Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

WBHO Barlow Park- Part 3 Section of Works

Critical Tracking Programme- Checkers


Standard Barchart
Activities: Entire program
2023 2024
Current
April May June July August September October November December January February
Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23

Time Now - 19/05/2023


B240 - Checkers Critical works tracker 224 22 May 23 21 Feb 24 -5
- Predesessors
B750 - As it stands bar Concrete 26 As it stands bar Concrete
C130 - Appointments Required(not yet linked) 0 20 Jan 23 0
- Bumper rails
- Tiling
- Cold rooms
- Poly Screed
- Painter
- Vinyl
- Timber roof
- Ceiling
- Roller shutter doors

B830 - External Yard and Facade 52 22 May 23 19 Jul 23 39


B840 - Yard Surface bed 13 22 May 23 05 Jun 23 39
B850 - Access 0 B850 Access
B860 - Install services(1x stormwater pipe) 3 22 May 23 22 May 23 39 B860 Install services(1x stormwater pipe)
B870 - G5 to final cut 2 23 May 23 24 May 23 39 B870 G5 to final cut
- Box outs for bollards and falls - Local (wash down)
B880 - Shutter to edges 1 25 May 23 25 May 23 39 B880 Shutter to edges
B910 - Rebar (around cols only) 1 25 May 23 25 May 23 39 B910 Rebar (around cols only)
B900 - Cast concrete to fall 1 26 May 23 26 May 23 39 B900 Cast concrete to fall
B890 - Sawcut 1 29 May 23 29 May 23 39 B890 Sawcut
B920 - Inspect 0 30 May 23 43 B920 Inspect
B970 - Curing 5 30 May 23 05 Jun 23 39 B970 Curing

B930 - Yard - trades 37 30 May 23 19 Jul 23 39


B950 - Setout walls 1 30 May 23 30 May 23 43 B950 Setout walls
B940 - Brick up facebrick walls 12 06 Jun 23 21 Jun 23 39 B940 Brick up facebrick walls
B960 - Cast wash down 4 06 Jun 23 09 Jun 23 47 B960 Cast wash down
B980 - Install bollards 5 22 Jun 23 28 Jun 23 39 B980 Install bollards
B990 - Install gates 8 29 Jun 23 10 Jul 23 39 B990 Install gates
C110 - Install RSD 10 22 Jun 23 05 Jul 23 48 C110 Install RSD
C000 - Yard MEP Second and Final Soffit level 6 11 Jul 23 18 Jul 23 39 C000 Yard MEP Second and Final Soffit level
C010 - Snag yard 1 19 Jul 23 19 Jul 23 39 C010 Snag yard

C020 - External facade +- 6m height 37 22 May 23 28 Jun 23 54


C030 - Access 0 C030 Access
C040 - Brick up 46 000 bricks 27 22 May 23 22 Jun 23 54 C040 Brick up 46 000 bricks
C050 - Snag facade and joint seal 4 23 Jun 23 28 Jun 23 54 C050 Snag facade and joint seal

B250 - Mechanical, Electrical and Plumbing (MEP) 44 22 May 23 28 Jun 23 0


By Area
A100 - Soffit Services 44 22 May 23 28 Jun 23 0
A010 - BOH (Galvanised) 18 22 May 23 25 May 23 0
A110 - Access from soffit 0 A110 Access from soffit
A120 - Havc 1st 10 22 May 23 22 May 23 0 A120 Havc 1st
A130 - Plumbing 1st 8 A130 Plumbing 1st
A140 - Electrical 1st 8 A140 Electrical 1st
A150 - Fire 1st (dand fire only) 3 22 May 23 24 May 23 78 A150 Fire 1st (dand fire only)
A160 - Inspect 1 25 May 23 25 May 23 78 A160 Inspect

A020 - Office (Painted services) 28 22 May 23 28 Jun 23 0


A040 - Access from soffit 0 22 May 23 0 A040 Access from soffit
A050 - Havc 1st 10 22 May 23 02 Jun 23 0 A050 Havc 1st
A060 - Plumbing 1st 7 05 Jun 23 13 Jun 23 0 A060 Plumbing 1st
A070 - Electrical 1st 7 14 Jun 23 22 Jun 23 54 A070 Electrical 1st
A080 - Fire 1st (dand fire only) 3 23 Jun 23 27 Jun 23 54 A080 Fire 1st (dand fire only)
A090 - Inspect for paint 1 28 Jun 23 28 Jun 23 54 A090 Inspect for paint

A170 - Ablutions (Painted services) 10 22 May 23 23 May 23 80


A180 - Access from soffit 0 A180 Access from soffit
A190 - Havc 1st 4 A190 Havc 1st
A200 - Plumbing 1st 5 A200 Plumbing 1st
A210 - Electrical 1st 5 A210 Electrical 1st
A220 - Fire 1st (hand fire only) 1 22 May 23 22 May 23 80 A220 Fire 1st (hand fire only)
A230 - Inspect for paint 1 23 May 23 23 May 23 80 A230 Inspect for paint

Printed 17:22:01 19 May 2023 Page 1 of 4


Candy 2.01f13.2 (2 6 0) R
WBHO Barlow Park- Part 3 Section of Works
Critical Tracking Programme- Checkers
Standard Barchart
Activities: Entire program
2023 2024
Current
April May June July August September October November December January February
Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23

Time Now - 19/05/2023


A240 - Main trading and managers office (Painted 32 22 May 23 12 Jun 23 66
services)
A250 - Access from soffit 0 A250 Access from soffit
A260 - Havc 1st 12 22 May 23 22 May 23 66 A260 Havc 1st
A270 - Plumbing 1st 10 23 May 23 25 May 23 66 A270 Plumbing 1st
A280 - Electrical 1st(Powder coated can not fit before 8 26 May 23 06 Jun 23 66 A280 Electrical 1st(Powder coated can not fit before soffit painting)
soffit painting)
A290 - Fire 1st (dand fire only) 3 07 Jun 23 09 Jun 23 66 A290 Fire 1st (dand fire only)
A300 - Inspect for paint 1 12 Jun 23 12 Jun 23 66 A300 Inspect for paint

A770 - Paint / Spray soffit services 27 22 May 23 21 Jun 23 59


A780 - Access 70% of service installed 0 A780 Access 70% of service installed
A790 - Prep for paint & Cover facebricks 2 22 May 23 23 May 23 59 A790 Prep for paint & Cover facebricks
A800 - Spray Services 15 24 May 23 13 Jun 23 59 A800 Spray Services
A810 - Prime and Paint all soffit exc BOH 15 31 May 23 20 Jun 23 59 A810 Prime and Paint all soffit exc BOH
A820 - Inspect 1 21 Jun 23 21 Jun 23 59 A820 Inspect

A310 - Internal areas (Ablution/ Office/ Main / 217 22 May 23 21 Feb 24 -5


BOH)
A440 - Trades- Ablutions 71 22 May 23 01 Aug 23 0
A320 - Abluitions 38 22 May 23 15 Jun 23 0
A340 - Access 0 A340 Access
A330 - Stock brick to height 10 22 May 23 23 May 23 0 A330 Stock brick to height
A350 - Wall services(Ducting and Plumbing 6 A350 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
A360 - Wall services electrical (Inc DB tray) 5 22 May 23 22 May 23 0 A360 Wall services electrical (Inc DB tray)
A370 - Inspect for plaster 1 A370 Inspect for plaster
A380 - Plaster walls (2 coat above tiles) 6 22 May 23 29 May 23 30 A380 Plaster walls (2 coat above tiles)
A390 - Prime walls where required 2 30 May 23 31 May 23 30 A390 Prime walls where required
A400 - Install shaddow lines 2 01 Jun 23 02 Jun 23 30 A400 Install shaddow lines
A410 - Ceiling grids 4 05 Jun 23 08 Jun 23 30 A410 Ceiling grids
A420 - Electrical second fix 2 09 Jun 23 12 Jun 23 30 A420 Electrical second fix
A430 - Ducting second fix soffit 2 13 Jun 23 14 Jun 23 30 A430 Ducting second fix soffit
A450 - Inspect 1 15 Jun 23 15 Jun 23 30 A450 Inspect

A030 - Finishing 33 16 Jun 23 01 Aug 23 30


A470 - Access 0 16 Jun 23 30 A470 Access
A480 - Ceilings - board and skimm 3 16 Jun 23 20 Jun 23 30 A480 Ceilings - board and skimm
A490 - Paint final 3 21 Jun 23 23 Jun 23 30 A490 Paint final
A500 - MEP Final fixes 5 26 Jun 23 30 Jun 23 30 A500 MEP Final fixes
A510 - Doors and Ironmongary 4 03 Jul 23 06 Jul 23 30 A510 Doors and Ironmongary
A520 - Tiling & Cnr Protectors 12 07 Jul 23 24 Jul 23 30 A520 Tiling & Cnr Protectors
A530 - Joinery and Vanity 5 25 Jul 23 31 Jul 23 30 A530 Joinery and Vanity
A460 - Inspect 1 01 Aug 23 01 Aug 23 30 A460 Inspect

A540 - Trades- Office 76 22 May 23 17 Aug 23 18


A830 - Steel support & bulkehead 21 05 Jun 23 03 Jul 23 18
A900 - Access from Brickwork 0 05 Jun 23 18 A900 Access from Brickwork
A890 - Install bulkhead steel 6 05 Jun 23 12 Jun 23 18 A890 Install bulkhead steel
A880 - Ceiling Grid to bulkhead 5 13 Jun 23 19 Jun 23 18 A880 Ceiling Grid to bulkhead
A870 - Board and Skim 3 20 Jun 23 22 Jun 23 18 A870 Board and Skim
A860 - Prime bulkead 2 23 Jun 23 26 Jun 23 18 A860 Prime bulkead
A840 - Snag bulkhead 2 27 Jun 23 28 Jun 23 18 A840 Snag bulkhead
A850 - Install bottom track 2 29 Jun 23 30 Jun 23 18 A850 Install bottom track
A910 - Inspect 1 03 Jul 23 03 Jul 23 18 A910 Inspect

A550 - Office 53 22 May 23 17 Jul 23 18


A560 - Access 0 A560 Access
A570 - Stock brick to height 10 22 May 23 25 May 23 18 A570 Stock brick to height
A580 - Wall services(Ducting and Plumbing 8 26 May 23 31 May 23 18 A580 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
A590 - Wall services electrical (Inc DB tray) 5 01 Jun 23 01 Jun 23 18 A590 Wall services electrical (Inc DB tray)
B740 - Cashroom Slab / Lintols and 90mm concrete 5 02 Jun 23 08 Jun 23 50 B740 Cashroom Slab / Lintols and 90mm concrete
A600 - Inspect for plaster 1 02 Jun 23 02 Jun 23 18 A600 Inspect for plaster
A610 - Plaster walls (2 coat above tiles) 15 05 Jun 23 23 Jun 23 41 A610 Plaster walls (2 coat above tiles)
A620 - Prime walls where required 5 26 Jun 23 30 Jun 23 41 A620 Prime walls where required
A630 - Install shaddow lines 2 03 Jul 23 04 Jul 23 41 A630 Install shaddow lines
A640 - Ceiling grids 4 05 Jul 23 10 Jul 23 41 A640 Ceiling grids
A650 - Electrical second fix 2 11 Jul 23 12 Jul 23 41 A650 Electrical second fix
A660 - Ducting second fix soffit 2 13 Jul 23 14 Jul 23 41 A660 Ducting second fix soffit
A670 - Inspect 1 17 Jul 23 17 Jul 23 41 A670 Inspect

Printed 17:22:01 19 May 2023 Page 2 of 4


Candy 2.01f13.2 (2 6 0) R
WBHO Barlow Park- Part 3 Section of Works
Critical Tracking Programme- Checkers
Standard Barchart
Activities: Entire program
2023 2024
Current
April May June July August September October November December January February
Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23

Time Now - 19/05/2023


A680 - Finishing 39 26 Jun 23 17 Aug 23 18
A690 - Access 0 04 Jul 23 18 A690 Access
A700 - Ceilings - board and skimm 3 04 Jul 23 06 Jul 23 18 A700 Ceilings - board and skimm
A710 - Paint final 3 07 Jul 23 11 Jul 23 18 A710 Paint final
A720 - MEP Final fixes 5 12 Jul 23 18 Jul 23 18 A720 MEP Final fixes
B680 - Install safe door and finish plaster 3 19 Jul 23 21 Jul 23 19 B680 Install safe door and finish plaster
C080 - View panels and shopfronts 7 26 Jun 23 04 Jul 23 44 C080 View panels and shopfronts
A730 - Doors and Ironmongary 4 19 Jul 23 24 Jul 23 18 A730 Doors and Ironmongary
A740 - Tiling & Cnr Protectors 12 25 Jul 23 09 Aug 23 18 A740 Tiling & Cnr Protectors
A750 - Joinery and Vanity 5 10 Aug 23 16 Aug 23 18 A750 Joinery and Vanity
A760 - Inspect 1 17 Aug 23 17 Aug 23 18 A760 Inspect

A920 - Trades- Main Trading and Managers 100 22 May 23 19 Sep 23 -5


A930 - Steel support & bulkehead 21 02 Jun 23 30 Jun 23 19
A940 - Access from Brickwork 0 02 Jun 23 19 A940 Access from Brickwork
A950 - Install bulkhead steel 6 02 Jun 23 09 Jun 23 19 A950 Install bulkhead steel
A960 - Ceiling Grid to bulkhead 5 12 Jun 23 16 Jun 23 19 A960 Ceiling Grid to bulkhead
A970 - Board and Skim 3 19 Jun 23 21 Jun 23 19 A970 Board and Skim
A980 - Prime bulkead 2 22 Jun 23 23 Jun 23 19 A980 Prime bulkead
A990 - Snag bulkhead 2 26 Jun 23 27 Jun 23 19 A990 Snag bulkhead
B000 - Install bottom track 2 28 Jun 23 29 Jun 23 19 B000 Install bottom track
B010 - Inspect 1 30 Jun 23 30 Jun 23 19 B010 Inspect

B020 - Main trading 58 22 May 23 21 Jul 23 -5


B030 - Access 0 B030 Access
B040 - Stock brick to height 18 22 May 23 25 May 23 -5 B040 Stock brick to height
B050 - Wall services(Ducting and Plumbing 6 26 May 23 26 May 23 -5 B050 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
B060 - Wall services electrical (Inc DB tray) 10 29 May 23 31 May 23 -5 B060 Wall services electrical (Inc DB tray)
B070 - Inspect for plaster 1 01 Jun 23 01 Jun 23 -5 B070 Inspect for plaster
B080 - Plaster walls (2 coat above tiles) 10 02 Jun 23 15 Jun 23 -5 B080 Plaster walls (2 coat above tiles)
B090 - Prime walls where required 5 16 Jun 23 22 Jun 23 -5 B090 Prime walls where required
B100 - Install shaddow lines 2 23 Jun 23 26 Jun 23 -5 B100 Install shaddow lines
B110 - Ceiling grids 8 27 Jun 23 06 Jul 23 -5 B110 Ceiling grids
B120 - Electrical second fix 15 30 Jun 23 20 Jul 23 -5 B120 Electrical second fix
B130 - Ducting second fix soffit 10 03 Jul 23 14 Jul 23 -1 B130 Ducting second fix soffit
B140 - Inspect 1 21 Jul 23 21 Jul 23 -5 B140 Inspect

B150 - Finishing 68 16 Jun 23 19 Sep 23 -5


B160 - Access 0 24 Jul 23 -5 B160 Access
B170 - Ceilings - board and skimm 10 24 Jul 23 04 Aug 23 -5 B170 Ceilings - board and skimm
B180 - Paint final 8 07 Aug 23 16 Aug 23 -2 B180 Paint final
B190 - MEP Final fixes 5 07 Aug 23 11 Aug 23 -5 B190 MEP Final fixes
C090 - View panels and shopfronts 7 16 Jun 23 26 Jun 23 38 C090 View panels and shopfronts
B200 - Doors and Ironmongary 5 15 Aug 23 21 Aug 23 -2 B200 Doors and Ironmongary
B210 - Tiling & Cnr Protectors 10 14 Aug 23 25 Aug 23 -5 B210 Tiling & Cnr Protectors
B220 - Joinery and Vanity 6 25 Aug 23 01 Sep 23 -5 B220 Joinery and Vanity
B270 - Self level grout 8 04 Sep 23 13 Sep 23 -5 B270 Self level grout
B280 - Sand down self leveling 3 14 Sep 23 18 Sep 23 -5 B280 Sand down self leveling
B230 - Inspect 1 19 Sep 23 19 Sep 23 -5 B230 Inspect

B340 - Trades- Back of House (BOH) 101 22 May 23 20 Sep 23 -5


B350 - Steel support & bulkehead 21 25 May 23 22 Jun 23 32
B360 - Access from Brickwork 0 25 May 23 32 B360 Access from Brickwork
B370 - Install bulkhead steel 6 25 May 23 01 Jun 23 32 B370 Install bulkhead steel
B380 - Ceiling Grid to bulkhead 5 02 Jun 23 08 Jun 23 32 B380 Ceiling Grid to bulkhead
B390 - Board and Skim 3 09 Jun 23 13 Jun 23 32 B390 Board and Skim
B400 - Prime bulkead 2 14 Jun 23 15 Jun 23 32 B400 Prime bulkead
B410 - Snag bulkhead 2 16 Jun 23 19 Jun 23 32 B410 Snag bulkhead
B420 - Install bottom track 2 20 Jun 23 21 Jun 23 32 B420 Install bottom track
B430 - Inspect 1 22 Jun 23 22 Jun 23 32 B430 Inspect

B690 - Cold Rooms / Freezer 35 08 Jun 23 26 Jul 23 0


- Access
B700 - Measure and order 12 08 Jun 23 23 Jun 23 0 B700 Measure and order
B710 - Install cold rooms 15 26 Jun 23 14 Jul 23 0 B710 Install cold rooms
B720 - Snag and inspect- With WSP 2 17 Jul 23 18 Jul 23 0 B720 Snag and inspect- With WSP
B730 - Cast coldroom infill and floors (by hand) 6 19 Jul 23 26 Jul 23 0 B730 Cast coldroom infill and floors (by hand)

B440 - Walls 62 22 May 23 27 Jul 23 0

Printed 17:22:01 19 May 2023 Page 3 of 4


Candy 2.01f13.2 (2 6 0) R
WBHO Barlow Park- Part 3 Section of Works
Critical Tracking Programme- Checkers
Standard Barchart
Activities: Entire program
2023 2024
Current
April May June July August September October November December January February
Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23

Time Now - 19/05/2023


B450 - Access 0 B450 Access
B460 - Stock and brick to height 18 22 May 23 24 May 23 0 B460 Stock and brick to height
B470 - Wall services(Ducting and Plumbing 6 25 May 23 26 May 23 0 B470 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
B480 - Wall services electrical (Inc DB tray) 7 29 May 23 06 Jun 23 0 B480 Wall services electrical (Inc DB tray)
B490 - Inspect for plaster 1 07 Jun 23 07 Jun 23 0 B490 Inspect for plaster
B500 - Plaster walls (2 coat above tiles) 5 08 Jun 23 14 Jun 23 5 B500 Plaster walls (2 coat above tiles)
B510 - Prime walls where required 3 15 Jun 23 19 Jun 23 5 B510 Prime walls where required
B520 - Install shaddow lines 2 20 Jun 23 21 Jun 23 5 B520 Install shaddow lines
B530 - Ceiling grids 5 22 Jun 23 28 Jun 23 5 B530 Ceiling grids
B540 - Electrical second fix 7 29 Jun 23 07 Jul 23 5 B540 Electrical second fix
B550 - Ducting second fix soffit 8 17 Jul 23 26 Jul 23 0 B550 Ducting second fix soffit
B560 - Inspect 1 27 Jul 23 27 Jul 23 0 B560 Inspect

B570 - Finishing 70 15 Jun 23 20 Sep 23 -5


B580 - Access 0 28 Jul 23 0 B580 Access
B590 - Ceilings - board and skimm 7 28 Jul 23 07 Aug 23 0 B590 Ceilings - board and skimm
B600 - Paint final 5 08 Aug 23 14 Aug 23 3 B600 Paint final
B610 - MEP Final fixes 5 08 Aug 23 14 Aug 23 0 B610 MEP Final fixes
C100 - View panels and Shopfronts 7 15 Jun 23 23 Jun 23 48 C100 View panels and Shopfronts
B620 - Doors and Ironmongary * Apex doors to go in 6 15 Aug 23 22 Aug 23 0 B620 Doors and Ironmongary * Apex doors to go in last
last
B630 - Tiling & Cnr Protectors 6 23 Aug 23 30 Aug 23 0 B630 Tiling & Cnr Protectors
B640 - Joinery and Vanity 6 31 Aug 23 07 Sep 23 0 B640 Joinery and Vanity
B650 - Patch Floor 2 08 Sep 23 11 Sep 23 0 B650 Patch Floor
B660 - Sand down 1 12 Sep 23 12 Sep 23 0 B660 Sand down
B670 - Inspect 1 20 Sep 23 20 Sep 23 -5 B670 Inspect

B780 - Completion 110 21 Sep 23 21 Feb 24 -5


B790 - Clean / Acid Wash 5 21 Sep 23 27 Sep 23 -5 B790 Clean / Acid Wash
B810 - Handover certs 1 28 Sep 23 28 Sep 23 -5 B810 Handover certs
B800 - Snag 2 29 Sep 23 02 Oct 23 -5 B800 Snag
B820 - Desnag and Inspect 5 03 Oct 23 09 Oct 23 -5 B820 Desnag and Inspect
C140 - Milestone completion 1 09 Oct 23 09 Oct 23 -5 C140 Milestone completion
B260 - Post BO items- Per BO requirements 35 04 Jan 24 21 Feb 24 0
C120 - Instruction from Checkers to proceed 2 04 Jan 24 05 Jan 24 0 C120 Instruction from Checkers to proceed
B290 - Cover trench (Bondek and Concrete cart 6 08 Jan 24 15 Jan 24 0 B290 Cover trench (Bondek and Concrete car
concrete by weelbarrow and protect floor)
B300 - Final self leveling 5 16 Jan 24 22 Jan 24 0 B300 Final self leveling
B310 - Sand self level 2 23 Jan 24 24 Jan 24 0 B310 Sand self level
B320 - Vinyl to Main trading 15 25 Jan 24 14 Feb 24 0 B320 Vinyl to Main trad
B330 - Final Snag 5 15 Feb 24 21 Feb 24 0 B330

Printed 17:22:01 19 May 2023 Page 4 of 4


Candy 2.01f13.2 (2 6 0) R

You might also like