Professional Documents
Culture Documents
Artson Engineering Limited Vs Indian Oil Corporaton Limited On 9 January 2015
Artson Engineering Limited Vs Indian Oil Corporaton Limited On 9 January 2015
rt
ORDINARY ORIGINAL CIVIL JURISDICTION
ou
APPEAL NO.307 OF 2007
IN
ARBITRATION PETITION NO.408 OF 2005
C
Artson Engineering Ltd. … Appellant
v/s
Indian Oil Corporation Ltd. … Respondent
h
Mr. Sharan Jagtiani a/w R. K. Satpalkar i/b Mulla & Mulla & Craigie
ig
Blunt and Caroe for the Appellant.
Mr. Mainsh Bhatt, Senior Advocate, i/b D Brijesh for the Respondent.
H
----------------------------------
CORAM : MOHIT S. SHAH, C.J. &
B.P. COLABAWALLA, J.
y
----------------------------------
ba
Act, 1996 (“the Act”) takes exception to two orders passed by the learned
Single Judge. The Appellant herein was the Claimant before the Arbitral
Tribunal. The Tribunal passed an Award dated 30th June, 2005 in favour of
the Appellant and the Respondent challenged the same by filing a Petition
VRD 1 of 28
under section 34 of the Act. In the said Petition, the first order was passed
rt
by the learned Single Judge dated 9th November, 2006 (“1st impugned
ou
order”) whereby the Award passed by the Arbitral Tribunal in favour of
the Appellant was set aside. The second order was passed by the learned
C
Judge on 21st December, 2006 (“2nd impugned order”) which was on an
Respondent. By this order, the learned Judge, added further reasons in the
h
1st impugned order for rejecting another claim granted to the Appellant.
ig
This Appeal was admitted by a Division Bench of this Court on 26 th April,
H
2007 and has now come up for final hearing before us.
y
2. The facts stated briefly, and which are material for our purpose, are
ba
that the Appellant had bid for a contract for execution of work of a “Crude
Respondent accepted the Appellant's bid and the work was awarded to the
B
Contract (SCC). The Contract Completion Date was fixed as eight months
from the date of the said fax i.e. 22nd October, 1998.
VRD 2 of 28
rt
3. As per the requirement of the contract, the Appellant established two
ou
bank guarantees (i) towards a security deposit for Rs.35,08,260/-; and (ii)
C
Rs.1,40,33,000/-. The Appellant was unable to adhere to the Contract
Completion Date i.e. 22nd October, 1998 and completed the work only on
h
Respondent to the Appellant on 3rd October, 2000 and on 6th October, 2000
ig
the Appellant raised its final bill for Rs.2,37,87,663/-.
H
4. As disputes arose between the parties, the Respondent wrote a letter
y
2002), inter alia seeking to restrain the Respondent from invoking the said
bank guarantees. Whilst the section 9 Petition was pending, the Appellant
also addressed a notice dated 24th January, 2002 invoking the arbitration
VRD 3 of 28
rt
ultimately disposed of in terms of the consent terms that were drawn up
ou
between the parties and filed before the Court on 1 st April, 2002. The
C
“The Petitioner and Respondent No.1 have arrived at a consensus,
which is recorded hereunder :-
1. The Petitioner and the Respondent No.1 agree that the
arbitration between them shall be time bound and shall be
concluded within a period of 8 months from the month following
h
the month of appointment of Arbitrator. The Arbitrator shall also
be bound by this condition. Subject to the above the Petitioner
ig
and the Respondent No.1 by mutual consent may extend the time
to conclude the arbitration, if necessary.
2. In lieu of the bank guarantee No.98/85 for Rs.35,08,260 and
H
Guarantee No.98/84 for Rs.1,40,33,000/- the Petitioner has
agreed to furnish a fresh bank guarantee for an amount of
Rs.65,00,000/- Lakhs. The said bank guarantee shall be kept in
force till the final determination of the disputes by the Arbitral
Tribunal by an Award unless the Arbitral Tribunal on an
y
(emphasis supplied)
VRD 4 of 28
6. On the very same day, i.e. on 1 st April 2002, the Appellant also
rt
agreed to the appointment of the Arbitrator, Mr H. Parikh, to act as the
ou
Sole Arbitrator. Accordingly, the Respondent appointed Mr H. Parikh to
act as the Sole Arbitrator under its letter dated 2 nd April, 2002. As Mr H.
C
Parikh could not make his Award in the time frame fixed in the consent
terms (eight months), a new Arbitrator was appointed in his place, who
was a retired Judge of this Court (Mr Justice A.B. Palkar). Before the
h
Arbitral Tribunal (the new Arbitrator), the Appellant had in all, made seven
ig
claims described as claims (a) to (g) and which were as follows:-
H
(a) Claim on account of items in the Schedule of Rates
(SOR) amounting to Rs.82,19,114/- together with
interest at the rate of 18% p.a. from 3rd October, 2000
y
VRD 5 of 28
rt
thereon;
(g) Claim of Rs.61,00,000/- on account of extra work
ou
together with interest thereon;
C
pleadings, and produced their respective evidence. After hearing the parties
and perusing the relevant terms of the contract and the evidence before it,
h
the Arbitral Tribunal granted claims (a), (b), (c), (d) and (g) (either in part
ig
or full), and rejected claims (e) and (f). The operative part of the Arbitral
H
Award reads as under:-
VRD 6 of 28
rt
8. Being aggrieved by the Arbitral Award, the Respondent herein
ou
challenged the same under the provisions of section 34 of the Act. After
hearing the parties, by the 1st impugned order, the learned Single Judge
C
allowed the section 34 Petition and set aside the entire Arbitral Award. The
principal ground of challenge to the Arbitral Award was that the Arbitral
Tribunal could not have issued directions against the Respondent herein
h
(the Petitioner before the learned Single Judge), to make payment of any
ig
amount against claim (d). Claim (d) was for Rs.26,97,759 being the cost
H
incurred in keeping the bank guarantee in force beyond the period required
under the contract, together with interest at 18% per annum till payment.
y
This claim was partly allowed by the Arbitral Tribunal, to the extent of
ba
learned Judge came to the conclusion that claim (d) could not have been
om
contemplated under the contract, and therefore the Arbitral Tribunal had no
B
jurisdiction to award any amount under claim (d). On this basis, and with
no discussion with reference to any other claims, the entire Arbitral Award
VRD 7 of 28
9. After the passing of the 1st impugned order, the Respondent moved
rt
an application for “speaking to the minutes of the order” on the ground
ou
that claim (g) was also a non-notified claim and therefore, for the reasons
given in the 1st impugned order in relation to claim (d), claim (g) also could
C
not have been awarded by the Arbitral Tribunal. The learned Judge,
accepting the aforesaid contention, held that claim (g), like claim (d) was
also not a notified claim and therefore the Arbitral Tribunal ought not to
h
have granted claim (g) also. The learned Judge therefore proceeded to pass
ig
the 2nd impugned order and made substantial modifications in the 1 st
H
impugned order. Being aggrieved by these two orders, the Appellant
first and main ground of challenge was that the learned Single Judge could
not have set aside the entire Award when there was no discussion at all in
B
the 1st impugned order with reference to claims (a) to (c) and (g). He
submitted that the only discussion in the 1st impugned order was with
reference to claim (d), and on that basis, the learned Single Judge set aside
VRD 8 of 28
impermissible and made the order of the learned Single Judge vulnerable
rt
to challenge. He submitted that there was not even a finding in either of
ou
the impugned orders that the claims could not be severed and therefore, by
allowing the Petition with reference to claim (d) or claim (g), the entire
C
Award was required to be set aside.
h
Arbitral Award can be severed and the power of the Court under section 34
ig
of the Act is wide enough to apply the doctrine of severability and / or pass
H
such other directions as are contemplated under section 34(4) of the Act.
There is nothing in the provisions of the Act which would debar the Court
y
for in the facts and circumstances of the case and in accordance with law,
Mr Jagtiani relied upon a Full Bench Judgment of this Court in the case of
R.S. Jiwani v/s Ircon International Ltd. 1 and a judgment of the Supreme
B
Court in the case of J.G. Engineers Pvt. Ltd. v/s Union of India and Anr 2.
was now well settled that the principle of severability applied to setting
VRD 9 of 28
aside an Arbitral Award and the Court had the power to segregate the
rt
Award on items/claims which did not suffer from any infirmity and uphold
ou
it to that extent. In the present case, Mr Jagtiani submitted that claims (a)
to (d) and (g) were ex-facie independent and distinct claims, and therefore
C
the learned Single Judge was in grave error in setting aside the entire
Arbitral Award only on the basis that the Award was unsustainable in
relation claim (d). This was more so in the facts of the present case because
h
the learned Judge did not render any finding that the claims were such that
ig
they could not be severed, was the submission. He submitted that in the
H
present case, there was absolutely no discussion in the 1 st impugned order
as to how claims (a), (b), (c) and (g) were unsustainable. He submitted that
y
the only discussion with reference to claim (g) was in the 2 nd impugned
ba
the order”. This could not have been done in the limited scope of such an
om
9th November, 2006 (1st impugned order), was the submission of Mr.
B
VRD 10 of 28
rt
original order, was the submission. In support of this proposition, Mr.
ou
Jagtiani placed reliance on a Division Bench Judgement of the Gujarat
High Court in the case of Kotak Mahindra Bank Ltd. Vs. Official
C
Liquidator of M/s. Gujarat BD Luggage Ltd. & Ors. 3 He therefore
submitted that both the impugned orders ought to be set aside and the
h
hearing the challenge to the Arbitral Award on all the claims including
ig
claims (d) and (g).
H
12. Mr Jagtiani next submitted that even otherwise, the learned Single
y
Judge erred in holding that claim (d) was not arbitrable. He submitted that
ba
the procedure for notification and the mechanism provided under clause 6
read with clause 9 of the GCC, could never apply in the case of claim (d)
om
as the cause of action for such a claim arose only after the final bill was
keeping the substituted bank guarantee alive after the expiry of the
contract. This claim therefore could never have been notified in the final
bill, was the submission. The submission of the Mr Jagtiani was that from
VRD 11 of 28
rt
parties intended to submit all disputes to arbitration. The disputes that
ou
related to work under the contract could be entertained by following the
C
claim (d) and which were inherently incapable of being subject to the said
h
submission was based on the ground that it could have never been the
ig
intention of the parties that disputes such as the one arising in claim (d),
H
would be adjudicated by a civil suit even though clearly arising out of the
Any other understanding would create a situation where the disputes before
om
We must state over here that Mr Jagtiani very fairly stated before us that
this argument was not canvassed before the learned Single Judge and has
VRD 12 of 28
rt
13. In the alternative to the above argument, Mr Jagtiani submitted that
ou
there was an additional reason for holding that the Arbitral Tribunal had
jurisdiction to award claim (d). This argument was canvassed on the basis
C
of the consent terms (dated 1st April, 2002) arrived at in the Petition filed
under section 9 of the Act. Under these consent terms, the Appellant
h
substituted the two bank guarantees furnished under the contract (for
Rs.35,08,260/- &
ig
Rs.1,40,33,000/-) with a bank guarantee of
within the domain of the Arbitral Tribunal's jurisdiction. Under the said
ba
consent terms, the Appellant was allowed to apply, even pending the
arbitration, for discharge of the bank guarantee. Though this was not done,
om
it would equally have jurisdiction to award the costs to the Appellant for
VRD 13 of 28
rt
therefore submitted that as per the consent terms arrived at between the
ou
parties, there was a novatio to the Arbitration Agreement and therefore
clearly claim (d) was arbitrable. Any other reading of the consent terms
C
would have the effect of partially curtailing the jurisdiction, was the
learned Single Judge was in error in holding that claim (d) was not
h
arbitrable as it was not a notified claim.
ig
H
14. On the other hand, Mr Manish Bhatt, the learned Senior Counsel
appearing on behalf of the Respondent, submitted that all the claims were
y
65. Point Nos. 1), 2) I to VII:- these points are so intertwined that it
is convenient to discuss them together. The major controversy between
B
VRD 14 of 28
rt
15. He submitted that in view of these facts, the learned Single Judge
was fully justified in setting aside the entire Award on the ground that
ou
claim (d) was not arbitrable. In the facts of the present case, it was not
possible to severe the separate claims made before the Arbitral Tribunal
C
and therefore, there was no infirmity in the impugned order, was the
h
severability of claims was not taken before the learned Single Judge and
ig
neither has this contention been specifically raised in the Appeal Memo
H
and therefore we ought not to take cognizance of this argument for the first
remand, Mr Bhatt submitted that even if this Court was inclined to remand
om
the matter back to the learned Single Judge for fresh consideration, the
same may be done only with reference to claims (a), (b) and (c). On the
B
other two claims viz. claims (d) and (g), the learned Judge has given
VRD 15 of 28
rt
17. We have heard the learned counsel at quite some length. We have
ou
perused the Appeal paper-book as well as the written submissions
C
considerable force in the argument of Mr Jagtiani. On perusing the Arbitral
Award, we find that claims (a), (b), (c) and (g) were independent of and
h
distinct from claim (d). In other words, merely because the learned Judge
ig
held that claim (d) was not arbitrable, did not ipso facto mean that claims
(a), (b), (c) and (g) also automatically failed. In fact, there is no such
H
finding of the learned Judge in this regard. For each of these claims, points
the affirmative.
ba
om
contend that all the claims were interlinked, is wholly misconceived. The
of the Award deals with Point Nos.1 & 2 (I to VII). Point No.1 as framed
by the Arbitral Tribunal (on page 75 of the paper-book) was whether the
specified due to various hindrances, and whether as per the contract, it was
rt
the obligation of the Respondent to remove the said hindrances, which the
ou
Respondent failed to discharge. This point was answered in the affirmative
and in favour of the Appellant. Similarly, Point No.2 was whether the
C
Claimant proved that the contract work could not be completed in the
VII (page 75 of the paper-book). On perusing the Award we find that these
h
two points have nothing to do with claim (d) which was covered under
ig
Point No.9, and which required the Claimant (Appellant before us) to
H
prove that it was entitled to recover Rs.26,97,579/- as costs for keeping the
bank guarantee alive beyond the period required under the contract. We are
y
therefore of the view that the reliance placed by Mr. Bhatt on paragraph 65
ba
Bhatt that the claims before the Arbitral Tribunal were so intertwined that
on the failure of one claim (claim (d) in the present case), the entire Award
B
was liable to be set aside. It would be important to note here, that in both
the impugned orders, there is no finding by the learned Judge that since
claim (d), or for that matter claim (g), were so intertwined with the other
VRD 17 of 28
claims, that failure of these two claims resulted in a failure of all the other
rt
claims also.
ou
19. On the issue of severability, the law is now quite well settled. The
C
reliance placed by Mr Jagtiani on the judgment of the Full Bench of this
Court in the case of R.S. Jiwani v/s Ircon International Ltd.1 (supra) is
h
well founded. Paragraphs 36 to 38 of the judgment, and which are material
claimants and the counter-claim filed by the company. The claimant was
satisfied with the award. An enforceable right by way of decree accrued
to the claimant in terms of sections 32, 35 and 36 of the Act. The compa-
ny approached this court by filing a petition under section 34 which par-
tially allowed in the sense that out of 15 claims allowed by the Arbitra-
om
tor in favour of the claimant, held that other claims were not payable to
the claimants but still did not make any observation that the award in so
far as it rejects the remaining claims and the counterclaim were unsus-
tainable. However, to conclude, the learned Single Judge despite having
upheld the claims in favour of the claimants, set aside the entire award
B
VRD 18 of 28
rt
completely frustrated if submissions of the respondent are accepted.
Partial challenge to an award is permissible then why not partial setting
aside of an award. In a given case, a party may be satisfied with major
ou
part of the award but is still entitled to challenge a limited part of the
award. It is obligatory on the court to deal with such a petition under
section 34(1)(2) of the Act. We may further take an example where the
Arbitral Tribunal has allowed more than one claim in favour of the
claimant and one of such claim is barred by time while all others are
C
within time and can be lawfully allowed in favour of the claimant. The
court while examining the challenge to the award could easily severe the
time barred claim which is hit by law of limitation. To say that it is
mandatory for the court without exception to set aside an award as a
whole and to restart the arbitral proceeding all over again would be un-
h
just, unfair, inequitable and would not in any way meet the ends of jus-
tice. ig
37. The interpretation put forward by the respondents is bound to
cause greater hardship, inconvenience and even injustice to some extent
H
to the parties. The process of arbitration even under 1996 Act encum-
bersome process which concludes after considerable lapse of time. To
compel the parties, particularly a party who had succeeded to undergo
the arbitral process all over again does not appear to be in conformity
with the scheme of the Act. The provisions of section 34 are quite pari
y
materia to the provisions of Article 34 of the Model Law except that the
proviso and explanation have been added to section 34(2)(iv). The at-
ba
tempt under the Model Law and the Indian Law appears to circumscribe
the jurisdiction of the court to set aside an award. There is nothing in
the provisions of the Act and for that matter absolutely nothing in the
Model Law which can debar the court from applying the principle of
severability provided it is otherwise called for in the facts and circum-
om
stances of the case and in accordance with law. The courts will not get
into the merits of the dispute. Thus, the interpretation which should be
accepted by the court should be the one which will tilt in favour of the
Model Laws, scheme of the Act and the objects sought to be achieved by
the Act of 1996.
B
VRD 19 of 28
rt
principle of severability to the award of the Arbitral Tribunal, le-
gality of which is questioned before the court. The Legislature
has vested wide discretion in the court to set aside an award
ou
wholly or partly, of course, within the strict limitations stated in
the said provisions. The scheme of the Act, the language of the
provisions and the legislative intent does not support the view
that judicial discretion of the court is intended to be whittled
down by these provisions.
C
2. The proviso to section 34(2)(a)(iv) has to be read ejusdem gener-
is to the main section, as in cases falling in that category, there
would be an absolute duty on the court to invoke the principle of
severability where the matter submitted to arbitration can clear-
h
ly be separated from the matters not referred to arbitration and
decision thereupon by the Arbitral Tribunal.”
ig (emphasis supplied)
H
20. The Full Bench of this Court has clearly held that there is nothing in
the provisions of the Act which would debar the Court from applying the
y
circumstances of the case, and in accordance with law. The judicial discre-
om
tion vested in the Court in terms of the provisions of section 34 of the Act
takes within its ambit the power to set aside an Arbitral Award partly or
21. In fact, the reliance placed by Mr. Jagtiani on the judgment of the
Supreme Court in the case of J.G. Engineers Pvt. Ltd. v/s Union of India
VRD 20 of 28
and Anr2 (supra), also clearly lays down that if an Award deals with and
rt
decides several claims separately and distinctly, and if the Court finds that
ou
the Award in regard to some of the claims is bad, the Court has the power
to segregate the Award in relation to the claims which do not suffer from
C
any infirmity, and uphold it to that extent. Paragraphs 24 and 25 of the said
h
“Re: Question (ii) ig
24. The arbitrator had considered and dealt with Claims 1, 2, 3, 4 and
5, 6, 7 and 8, 9 and 11 separately and distinctly. The High Court found
that the award in regard to Items 1, 3, 5 and 11 was liable to be set
H
aside. The High Court did not find any error in regard to the award on
Claims 2, 4, 6, 7, 8 and 9, but nevertheless chose to set aside the award
in regard to these six items, only on the ground that in the event
Counterclaims 1 to 4 were to be allowed by the arbitrator on
reconsideration, the respondents would have been entitled to adjust the
y
25. It is now well settled that if an award deals with and decides several
om
claims separately and distinctly, even if the court finds that the award in
regard to some items is bad, the court will segregate the award on items
which did not suffer from any infirmity and uphold the award to that
extent. As the award on Items 2, 4, 6, 7, 8 and 9 was upheld by the civil
court and as the High Court in appeal did not find any infirmity in
B
regard to the award on those claims, the judgment of the High Court
setting aside the award in regard to Claims 2, 4, 6, 7, 8 and 9 of the
appellant, cannot be sustained. The judgment to that extent is liable to
be set aside and the award has to be upheld in regard to Claims 2, 4, 6,
7, 8 and 9.”
(emphasis supplied)
VRD 21 of 28
rt
22. It is therefore now well settled that the judicial discretion vested in
the Court in terms of the provisions of section 34 of the Act takes within its
ou
ambit the power to set aside an Award partly or wholly depending on the
C
provisions of the Act which would debar the Court from applying the
h
circumstances of the case. To be fair to Mr. Bhatt, he did not dispute the
ig
aforesaid proposition.
H
23. In the present case, we have no doubt that claims (a), (b), (c) and (g)
y
were distinct and independent claims from claim (d). We are therefore of
ba
the view that the entire Arbitral Award could not have been set aside
merely on the ground that claim (d) was not arbitrable. We find that the
om
to which claim could be upheld and which claim ought to have been
of the view that the impugned orders ought to be set aside and the matter
VRD 22 of 28
rt
24. Having held so, the only question that now needs to be answered is
ou
to the extent of the remand. Mr Jagtiani submitted that the matter ought to
be remanded back with reference to all claims including claims (d) and (g).
C
On the other hand, Mr Bhatt submitted that the learned Judge having
h
claim (d) as well as claim (g), the remand ought to be only with reference
that the same also ought to be remanded back alongwith claims (a), (b) and
y
the reasons given for setting aside claim (g) was in the 2 nd impugned order
om
order”. In this regard, we fully agree with the ratio of the judgment of the
Gujarat High Court in the case of Kotak Mahindra Bank Ltd. Vs. Official
B
Liquidator of M/s. Gujarat BD Luggage Ltd. & Ors 3 (supra). Before the
Gujarat High Court, the Appellant therein had challenged the order passed
VRD 23 of 28
Whilst disposing of the said application, the learned Single Judge passed a
rt
detailed order and issued further directions. Being aggrieved thereby,
ou
Kotak Mahindra Bank Ltd. (the Appellant therein) approached the Division
Bench. In this background, the Gujarat High Court held that once a
C
judgment / order is pronounced and if any party wants any correction in the
party can apply to the Court for correction. The Gujarat High Court further
h
held that after dictating the judgment / order, if any mistake on factual
ig
aspects has crept in while transcribing the same, those also can be
H
corrected on an application for “speaking to the minutes of the order”. So
also, if any argument of either side is missed in the original order, then
y
also, on such application, the concerned Court can modify the original
ba
“7. We have heard learned Counsel for the parties at length and we
have also gone through the order of the learned Single Judge passed
below the note for speaking to minutes. It is required to be noted that
once, a judgment/order is pronounced and if, any party to the same
wants any rectification of any typographical or clerical mistake
regarding date or number, such a party may apply to the concerned
Court for correcting such an error in the judgment/order. After dictating
a judgment/order, if any, mistake on factual aspect has crept in while
transcribing the same, same can be corrected by way of filing a note for
VRD 24 of 28
rt
such argument in the original order to give complete effect to it.
However, a note for speaking to minutes cannot be considered at par
with a review application or in a given case with an application for
ou
clarification/modification of an order. A note for speaking to minutes
can never be considered to be an application of such a nature. Such a
note is, therefore, not even given any number by the Registry. A note for
speaking to minutes is, required to be entertained only for the limited
purpose of correcting a typographical error or an error through
C
oversight, which may have crept in while transcribing the same. The
present note for speaking to minutes was filed only for the limited
purpose of drawing the attention of the Court to a particular mistake
and the scope of deciding such a note was, therefore, extremely limited.
Surely, while deciding such a note, there is no/scope for modifying the
h
original order or to give further direction in connection with the earlier
order and as such the original foundation of the order cannot be
ig
changed by passing a subsequent order below note for speaking to
minutes.
H
In the instant case, while passing the impugned order, the learned Single
Judge has given further directions, and thereby, has virtually modified
the original order. Such a course was not open to the learned Single
Judge, while deciding a note for speaking to minutes. When a note for
speaking to minutes is filed, it is not required to be argued, as if the
y
that the same could never have been passed on an application for
VRD 25 of 28
rt
inadvertence or oversight, the reasons given in the 2nd impugned order were
ou
missed out in the original order (1st impugned order). The 2nd impugned
C
27. Mr Bhatt however submitted that the same arguments that were
h
advanced in relation to claim (d) were also canvassed in relation to claim
ig
(g). Since these arguments [with reference to claim (g)] were not recorded
2nd impugned order does not record the same. The 2 nd impugned order does
ba
not proceed on the basis that arguments with reference to claim (g) had in
fact been advanced, but the same had not been incorporated in the original
om
order due to any oversight. The 2nd impugned order in fact independently
records the satisfaction of the learned Judge that claim (g), like claim (d),
B
was also not notified, and therefore, for the reasons that have been given in
relation to claim (d), the Arbitral Tribunal ought not to have awarded claim
(g) also. To our mind, such an order could never have been passed on an
VRD 26 of 28
Gujarat High Court, and in our view rightly, an application for “speaking
rt
to the minutes of the order” is required to be entertained only for the
ou
limited purpose of correcting a typographical error or an error through
oversight, which may have crept in while transcribing the original order.
C
Therefore, as far as claim (g) is concerned, the 2 nd impugned order cannot
stand and has to be set aside, and claim (g) will also have to be remanded
h
ig
28. This brings us to the question whether the Arbitration Petition ought
H
to be remanded back also with reference to claim (d). It is true that the
learned Single Judge has given detailed reasons for setting aside the Award
y
in relation to claim (d) by holding that the same was not arbitrable. It is
ba
also true that the arguments advanced before us by Mr Jagtiani were not
opinion on this issue, we think that it would be in the fitness of things if the
Judge. This is more so since we have already held that the challenge to
claims (a), (b), (c) and (g) ought to be remanded back to the learned Single
VRD 27 of 28
rt
would be served even if the challenge to claim (d) is remanded back to the
ou
learned Single Judge for consideration afresh.
C
29. For all the aforesaid reasons, we allow the Appeal and set aside the
orders dated 9th November, 2006 and 21st December, 2006 and direct that
h
Arbitration Petition No.408 of 2005 be restored to file of the learned Single
ig
Judge and be heard afresh. It is clarified that we have not expressed any
opinion on the merits of the matter and the learned Single Judge shall
H
decide the challenge to the Arbitral Award on is own merits and in
this judgment. The Appeal is allowed in the aforesaid terms. In the facts
ba
CHIEF JUSTICE
B
B.P. COLABAWALLA, J.
VRD 28 of 28