BILL OF QUANTITIES

CALATAGAN DOME STORAGE BUILDING - COAL STORAGE


PROJECT:
- STORAGE
LOCATION: CALATAGAN, BATANGAS, PHILIPPINES
AREA: 35400 sqm
DATE: 07/05/2023
REVISION: 0

No. Description Unit Quantity Rate (USD) Amount (USD) Remark


[1] [2] [3] [4] [5] [6]=[4]*[5] [7]
A1 MAIN FRAME WORKS
1 Structural Built-up section kg 2,083,826 1.26 2,624,579 *ASTM A572 Fy=34.5kN/cm2
2 Structural Hot roll Steel kg 607,330 1.52 921,170 *JISG 3101 SS400 Fy=24.5kN/cm2
3 Structural Bracing kg 70,222 1.18 83,189 *JISG 3101 SS400 Fy=24.5kN/cm2
EPOXY PAINT (140 ~ 150 micron thickness),
4 Painting lumpsum 5,273,808 0.06 319,625
Blasting Steel Structure SA 2.0
A2 PURLIN & GIRT
1 Galvanised Purlins & Girt kg 259,247 1.19 307,227 Cold Formed G450 Z275, Fy=45.0kN/cm2
A3 PANEL & CLADDING WORKS
1 Roof sheeting m2 44,088 8.88 391,281 Sheeting SR32 0.60mm Prepainted
2
2 Wall sheeting m 6,932 8.88 61,522 Sheeting SR32 0.60mm Prepainted
A4 OTHER WORKS
1 Trims & Flashings m 1,281 3.98 5,102 AZ150 ASTM G300 Fy=30 kN/cm2
2 Rain Gutter m 758 12.10 9,172 Prepainted Steel Panel Follow BMB Standard
3 Drainage Downspout m 1,207 30.02 36,237 PVC Downspout
4 High strength Connection Bolts set 121,086 0.83 100,744 Galvanized, Grade 10.9, Fu = 100 kN/cm2
5 Anchor bolts set 2,592 36.13 93,649 Galvanized, Grade 5.6, Fu = 50 kN/cm2
6 Miscellaneous lumpsum 46,381 1.14 52,828
A TOTAL OF SUPPLY lumpsum 5,006,323

B DELIVERY lumpsum 445,287 CIF TO MANILA PORT

C ERECTION lumpsum 2,992,864

D COST BEFORE VAT 8,444,473

DISCOUNT 250,316

E COST BEFORE VAT (AFTER DISCOUNT) 8,194,157

VAT 12% FOR ERECTION 359,144

SUM TOTAL (SUPPLY + DELIVERY + ERECTION + 12% VAT FOR ERECTION) 8,553,000 LUMP SUM CONTRACT - NO ANY ADDITIONAL COST

GENERAL NOTES ERECTION INCLUDED


1. Price quotation is valid for the period of 10 days; 1. Unloading of materials on site;
2. Price includes opening frames; 2. Site Engineers, Surveyor, Manpower;
3. Currency: USD; 3. Crane, Forklift, Hantools;
4. The rafter had been designed camber. 4. Safety equipments;

This Bill of Quantities is prepared by BMB & ACCESSORIES (PHILIPPINES)


Manila Office: Unit 1415, AIC Burgundy Empire Tower, ADB Avenue cor. Garnet and Sapphire Road, Ortigas Center, Pasig City
Cebu Office: 1508 Park Centrale, Jose Maria del Mar St, Cebu IT Park, Apas, Cebu City
Landline: (+632) 470-76-24 / 470-76-33 / 470-76-34

You might also like