1.253 38.140 24.791 11.442 1.907 16.370
4620.0 1.89 1.201 38.000 24.700 11.400 1.900 24.540
4640.0 1.99 0.935 38.810 25.227 11.643 1.941 21.360
4660.0 1.81 1.161 37.980 24.687 11.394 1.899 20.960
4680.0 1.90 0.320 37.090 24.109 11.127 1.855 14.810
Anx 6- 48
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
4700.0 2.03 0.866 39.310 25.552 11.793 1.966 11.860
4720.0 1.71 0.975 37.340 24.271 11.202 1.867 18.410
4740.0 1.24 1.130 29.460 19.149 8.838 1.473 21.050
4760.0 2.17 0.697 34.150 22.198 10.245 1.708 18.270
4780.0 2.10 0.870 42.710 27.762 12.813 2.136 15.670
4800.0 1.90 1.176 39.950 25.968 11.985 1.998 20.460
4820.0 1.91 0.695 38.120 24.778 11.436 1.906 18.710
4840.0 1.30 0.787 32.170 20.911 9.651 1.609 14.820
4860.0 1.64 0.808 29.410 19.117 8.823 1.471 15.950
4880.0 1.66 1.091 32.970 21.431 9.891 1.649 18.990
4900.0 1.65 0.458 33.080 21.502 9.924 1.654 15.490
4920.0 1.51 0.802 31.540 20.501 9.462 1.577 12.600
4940.0 2.21 0.739 37.130 24.135 11.139 1.857 15.410
4960.0 1.79 1.047 39.940 25.961 11.982 1.997 17.860
4980.0 1.26 0.400 30.450 19.793 9.135 1.523 14.470
5000.0 2.22 0.988 34.760 22.594 10.428 1.738 13.880
5020.0 2.07 1.199 42.910 27.892 12.873 2.146 21.870
5040.0 1.64 1.180 37.100 24.115 11.130 1.855 23.790
5060.0 2.06 0.307 36.980 24.037 11.094 1.849 14.870
5080.0 1.61 0.460 36.730 23.875 11.019 1.837 7.670
5100.0 1.63 1.040 32.360 21.034 9.708 1.618 15.000
5120.0 2.06 0.994 36.860 23.959 11.058 1.843 20.340
5140.0 1.34 0.531 33.970 22.081 10.191 1.699 15.250
5160.0 1.35 0.317 26.820 17.433 8.046 1.341 8.480
5180.0 1.97 0.665 33.200 21.580 9.960 1.660 9.820
5200.0 2.07 0.715 40.440 26.286 12.132 2.022 13.800
5220.0 1.87 0.468 39.390 25.604 11.817 1.970 11.830
5240.0 1.95 0.889 38.200 24.830 11.460 1.910 13.570
5260.0 1.51 0.912 34.590 22.484 10.377 1.730 18.010
5280.0 1.77 0.838 32.730 21.275 9.819 1.637 17.500
5300.0 1.86 1.055 36.260 23.569 10.878 1.813 18.930
5320.0 2.00 1.152 38.650 25.123 11.595 1.933 22.070
5340.0 1.54 0.526 35.430 23.030 10.629 1.772 16.780
5360.0 1.49 1.108 30.320 19.708 9.096 1.516 16.340
5380.0 1.28 0.686 27.690 17.999 8.307 1.385 17.940
5400.0 1.70 0.993 29.760 19.344 8.928 1.488 16.790
Anx 6- 49
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
5420.0 2.20 0.410 38.960 25.324 11.688 1.948 14.030
5440.0 2.00 1.289 41.990 27.294 12.597 2.100 16.990
5460.0 1.71 0.610 37.140 24.141 11.142 1.857 18.990
5480.0 1.34 0.931 30.460 19.799 9.138 1.523 15.410
5500.0 1.37 0.444 27.050 17.583 8.115 1.353 13.750
5520.0 1.94 1.140 33.080 21.502 9.924 1.654 15.840
5540.0 1.78 1.011 37.180 24.167 11.154 1.859 21.510
5560.0 1.81 0.414 35.890 23.329 10.767 1.795 14.250
5580.0 1.68 0.770 34.870 22.666 10.461 1.744 11.840
5600.0 1.37 0.968 30.520 19.838 9.156 1.526 17.380
5620.0 1.96 0.844 33.370 21.691 10.011 1.669 18.120
5640.0 2.13 1.088 40.960 26.624 12.288 2.048 19.320
5660.0 2.20 0.587 43.310 28.152 12.993 2.166 16.750
5680.0 1.94 0.613 41.410 26.917 12.423 2.071 12.000
5700.0 1.28 0.422 32.210 20.937 9.663 1.611 10.350
5720.0 1.56 0.506 28.330 18.415 8.499 1.417 9.280
5740.0 2.19 0.565 37.480 24.362 11.244 1.874 10.710
5760.0 1.50 0.603 36.920 23.998 11.076 1.846 11.680
5780.0 1.52 1.138 30.220 19.643 9.066 1.511 17.410
5800.0 1.41 0.684 29.360 19.084 8.808 1.468 18.220
5820.0 1.98 1.089 33.970 22.081 10.191 1.699 17.730
5840.0 1.72 0.975 37.080 24.102 11.124 1.854 20.640
5860.0 1.52 0.930 32.470 21.106 9.741 1.624 19.050
5880.0 2.12 1.245 36.460 23.699 10.938 1.823 21.750
5900.0 1.51 0.322 36.320 23.608 10.896 1.816 15.670
5920.0 1.91 0.637 34.180 22.217 10.254 1.709 9.590
5940.0 1.84 0.492 37.440 24.336 11.232 1.872 11.290
5960.0 1.69 1.146 35.290 22.939 10.587 1.765 16.380
5980.0 1.99 1.162 36.840 23.946 11.052 1.842 23.080
6000.0 1.79 0.622 37.820 24.583 11.346 1.891 17.840
6020.0 1.32 1.092 31.140 20.241 9.342 1.557 17.140
6040.0 1.95 1.133 32.720 21.268 9.816 1.636 22.250
6060.0 1.97 0.738 39.210 25.487 11.763 1.961 18.710
6080.0 1.73 1.108 37.020 24.063 11.106 1.851 18.460
6100.0 2.02 0.487 37.500 24.375 11.250 1.875 15.950
6120.0 1.89 0.616 39.070 25.396 11.721 1.954 11.030
Anx 6- 50
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
6140.0 1.24 1.199 31.290 20.339 9.387 1.565 18.150
6160.0 1.76 0.504 30.050 19.533 9.015 1.503 17.030
6180.0 2.01 1.076 37.750 24.538 11.325 1.888 15.800
6200.0 2.18 1.146 41.890 27.229 12.567 2.095 22.220
6220.0 1.53 0.594 37.040 24.076 11.112 1.852 17.400
6240.0 1.81 0.725 33.400 21.710 10.020 1.670 13.190
6260.0 1.30 0.453 31.170 20.261 9.351 1.559 11.780
6280.0 1.98 0.606 32.850 21.353 9.855 1.643 10.590
6300.0 1.48 1.003 34.570 22.471 10.371 1.729 16.090
6320.0 1.40 0.437 28.710 18.662 8.613 1.436 14.400
6340.0 1.85 0.713 32.430 21.080 9.729 1.622 11.500
6360.0 2.01 0.386 38.570 25.071 11.571 1.929 10.990
6380.0 2.01 0.832 40.200 26.130 12.060 2.010 12.180
6400.0 1.58 1.278 35.850 23.303 10.755 1.793 21.100
6420.0 1.46 0.345 30.360 19.734 9.108 1.518 16.230
6440.0 1.46 0.947 29.170 18.961 8.751 1.459 12.920
6460.0 1.89 0.616 33.500 21.775 10.050 1.675 15.630
6480.0 2.21 1.024 40.990 26.644 12.297 2.050 16.400
6500.0 1.99 1.240 41.910 27.242 12.573 2.096 22.640
6520.0 1.83 1.228 38.140 24.791 11.442 1.907 24.680
6540.0 1.31 1.046 31.370 20.391 9.411 1.569 22.740
6560.0 1.52 1.096 28.270 18.376 8.481 1.414 21.420
6580.0 1.67 1.161 31.920 20.748 9.576 1.596 22.570
6600.0 1.75 0.401 34.200 22.230 10.260 1.710 15.620
6620.0 1.69 0.633 34.370 22.341 10.311 1.719 10.340
6640.0 2.04 0.462 37.280 24.232 11.184 1.864 10.950
6660.0 1.26 0.497 32.930 21.405 9.879 1.647 9.590
6680.0 1.46 0.697 27.160 17.654 8.148 1.358 11.940
6700.0 1.95 1.171 34.100 22.165 10.230 1.705 18.680
6720.0 1.81 0.475 37.570 24.421 11.271 1.879 16.460
6740.0 2.07 0.737 38.770 25.201 11.631 1.939 12.120
6760.0 1.56 0.931 36.320 23.608 10.896 1.816 16.680
6780.0 1.55 0.405 31.120 20.228 9.336 1.556 13.360
6800.0 1.81 1.182 33.610 21.847 10.083 1.681 15.870
6820.0 2.01 1.011 38.180 24.817 11.454 1.909 21.930
6840.0 1.92 0.512 39.240 25.506 11.772 1.962 15.230
Anx 6- 51
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
6860.0 1.29 0.362 32.110 20.872 9.633 1.606 8.740
6880.0 1.37 0.583 26.660 17.329 7.998 1.333 9.450
6900.0 1.78 0.688 31.560 20.514 9.468 1.578 12.710
6920.0 1.43 0.647 32.170 20.911 9.651 1.609 13.350
6940.0 1.80 1.223 32.370 21.041 9.711 1.619 18.700
6960.0 1.88 1.279 36.840 23.946 11.052 1.842 25.020
6980.0 1.94 1.104 38.190 24.824 11.457 1.910 23.830
7000.0 1.97 0.731 39.130 25.435 11.739 1.957 18.350
7020.0 1.88 1.019 38.560 25.064 11.568 1.928 17.500
7040.0 1.83 0.629 37.110 24.122 11.133 1.856 16.480
7060.0 1.74 1.010 35.690 23.199 10.707 1.785 16.390
7080.0 2.04 0.609 37.840 24.596 11.352 1.892 16.190
7100.0 1.92 0.871 39.640 25.766 11.892 1.982 14.800
7120.0 1.90 0.324 38.230 24.850 11.469 1.912 11.950
7140.0 1.25 0.836 31.570 20.521 9.471 1.579 11.600
7160.0 2.12 0.430 33.690 21.899 10.107 1.685 12.660
7180.0 1.81 0.442 39.220 25.493 11.766 1.961 8.720
7200.0 1.75 1.019 35.550 23.108 10.665 1.778 14.610
7220.0 1.46 0.971 32.050 20.833 9.615 1.603 19.900
7240.0 1.81 0.713 32.690 21.249 9.807 1.635 16.840
7260.0 2.22 1.045 40.310 26.202 12.093 2.016 17.580
7280.0 1.94 0.455 41.540 27.001 12.462 2.077 15.000
7300.0 2.18 0.651 41.180 26.767 12.354 2.059 11.060
7320.0 1.68 0.466 38.630 25.110 11.589 1.932 11.170
7340.0 1.54 1.229 32.170 20.911 9.651 1.609 16.950
7360.0 1.84 0.336 33.800 21.970 10.140 1.690 15.650
7380.0 2.06 0.909 39.060 25.389 11.718 1.953 12.450
7400.0 2.00 0.398 40.590 26.384 12.177 2.030 13.070
7420.0 2.07 0.953 40.650 26.423 12.195 2.033 13.510
7440.0 1.42 1.149 34.870 22.666 10.461 1.744 21.020
7460.0 1.50 0.616 29.220 18.993 8.766 1.461 17.650
7480.0 1.47 0.341 29.780 19.357 8.934 1.489 9.570
7500.0 2.01 0.632 34.830 22.640 10.449 1.742 9.730
7520.0 1.80 1.142 38.130 24.785 11.439 1.907 17.740
7540.0 2.01 0.978 38.150 24.798 11.445 1.908 21.200
7560.0 2.04 1.068 40.500 26.325 12.150 2.025 20.460
Anx 6- 52
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
7580.0 2.11 0.329 41.510 26.982 12.453 2.076 13.970
7600.0 2.15 0.347 42.610 27.697 12.783 2.131 6.760
7620.0 1.34 0.444 34.840 22.646 10.452 1.742 7.910
7640.0 1.90 0.407 32.370 21.041 9.711 1.619 8.510
7660.0 1.54 0.370 34.430 22.380 10.329 1.722 7.770
7680.0 2.04 0.401 35.790 23.264 10.737 1.790 7.710
7700.0 1.92 0.934 39.550 25.708 11.865 1.978 13.350
7720.0 1.99 1.073 39.080 25.402 11.724 1.954 20.070
7740.0 1.33 0.858 33.200 21.580 9.960 1.660 19.310
7760.0 2.20 0.476 35.280 22.932 10.584 1.764 13.340
7780.0 2.16 1.137 43.590 28.334 13.077 2.180 16.130
7800.0 1.38 0.884 35.380 22.997 10.614 1.769 20.210
7820.0 1.42 0.639 27.940 18.161 8.382 1.397 15.230
7840.0 1.24 1.267 26.550 17.258 7.965 1.328 19.060
7860.0 1.49 1.201 27.250 17.713 8.175 1.363 24.680
7880.0 2.02 0.420 35.010 22.757 10.503 1.751 16.210
7900.0 2.03 0.496 40.400 26.260 12.120 2.020 9.160
7920.0 1.89 0.842 39.140 25.441 11.742 1.957 13.380
7940.0 1.26 0.943 31.530 20.495 9.459 1.577 17.850
7960.0 1.81 0.828 30.690 19.949 9.207 1.535 17.710
7980.0 1.74 0.616 35.420 23.023 10.626 1.771 14.440
8000.0 1.87 0.698 36.110 23.472 10.833 1.806 13.140
8020.0 2.17 0.797 40.420 26.273 12.126 2.021 14.950
8040.0 1.70 0.458 38.670 25.136 11.601 1.934 12.550
8060.0 1.42 0.409 31.160 20.254 9.348 1.558 8.670
8080.0 1.92 0.692 33.360 21.684 10.008 1.668 11.010
8100.0 1.56 1.196 34.770 22.601 10.431 1.739 18.880
8120.0 2.12 0.749 36.750 23.888 11.025 1.838 19.450
8140.0 2.09 0.631 42.100 27.365 12.630 2.105 13.800
8160.0 1.70 0.998 37.960 24.674 11.388 1.898 16.290
8180.0 1.63 0.516 33.370 21.691 10.011 1.669 15.140
8200.0 1.71 1.236 33.390 21.704 10.017 1.670 17.520
8220.0 1.32 1.122 30.220 19.643 9.066 1.511 23.580
8240.0 1.23 0.579 25.430 16.530 7.629 1.272 17.010
8260.0 2.20 0.462 34.290 22.289 10.287 1.715 10.410
8280.0 2.11 0.511 43.090 28.009 12.927 2.155 9.730
Anx 6- 53
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
8300.0 2.01 1.019 41.170 26.761 12.351 2.059 15.300
8320.0 2.15 0.372 41.650 27.073 12.495 2.083 13.910
8340.0 1.82 0.858 39.740 25.831 11.922 1.987 12.300
8360.0 1.48 0.503 32.960 21.424 9.888 1.648 13.610
8380.0 1.44 0.876 29.150 18.948 8.745 1.458 13.790
8400.0 1.80 0.962 32.340 21.021 9.702 1.617 18.380
8420.0 1.35 0.375 31.470 20.456 9.441 1.574 13.370
8440.0 1.48 0.533 28.340 18.421 8.502 1.417 9.080
8460.0 1.45 0.440 29.350 19.078 8.805 1.468 9.730
8480.0 1.92 1.127 33.740 21.931 10.122 1.687 15.670
8500.0 2.03 0.348 39.470 25.656 11.841 1.974 14.750
8520.0 1.95 1.200 39.750 25.838 11.925 1.988 15.480
8540.0 2.08 0.694 40.300 26.195 12.090 2.015 18.940
8560.0 1.62 1.075 37.040 24.076 11.112 1.852 17.690
8580.0 1.99 0.847 36.100 23.465 10.830 1.805 19.220
8600.0 1.72 0.826 37.050 24.083 11.115 1.853 16.730
8620.0 1.39 0.654 31.080 20.202 9.324 1.554 14.800
8640.0 1.87 0.767 32.580 21.177 9.774 1.629 14.210
8660.0 1.89 0.654 37.550 24.408 11.265 1.878 14.210
8680.0 1.38 1.180 32.660 21.229 9.798 1.633 18.340
8700.0 1.33 0.854 27.040 17.576 8.112 1.352 20.340
8720.0 1.50 1.239 28.280 18.382 8.484 1.414 20.930
8740.0 1.27 0.455 27.760 18.044 8.328 1.388 16.940
8760.0 2.21 1.157 34.850 22.653 10.455 1.743 16.120
8780.0 1.63 0.796 38.450 24.993 11.535 1.923 19.530
8800.0 1.40 1.089 30.340 19.721 9.102 1.517 18.850
8820.0 2.12 1.126 35.170 22.861 10.551 1.759 22.150
8840.0 1.90 0.983 40.190 26.124 12.057 2.010 21.090
8860.0 1.65 0.703 35.560 23.114 10.668 1.778 16.860
8880.0 1.48 0.768 31.310 20.352 9.393 1.566 14.710
8900.0 2.21 0.662 36.830 23.940 11.049 1.842 14.300
8920.0 1.82 0.891 40.280 26.182 12.084 2.014 15.530
8940.0 1.66 0.727 34.820 22.633 10.446 1.741 16.180
8960.0 2.13 0.736 37.920 24.648 11.376 1.896 14.630
8980.0 1.47 0.329 35.980 23.387 10.794 1.799 10.650
9000.0 2.18 0.399 36.410 23.667 10.923 1.821 7.280
Anx 6- 54
Annexure 6
EARTHWORK QUANTITES ###
Chainage AREA Ordinary VOLUME
CUT FILL CUT soil Soft Rock Hard Rock FILL
9020.0 1.58 0.468 37.590 24.434 11.277 1.880 8.670
9040.0 1.26 1.086 28.390 18.454 8.517 1.420 15.540
9060.0 1.71 0.468 29.650 19.273 8.895 1.483 15.540
9080.0 1.68 0.819 33.910 22.042 10.173 1.696 12.870
9100.0 2.09 0.803 37.700 24.505 11.310 1.885 16.220
9120.0 1.42 1.253 35.080 22.802 10.524 1.754 20.560
9140.0 1.30 0.523 27.160 17.654 8.148 1.358 17.760
9160.0 1.70 0.366 29.930 19.455 8.979 1.497 8.890
9180.0 2.14 1.090 38.360 24.934 11.508 1.918 14.560
9198.7 2.00 0.762 38.830 25.240 11.649 1.942 17.358
Total valume= 16137.410 10403.563 4558.269 1175.784 7430.668
Anx 6- 55
Annexure 6
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
Annexure 6 : Pavement Quantities
Anx-6- 56
Annexure 6
Anx-6- 57
Annexure 6
Anx-6- 58
Annexure 6
Anx-6- 59
Annexure 6
Anx-6- 60
Annexure 6
Anx-6- 61
Annexure 6
Anx-6- 62
Annexure 6
Anx-6- 63
Annexure 6
Anx-6- 64
Annexure 6
Anx-6- 65
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
ANNEXURE -7
Cost Analysis of Breast Wall
Providing Breast wall in stone masonry including 300 mm PCC (Prop. 1:3:6) in foundation
including plastering (Considering 10.00 m long and 1.50 m clear height).
1/3.13 Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)
Anx-7- 66
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
ANNEXURE -7
Cost Analysis of Breast Wall
Providing Breast wall in stone masonry including 300 mm PCC (Prop. 1:3:6) in foundation
including plastering (Considering 10.00 m long and 1.50 m clear height).
@ Rs. 177.40 ./m3 Rs. 590.742
6/13.8 Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment,
wing wall/return wall with 100 mm dia AC pipe, extending through the full width
of the structure with slope of 1V :20H towards drawing foce. Complete as per
drawing and Technical specifications
1x 1 = 1 No
= 1 No
@ Rs. 176.00 ./m3 Rs. 176.000
Rs. 18,326.210
Anx-7- 67
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
ANNEXURE -8
Cost Analysis of Retaining Wall
Providing Retaining wall in stone masonry (Considering 10.00 m long and 1.00 m clear height).
Anx-8 RW2.0- 68
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on
Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi
Segment , Length = 9+200 km)
ANNEXURE -8
Cost Analysis of Retaining Wall
Providing Retaining wall in stone masonry (Considering 10.00 m long and 1.00 m clear height).
Anx-8 RW2.0- 69
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi
segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length
= 9+200 km)
ANNEXURE -9
Cost Analysis of Retaining Wall
Providing Retaining wall in stone masonry (Considering 10.00 m long and 2.00 m clear height).
Rs Rs. 26,692.854
Anx-9 RW3.5- 70
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi
segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length
= 9+200 km)
ANNEXURE -10
Cost Analysis of Retaining Wall
Providing Retaining wall in stone masonry (Considering 10.00 m long and 3.00 m clear height).
1/3.13 Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)
(I) )Ordinary soil
A.Manual Means ( Depth upto 3 m)
For wall. 1x 1.00 x 2.025 x 1.50 = 3.038 m3
= 3.038 m3
@ Rs. 82.00 ./m3 Rs. 249.075
2/12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration including curing for 14
days.)
For wall. 1x 1.00 x 2.025 x 0.15= 0.304 m3
= 0.304 m3
@ Rs. 6578.00 ./m3 Rs. 1,998.068
3/12.7 Stone masonry work in cement mortar 1:3 in foundation complete as per
drawing and Technical Specification
b) Random Rubble Masonry
Wall 1 x 1.00 x( 1.725 + 0.60 )/2 x 4.500 = 5.231 m3
1 x 1.00 x( 1/2 X 1.725 x 0.350 = 0.302 m3
Parapet wall 1 x 1.00 x 0.45 x 0.60 = 0.270 m3
= 5.803 m3
@ Rs. 5351.00 ./m3 Rs. 31,052.522
4/13.10 Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical specification.
Anx-10 RW4.5- 72
ion on Nechipu to Hoj Section of NH-13 (Bypass on Khupi
o Pakro & Khodaso to Dee Dolo)''(Khupi Segment , Length
= 9+200 km)
ANNEXURE -10
alysis of Retaining Wall
nry (Considering 10.00 m long and 3.00 m clear height).
249.075
1,998.068
31,052.522
2,439.900
867.899
352.000
Anx-10 RW4.5- 73
Rs. 36,959.46
Anx-10 RW4.5- 74
Appendix-I
“One time Improvement of bypassed Section on Nechipu to Hoj Section of NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to
Dee Dolo)''(Khupi Segment , Length = 9+200 km)
Sl. Name of Item of Unit of Lead from Extra lead of different roads Rate/ Loose Cost of Total Cost Cost as Total
No. Quarry works work quarry of (in KM) m3/Km quantity extra of Carriage per SOR (in Rs)
work site as per reqd/unit carriage 12=10+11
SOR (m3) 9=6x7x8
(in Rs)
1 2 3 4 5 6 7 8 9 10 11 12
Surfaced Road 6.00 13.47 1.277 103.19 475.52 1428.00 1903.52
1 GSB m3 19.00 Unsurfaced Road 8.00 16.20 1.277 165.48
Kutcha Road 5.00 32.40 1.277 206.85
Surfaced Road 6.00 13.47 1.320 106.67 491.53 1837.00 2328.53
2 WMM m 3
19.00 Unsurfaced Road 8.00 16.20 1.320 171.05
Kutcha Road 5.00 32.40 1.320 213.81
Surfaced Road 6.00 11.60 0.015 1.04 4.84 139.00 143.84
Surface
3 m2 19.00 Unsurfaced Road 8.00 14.00 0.015 1.68
Dressing
Kutcha Road 5.00 28.20 0.015 2.12
41.00 41.00
4 Prime Coat m3
15.00 15.00
5 Tack coat m3
Appendix-I
NH-13 (Bypass on Khupi segment, Nepua Cheda segment, Sedde to Pakro & Khodaso to
i Segment , Length = 9+200 km)
Remarks
13
ANNEXURE 9
Length (m) 0 0 0 0
Length (m) 0 0 0 0 0
Total per Total per Total per Total per Total per
99844 129328 162470 195979 245620 0
m m m m m
Total for 0 Total for 0 Total for 0 Total for 0 Total for 0
0m 0m 0m 0m 0m
ANNEXURE 13
A13.3
Annexure 6
Anx 6.- 27
Annexure 18
Analysis of Rate for the Disposing of excavated earth beyond the initial lead as per schedule of rates
Sl. Item of Unit Unit Densi Rate Rate of loose qty Cost of carriage
No. works Quan ty of of carriage for per Km
tity Earth carria /Cum.km
cum T/m3 ge
1 2 3 4 5 6 7 8 9
/T.km
Col. 5 x
Col. 6 Col.7 x Col.8
Earth
1 Work in m3 1.0 1.8 6.30 11.34 1.25 ₹ 14.18
Cutting
Chaia Lead Initial Total Rate Quantity Quantity for Reused of Quantity for Amount
nge lead Lead Embankment Quant Disposed
₹ 14.13
10 8 1 7 ₹ 98.91 Err:509 Err:509 Err:509 Err:509 Err:509
11 7 1 6 ₹ 84.78 Err:509 Err:509 Err:509 Err:509 Err:509
12 6 1 5 ₹ 70.65 Err:509 Err:509 Err:509 Err:509 Err:509
13 5 1 4 ₹ 56.52 Err:509 Err:509 Err:509 Err:509 Err:509
14 4 1 3 ₹ 42.39 Err:509 Err:509 Err:509 Err:509 Err:509
15 3 1 2 ₹ 28.26 Err:509 Err:509 Err:509 Err:509 Err:509
16 2 1 1 ₹ 14.13 Err:509 Err:509 Err:509 Err:509 Err:509
17 1 1 0 ₹ 0.00 Err:509 Err:509 Err:509 Err:509 Err:509
18 0 1 0 ₹ 0.00 Err:509 Err:509 Err:509 Err:509 Err:509
19 1 1 0 ₹ 0.00 Err:509 Err:509 Err:509 Err:509 Err:509
20 2 1 1 ₹ 14.13 Err:509 Err:509 Err:509 Err:509 Err:509
21 3 1 2 ₹ 28.26 Err:509 Err:509 Err:509 Err:509 Err:509
22 4 1 3 ₹ 42.39 Err:509 Err:509 Err:509 Err:509 Err:509
23 5 1 4 ₹ 56.52 Err:509 Err:509 Err:509 Err:509 Err:509
24 6 1 5 ₹ 70.65 Err:509 Err:509 Err:509 Err:509 Err:509
25 7 1 6 ₹ 84.78 Err:509 Err:509 Err:509 Err:509 Err:509
26 8 1 7 ₹ 98.91 Err:509 Err:509 Err:509 Err:509 Err:509
27 9 1 8 ₹ 113.04 Err:509 Err:509 Err:509 Err:509 Err:509
28 10 1 9 ₹ 127.17 Err:509 Err:509 Err:509 Err:509 Err:509
29 11 1 10 ₹ 141.30 Err:509 Err:509 Err:509 Err:509 Err:509
30 12 1 11 ₹ 155.43 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
ANNEXURE 6
1 Earth work in excavation in foundation in trenches Cum 51.00 1.800 91.800 1080.000 55080.00
etc. not exceeding 2m depth including dressing to
bottom and sides of trenchesthe excavted soil clear of
the edges of excavated for Covered drain.
2 Plain cement concrete M15 in Levelling course with Cum 4310.00 0.225 969.750 135.000 581850.00
crushed stone, mechanically mixed, placed in
foundation upto a depth of 1.5m below ground level
and compacted.
A6.1
ANNEXURE 6
4 Reinforced Cement Concrete in slab of covered drain Cum 5204.00 0.325 1691.300 195.000 1014780.00
complete as per drawing and technical specifications
RCC Grade M20.
Slab = 1 x 1.5 x 0.1 = 0.15 cum
Tie Beam = 2 x 1 x 0.35 x 0.25 = 0.175 cum
Total = 0.15 + 0.175 = 0.325 cum
5 Supplying, fitting and placing TMT reinforcement MT 55668.00 0.013 723.684 7.800 434210.40
complete in sub-structure as per drawing and
technical specifications
6 Plastering on inner side of stone amsonary of covered Sqm 96.10 1.900 182.590 1140.000 109554.00
wall with 1:4 CM as per drawing
width = 2 x 0.95 x 1 = 1.9 sqm
7 Providing Weep Holes in stone masonry wall Nos 121.00 2.000 242.000 1200.000 145200.00
Quantity - 1 x 2 = 2 nos
2 Plain cement concrete M15 in Levelling course with Cum 4310.00 0.270 1163.700 162.000 698220.00
crushed stone, mechanically mixed, placed in
foundation upto a depth of 1.5m below ground level
and compacted.
7 Providing Weep Holes in stone masonry wall Nos 121.00 2.000 242.000 1200.000 145200.00
Quantity - 1 x 2 = 2 nos
A6.2