Barlow Park (Phase1)BASE Rev.1.

3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10

Time Now - 23/06/2023


1 A0... Barlow Park (Phase 1) BASE Rev.00 - Table Form - 429 14 Jul 22 02 May 24 26 Jun 23 30 May 24 1 209
2022.09.19
2 A0... Appointments 306 14 Jul 22 02 Nov 23 26 Jun 23 03 Nov 23 1 86
B A031 Internal Door & Frames, etc 0 27 Feb 23 26 Jun 23 A031 Internal Door & Frames, etc
F A037 Waterproofing - Slabs 0 03 Mar 23 10 Jul 23 A037 Waterproofing - Slabs
B A038 Aluminium, Shopfronts, Windows & Doors, etc 0 05 May 23 26 Jun 23 A038 Aluminium, Shopfronts, Windows & Doors, etc
F F997 Residential Punchout Windows 0 20 Apr 23 26 Jun 23 F997 Residential Punchout Windows
F A039 Mechanical extraction & Ventilation 0 27 Jun 23 21 Jul 23 A039 Mechanical extraction & Ventilation
F A040 Ceilings & Partitions incl. Part doors & Glazed Part. 0 19 Jun 23 01 Aug 23 A040 Ceilings & Partitions incl. Part doors & Glazed Part.
F G137 Smoke Detection Basements - Retail & Residential 0 22 Jun 23 14 Jul 23 G137 Smoke Detection Basements - Retail & Residential
F F948 Electronic Installation CCTV & Access Control 0 04 Jul 23 19 Jul 23 F948 Electronic Installation CCTV & Access Control
F A041 Handrails & Balustrades, etc 0 27 Jun 23 25 Jul 23 A041 Handrails & Balustrades, etc
F A042 Joinery - Skirtings, Cills, Mirrors, etc 0 27 Jun 23 21 Jul 23 A042 Joinery - Skirtings, Cills, Mirrors, etc
F G133 Floor Coverings/Vinyl 0 03 Jul 23 26 Jul 23 G133 Floor Coverings/Vinyl
F F996 Epoxy Floors 0 03 Jul 23 14 Jul 23 F996 Epoxy Floors
F G134 Shower Screens 0 03 Jul 23 26 Jul 23 G134 Shower Screens
F A043 Tiling 0 22 Jun 23 19 Jul 23 A043 Tiling
F A044 Vanity Slabs, etc 0 28 Jun 23 13 Jul 23 A044 Vanity Slabs, etc
F G034 Kitchens Units & Tops & Stoves 0 21 Jul 23 21 Jul 23 G034 Kitchens Units & Tops & Stoves
F F998 Iron Mongery 0 21 Jun 23 05 Jul 23 F998 Iron Mongery
F F952 Retail Feature Stairs 1 07 Nov 22 14 Nov 22 26 Jun 23 26 Jun 23 F952 Retail Feature Stairs
F F953 Retail Steel Stairs 0 07 Nov 22 14 Nov 22 26 Jun 23 F953 Retail Steel Stairs
B F958 Laundry Shaft/ Chute 0 20 Jul 23 20 Jul 23 F958 Laundry Shaft/ Chute
F F954 Statutory Signage 0 06 Jul 23 24 Jul 23 F954 Statutory Signage
F A049 Structural Steelwork 0 31 Jul 23 08 Aug 23 A049 Structural Steelwork
F G135 Turnstiles & Swing Gates 0 28 Jun 23 19 Jul 23 G135 Turnstiles & Swing Gates
F F940 Sundry Steel work 0 07 Nov 22 14 Nov 22 26 Jun 23 F940 Sundry Steel work
F G036 Standby Generators 0 07 Jul 23 11 Jul 23 G036 Standby Generators
F G136 Curro Communal Playground 0 15 Jun 23 26 Jun 23 G136 Curro Communal Playground
F F943 Communal Pool 5 07 Nov 22 14 Nov 22 26 Jun 23 03 Jul 23 F943 Communal Pool
F G038 Retail Canopy 0 30 Mar 23 26 Jun 23 G038 Retail Canopy
F G039 Steel & Timber Roofs 0 30 Mar 23 26 Jun 23 G039 Steel & Timber Roofs
F F939 Solar Panels for Parking Roof 0 07 Nov 22 14 Nov 22 26 Jun 23 F939 Solar Panels for Parking Roof

2 A0... Structure 275 09 Sep 22 01 Nov 23 26 Jun 23 15 Nov 23 40 94


3 A054 Structure - Core/Shafts 226 09 Sep 22 02 Jun 23 26 Jun 23 31 Aug 23 40 45
4 A094 Shaft # 2 - GL.E-F/16-17 213 06 Oct 22 02 Jun 23 26 Jun 23 31 Aug 23 53 45
5 A125 7th To 8th 9 13 Mar 23 27 Mar 23 26 Jun 23 28 Jun 23 215 3 A125 7th To 8th

5 A128 8th To 9th 11 27 Mar 23 06 Apr 23 26 Jun 23 11 Jul 23 A128 8th To 9th

5 A131 9th To 10th 9 06 Apr 23 24 Apr 23 11 Jul 23 21 Jul 23 A131 9th To 10th

5 A134 10th To 11th 9 24 Apr 23 08 May 23 21 Jul 23 03 Aug 23 A134 10th To 11th

5 A137 11th To 12th 19 08 May 23 02 Jun 23 03 Aug 23 31 Aug 23 A137 11th To 12th

4 A141 Shaft # 4 - GL.S-R/03-04 191 09 Sep 22 03 May 23 26 Jun 23 10 Jul 23 40 10


5 A172 7th To 8th 24 14 Feb 23 03 May 23 26 Jun 23 10 Jul 23 207 10 A172 7th To 8th

4 F328 Shaft # 3 - GL.U-V/09-10 181 19 Sep 22 23 Mar 23 26 Jun 23 05 Jul 23 47 7


5 F359 7th To 8th 19 22 Feb 23 23 Mar 23 26 Jun 23 05 Jul 23 209 7 F359 7th To 8th

3 A629 Ground Floor (Podium) 139 09 Nov 22 11 May 23 26 Jun 23 18 Jul 23 98 16


4 A813 Grid 24-41 (Retail) 117 09 Nov 22 11 May 23 26 Jun 23 18 Jul 23 120 16
5 A839 Pour 03-01 91 06 Dec 22 03 Feb 23 26 Jun 23 23 Jun 23 130
6 A847 Cure & strip deck 79 13 Jan 23 03 Feb 23 26 Jun 23 23 Jun 23 142
F F664 Access 0 06 Feb 23 26 Jun 23 F664 Access

5 A863 Pour 05-01 77 24 Jan 23 11 May 23 26 Jun 23 18 Jul 23 160 16


6 F728 Structural Steel Restaurant area 42 02 Mar 23 26 Apr 23 26 Jun 23 05 Jul 23 186 7
S F729 Erect Structural Steel Roof 23 02 Mar 23 06 Apr 23 26 Jun 23 27 Jun 23 186 2 F729 Erect Structural Steel Roof
F F730 Paint Steelwork/Beamfilling 15 31 Mar 23 26 Apr 23 26 Jun 23 05 Jul 23 212 7 F730 Paint Steelwork/Beamfilling

6 F731 Roof Sheeting 12 24 Apr 23 11 May 23 03 Jul 23 18 Jul 23


F732 Roof Sheeting 12 24 Apr 23 11 May 23 03 Jul 23 18 Jul 23 F732 Roof Sheeting

3 B291 04th FLoor 40 26 Apr 23 19 Jun 23 26 Jun 23 04 Jul 23 187 6 B291 04th FLoor

3 B426 05th FLoor 44 17 May 23 07 Jul 23 26 Jun 23 21 Jul 23 196 19 B426 05th FLoor

3 B561 06th FLoor 42 06 Jun 23 26 Jul 23 26 Jun 23 11 Aug 23 211 32 B561 06th FLoor

3 B696 07th FLoor 39 27 Jun 23 16 Aug 23 05 Jul 23 31 Aug 23


4 B697 Grid 01-10 (Block 1) 23 27 Jun 23 27 Jul 23 05 Jul 23 07 Aug 23 B697 Grid 01-10 (Block 1)

4 B716 Grid 10-23 (Block 2) 25 11 Jul 23 16 Aug 23 25 Jul 23 31 Aug 23 B716 Grid 10-23 (Block 2)

3 B939 Structural Roof 65 31 Jul 23 01 Nov 23 08 Aug 23 15 Nov 23


5 B940 Grid 01-4/B-W (Block 1) 48 31 Jul 23 21 Sep 23 08 Aug 23 19 Oct 23
6 B941 Structural Steel 44 31 Jul 23 15 Sep 23 08 Aug 23 13 Oct 23
F B942 Erect Structural Steel/Timber Roof 12 31 Jul 23 16 Aug 23 08 Aug 23 24 Aug 23 B942 Erect Structural Steel/Timber Roof

2 B9... Finishes 266 07 Nov 22 09 Apr 24 26 Jun 23 18 Apr 24 136 181


3 B947 Basements 188 29 Mar 23 14 Dec 23 26 Jun 23 28 Nov 23 136 103
4 B948 Basement -02 187 29 Mar 23 13 Dec 23 26 Jun 23 27 Nov 23 136 102
5 B949 Wet Trades & Services 93 29 Mar 23 22 Jun 23 26 Jun 23 06 Jul 23 136 8
B960 Plaster 20 11 May 23 08 Jun 23 26 Jun 23 06 Jul 23 194 8 B960 Plaster

5 B961 Finishes 89 16 May 23 22 Nov 23 26 Jun 23 08 Nov 23


6 B962 General Area 81 09 Jun 23 22 Nov 23 07 Jul 23 08 Nov 23
B963 1st Coat Paint 7 09 Jun 23 20 Jun 23 07 Jul 23 17 Jul 23 B963 1st Coat Paint
B964 2nd Fix Plumbing 5 19 Jun 23 26 Jun 23 14 Jul 23 20 Jul 23 B964 2nd Fix Plumbing
B965 2nd Fix Sprinklers 5 19 Jun 23 26 Jun 23 14 Jul 23 20 Jul 23 B965 2nd Fix Sprinklers
B966 2nd Fix Ventilation 5 20 Jun 23 27 Jun 23 17 Jul 23 21 Jul 23 B966 2nd Fix Ventilation

Page 1 of 6
Candy 2.01f14.8 (2 6 0) R
Barlow Park (Phase1)BASE Rev.1.3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10

Time Now - 23/06/2023


B967 2nd Fix Electrical / DATA / CCTV / AV 5 22 Jun 23 29 Jun 23 19 Jul 23 25 Jul 23 B967 2nd Fix Electrical / DATA / CCTV / AV
B968 Paint Columns 6 21 Jun 23 29 Jun 23 18 Jul 23 25 Jul 23 B968 Paint Columns
B969 Inst.ventilation Louvers 6 20 Jun 23 28 Jun 23 17 Jul 23 24 Jul 23 B969 Inst.ventilation Louvers
B970 Joinery & Ironmongery (general) 3 27 Jun 23 29 Jun 23 21 Jul 23 25 Jul 23 B970 Joinery & Ironmongery (general)

6 B973 Ventelation shaft 1 19 21 Jun 23 18 Jul 23 18 Jul 23 15 Aug 23 B973 Ventelation shaft 1

6 B980 Ventelation shaft 2 24 27 Jun 23 31 Jul 23 21 Jul 23 28 Aug 23 B980 Ventelation shaft 2

6 B987 Fire, Electrical, Mechanical rooms and risers 17 16 May 23 08 Jun 23 26 Jun 23 19 Jul 23 B987 Fire, Electrical, Mechanical rooms and risers

6 C001 Store Room 17 27 Jun 23 19 Jul 23 21 Jul 23 16 Aug 23 C001 Store Room

6 C015 Lift Lobby 21 09 Jun 23 11 Jul 23 07 Jul 23 07 Aug 23 C015 Lift Lobby

4 C031 Basement -01 165 11 May 23 14 Dec 23 26 Jun 23 28 Nov 23 159 103
5 C032 Wet Trades & Services 101 11 May 23 31 Jul 23 26 Jun 23 22 Aug 23 159 39 C032 Wet Trades & Services

3 C114 Retail 193 07 Nov 22 06 Dec 23 26 Jun 23 14 Dec 23 142 114


4 C115 Line Shops 182 07 Nov 22 25 Oct 23 26 Jun 23 28 Nov 23 142 103
5 C116 Wet Trades, Partitions, Bulkeads & 1st Fix Services 128 23 Feb 23 24 Jul 23 26 Jun 23 07 Sep 23 142 49
F C118 Electrical 1fix (ce) 55 22 Mar 23 15 Jun 23 18 Jul 23 31 Jul 23 169 9 C118 Electrical 1fix (ce)
F C119 Plumbing 1fix (ce) 55 22 Mar 23 15 Jun 23 24 Jul 23 31 Jul 23 169 5 C119 Plumbing 1fix (ce)
F C120 Hvac 1fix (ce) 55 22 Mar 23 15 Jun 23 18 Jul 23 31 Jul 23 169 9 C120 Hvac 1fix (ce)
E G187 Clicks - Exstract Fan 10 29 May 23 12 Jun 23 26 Jun 23 07 Jul 23 220 9 G187 Clicks - Exstract Fan
F C121 Sprinkler - Void 55 22 Mar 23 15 Jun 23 10 Jul 23 12 Jul 23 169 3 C121 Sprinkler - Void
C122 Brickwork - Internal/div 55 27 Feb 23 25 May 23 26 Jun 23 27 Jul 23 143 23 Brickwork - Internal/div
C123 Plaster - Internal/div 54 23 Mar 23 26 Jun 23 01 Aug 23 07 Aug 23 191 5 C123 Plaster - Internal/div
C124 Screed 20 27 Jun 23 24 Jul 23 08 Aug 23 07 Sep 23 C124 Screed
C125 Electrical 1f (Wall & Soffit) 50 15 Mar 23 05 Jun 23 04 Jul 23 02 Aug 23 154 21 C125 Electrical 1f (Wall & Soffit)
C126 Plumbing 1f ((Wall & Soffit) 50 15 Mar 23 05 Jun 23 04 Jul 23 02 Aug 23 154 21 C126 Plumbing 1f ((Wall & Soffit)
F F452 Screed & Waterproofing slab above retail 61 23 Feb 23 01 Jun 23 05 Jul 23 11 Jul 23 167 5 F452 Screed & Waterproofing slab above retail
C127 Paint 1ct 25 02 Jun 23 10 Jul 23 10 Jul 23 15 Aug 23 C127 Paint 1ct
C128 Steel Sub-grid To Mall Bulkhead 19 05 Jun 23 03 Jul 23 18 Jul 23 15 Aug 23 C128 Steel Sub-grid To Mall Bulkhead
C129 Mall Bulkhead Grid 15 19 Jun 23 10 Jul 23 01 Aug 23 22 Aug 23 C129 Mall Bulkhead Grid
C130 Mall Bulkhead Electrical 1fix 15 22 Jun 23 13 Jul 23 04 Aug 23 28 Aug 23 C130 Mall Bulkhead Electrical 1fix
C131 Mall Bulkhead Board & Skim 15 27 Jun 23 17 Jul 23 08 Aug 23 30 Aug 23 C131 Mall Bulkhead Board & Skim

5 C132 Finishes 181 07 Nov 22 25 Oct 23 26 Jun 23 28 Nov 23 143 103


6 C163 Shop 03 (Clicks) - 709m2 - 60 - OK 143 07 Nov 22 22 Jun 23 26 Jun 23 03 Oct 23 143 65
7 C164 Trading Floor 134 07 Nov 22 08 Jun 23 26 Jun 23 18 Sep 23 143 56
F C166 Electrical 1f (wl) 20 14 Feb 23 14 Mar 23 26 Jun 23 28 Jun 23 143 3 Electrical 1f (wl)
F C167 Plaster 16 21 Feb 23 23 Mar 23 26 Jun 23 29 Jun 23 191 4 C167 Plaster
F C168 Bulkheads 16 06 Mar 23 17 Apr 23 27 Jun 23 19 Jul 23 C168 Bulkheads
C169 Ceiling Grids 12 14 Mar 23 02 May 23 05 Jul 23 20 Jul 23 C169 Ceiling Grids
C170 Electrical 2fix (ce) 25 28 Mar 23 09 May 23 11 Jul 23 18 Jul 23 202 6 C170 Electrical 2fix (ce)
C171 Hvac 2fix (ce) 25 28 Mar 23 09 May 23 13 Jul 23 24 Jul 23 204 8 C171 Hvac 2fix (ce)
C172 Sprinkler 2fix (ce) 25 28 Mar 23 09 May 23 21 Jul 23 24 Jul 23 198 2 C172 Sprinkler 2fix (ce)
C173 Paint 1ct 15 28 Mar 23 20 Apr 23 11 Jul 23 01 Aug 23 C173 Paint 1ct
C174 Floor Tiles 25 04 Apr 23 16 May 23 18 Jul 23 23 Aug 23 C174 Floor Tiles
C175 Front Stores/baby Change Ceilings 3 24 Apr 23 26 Apr 23 02 Aug 23 04 Aug 23 C175 Front Stores/baby Change Ceilings
C176 Front Stores/baby Change Tiling 4 28 Apr 23 04 May 23 07 Aug 23 11 Aug 23 C176 Front Stores/baby Change Tiling

6 C193 Shop 05 (Hair) - 73m2 - 30 - OK 53 26 Apr 23 11 Jul 23 26 Jun 23 13 Sep 23


7 C194 Services (shop) 3 26 Apr 23 02 May 23 26 Jun 23 28 Jun 23
F C195 Electrical 2fix 3 26 Apr 23 02 May 23 26 Jun 23 28 Jun 23 C195 Electrical 2fix
F C196 Plumbing 2fix 3 26 Apr 23 02 May 23 26 Jun 23 28 Jun 23 C196 Plumbing 2fix
F C197 Hvac 2fix 3 26 Apr 23 02 May 23 26 Jun 23 28 Jun 23 C197 Hvac 2fix
F C198 Sprinkler 2fix 3 26 Apr 23 02 May 23 26 Jun 23 28 Jun 23 C198 Sprinkler 2fix

7 C199 Fit-out (shop) 39 03 May 23 26 Jun 23 29 Jun 23 28 Aug 23


C200 Ceiling Grids 7 03 May 23 11 May 23 29 Jun 23 10 Jul 23 C200 Ceiling Grids
G091 Floor Tiles 7 30 May 23 08 Jun 23 07 Jul 23 17 Jul 23 G091 Floor Tiles
C201 Paint 1ct 5 12 May 23 18 May 23 14 Jul 23 20 Jul 23 C201 Paint 1ct
C202 Shopfront 5 12 May 23 18 May 23 14 Jul 23 20 Jul 23 C202 Shopfront
C203 Door & Ironnmongery 4 19 May 23 24 May 23 21 Jul 23 26 Jul 23 C203 Door & Ironnmongery
C204 Install Whb 4 25 May 23 31 May 23 27 Jul 23 02 Aug 23 C204 Install Whb
C205 Tile:splashback To Whb 4 01 Jun 23 06 Jun 23 03 Aug 23 08 Aug 23 C205 Tile:splashback To Whb
C206 Db:wire-in 4 25 May 23 31 May 23 27 Jul 23 02 Aug 23 C206 Db:wire-in
C207 Ceiling:drop In-boards 4 25 May 23 31 May 23 27 Jul 23 02 Aug 23 C207 Ceiling:drop In-boards
C208 Electrical Ffix 4 01 Jun 23 06 Jun 23 03 Aug 23 08 Aug 23 C208 Electrical Ffix
C209 Hvac Ffix 4 25 May 23 31 May 23 27 Jul 23 02 Aug 23 C209 Hvac Ffix
C210 Sprinkler Ffix 4 25 May 23 31 May 23 27 Jul 23 02 Aug 23 C210 Sprinkler Ffix

6 C221 Shop 07 (ATM) - 15m2 - 30 57 09 May 23 20 Jul 23 26 Jun 23 19 Sep 23


7 C222 Services (shop) 3 09 May 23 11 May 23 26 Jun 23 28 Jun 23
F C223 Electrical 2fix 3 09 May 23 11 May 23 26 Jun 23 28 Jun 23 C223 Electrical 2fix
F C224 Plumbing 2fix 3 09 May 23 11 May 23 26 Jun 23 28 Jun 23 C224 Plumbing 2fix
F C225 Hvac 2fix 3 09 May 23 11 May 23 26 Jun 23 28 Jun 23 C225 Hvac 2fix
F C226 Sprinkler 2fix 3 09 May 23 11 May 23 26 Jun 23 28 Jun 23 C226 Sprinkler 2fix

7 C227 Fit-out (shop) 43 12 May 23 05 Jul 23 29 Jun 23 04 Sep 23


C228 Ceiling Grids 7 12 May 23 22 May 23 29 Jun 23 10 Jul 23 C228 Ceiling Grids
C229 Paint 1ct 5 23 May 23 30 May 23 11 Jul 23 17 Jul 23 C229 Paint 1ct
C230 Shopfront 5 23 May 23 30 May 23 21 Jul 23 27 Jul 23 C230 Shopfront
C231 Door & Ironnmongery 4 31 May 23 05 Jun 23 18 Jul 23 21 Jul 23 C231 Door & Ironnmongery
C232 Install Whb 4 06 Jun 23 09 Jun 23 31 Jul 23 03 Aug 23 C232 Install Whb
C234 Db:wire-in 4 06 Jun 23 09 Jun 23 31 Jul 23 03 Aug 23 C234 Db:wire-in
C235 Ceiling:drop In-boards 4 06 Jun 23 09 Jun 23 31 Jul 23 03 Aug 23 C235 Ceiling:drop In-boards
C236 Electrical Ffix 4 12 Jun 23 15 Jun 23 04 Aug 23 10 Aug 23 C236 Electrical Ffix
C237 Hvac Ffix 4 06 Jun 23 09 Jun 23 31 Jul 23 03 Aug 23 C237 Hvac Ffix
C238 Sprinkler Ffix 4 06 Jun 23 09 Jun 23 31 Jul 23 03 Aug 23 C238 Sprinkler Ffix

6 C249 Shop 09 (PepH) - 262m2 - 60 59 07 Nov 22 01 Aug 23 26 Jun 23 21 Sep 23


7 C250 Services (shop) 3 18 May 23 22 May 23 26 Jun 23 28 Jun 23

Page 2 of 6
Candy 2.01f14.8 (2 6 0) R
Barlow Park (Phase1)BASE Rev.1.3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10

Time Now - 23/06/2023


F C251 Electrical 2fix 3 18 May 23 22 May 23 26 Jun 23 28 Jun 23 C251 Electrical 2fix
F C252 Plumbing 2fix 3 18 May 23 22 May 23 26 Jun 23 28 Jun 23 C252 Plumbing 2fix
F C253 Hvac 2fix 3 18 May 23 22 May 23 26 Jun 23 28 Jun 23 C253 Hvac 2fix
F C254 Sprinkler 2fix 3 18 May 23 22 May 23 26 Jun 23 28 Jun 23 C254 Sprinkler 2fix

7 C255 Fit-out (shop) 45 07 Nov 22 14 Jul 23 29 Jun 23 06 Sep 23


C256 Ceiling Grids 7 23 May 23 01 Jun 23 29 Jun 23 10 Jul 23 C256 Ceiling Grids
G090 Floor Tiles 7 22 Jun 23 03 Jul 23 07 Jul 23 17 Jul 23 G090 Floor Tiles
C257 Paint 1ct 5 02 Jun 23 08 Jun 23 13 Jul 23 19 Jul 23 C257 Paint 1ct
C258 Shopfront 5 02 Jun 23 08 Jun 23 31 Jul 23 04 Aug 23 C258 Shopfront
C259 Door & Ironnmongery 4 09 Jun 23 14 Jun 23 20 Jul 23 25 Jul 23 C259 Door & Ironnmongery
C260 Install Whb 4 15 Jun 23 21 Jun 23 07 Aug 23 11 Aug 23 C260 Install Whb
C262 Db:wire-in 4 15 Jun 23 21 Jun 23 07 Aug 23 11 Aug 23 C262 Db:wire-in
C263 Ceiling:drop In-boards 4 15 Jun 23 21 Jun 23 07 Aug 23 11 Aug 23 C263 Ceiling:drop In-boards
C265 Hvac Ffix 4 15 Jun 23 21 Jun 23 07 Aug 23 11 Aug 23 C265 Hvac Ffix
C266 Sprinkler Ffix 4 15 Jun 23 21 Jun 23 07 Aug 23 11 Aug 23 C266 Sprinkler Ffix

6 C277 Shop 11 (Vacant) - 108m2 - 30 58 29 May 23 10 Aug 23 05 Jul 23 02 Oct 23


7 C278 Services (shop) 3 29 May 23 31 May 23 05 Jul 23 07 Jul 23
F C279 Electrical 2fix 3 29 May 23 31 May 23 05 Jul 23 07 Jul 23 C279 Electrical 2fix
F C280 Plumbing 2fix 3 29 May 23 31 May 23 05 Jul 23 07 Jul 23 C280 Plumbing 2fix
F C281 Hvac 2fix 3 29 May 23 31 May 23 05 Jul 23 07 Jul 23 C281 Hvac 2fix
F C282 Sprinkler 2fix 3 29 May 23 31 May 23 05 Jul 23 07 Jul 23 C282 Sprinkler 2fix

7 C283 Fit-out (shop) 44 01 Jun 23 24 Jul 23 10 Jul 23 13 Sep 23


C284 Ceiling Grids 7 01 Jun 23 09 Jun 23 10 Jul 23 18 Jul 23 C284 Ceiling Grids
G092 Floor Tiles 7 03 Jul 23 11 Jul 23 17 Jul 23 25 Jul 23 G092 Floor Tiles
C285 Paint 1ct 5 12 Jun 23 19 Jun 23 24 Jul 23 31 Jul 23 C285 Paint 1ct
C286 Shopfront 5 12 Jun 23 19 Jun 23 07 Aug 23 14 Aug 23 C286 Shopfront
C287 Door & Ironnmongery 4 20 Jun 23 26 Jun 23 01 Aug 23 04 Aug 23 C287 Door & Ironnmongery

6 F392 Shop 13 Vacant) - 207m2 - 30 53 07 Nov 22 21 Aug 23 05 Jul 23 21 Sep 23


7 F393 Services (shop) 3 07 Jun 23 09 Jun 23 05 Jul 23 07 Jul 23
F F394 Electrical 2fix 3 07 Jun 23 09 Jun 23 05 Jul 23 07 Jul 23 F394 Electrical 2fix
F F395 Plumbing 2fix 3 07 Jun 23 09 Jun 23 05 Jul 23 07 Jul 23 F395 Plumbing 2fix
F F396 Hvac 2fix 3 07 Jun 23 09 Jun 23 05 Jul 23 07 Jul 23 F396 Hvac 2fix
F F397 Sprinkler 2fix 3 07 Jun 23 09 Jun 23 05 Jul 23 07 Jul 23 F397 Sprinkler 2fix

7 F398 Fit-out (shop) 39 07 Nov 22 03 Aug 23 10 Jul 23 06 Sep 23


F399 Ceiling Grids 7 12 Jun 23 21 Jun 23 10 Jul 23 18 Jul 23 F399 Ceiling Grids
G093 Floor Tiles 7 12 Jul 23 20 Jul 23 17 Jul 23 25 Jul 23 G093 Floor Tiles
F400 Paint 1ct 5 22 Jun 23 29 Jun 23 24 Jul 23 31 Jul 23 F400 Paint 1ct
F401 Shopfront 5 22 Jun 23 29 Jun 23 24 Jul 23 31 Jul 23 F401 Shopfront
F402 Door & Ironnmongery 4 30 Jun 23 05 Jul 23 01 Aug 23 04 Aug 23 F402 Door & Ironnmongery
F403 Install Whb 4 06 Jul 23 11 Jul 23 07 Aug 23 11 Aug 23 F403 Install Whb
F405 Db:wire-in 4 06 Jul 23 11 Jul 23 07 Aug 23 11 Aug 23 F405 Db:wire-in
F406 Ceiling:drop In-boards 4 06 Jul 23 11 Jul 23 07 Aug 23 11 Aug 23 F406 Ceiling:drop In-boards
F408 Hvac Ffix 4 06 Jul 23 11 Jul 23 07 Aug 23 11 Aug 23 F408 Hvac Ffix
F409 Sprinkler Ffix 4 06 Jul 23 11 Jul 23 07 Aug 23 11 Aug 23 F409 Sprinkler Ffix

6 C305 Shop 15 (Levingers) - 38m2 - 30 53 07 Nov 22 18 Aug 23 06 Jul 23 22 Sep 23


7 C306 Services (shop) 3 06 Jun 23 08 Jun 23 06 Jul 23 10 Jul 23
F C307 Electrical 2fix 3 06 Jun 23 08 Jun 23 06 Jul 23 10 Jul 23 C307 Electrical 2fix
F C308 Plumbing 2fix 3 06 Jun 23 08 Jun 23 06 Jul 23 10 Jul 23 C308 Plumbing 2fix
F C309 Hvac 2fix 3 06 Jun 23 08 Jun 23 06 Jul 23 10 Jul 23 C309 Hvac 2fix
F C310 Sprinkler 2fix 3 06 Jun 23 08 Jun 23 06 Jul 23 10 Jul 23 C310 Sprinkler 2fix

7 C311 Fit-out (shop) 39 07 Nov 22 02 Aug 23 11 Jul 23 07 Sep 23


C312 Ceiling Grids 7 09 Jun 23 20 Jun 23 11 Jul 23 19 Jul 23 C312 Ceiling Grids
G094 Floor Tiles 7 11 Jul 23 19 Jul 23 18 Jul 23 26 Jul 23 G094 Floor Tiles
C313 Paint 1ct 5 21 Jun 23 28 Jun 23 25 Jul 23 01 Aug 23 C313 Paint 1ct
C314 Shopfront 5 21 Jun 23 28 Jun 23 25 Jul 23 01 Aug 23 C314 Shopfront
C315 Door & Ironnmongery 4 29 Jun 23 04 Jul 23 02 Aug 23 07 Aug 23 C315 Door & Ironnmongery
C316 Install Whb 4 05 Jul 23 10 Jul 23 08 Aug 23 14 Aug 23 C316 Install Whb
C318 Db:wire-in 4 05 Jul 23 10 Jul 23 08 Aug 23 14 Aug 23 C318 Db:wire-in
C319 Ceiling:drop In-boards 4 05 Jul 23 10 Jul 23 08 Aug 23 14 Aug 23 C319 Ceiling:drop In-boards
C321 Hvac Ffix 4 05 Jul 23 10 Jul 23 08 Aug 23 14 Aug 23 C321 Hvac Ffix
C322 Sprinkler Ffix 4 05 Jul 23 10 Jul 23 08 Aug 23 14 Aug 23 C322 Sprinkler Ffix

6 C333 Shop 17 (Vacant) - 117m2 - 30 53 07 Nov 22 29 Aug 23 13 Jul 23 03 Oct 23


7 C334 SERVICES (SHOP) 3 15 Jun 23 20 Jun 23 13 Jul 23 17 Jul 23
F C335 Electrical 2fix 3 15 Jun 23 20 Jun 23 13 Jul 23 17 Jul 23 C335 Electrical 2fix
F C336 Plumbing 2fix 3 15 Jun 23 20 Jun 23 13 Jul 23 17 Jul 23 C336 Plumbing 2fix
F C337 Hvac 2fix 3 15 Jun 23 20 Jun 23 13 Jul 23 17 Jul 23 C337 Hvac 2fix
F C338 Sprinkler 2fix 3 15 Jun 23 20 Jun 23 13 Jul 23 17 Jul 23 C338 Sprinkler 2fix

7 C339 FIT-OUT (SHOP) 39 07 Nov 22 14 Aug 23 18 Jul 23 14 Sep 23


C340 Ceiling Grids 7 21 Jun 23 30 Jun 23 18 Jul 23 26 Jul 23 C340 Ceiling Grids
G095 Floor Tiles 7 20 Jul 23 31 Jul 23 25 Jul 23 03 Aug 23 G095 Floor Tiles
C341 Paint 1ct 5 03 Jul 23 07 Jul 23 02 Aug 23 08 Aug 23 C341 Paint 1ct
C342 Shopfront 5 03 Jul 23 07 Jul 23 02 Aug 23 08 Aug 23 C342 Shopfront

6 F421 Shop 18 (SpecSavers) - 52m2 - 30 53 28 Jun 23 07 Sep 23 13 Jul 23 03 Oct 23


7 F422 SERVICES (SHOP) 3 28 Jun 23 30 Jun 23 13 Jul 23 17 Jul 23
F F423 Electrical 2fix 3 28 Jun 23 30 Jun 23 13 Jul 23 17 Jul 23 F423 Electrical 2fix
F F424 Plumbing 2fix 3 28 Jun 23 30 Jun 23 13 Jul 23 17 Jul 23 F424 Plumbing 2fix
F F425 Hvac 2fix 3 28 Jun 23 30 Jun 23 13 Jul 23 17 Jul 23 F425 Hvac 2fix
F F426 Sprinkler 2fix 3 28 Jun 23 30 Jun 23 13 Jul 23 17 Jul 23 F426 Sprinkler 2fix

7 F427 FIT-OUT (SHOP) 39 03 Jul 23 23 Aug 23 18 Jul 23 14 Sep 23


F428 Ceiling Grids 7 03 Jul 23 11 Jul 23 18 Jul 23 26 Jul 23 F428 Ceiling Grids
G096 Floor Tiles 7 01 Aug 23 11 Aug 23 25 Jul 23 03 Aug 23 G096 Floor Tiles
F429 Paint 1ct 5 12 Jul 23 18 Jul 23 02 Aug 23 08 Aug 23 F429 Paint 1ct
F430 Shopfront 5 12 Jul 23 18 Jul 23 02 Aug 23 08 Aug 23 F430 Shopfront

Page 3 of 6
Candy 2.01f14.8 (2 6 0) R
Barlow Park (Phase1)BASE Rev.1.3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10

Time Now - 23/06/2023


6 C361 Shop 19 (PnP Clothing) - 403m2 - 60 53 07 Nov 22 01 Sep 23 17 Jul 23 05 Oct 23
7 C362 Services (shop) 3 21 Jun 23 26 Jun 23 17 Jul 23 19 Jul 23
F C363 Electrical 2fix 3 21 Jun 23 26 Jun 23 17 Jul 23 19 Jul 23 C363 Electrical 2fix
F C364 Plumbing 2fix 3 21 Jun 23 26 Jun 23 17 Jul 23 19 Jul 23 C364 Plumbing 2fix
F C365 Hvac 2fix 3 21 Jun 23 26 Jun 23 17 Jul 23 19 Jul 23 C365 Hvac 2fix
F C366 Sprinkler 2fix 3 21 Jun 23 26 Jun 23 17 Jul 23 19 Jul 23 C366 Sprinkler 2fix

7 C367 Fit-out (shop) 39 07 Nov 22 17 Aug 23 20 Jul 23 18 Sep 23


C368 Ceiling Grids 7 27 Jun 23 05 Jul 23 20 Jul 23 31 Jul 23 C368 Ceiling Grids
G097 Floor Tiles 7 25 Jul 23 03 Aug 23 27 Jul 23 07 Aug 23 G097 Floor Tiles
C369 Paint 1ct 5 06 Jul 23 12 Jul 23 04 Aug 23 11 Aug 23 C369 Paint 1ct
C370 Shopfront 5 06 Jul 23 12 Jul 23 04 Aug 23 11 Aug 23 C370 Shopfront

6 C389 Shop 21 (ATM: Capitec) - 8m2 - 30 56 07 Nov 22 13 Sep 23 21 Jul 23 16 Oct 23


7 C390 Services (shop) 3 03 Jul 23 05 Jul 23 21 Jul 23 25 Jul 23
F C391 Electrical 2fix 3 03 Jul 23 05 Jul 23 21 Jul 23 25 Jul 23 C391 Electrical 2fix
F C392 Plumbing 2fix 3 03 Jul 23 05 Jul 23 21 Jul 23 25 Jul 23 C392 Plumbing 2fix
F C393 Hvac 2fix 3 03 Jul 23 05 Jul 23 21 Jul 23 25 Jul 23 C393 Hvac 2fix
F C394 Sprinkler 2fix 3 03 Jul 23 05 Jul 23 21 Jul 23 25 Jul 23 C394 Sprinkler 2fix

7 C395 Fit-out (shop) 42 07 Nov 22 28 Aug 23 26 Jul 23 28 Sep 23


C396 Ceiling Grids 7 06 Jul 23 14 Jul 23 26 Jul 23 04 Aug 23 C396 Ceiling Grids
G098 Floor Tiles 7 07 Aug 23 16 Aug 23 03 Aug 23 14 Aug 23 G098 Floor Tiles

6 C417 Shop 23 (Mr Price) - 403m2 - 60 57 11 Jul 23 21 Sep 23 21 Jul 23 17 Oct 23


7 C418 Services (shop) 3 11 Jul 23 13 Jul 23 21 Jul 23 25 Jul 23
F C419 Electrical 2fix 3 11 Jul 23 13 Jul 23 21 Jul 23 25 Jul 23 C419 Electrical 2fix
F C420 Plumbing 2fix 3 11 Jul 23 13 Jul 23 21 Jul 23 25 Jul 23 C420 Plumbing 2fix
F C421 Hvac 2fix 3 11 Jul 23 13 Jul 23 21 Jul 23 25 Jul 23 C421 Hvac 2fix
F C422 Sprinkler 2fix 3 11 Jul 23 13 Jul 23 21 Jul 23 25 Jul 23 C422 Sprinkler 2fix

7 C423 Fit-out (shop) 43 14 Jul 23 05 Sep 23 26 Jul 23 02 Oct 23


C424 Ceiling Grids 7 14 Jul 23 24 Jul 23 26 Jul 23 04 Aug 23 C424 Ceiling Grids
G099 Floor Tiles 7 16 Aug 23 24 Aug 23 03 Aug 23 14 Aug 23 G099 Floor Tiles

6 C445 Shop 25 (Vida E) - 150m2 - 60 58 20 Jul 23 03 Oct 23 26 Jul 23 24 Oct 23


7 C446 Services (shop) 3 20 Jul 23 24 Jul 23 26 Jul 23 31 Jul 23
F C447 Electrical 2fix 3 20 Jul 23 24 Jul 23 26 Jul 23 31 Jul 23 C447 Electrical 2fix
F C448 Plumbing 2fix 3 20 Jul 23 24 Jul 23 26 Jul 23 31 Jul 23 C448 Plumbing 2fix
F C449 Hvac 2fix 3 20 Jul 23 24 Jul 23 26 Jul 23 31 Jul 23 C449 Hvac 2fix
F C450 Sprinkler 2fix 3 20 Jul 23 24 Jul 23 26 Jul 23 31 Jul 23 C450 Sprinkler 2fix

7 C451 Fit-out (shop) 44 25 Jul 23 15 Sep 23 01 Aug 23 06 Oct 23


C452 Ceiling Grids 7 25 Jul 23 03 Aug 23 01 Aug 23 10 Aug 23 C452 Ceiling Grids
G100 Floor Tiles 7 25 Aug 23 04 Sep 23 08 Aug 23 17 Aug 23 G100 Floor Tiles

6 C473 Shop 27 (Checkers Liquor) - 196m2 - 60 53 01 Aug 23 13 Oct 23 02 Aug 23 23 Oct 23


7 C474 Services (shop) 3 01 Aug 23 03 Aug 23 02 Aug 23 04 Aug 23
F C475 Electrical 2fix 3 01 Aug 23 03 Aug 23 02 Aug 23 04 Aug 23 C475 Electrical 2fix
F C476 Plumbing 2fix 3 01 Aug 23 03 Aug 23 02 Aug 23 04 Aug 23 C476 Plumbing 2fix
F C477 Hvac 2fix 3 01 Aug 23 03 Aug 23 02 Aug 23 04 Aug 23 C477 Hvac 2fix
F C478 Sprinkler 2fix 3 01 Aug 23 03 Aug 23 02 Aug 23 04 Aug 23 C478 Sprinkler 2fix

7 C479 Fit-out (shop) 39 04 Aug 23 27 Sep 23 07 Aug 23 05 Oct 23


C480 Ceiling Grids 7 04 Aug 23 15 Aug 23 07 Aug 23 16 Aug 23 C480 Ceiling Grids

6 C529 Shop 31 (All Fix) - 48m2 - 30 53 30 Jun 23 12 Sep 23 02 Aug 23 23 Oct 23


7 C530 Services (shop) 3 30 Jun 23 04 Jul 23 02 Aug 23 04 Aug 23
F C531 Electrical 2fix 3 30 Jun 23 04 Jul 23 02 Aug 23 04 Aug 23 C531 Electrical 2fix
F C532 Plumbing 2fix 3 30 Jun 23 04 Jul 23 02 Aug 23 04 Aug 23 C532 Plumbing 2fix
F C533 Hvac 2fix 3 30 Jun 23 04 Jul 23 02 Aug 23 04 Aug 23 C533 Hvac 2fix
F C534 Sprinkler 2fix 3 30 Jun 23 04 Jul 23 02 Aug 23 04 Aug 23 C534 Sprinkler 2fix

7 C535 Fit-out (shop) 39 05 Jul 23 25 Aug 23 07 Aug 23 05 Oct 23


C536 Ceiling Grids 7 05 Jul 23 13 Jul 23 07 Aug 23 16 Aug 23 C536 Ceiling Grids

6 C557 Shop 33 (Vacant) - 25m2 - 30 54 10 Jul 23 20 Sep 23 07 Aug 23 30 Oct 23


7 C558 Services (shop) 3 10 Jul 23 12 Jul 23 07 Aug 23 10 Aug 23
F C559 Electrical 2fix 3 10 Jul 23 12 Jul 23 07 Aug 23 10 Aug 23 C559 Electrical 2fix
F C560 Plumbing 2fix 3 10 Jul 23 12 Jul 23 07 Aug 23 10 Aug 23 C560 Plumbing 2fix
F C561 Hvac 2fix 3 10 Jul 23 12 Jul 23 07 Aug 23 10 Aug 23 C561 Hvac 2fix
F C562 Sprinkler 2fix 3 10 Jul 23 12 Jul 23 07 Aug 23 10 Aug 23 C562 Sprinkler 2fix

4 C842 Delivery / Service Yards / Service Areas 138 03 May 23 06 Dec 23 26 Jun 23 06 Dec 23 191 108
5 C881 Services 80 03 May 23 04 Sep 23 26 Jun 23 08 Sep 23 191 50 C881 Services

3 C955 CURO 82 18 Apr 23 31 Aug 23 26 Jun 23 05 Sep 23 186 47 C955 CURO

3 D054 Ground FLoor 101 28 Apr 23 23 Aug 23 26 Jun 23 22 Sep 23 180 60 D054 Ground FLoor

3 D164 01st Floor 103 11 Apr 23 21 Sep 23 26 Jun 23 06 Oct 23 186 68 D164 01st Floor

3 D403 02nd Floor 113 05 May 23 12 Oct 23 26 Jun 23 08 Nov 23 197 89 D403 02nd Floor

3 D642 03rd Floor 109 24 May 23 01 Nov 23 26 Jun 23 22 Nov 23 211 99 D642 03rd Floor

3 D881 04th Floor 109 13 Jun 23 22 Nov 23 26 Jun 23 07 Dec 23 D881 04th Floor

3 E120 05th Floor 111 04 Jul 23 13 Dec 23 12 Jul 23 18 Jan 24 E120 05th Floor

3 E359 06th Floor 108 31 Jul 23 22 Jan 24 08 Aug 23 09 Feb 24 E359 06th Floor

3 E958 Facades 205 03 Apr 23 05 Mar 24 26 Jun 23 18 Mar 24 178 162 E958 Facades

3 F089 Roof 160 20 Feb 23 27 Feb 24 26 Jun 23 14 Mar 24 F089 Roof

Page 4 of 6
Candy 2.01f14.8 (2 6 0) R
Barlow Park (Phase1)BASE Rev.1.3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10
3 F143 Lifts A & B & Staircases 130 24 Mar 23 11 Jan 24 06 Jul 23 09 Feb 24

Time Now - 23/06/2023


F143 Lifts A & B & Staircases

3 F165 External Works 211 11 May 23 09 Apr 24 26 Jun 23 18 Apr 24 191 181
4 F166 Externals Parking Area 184 11 May 23 06 Feb 24 26 Jun 23 06 Mar 24 191 154
5 F167 Paving Areas / Roads 138 11 May 23 06 Dec 23 26 Jun 23 06 Dec 23 191 108
S G185 Perimeter Fence 45 11 May 23 18 Jul 23 26 Jun 23 01 Aug 23 191 25 G185 Perimeter Fence

1 F4... Additional 318 14 Oct 22 15 Apr 24 26 Jun 23 18 Mar 24 65 162


2 F4... Finishes 120 07 Nov 22 11 Oct 23 26 Jun 23 17 Nov 23 197 96
3 F461 Retail 120 07 Nov 22 11 Oct 23 26 Jun 23 17 Nov 23 197 96
4 F462 Shops 120 07 Nov 22 11 Oct 23 26 Jun 23 17 Nov 23 197 96
5 F764 Wet Trades, Partition, Restaurant & 1st Fix Services 120 07 Nov 22 11 Oct 23 26 Jun 23 17 Nov 23 197 96
F F766 Electrical 1fix (ce) 20 31 May 23 29 Jun 23 10 Jul 23 07 Aug 23 F766 Electrical 1fix (ce)
F F767 Plumbing 1fix (ce) 20 30 May 23 28 Jun 23 07 Jul 23 04 Aug 23 F767 Plumbing 1fix (ce)
F F768 Hvac 1fix (ce) 20 22 Jun 23 20 Jul 23 01 Aug 23 30 Aug 23 F768 Hvac 1fix (ce)
E G186 Checkers - Exstract Fan 10 06 Jul 23 19 Jul 23 06 Jul 23 19 Jul 23 G186 Checkers - Exstract Fan
F F769 Sprinkler - Void 20 22 Jun 23 20 Jul 23 01 Aug 23 30 Aug 23 F769 Sprinkler - Void
F770 Brickwork/Upstands - External/ Internal/div 35 28 Apr 23 20 Jun 23 26 Jun 23 27 Jul 23 197 23 F770 Brickwork/Upstands - External/ Internal/div
F771 Plaster - Internal/div 25 15 Jun 23 21 Jul 23 25 Jul 23 31 Aug 23 F771 Plaster - Internal/div
F773 Electrical 1f (Wall & Soffit) 20 31 May 23 29 Jun 23 10 Jul 23 07 Aug 23 F773 Electrical 1f (Wall & Soffit)
F774 Plumbing 1f ((Wall & Soffit) 20 31 May 23 29 Jun 23 10 Jul 23 07 Aug 23 F774 Plumbing 1f ((Wall & Soffit)
F F775 Screed & Waterproofing slab above retail 33 05 Jun 23 21 Jul 23 19 Jul 23 22 Aug 23 211 23 F775 Screed & Waterproofing slab above retail
6 F790 Shop 49 - 195m2 - 60 46 06 Jun 23 14 Aug 23 14 Jul 23 21 Sep 23
7 F791 Services (shop) 3 06 Jun 23 08 Jun 23 14 Jul 23 18 Jul 23
F F792 Electrical 2fix 3 06 Jun 23 08 Jun 23 14 Jul 23 18 Jul 23 F792 Electrical 2fix
F F793 Plumbing 2fix 3 06 Jun 23 08 Jun 23 14 Jul 23 18 Jul 23 F793 Plumbing 2fix
F F794 Hvac 2fix 3 06 Jun 23 08 Jun 23 14 Jul 23 18 Jul 23 F794 Hvac 2fix
F F795 Sprinkler 2fix 3 06 Jun 23 08 Jun 23 14 Jul 23 18 Jul 23 F795 Sprinkler 2fix

7 F796 Fit-out (shop) 32 09 Jun 23 26 Jul 23 19 Jul 23 06 Sep 23


F797 Ceiling Grids 7 09 Jun 23 20 Jun 23 19 Jul 23 27 Jul 23 F797 Ceiling Grids
F798 Paint 1ct 5 21 Jun 23 28 Jun 23 31 Jul 23 04 Aug 23 F798 Paint 1ct
F799 Shopfront 5 21 Jun 23 28 Jun 23 31 Jul 23 04 Aug 23 F799 Shopfront
F800 Door & Ironnmongery 4 29 Jun 23 04 Jul 23 07 Aug 23 11 Aug 23 F800 Door & Ironnmongery

6 F763 Sales/ Security Office 150m2 66 20 Jun 23 29 Sep 23 27 Jul 23 07 Nov 23


7 F818 Internal fitout 57 20 Jun 23 28 Sep 23 27 Jul 23 24 Oct 23
F F819 Access From Brickwork 0 20 Jun 23 27 Jul 23 F819 Access From Brickwork
F F820 Electrical 1f (wl) 17 20 Jun 23 13 Jul 23 27 Jul 23 22 Aug 23 F820 Electrical 1f (wl)
F F821 Plaster 18 26 Jun 23 19 Jul 23 02 Aug 23 29 Aug 23 F821 Plaster

6 F848 Shop Gym - 205m2 - 60 46 21 Jun 23 28 Aug 23 31 Jul 23 09 Oct 23


7 F849 Services (shop) 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23
F F850 Electrical 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F850 Electrical 2fix
F F851 Plumbing 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F851 Plumbing 2fix
F F852 Hvac 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F852 Hvac 2fix
F F853 Sprinkler 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F853 Sprinkler 2fix

7 F854 Fit-out (shop) 32 27 Jun 23 17 Aug 23 03 Aug 23 20 Sep 23


F855 Ceiling Grids 7 27 Jun 23 05 Jul 23 03 Aug 23 14 Aug 23 F855 Ceiling Grids

6 F875 Shop Buisness Lounge - 300m2 - 60 46 21 Jun 23 28 Aug 23 31 Jul 23 09 Oct 23


7 F876 Services (shop) 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23
F F877 Electrical 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F877 Electrical 2fix
F F878 Plumbing 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F878 Plumbing 2fix
F F879 Hvac 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F879 Hvac 2fix
F F880 Sprinkler 2fix 3 21 Jun 23 26 Jun 23 31 Jul 23 02 Aug 23 F880 Sprinkler 2fix

7 F881 Fit-out (shop) 32 27 Jun 23 11 Aug 23 03 Aug 23 20 Sep 23


F882 Ceiling Grids 7 27 Jun 23 05 Jul 23 03 Aug 23 14 Aug 23 F882 Ceiling Grids

6 F464 Checkers hyper/ 60 bo) 115 07 Nov 22 11 Oct 23 26 Jun 23 17 Nov 23 202 96
7 F465 Trading floor 85 07 Nov 22 04 Oct 23 03 Aug 23 13 Nov 23 202 66
F F657 Access From Waterproofing 0 03 Jul 23 03 Aug 23 F657 Access From Waterproofing
F F466 Bulkheads 25 03 Jul 23 07 Aug 23 03 Aug 23 11 Sep 23 F466 Bulkheads
F469 Hvac 2fix (ce) 25 18 Jul 23 23 Aug 23 18 Sep 23 26 Sep 23 202 6 F469 Hvac 2fix (ce)
F470 Sprinkler 2fix (ce) 25 18 Jul 23 23 Aug 23 18 Sep 23 26 Sep 23 202 6 F470 Sprinkler 2fix (ce)

7 F548 Plant room-ahu 51 05 Apr 23 27 Jun 23 12 Jul 23 27 Sep 23


S F549 Frc Plinths 5 05 Apr 23 13 Apr 23 12 Jul 23 18 Jul 23 F549 Frc Plinths
F F550 Electrical 1f(Wl) 2 17 Apr 23 18 Apr 23 19 Jul 23 20 Jul 23 F550 Electrical 1f(Wl)
F551 Plaster ( 40/4/160m2) 3 19 Apr 23 24 Apr 23 21 Jul 23 25 Jul 23 F551 Plaster ( 40/4/160m2)
F552 Waterproof Plinths 2 25 Apr 23 26 Apr 23 26 Jul 23 27 Jul 23 F552 Waterproof Plinths
F553 Doors & Joinery 2 25 Apr 23 26 Apr 23 26 Jul 23 27 Jul 23 F553 Doors & Joinery
F554 A/c Grills 2 25 Apr 23 26 Apr 23 26 Jul 23 27 Jul 23 F554 A/c Grills
F555 Elec Wiring & Lighting 2 28 Apr 23 02 May 23 31 Jul 23 01 Aug 23 F555 Elec Wiring & Lighting
F556 Paint 1ct 2 03 May 23 04 May 23 02 Aug 23 03 Aug 23 F556 Paint 1ct
F557 Hand Over To Specialist Contractor 0 05 May 23 04 Aug 23 F557 Hand Over To Specialist Contractor
F558 Position Plant 10 05 May 23 18 May 23 04 Aug 23 18 Aug 23 F558 Position Plant

7 F563 Butcher prep 79 25 May 23 14 Sep 23 26 Jun 23 24 Oct 23


F F658 Access From plaster 0 25 May 23 26 Jun 23 F658 Access From plaster
F564 Coldroom Screeds 3 25 May 23 30 May 23 26 Jun 23 28 Jun 23 F564 Coldroom Screeds
F565 Coldroom Floor Tiles 3 30 May 23 01 Jun 23 28 Jun 23 03 Jul 23 F565 Coldroom Floor Tiles
F570 Wall Tiles 10 02 Jun 23 15 Jun 23 04 Jul 23 17 Jul 23 F570 Wall Tiles
F571 Extract Canopies 3 13 Jun 23 15 Jun 23 13 Jul 23 17 Jul 23 F571 Extract Canopies

7 F586 Deli prep 83 30 May 23 27 Sep 23 26 Jun 23 31 Oct 23


F F659 Access From plaster 0 30 May 23 26 Jun 23 F659 Access From plaster
F587 Coldroom Screeds 3 30 May 23 01 Jun 23 26 Jun 23 28 Jun 23 F587 Coldroom Screeds
F588 Coldroom Floor Tiles 3 01 Jun 23 05 Jun 23 28 Jun 23 03 Jul 23 F588 Coldroom Floor Tiles

7 F609 Bakery 84 29 May 23 02 Oct 23 26 Jun 23 01 Nov 23


F F660 Access From plaster 0 29 May 23 26 Jun 23 F660 Access From plaster
F F610 Coldroom Appt 1 29 May 23 29 May 23 26 Jun 23 26 Jun 23 F610 Coldroom Appt

Page 5 of 6
Candy 2.01f14.8 (2 6 0) R
Barlow Park (Phase1)BASE Rev.1.3Update 22-06-23
Standard Barchart Retail
Activities: As per screen
2023 2024
Activity Base Program Current Actual Rem F March April May June July August September October November December January February March April May
Type Nº Activity description Durn Start Finish Start Finish Strt Durn 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10

Time Now - 23/06/2023


F F611 Coldroom Lead Time 41 30 May 23 27 Jul 23 27 Jun 23 28 Aug 23 F611 Coldroom Lead Time

2 F9... NOD's 160 14 Oct 22 12 Jul 23 26 Jun 23 29 Jun 23 65 4


3 G384 NOD - CURO 51 18 Apr 23 12 Jul 23 26 Jun 23 29 Jun 23 174 4
G386 CURO Perimeter Brickwork Remainder 19 29 May 23 26 Jun 23 26 Jun 23 29 Jun 23 201 4 G386 CURO Perimeter Brickwork Remainder
G590 CURO Installation 7 19 Jun 23 27 Jun 23 26 Jun 23 28 Jun 23 217 3 G590 CURO Installation

3 G138 Steel Hangers/Stiffners 107 20 Jan 23 30 May 23 26 Jun 23 29 Jun 23 118 4


4 G141 Appointment 107 20 Jan 23 30 May 23 26 Jun 23 29 Jun 23 118 4
G184 Installation (Checkers) 10 16 May 23 30 May 23 26 Jun 23 29 Jun 23 206 4 G184 Installation (Checkers)

3 G147 Shopfronts 93 10 Feb 23 19 Jun 23 26 Jun 23 29 Jun 23 132 4


4 G150 Appointment 93 10 Feb 23 19 Jun 23 26 Jun 23 29 Jun 23 132 4
G154 Procurement/Manufacture 25 10 May 23 19 Jun 23 26 Jun 23 29 Jun 23 185 4 G154 Procurement/Manufacture

3 G155 Retail Ceilngs 36 27 Mar 23 12 Apr 23 26 Jun 23 26 Jun 23 186 1


4 G157 Appointment 36 27 Mar 23 12 Apr 23 26 Jun 23 26 Jun 23 186 1
G159 Procurement 5 04 Apr 23 12 Apr 23 26 Jun 23 26 Jun 23 204 1 G159 Procurement

2 F9... Retail Canopy 176 17 Mar 23 11 Dec 23 26 Jun 23 11 Dec 23 156 111
5 G000 (Block 1) 82 22 Jun 23 24 Oct 23 26 Jun 23 30 Oct 23
6 G001 Structural Steel 62 22 Jun 23 21 Sep 23 26 Jun 23 27 Sep 23
S G009 Procurement 30 22 Jun 23 04 Aug 23 26 Jun 23 08 Aug 23 G009 Procurement
G002 Erect Structural Steel/Timber Roof 30 31 Jul 23 12 Sep 23 02 Aug 23 15 Sep 23 G002 Erect Structural Steel/Timber Roof

5 G010 (Block 2) 82 14 Jul 23 15 Nov 23 18 Jul 23 20 Nov 23 G010 (Block 2)

5 G020 (Retail) 176 17 Mar 23 11 Dec 23 26 Jun 23 11 Dec 23 156 111


6 G112 Feature Stairs 112 17 Mar 23 17 Jul 23 26 Jun 23 05 Sep 23 156 47
G118 Formwork to Stair Soffit 10 14 Apr 23 03 May 23 26 Jun 23 10 Jul 23 G118 Formwork to Stair Soffit
G119 Rebar to Stair soffit 7 24 Apr 23 05 May 23 04 Jul 23 12 Jul 23 G119 Rebar to Stair soffit
G120 Formwork to sides & Treads 7 26 Apr 23 09 May 23 06 Jul 23 14 Jul 23 G120 Formwork to sides & Treads
G121 Cast Stairs 4 05 May 23 10 May 23 12 Jul 23 17 Jul 23 G121 Cast Stairs
G122 Cast Planter surfacebeds 4 08 May 23 11 May 23 13 Jul 23 18 Jul 23 G122 Cast Planter surfacebeds
G123 Brickwork to sides of Stair 12 11 May 23 29 May 23 18 Jul 23 03 Aug 23 G123 Brickwork to sides of Stair
G124 Brickwork to Planters 8 12 May 23 23 May 23 19 Jul 23 31 Jul 23 G124 Brickwork to Planters
G125 Screeds to Planters 5 18 May 23 24 May 23 25 Jul 23 01 Aug 23 G125 Screeds to Planters
G126 Waterproofing to Planter surface beds 5 25 May 23 01 Jun 23 01 Aug 23 07 Aug 23 G126 Waterproofing to Planter surface beds
G127 2nd layer Screed 3 31 May 23 05 Jun 23 04 Aug 23 08 Aug 23 G127 2nd layer Screed
G128 No Fines 3 05 Jun 23 07 Jun 23 08 Aug 23 11 Aug 23 G128 No Fines
G129 Access Ready for Planter filling 10 05 Jun 23 20 Jun 23 08 Aug 23 22 Aug 23 G129 Access Ready for Planter filling

2 G1... Pods Checkers Roof Slab 40 09 May 23 15 Jun 23 26 Jun 23 04 Jul 23 187 6
3 G215 POD 3 27 16 May 23 01 Jun 23 26 Jun 23 03 Jul 23 199 5
G219 Grout 1 24 May 23 24 May 23 26 Jun 23 26 Jun 23 G219 Grout
G220 Final Waterproofing onto columns 1 29 May 23 29 May 23 27 Jun 23 27 Jun 23 G220 Final Waterproofing onto columns
G221 Shutter POD Upstands 1 30 May 23 30 May 23 28 Jun 23 28 Jun 23 G221 Shutter POD Upstands
G222 Rebar to POD upstands 1 31 May 23 31 May 23 29 Jun 23 29 Jun 23 G222 Rebar to POD upstands
G223 Cast POD Upstands 1 01 Jun 23 01 Jun 23 03 Jul 23 03 Jul 23 G223 Cast POD Upstands

3 G224 POD 4 19 18 May 23 15 Jun 23 26 Jun 23 04 Jul 23 208 6


G226 Errect columns(33no) 5 19 May 23 25 May 23 26 Jun 23 27 Jun 23 219 2 G226 Errect columns(33no)
G229 Grout 1 07 Jun 23 07 Jun 23 26 Jun 23 26 Jun 23 G229 Grout
G230 Final Waterproofing onto columns 1 12 Jun 23 12 Jun 23 27 Jun 23 27 Jun 23 G230 Final Waterproofing onto columns
G231 Shutter POD Upstands 1 13 Jun 23 13 Jun 23 28 Jun 23 28 Jun 23 G231 Shutter POD Upstands
G232 Rebar to POD upstands 1 14 Jun 23 14 Jun 23 29 Jun 23 29 Jun 23 G232 Rebar to POD upstands
G233 Cast POD Upstands 1 15 Jun 23 15 Jun 23 04 Jul 23 04 Jul 23 G233 Cast POD Upstands

2 G2... Mock Up Rooms 43 15 May 23 29 Jun 23 26 Jun 23 13 Jul 23 191 13 G234 Mock Up Rooms

Page 6 of 6