Erection Sequence For Reformer Furnaces
Erection Sequence For Reformer Furnaces
(1-A ) Set Of 90 deg. And 270 deg. sides Main column (A-1~3,
E-1~3)
(1-B) Set of Floor beam support stanchion (B∼D-1, B∼D-2,
B∼D-3)
(1-C) Installation of 90 deg. and 270 deg. side beams (between
A-1 ∼ 3, E-1 ∼ 3) (1-D) Installation of Floor beam (Line Nos.
1∼3)
(1-E) Installation of Reinforcement column & beams of 0 deg.
side
(1-F) Installation of 90 deg. and 270 deg. side lower/Upper
panels (Total : 24 panels) for J10-F-0401, 0402 Lower Panel :
12 Panels Upper Panel : 12 Panels
(1-G) Installation of 0 deg. side lower panels (Total: 16 Panels)
Lower Panels: 8 , Upper Panels ; 8
(2-A) Set of Main column (A-4 & 5 , E-4 & 5)
(2-B) Set of Floor Beam Support Stanchion (B ∼ D-4, B ∼ D-5)
(2-C) Installation of Floor beam (Line Nos. 4 & 5)
(2-D) Installation of Reinforcement Column & beam of 180
deg. Side
(2-G) Installation of Header support
(B-11∼26, D-11 ∼ 26, E-11 ∼26, F-11 ∼26, G-11 ∼26, H-11 ∼26,
I-11~26, J-11 ∼26, K-11 ∼26, L-11∼26, M-11~26)
2-H) Installation of Floor panels (Inside section of Rad. coil )
(4-D) Installation of Radiant arch structure for Column Line
Nos. A & E
(4-E) Installation of Radiant arch panels
(4-F) installation of Transition duct block ( Refractory lining
to be done on the ground)
(4-G) Installation of Radiant arch structure for Column line
nos. B1, B2,- C1, C2, D1, D2 —
(5-A) Installation of lower convection module
(5-B) Installation of upper convection module with breeching
(6-A) lnstallation of Stack bottom duct·
(6-B) Installation of Flue gas outlet duct between Flue gas x-
over duct and Stack bottom duct
(6-C) Installation of Flue gas x-over duct
(6-D) Installation of Stack structure
(6-E) Installation of Stack lower block