Project: 132KV Mirama-Kabale OHTL and Susbtations

ID Task Name Duration Start Finish 2022 2023 2024 2025 2026
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
0 MK- LOT1 (OHTL) & LOT2 (SS) 766 days Sat 1/1/22 Wed 1/10/24
1 Contract Effectiveness (Lot 2 SS) 198 days Sat 1/1/22 Sun 7/10/22
2 Bid Submission, Opening & Evaluation 108 days Sat 1/1/22 Fri 4/15/22 PM

3 Contract Agreement & Site Handing Over 90 days Fri 4/15/22 Sun 7/10/22 PM

4 LOT2- SUBSTATIONS 766 days Sat 1/1/22 Wed 1/10/24


5 Design and Engineering 140 days Mon 7/11/22 Wed 11/23/22
6 Site survey and soil investigation 30 days Mon 7/11/22 Mon 8/8/22 COW,PM,RE Civil,Surveyor

7 Civil Design, S/Yard layouts 30 days Tue 8/9/22 Tue 9/6/22 COW,PM,RE Civil,RE Elect,SS Expert

8 Electrical designs, data sheets 110 days Tue 8/9/22 Wed 11/23/22 PM,Prot Expert,Scada Expert

9 Civil Activities 330 days Wed 9/7/22 Sat 7/22/23


10 Land development 120 days Wed 9/7/22 Sat 12/31/22 COW,PM,RE Civil,Surveyor,EHS Expert

11 Fencing 60 days Sat 12/31/22 Mon 2/27/23 COW,PM,RE Civil

12 CR Building, foundations ,cable trenches 120 days Sat 12/31/22 Wed 4/26/23 COW,PM,RE Civil,SS Expert,RE Elect

13 Internal roads, gravel, fire fighting, 60 days Wed 4/26/23 Fri 6/23/23 COW,PM,RE Civil

14 Access road and finsihing activities 30 days Fri 6/23/23 Sat 7/22/23 COW,PM,RE Civil

15 Elecrical Activities 398 days Wed 11/23/22 Tue 12/12/23


16 Manufacturing, FAT, delivery of equipments 120 days Wed 11/23/22 Sun 3/19/23 PM

17 Installation of equipments 75 days Wed 4/26/23 Sat 7/8/23 PM,SS Expert,EHS Expert,Prot Expert,Scada Expert,RE Elect

18 Installation of necessary equipments, 60 days Thu 5/11/23 Sat 7/8/23 PM,Prot Expert,Scada Expert
checking of interfacing arrangements at
NLDC

19 Manufacturing , FAT, delivery of power Trafo 235 days Wed 11/23/22 Sat 7/8/23 PM
& installation

20 Earthing, Cabling and precomm checks at SS 133 days Sat 7/8/23 Mon 11/13/23 PM,Prot Expert,Scada Expert,SS Expert,EHS Expert,RE Elect

21 Testing and comm. 30 days Mon 11/13/23 Tue 12/12/23 PM,Prot Expert,Scada Expert,SS Expert,RE Elect

22 Post closing activities 30 days Tue 12/12/23 Wed 1/10/24


23 Handing over and closing 30 days Tue 12/12/23 Wed 1/10/24 COW,PM,RE Civil,Prot Expert,Scada Expert

24 LOT1-(OHTL) 378 days Sat 1/1/22 Sat 12/31/22


25 Civil activities 190 days Sat 1/1/22 Sun 7/3/22
26 Foundation activities 190 days Sat 1/1/22 Sun 7/3/22 COW,PM,RE Civil,EHS Expert

27 Tower and string activities 348 days Sat 1/1/22 Fri 12/2/22
28 Tower manufacturing and delivery 135 days Sat 1/1/22 Wed 5/11/22 PM

29 Tower erection 120 days Wed 5/25/22 Sun 9/18/22 COW,PM,TL Expert

30 Stringing 110 days Sat 8/6/22 Sun 11/20/22 COW,PM,TL Expert

31 Testing and commissioning 13 days Sun 11/20/22 Fri 12/2/22 COW,PM,TL Expert

32 Post closing activities 30 days Sat 12/3/22 Sat 12/31/22


33 Handing over and closing 30 days Sat 12/3/22 Sat 12/31/22 COW,PM,RE Elect,SS Expert

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Project: MK- LOT1 (OHTL) & LOT2 Split External Tasks Inactive Summary Manual Summary Critical
Date: Thu 6/29/23
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress