PROJECT NAME: Renovation for Ministry of Finance

PROJECT LOCATION: Abu Dhabi


CONSULTANT: CEO
MAIN CONTRACTOR: UECC

Non Conformance Register(MECHANICAL)


NCR No. Discpline Discription Date Issued

HVAC

MEC-01 AC 3rd Floor Site Inspection 11/6/2023

MEC-02 AC 3rd Floor Site Inspection 11/6/2023

MEC-03 AC 3rd Floor Site Inspection 11/6/2023

MEC-04 AC 3rd Floor Site Inspection 11/6/2023

MEC-05 AC 3rd Floor Site Inspection 11/6/2023

MEC-06 AC 3rd Floor Site Inspection 11/6/2023

MEC-07 AC 3rd Floor Site Inspection 11/6/2023

MEC-08 AC 3rd Floor Site Inspection 11/6/2023

MEC-09 AC 3rd Floor Site Inspection 11/6/2023

MEC-10 AC 3rd Floor Site Inspection 11/6/2023

MEC-11 AC 3rd Floor Site Inspection 11/6/2023

MEC-12 AC 3rd Floor Site Inspection 11/6/2023

MEC-13 AC 3rd Floor Site Inspection 11/6/2023

MEC-14 AC 3rd Floor Site Inspection 11/6/2023

MEC-15 AC 3rd Floor Site Inspection 11/6/2023

FIREFIGHTING

MEC-16 FF 3rd Floor Site Inspection 11/6/2023

MEC-17 FF 3rd Floor Site Inspection 11/6/2023

MEC-18 FF 3rd Floor Site Inspection 11/6/2023


MEC-18 FF 3rd Floor Site Inspection 11/6/2023

MEC-19 FF 3rd Floor Site Inspection 11/6/2023

MEC-20 FF 3rd Floor Site Inspection 11/6/2023

BMS

MEC-21 BMS 3rd Floor Site Inspection 11/6/2023

MEC-22 BMS 3rd Floor Site Inspection 11/6/2023

MEC-23 BMS 3rd Floor Site Inspection 11/6/2023

MEC-24 BMS 3rd Floor Site Inspection 11/6/2023

MEC-25 BMS 3rd Floor Site Inspection 11/6/2023


MECHANICAL)
Date Issued Response Date Status

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN
11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN
PROJECT NAME: Renovation for Ministry of Finance
PROJECT LOCATION: Abu Dhabi
CONSULTANT: CEO
MAIN CONTRACTOR: UECC

Non Conformance Register(ELECTRICAL)


NCR No. Discpline Discription Date Issued

ELEC-01 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-02 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-03 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-04 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-05 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-06 ELEC 3rd Floor Site Inspection 11/6/2023

ELEC-07 ELEC 3rd Floor Site Inspection 11/6/2023


(ELECTRICAL)
Date Issued Response Date Status

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN

11/6/2023 OPEN