序号 问题 地点 问题描述 问题

专业 分类 等级
6#桥40号墩墩身高度超过
3m,未设置吊篮
工务专业 The height of pier No. 40
4724 建议类问题 DK46+935 B
(桥涵) of 6# bridge exceeds 3m,
and no hanging basket
installed

7#桥0号台步板开裂2块
4947 工务专业 工程质量类 DK48+123 2 pieces of 0 # abutment B
(桥涵) 问题
plate of 7 # bridge cracked

7#桥0号台步板缺少1块
工务专业 工程质量类 1 piece of 0 # abutment
4948 DK48+123 B
(桥涵) 问题 plate of 7 # bridge is
missing

7#桥0号台吊篮圆钢转角
处焊接与设计不符
The welding at the round
4949 工务专业 工程质量类 DK48+123 steel corner of the hanging B
(桥涵) 问题
basket of platform 0 of the
7# bridge does not match
the design

7#桥1孔下行侧梁体排水
孔渗漏水3处
工务专业 工程质量类 DK48+123 - 3 leaks from the drainage
4950 B
(桥涵) 问题 DK48+155 holes of the downlink side
beam body in the 1st hole
of the 7# bridge

7#桥全桥吊篮螺母单母
工务专业 工程质量类 DK48+123- 7 # bridge full bridge
4951 B
(桥涵) 问题 DK48+580 hanging basket nut single
nut
7#桥全桥吊篮圆钢末端无
螺母
工务专业 工程质量类 DK48+123- There is no nut at the end
4952 B
(桥涵) 问题 DK48+580 of round steel of
suspension basket of bridge
7#

7#桥全桥吊篮转角处,步
板规格不达标
At the corner of the
工务专业 工程质量类 DK48+123-
4953 hanging basket of the B
(桥涵) 问题 DK48+580
whole bridge of 7 # bridge,
the specification of the step
plate is not up to standard

7#桥全桥吊篮转角处,角
钢与墩身不密贴
At the corner of the
工务专业 工程质量类 DK48+123- hanging basket of the
4954 B
(桥涵) 问题 DK48+580 whole bridge of Bridge 7 #,
the angle steel is not
closely attached to the pier
body

7#桥全桥竖向落水管未安
工务专业 工程质量类 DK48+123- 装
4955 B
(桥涵) 问题 DK48+580 The vertical downpipe of
bridge 7 # is not installed

7#桥3号墩墩身高度超过
3m,未设置吊篮
工务专业 The height of pier body of
4956 建议类问题 DK48+220 B
(桥涵) 3 # pier of 7 # bridge is
more than 3m, and hanging
basket is not installed

7#桥4孔上行侧梁体排水
孔渗漏水2处
工务专业 工程质量类 DK48+220- 2 leaks from the drainage
4957 B
(桥涵) 问题 DK48+253 holes of the 4th hole of the
7# bridge ascending side
girder
7#桥4号墩墩身高度超过
3m,未设置吊篮
工务专业 The height of pier No. 4 of
4958 建议类问题 DK48+253 B
(桥涵) 7# bridge more than 3m,
and hanging basket is not
installed

7#桥6号墩吊篮钢筋网片
安装不到位
工务专业 工程质量类 The reinforcement mesh of
4959 DK48+318 B
(桥涵) 问题 the hanging basket of the 6
# pier of the 7 # bridge is
not installed properly

17#桥第59孔梁内排水管
卡锁损坏1处
5040 工务专业 工程质量类 DK66+120 1 damage to the drainpipe B
(桥涵) 问题
locking in the 59th hole
beam of the 17# bridge

17#桥第60孔梁内排水管
卡锁损坏3处
工务专业 工程质量类 DK66+141- The drain pipe lock in the
5041 B
(桥涵) 问题 DK66+174 60th hole beam of 17 #
bridge was damaged at 3
places

17#桥第63孔梁内排水管
卡锁损坏2处
工务专业 工程质量类 DK66+239-
5042 2 drainage pipe locks in the B
(桥涵) 问题 DK66+272
63rd hole beam of 17 #
bridge were damaged

17-1#桥全桥检查梯未安

工务专业 工程质量类 DK67+177- Inspection ladder for the
5043 B
(桥涵) 问题 DK67+833 whole bridge of 17-1 #
bridge is not installed

17-1#桥全桥墩身落水管
未安装
工务专业 工程质量类 DK67+177-
5044 The downpipe of pier body B
(桥涵) 问题 DK67+833
of bridge 17-1 # is not
installed
提出问题依据
周围同等高度墩都设置有吊篮,缺少吊篮无法完场日常的支座
养护维修工作
The surrounding piers of the same height are equipped with hanging baskets, and the
daily support maintenance and repair work cannot be completed without hanging
baskets

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.3.4条:盖板
、人行步板安装前应符合设计要求,铺设应齐全、稳固、无损坏、板间空隙一

Article 17.3.4 of "Construction Quality Acceptance Standards for Bridge and Culvert
Projects on High-Speed Railways" (TB10752-2018): Covers and walkways should
meet the design requirements before installation, and the laying should be complete,
stable, free of damage, and the gaps between the boards should be consistent

JBHSR-1-RB-C-DR-2-03桥墩附属设施,吊篮应在桥墩四周对称布置
Auxiliary facilities of JBHSR-1-RB-C-DR-2-03 bridge pier, hanging baskets should
be arranged symmetrically around the pier

JBHSR-1-RB-C-DR-2-03桥墩附属设施,M16栏杆圆钢为双螺母
JBHSR-1-RB-C-DR-2-03 pier auxiliary facilities, M16 railing round steel is double
nut

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水。
Article 17.6.6 of the "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be firmly fixed, and have no damage or
water leakage.

桥梁吊篮安装中预埋件未预留整改处理施工方案的会议纪要,根据CRDC通过
检算,采用直径20mm的螺杆,螺杆与吊篮采用双螺母固定,橡胶垫片调平间
隙,双螺母固定,钻孔孔径不小于25mm,植筋钻孔(植筋)深度不小于
400mm
The meeting minutes of the construction plan for the rectification and treatment of
the embedded parts in the installation of the bridge hanging basket are checked and
calculated according to CRDC, and a screw with a diameter of 20mm is used. The
screw and the hanging basket are fixed with double nuts, and rubber gaskets are used
to level the gap and fixed with double nuts. , the drilling diameter is not less than
25mm, and the depth of the planting bar drilling (planting bar) is not less than
400mm
JBHSR-1-RB-C-DR-2-03桥墩附属设施,M16栏杆圆钢为双螺母
JBHSR-1-RB-C-DR-2-03 pier auxiliary facilities, M16 railing round steel is double
nut

JBHSR-1-RB-C-DR-2-03桥墩附属设施,吊篮应在桥墩四周对称布置
Auxiliary facilities of JBHSR-1-RB-C-DR-2-03 bridge pier, hanging baskets should
be arranged symmetrically around the pier

桥梁吊篮安装中预埋件未预留整改处理施工方案的会议纪要,根据CRDC通过
检算,采用直径20mm的螺杆,螺杆与吊篮采用双螺母固定,橡胶垫片调平间
隙,双螺母固定,钻孔孔径不小于25mm,植筋钻孔(植筋)深度不小于
400mm
The meeting minutes of the construction plan for the rectification and treatment of
the embedded parts in the installation of the bridge hanging basket are checked and
calculated according to CRDC, and a screw with a diameter of 20mm is used. The
screw and the hanging basket are fixed with double nuts, and rubber gaskets are used
to level the gap and fixed with double nuts. , the drilling diameter is not less than
25mm, and the depth of the planting bar drilling (planting bar) is not less than
400mm

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage

周围同等高度墩都设置有吊篮,缺少吊篮无法完场日常的支座
养护维修工作
The surrounding piers of the same height are equipped with hanging baskets, and the
daily support maintenance and repair work cannot be completed without hanging
baskets

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage
周围同等高度墩都设置有吊篮,缺少吊篮无法完场日常的支座
养护维修工作
The surrounding piers of the same height are equipped with hanging baskets, and the
daily support maintenance and repair work cannot be completed without hanging
baskets

JBHSR-1-RB-C-DR-2-03桥墩附属设施,吊篮应在桥墩四周对称布置
Auxiliary facilities of JBHSR-1-RB-C-DR-2-03 bridge pier, hanging baskets should
be arranged symmetrically around the pier

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage

JBHSR-1-RB-C-DR-2-03桥墩附属设施,应在每孔简支梁固定端设置检查梯
For auxiliary facilities of JBHSR-1-RB-C-DR-2-03 bridge piers, an inspection
ladder shall be installed at the fixed end of each simply supported beam

《高速铁路桥涵工程施工质量验收标准》(TB10752-2018)第17.6.6条:桥梁
排水设施应部件齐全、固定牢靠,无破损、无漏水
Article 17.6.6 of "Construction Quality Acceptance Standards for High-Speed
Railway Bridge and Culvert Engineering" (TB10752-2018): Bridge drainage
facilities should have complete components, be fixed firmly, without damage and
water leakage
建议整改方案 整改时限 检查人

按设计图纸、验标进行整改落 4/15/2023
实 邢剑威 王亮

按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇



按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇

按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023
实 张宝辰、孙国勇

按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇



按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇

按设计图纸、验标进行整改落 4/15/2023 张宝辰、孙国勇


按设计图纸、验标进行整改落 4/15/2023 孙国勇、张宝辰


按设计图纸、验标进行整改落 4/15/2023 孙国勇、张宝辰


按设计图纸、验标进行整改落 4/15/2023 孙国勇、张宝辰


按设计图纸、验标进行整改落 4/15/2023 孙国勇、张宝辰


按设计图纸、验标进行整改落 4/15/2023 孙国勇、张宝辰



检查日期 责任单位

2/28/2023 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2
2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月3日 SINO2
2023年3月3日 SINO2

2023年3月3日 SINO2

2023年3月4日 SINO2

2023年3月4日 SINO2

2023年3月4日 SINO2

2023年3月4日 SINO2

2023年3月4日 SINO2
责任单位 问题整改意见回复

CRDC
CRDC
CRDC
整改情况 复验结论 复验人 复验日期
备注