This document provides a critical tracking programme for various activities on the Barlow Park Part 3 Section of Works project taking place between May 2023 and February 2024. It details over 50 separate activities with descriptions and scheduled start and finish dates. The activities include external yard and facade works, mechanical, electrical and plumbing installation by area, and appointments required for other trades. Predecessor relationships between activities are also mapped out on the standard bar chart.
This document provides a critical tracking programme for various activities on the Barlow Park Part 3 Section of Works project taking place between May 2023 and February 2024. It details over 50 separate activities with descriptions and scheduled start and finish dates. The activities include external yard and facade works, mechanical, electrical and plumbing installation by area, and appointments required for other trades. Predecessor relationships between activities are also mapped out on the standard bar chart.
This document provides a critical tracking programme for various activities on the Barlow Park Part 3 Section of Works project taking place between May 2023 and February 2024. It details over 50 separate activities with descriptions and scheduled start and finish dates. The activities include external yard and facade works, mechanical, electrical and plumbing installation by area, and appointments required for other trades. Predecessor relationships between activities are also mapped out on the standard bar chart.
Standard Barchart Activities: Entire program 2023 2024 Current April May June July August September October November December January February Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
Time Now - 19/05/2023
B240 - Checkers Critical works tracker 224 22 May 23 21 Feb 24 -5 - Predesessors B750 - As it stands bar Concrete 26 As it stands bar Concrete C130 - Appointments Required(not yet linked) 0 20 Jan 23 0 - Bumper rails - Tiling - Cold rooms - Poly Screed - Painter - Vinyl - Timber roof - Ceiling - Roller shutter doors
B830 - External Yard and Facade 52 22 May 23 19 Jul 23 39
B840 - Yard Surface bed 13 22 May 23 05 Jun 23 39 B850 - Access 0 B850 Access B860 - Install services(1x stormwater pipe) 3 22 May 23 22 May 23 39 B860 Install services(1x stormwater pipe) B870 - G5 to final cut 2 23 May 23 24 May 23 39 B870 G5 to final cut - Box outs for bollards and falls - Local (wash down) B880 - Shutter to edges 1 25 May 23 25 May 23 39 B880 Shutter to edges B910 - Rebar (around cols only) 1 25 May 23 25 May 23 39 B910 Rebar (around cols only) B900 - Cast concrete to fall 1 26 May 23 26 May 23 39 B900 Cast concrete to fall B890 - Sawcut 1 29 May 23 29 May 23 39 B890 Sawcut B920 - Inspect 0 30 May 23 43 B920 Inspect B970 - Curing 5 30 May 23 05 Jun 23 39 B970 Curing
B930 - Yard - trades 37 30 May 23 19 Jul 23 39
B950 - Setout walls 1 30 May 23 30 May 23 43 B950 Setout walls B940 - Brick up facebrick walls 12 06 Jun 23 21 Jun 23 39 B940 Brick up facebrick walls B960 - Cast wash down 4 06 Jun 23 09 Jun 23 47 B960 Cast wash down B980 - Install bollards 5 22 Jun 23 28 Jun 23 39 B980 Install bollards B990 - Install gates 8 29 Jun 23 10 Jul 23 39 B990 Install gates C110 - Install RSD 10 22 Jun 23 05 Jul 23 48 C110 Install RSD C000 - Yard MEP Second and Final Soffit level 6 11 Jul 23 18 Jul 23 39 C000 Yard MEP Second and Final Soffit level C010 - Snag yard 1 19 Jul 23 19 Jul 23 39 C010 Snag yard
C020 - External facade +- 6m height 37 22 May 23 28 Jun 23 54
C030 - Access 0 C030 Access C040 - Brick up 46 000 bricks 27 22 May 23 22 Jun 23 54 C040 Brick up 46 000 bricks C050 - Snag facade and joint seal 4 23 Jun 23 28 Jun 23 54 C050 Snag facade and joint seal
B250 - Mechanical, Electrical and Plumbing (MEP) 44 22 May 23 28 Jun 23 0
By Area A100 - Soffit Services 44 22 May 23 28 Jun 23 0 A010 - BOH (Galvanised) 18 22 May 23 25 May 23 0 A110 - Access from soffit 0 A110 Access from soffit A120 - Havc 1st 10 22 May 23 22 May 23 0 A120 Havc 1st A130 - Plumbing 1st 8 A130 Plumbing 1st A140 - Electrical 1st 8 A140 Electrical 1st A150 - Fire 1st (dand fire only) 3 22 May 23 24 May 23 78 A150 Fire 1st (dand fire only) A160 - Inspect 1 25 May 23 25 May 23 78 A160 Inspect
A020 - Office (Painted services) 28 22 May 23 28 Jun 23 0
A040 - Access from soffit 0 22 May 23 0 A040 Access from soffit A050 - Havc 1st 10 22 May 23 02 Jun 23 0 A050 Havc 1st A060 - Plumbing 1st 7 05 Jun 23 13 Jun 23 0 A060 Plumbing 1st A070 - Electrical 1st 7 14 Jun 23 22 Jun 23 54 A070 Electrical 1st A080 - Fire 1st (dand fire only) 3 23 Jun 23 27 Jun 23 54 A080 Fire 1st (dand fire only) A090 - Inspect for paint 1 28 Jun 23 28 Jun 23 54 A090 Inspect for paint
A170 - Ablutions (Painted services) 10 22 May 23 23 May 23 80
A180 - Access from soffit 0 A180 Access from soffit A190 - Havc 1st 4 A190 Havc 1st A200 - Plumbing 1st 5 A200 Plumbing 1st A210 - Electrical 1st 5 A210 Electrical 1st A220 - Fire 1st (hand fire only) 1 22 May 23 22 May 23 80 A220 Fire 1st (hand fire only) A230 - Inspect for paint 1 23 May 23 23 May 23 80 A230 Inspect for paint
Printed 17:22:01 19 May 2023 Page 1 of 4
Candy 2.01f13.2 (2 6 0) R WBHO Barlow Park- Part 3 Section of Works Critical Tracking Programme- Checkers Standard Barchart Activities: Entire program 2023 2024 Current April May June July August September October November December January February Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
Time Now - 19/05/2023
A240 - Main trading and managers office (Painted 32 22 May 23 12 Jun 23 66 services) A250 - Access from soffit 0 A250 Access from soffit A260 - Havc 1st 12 22 May 23 22 May 23 66 A260 Havc 1st A270 - Plumbing 1st 10 23 May 23 25 May 23 66 A270 Plumbing 1st A280 - Electrical 1st(Powder coated can not fit before 8 26 May 23 06 Jun 23 66 A280 Electrical 1st(Powder coated can not fit before soffit painting) soffit painting) A290 - Fire 1st (dand fire only) 3 07 Jun 23 09 Jun 23 66 A290 Fire 1st (dand fire only) A300 - Inspect for paint 1 12 Jun 23 12 Jun 23 66 A300 Inspect for paint
A770 - Paint / Spray soffit services 27 22 May 23 21 Jun 23 59
A780 - Access 70% of service installed 0 A780 Access 70% of service installed A790 - Prep for paint & Cover facebricks 2 22 May 23 23 May 23 59 A790 Prep for paint & Cover facebricks A800 - Spray Services 15 24 May 23 13 Jun 23 59 A800 Spray Services A810 - Prime and Paint all soffit exc BOH 15 31 May 23 20 Jun 23 59 A810 Prime and Paint all soffit exc BOH A820 - Inspect 1 21 Jun 23 21 Jun 23 59 A820 Inspect
A310 - Internal areas (Ablution/ Office/ Main / 217 22 May 23 21 Feb 24 -5
BOH) A440 - Trades- Ablutions 71 22 May 23 01 Aug 23 0 A320 - Abluitions 38 22 May 23 15 Jun 23 0 A340 - Access 0 A340 Access A330 - Stock brick to height 10 22 May 23 23 May 23 0 A330 Stock brick to height A350 - Wall services(Ducting and Plumbing 6 A350 Wall services(Ducting and Plumbing penetratrations to final finish requirement ) penetratrations to final finish requirement ) A360 - Wall services electrical (Inc DB tray) 5 22 May 23 22 May 23 0 A360 Wall services electrical (Inc DB tray) A370 - Inspect for plaster 1 A370 Inspect for plaster A380 - Plaster walls (2 coat above tiles) 6 22 May 23 29 May 23 30 A380 Plaster walls (2 coat above tiles) A390 - Prime walls where required 2 30 May 23 31 May 23 30 A390 Prime walls where required A400 - Install shaddow lines 2 01 Jun 23 02 Jun 23 30 A400 Install shaddow lines A410 - Ceiling grids 4 05 Jun 23 08 Jun 23 30 A410 Ceiling grids A420 - Electrical second fix 2 09 Jun 23 12 Jun 23 30 A420 Electrical second fix A430 - Ducting second fix soffit 2 13 Jun 23 14 Jun 23 30 A430 Ducting second fix soffit A450 - Inspect 1 15 Jun 23 15 Jun 23 30 A450 Inspect
A030 - Finishing 33 16 Jun 23 01 Aug 23 30
A470 - Access 0 16 Jun 23 30 A470 Access A480 - Ceilings - board and skimm 3 16 Jun 23 20 Jun 23 30 A480 Ceilings - board and skimm A490 - Paint final 3 21 Jun 23 23 Jun 23 30 A490 Paint final A500 - MEP Final fixes 5 26 Jun 23 30 Jun 23 30 A500 MEP Final fixes A510 - Doors and Ironmongary 4 03 Jul 23 06 Jul 23 30 A510 Doors and Ironmongary A520 - Tiling & Cnr Protectors 12 07 Jul 23 24 Jul 23 30 A520 Tiling & Cnr Protectors A530 - Joinery and Vanity 5 25 Jul 23 31 Jul 23 30 A530 Joinery and Vanity A460 - Inspect 1 01 Aug 23 01 Aug 23 30 A460 Inspect
A540 - Trades- Office 76 22 May 23 17 Aug 23 18
A830 - Steel support & bulkehead 21 05 Jun 23 03 Jul 23 18 A900 - Access from Brickwork 0 05 Jun 23 18 A900 Access from Brickwork A890 - Install bulkhead steel 6 05 Jun 23 12 Jun 23 18 A890 Install bulkhead steel A880 - Ceiling Grid to bulkhead 5 13 Jun 23 19 Jun 23 18 A880 Ceiling Grid to bulkhead A870 - Board and Skim 3 20 Jun 23 22 Jun 23 18 A870 Board and Skim A860 - Prime bulkead 2 23 Jun 23 26 Jun 23 18 A860 Prime bulkead A840 - Snag bulkhead 2 27 Jun 23 28 Jun 23 18 A840 Snag bulkhead A850 - Install bottom track 2 29 Jun 23 30 Jun 23 18 A850 Install bottom track A910 - Inspect 1 03 Jul 23 03 Jul 23 18 A910 Inspect
A550 - Office 53 22 May 23 17 Jul 23 18
A560 - Access 0 A560 Access A570 - Stock brick to height 10 22 May 23 25 May 23 18 A570 Stock brick to height A580 - Wall services(Ducting and Plumbing 8 26 May 23 31 May 23 18 A580 Wall services(Ducting and Plumbing penetratrations to final finish requirement ) penetratrations to final finish requirement ) A590 - Wall services electrical (Inc DB tray) 5 01 Jun 23 01 Jun 23 18 A590 Wall services electrical (Inc DB tray) B740 - Cashroom Slab / Lintols and 90mm concrete 5 02 Jun 23 08 Jun 23 50 B740 Cashroom Slab / Lintols and 90mm concrete A600 - Inspect for plaster 1 02 Jun 23 02 Jun 23 18 A600 Inspect for plaster A610 - Plaster walls (2 coat above tiles) 15 05 Jun 23 23 Jun 23 41 A610 Plaster walls (2 coat above tiles) A620 - Prime walls where required 5 26 Jun 23 30 Jun 23 41 A620 Prime walls where required A630 - Install shaddow lines 2 03 Jul 23 04 Jul 23 41 A630 Install shaddow lines A640 - Ceiling grids 4 05 Jul 23 10 Jul 23 41 A640 Ceiling grids A650 - Electrical second fix 2 11 Jul 23 12 Jul 23 41 A650 Electrical second fix A660 - Ducting second fix soffit 2 13 Jul 23 14 Jul 23 41 A660 Ducting second fix soffit A670 - Inspect 1 17 Jul 23 17 Jul 23 41 A670 Inspect
Printed 17:22:01 19 May 2023 Page 2 of 4
Candy 2.01f13.2 (2 6 0) R WBHO Barlow Park- Part 3 Section of Works Critical Tracking Programme- Checkers Standard Barchart Activities: Entire program 2023 2024 Current April May June July August September October November December January February Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
Time Now - 19/05/2023
A680 - Finishing 39 26 Jun 23 17 Aug 23 18 A690 - Access 0 04 Jul 23 18 A690 Access A700 - Ceilings - board and skimm 3 04 Jul 23 06 Jul 23 18 A700 Ceilings - board and skimm A710 - Paint final 3 07 Jul 23 11 Jul 23 18 A710 Paint final A720 - MEP Final fixes 5 12 Jul 23 18 Jul 23 18 A720 MEP Final fixes B680 - Install safe door and finish plaster 3 19 Jul 23 21 Jul 23 19 B680 Install safe door and finish plaster C080 - View panels and shopfronts 7 26 Jun 23 04 Jul 23 44 C080 View panels and shopfronts A730 - Doors and Ironmongary 4 19 Jul 23 24 Jul 23 18 A730 Doors and Ironmongary A740 - Tiling & Cnr Protectors 12 25 Jul 23 09 Aug 23 18 A740 Tiling & Cnr Protectors A750 - Joinery and Vanity 5 10 Aug 23 16 Aug 23 18 A750 Joinery and Vanity A760 - Inspect 1 17 Aug 23 17 Aug 23 18 A760 Inspect
A920 - Trades- Main Trading and Managers 100 22 May 23 19 Sep 23 -5
A930 - Steel support & bulkehead 21 02 Jun 23 30 Jun 23 19 A940 - Access from Brickwork 0 02 Jun 23 19 A940 Access from Brickwork A950 - Install bulkhead steel 6 02 Jun 23 09 Jun 23 19 A950 Install bulkhead steel A960 - Ceiling Grid to bulkhead 5 12 Jun 23 16 Jun 23 19 A960 Ceiling Grid to bulkhead A970 - Board and Skim 3 19 Jun 23 21 Jun 23 19 A970 Board and Skim A980 - Prime bulkead 2 22 Jun 23 23 Jun 23 19 A980 Prime bulkead A990 - Snag bulkhead 2 26 Jun 23 27 Jun 23 19 A990 Snag bulkhead B000 - Install bottom track 2 28 Jun 23 29 Jun 23 19 B000 Install bottom track B010 - Inspect 1 30 Jun 23 30 Jun 23 19 B010 Inspect
B020 - Main trading 58 22 May 23 21 Jul 23 -5
B030 - Access 0 B030 Access B040 - Stock brick to height 18 22 May 23 25 May 23 -5 B040 Stock brick to height B050 - Wall services(Ducting and Plumbing 6 26 May 23 26 May 23 -5 B050 Wall services(Ducting and Plumbing penetratrations to final finish requirement ) penetratrations to final finish requirement ) B060 - Wall services electrical (Inc DB tray) 10 29 May 23 31 May 23 -5 B060 Wall services electrical (Inc DB tray) B070 - Inspect for plaster 1 01 Jun 23 01 Jun 23 -5 B070 Inspect for plaster B080 - Plaster walls (2 coat above tiles) 10 02 Jun 23 15 Jun 23 -5 B080 Plaster walls (2 coat above tiles) B090 - Prime walls where required 5 16 Jun 23 22 Jun 23 -5 B090 Prime walls where required B100 - Install shaddow lines 2 23 Jun 23 26 Jun 23 -5 B100 Install shaddow lines B110 - Ceiling grids 8 27 Jun 23 06 Jul 23 -5 B110 Ceiling grids B120 - Electrical second fix 15 30 Jun 23 20 Jul 23 -5 B120 Electrical second fix B130 - Ducting second fix soffit 10 03 Jul 23 14 Jul 23 -1 B130 Ducting second fix soffit B140 - Inspect 1 21 Jul 23 21 Jul 23 -5 B140 Inspect
B150 - Finishing 68 16 Jun 23 19 Sep 23 -5
B160 - Access 0 24 Jul 23 -5 B160 Access B170 - Ceilings - board and skimm 10 24 Jul 23 04 Aug 23 -5 B170 Ceilings - board and skimm B180 - Paint final 8 07 Aug 23 16 Aug 23 -2 B180 Paint final B190 - MEP Final fixes 5 07 Aug 23 11 Aug 23 -5 B190 MEP Final fixes C090 - View panels and shopfronts 7 16 Jun 23 26 Jun 23 38 C090 View panels and shopfronts B200 - Doors and Ironmongary 5 15 Aug 23 21 Aug 23 -2 B200 Doors and Ironmongary B210 - Tiling & Cnr Protectors 10 14 Aug 23 25 Aug 23 -5 B210 Tiling & Cnr Protectors B220 - Joinery and Vanity 6 25 Aug 23 01 Sep 23 -5 B220 Joinery and Vanity B270 - Self level grout 8 04 Sep 23 13 Sep 23 -5 B270 Self level grout B280 - Sand down self leveling 3 14 Sep 23 18 Sep 23 -5 B280 Sand down self leveling B230 - Inspect 1 19 Sep 23 19 Sep 23 -5 B230 Inspect
B340 - Trades- Back of House (BOH) 101 22 May 23 20 Sep 23 -5
B350 - Steel support & bulkehead 21 25 May 23 22 Jun 23 32 B360 - Access from Brickwork 0 25 May 23 32 B360 Access from Brickwork B370 - Install bulkhead steel 6 25 May 23 01 Jun 23 32 B370 Install bulkhead steel B380 - Ceiling Grid to bulkhead 5 02 Jun 23 08 Jun 23 32 B380 Ceiling Grid to bulkhead B390 - Board and Skim 3 09 Jun 23 13 Jun 23 32 B390 Board and Skim B400 - Prime bulkead 2 14 Jun 23 15 Jun 23 32 B400 Prime bulkead B410 - Snag bulkhead 2 16 Jun 23 19 Jun 23 32 B410 Snag bulkhead B420 - Install bottom track 2 20 Jun 23 21 Jun 23 32 B420 Install bottom track B430 - Inspect 1 22 Jun 23 22 Jun 23 32 B430 Inspect
- Access B700 - Measure and order 12 08 Jun 23 23 Jun 23 0 B700 Measure and order B710 - Install cold rooms 15 26 Jun 23 14 Jul 23 0 B710 Install cold rooms B720 - Snag and inspect- With WSP 2 17 Jul 23 18 Jul 23 0 B720 Snag and inspect- With WSP B730 - Cast coldroom infill and floors (by hand) 6 19 Jul 23 26 Jul 23 0 B730 Cast coldroom infill and floors (by hand)
B440 - Walls 62 22 May 23 27 Jul 23 0
Printed 17:22:01 19 May 2023 Page 3 of 4
Candy 2.01f13.2 (2 6 0) R WBHO Barlow Park- Part 3 Section of Works Critical Tracking Programme- Checkers Standard Barchart Activities: Entire program 2023 2024 Current April May June July August September October November December January February Activity description Durn Start Finish Float 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23
Time Now - 19/05/2023
B450 - Access 0 B450 Access B460 - Stock and brick to height 18 22 May 23 24 May 23 0 B460 Stock and brick to height B470 - Wall services(Ducting and Plumbing 6 25 May 23 26 May 23 0 B470 Wall services(Ducting and Plumbing penetratrations to final finish requirement ) penetratrations to final finish requirement ) B480 - Wall services electrical (Inc DB tray) 7 29 May 23 06 Jun 23 0 B480 Wall services electrical (Inc DB tray) B490 - Inspect for plaster 1 07 Jun 23 07 Jun 23 0 B490 Inspect for plaster B500 - Plaster walls (2 coat above tiles) 5 08 Jun 23 14 Jun 23 5 B500 Plaster walls (2 coat above tiles) B510 - Prime walls where required 3 15 Jun 23 19 Jun 23 5 B510 Prime walls where required B520 - Install shaddow lines 2 20 Jun 23 21 Jun 23 5 B520 Install shaddow lines B530 - Ceiling grids 5 22 Jun 23 28 Jun 23 5 B530 Ceiling grids B540 - Electrical second fix 7 29 Jun 23 07 Jul 23 5 B540 Electrical second fix B550 - Ducting second fix soffit 8 17 Jul 23 26 Jul 23 0 B550 Ducting second fix soffit B560 - Inspect 1 27 Jul 23 27 Jul 23 0 B560 Inspect
B570 - Finishing 70 15 Jun 23 20 Sep 23 -5
B580 - Access 0 28 Jul 23 0 B580 Access B590 - Ceilings - board and skimm 7 28 Jul 23 07 Aug 23 0 B590 Ceilings - board and skimm B600 - Paint final 5 08 Aug 23 14 Aug 23 3 B600 Paint final B610 - MEP Final fixes 5 08 Aug 23 14 Aug 23 0 B610 MEP Final fixes C100 - View panels and Shopfronts 7 15 Jun 23 23 Jun 23 48 C100 View panels and Shopfronts B620 - Doors and Ironmongary * Apex doors to go in 6 15 Aug 23 22 Aug 23 0 B620 Doors and Ironmongary * Apex doors to go in last last B630 - Tiling & Cnr Protectors 6 23 Aug 23 30 Aug 23 0 B630 Tiling & Cnr Protectors B640 - Joinery and Vanity 6 31 Aug 23 07 Sep 23 0 B640 Joinery and Vanity B650 - Patch Floor 2 08 Sep 23 11 Sep 23 0 B650 Patch Floor B660 - Sand down 1 12 Sep 23 12 Sep 23 0 B660 Sand down B670 - Inspect 1 20 Sep 23 20 Sep 23 -5 B670 Inspect
B780 - Completion 110 21 Sep 23 21 Feb 24 -5
B790 - Clean / Acid Wash 5 21 Sep 23 27 Sep 23 -5 B790 Clean / Acid Wash B810 - Handover certs 1 28 Sep 23 28 Sep 23 -5 B810 Handover certs B800 - Snag 2 29 Sep 23 02 Oct 23 -5 B800 Snag B820 - Desnag and Inspect 5 03 Oct 23 09 Oct 23 -5 B820 Desnag and Inspect C140 - Milestone completion 1 09 Oct 23 09 Oct 23 -5 C140 Milestone completion B260 - Post BO items- Per BO requirements 35 04 Jan 24 21 Feb 24 0 C120 - Instruction from Checkers to proceed 2 04 Jan 24 05 Jan 24 0 C120 Instruction from Checkers to proceed B290 - Cover trench (Bondek and Concrete cart 6 08 Jan 24 15 Jan 24 0 B290 Cover trench (Bondek and Concrete car concrete by weelbarrow and protect floor) B300 - Final self leveling 5 16 Jan 24 22 Jan 24 0 B300 Final self leveling B310 - Sand self level 2 23 Jan 24 24 Jan 24 0 B310 Sand self level B320 - Vinyl to Main trading 15 25 Jan 24 14 Feb 24 0 B320 Vinyl to Main trad B330 - Final Snag 5 15 Feb 24 21 Feb 24 0 B330