问题分类

序号 专 业 Problem 地点
NO Professional Classificat Location
ion

卡拉旺至瓦
里尼站间
供电专业
(接触网) 工程质量类 DK57+364
问题 DK57+364
5574 Power supply
Works quality between
professional
problem Karawang
(catenary)
and Walini
Stations

工务专业
(隧道) 工程质量类
Public works 问题
5648 Works quality DK81+950
professional
problem
(Tunnel)

工务专业
(隧道) 工程质量类
Public works 问题
5649 Works quality Dk81+965
professional
problem
(Tunnel)

工务专业
(隧道) 工程质量类
Public works 问题
5650 Works quality DK82+025
professional
problem
(Tunnel)
工务专业
(隧道) 工程质量类
Public works 问题
5715 Works quality DK77+922
professional
problem
(Tunnel)

工务专业
(隧道) 工程质量类
Public works 问题
5716 Works quality DK77+925
professional
problem
(Tunnel)

工务专业
(隧道) 工程质量类
Public works 问题
5717 Works quality DK78+217
professional
problem
(Tunnel)

供电专业
(电力) 工程质量类
Power supply 问题
5789 Works quality DK75+050
professional
problem
(electric power)

供电专业
(电力) 工程质量类
Power supply 问题
5790 Works quality DK75+050
professional
problem
(electric power)

供电专业
(电力) 工程质量类
Power supply 问题
5791 Works quality DK75+050
professional
problem
(electric power)
供电专业
(电力) 工程质量类
Power supply 问题 2#隧道
5792 Works quality Tunnel 2#
professional
problem
(electric power)

供电专业
(电力) 工程质量类
Power supply 问题 2#隧道
5793 Works quality Tunnel 2#
professional
problem
(electric power)
供电专业
(电力) 工程质量类
Power supply 问题 DK73+370-
5795 Works quality DK75+050
professional
problem
(electric power)

供电专业
(电力) 工程质量类
Power supply 问题 DK73+370-
5797 Works quality DK75+050
professional
problem
(electric power)
问题描述 问题等级
Problem Description Problem
Level

628#支柱处的CP3桩影响坠砣升降
The CP3 pile at the 628 # pillar affects the B
lifting of the weight

81-82隧道上行拱腰掉块,目测长
10cm*10cm
The upward arch waist of 81-82 tunnel has B
fallen off, with a visual inspection length of
10cm * 10cm

81-82隧道下行拱顶敲击掉块1处(局部
混凝土不密实,目测10cm*6cm)
One block was knocked off the downward
B
arch crown of Tunnel 81-82 (partial
concrete is not dense, visual inspection is
10cm * 6cm)

81-82隧道下行拱顶敲击掉碴1处(局部
混凝土不密实,目测10cm*10cm )
One point of ballast falling off the arch
B
crown of tunnel 81-82 by knocking (partial
concrete is not dense, visual inspection is
10cm * 10cm)
4#隧道上行边墙渗水、露筋
4# Tunnel upward side wall water seepage B
and exposed ribs

4#隧道上行边墙局部不密
实,15cm*10cm
B
The upward side wall of Tunnel 4 is
partially not dense, 15cm * 10cm

4#隧道上行拱顶敲击掉块1处(局部混凝
土不密实,目测10cm*10cm)
Knock off 1 block on the ascending vault of B
the 4# tunnel (local concrete is not dense,
10cm*10cm by visual inspection)

DK75+050电力箱变基础周边无环形接地
网。
There is no ring-shaped grounding grid B
around the base of the DK75+050 power
box transformer.

DK75+050电力箱变基础内无接地网。
There is no grounding grid in the
B
foundation of DK75+050 power box
transformer.

DK75+050电力箱变箱体外壳接地未连接
环形接地网。
DK75+050 power box transformer casing B
grounding is not connected to the ring
grounding grid.
2#隧道内一级贯通侧2#隧道出口小里程
第一个洞室一级贯通电缆沟未贯通,电
缆盖板无法安装,电力电缆裸漏地面敷
设。
The first level through cable trench at the
exit of Tunnel 2 at the small mileage of the B
first level through side of Tunnel 2 is not
connected, and the cable cover cannot be
installed. The power cable is laid on the
ground with bare leakage.

2#隧道进口一级贯通侧和综合贯通侧,
电力电缆井、通信电缆井内,施工单位
未制作隔离挡墙,造成电力贯通电缆与
电务通信专业电缆混放无隔离措施。
At the entrance of Tunnel 2 #, at the first
level through side and comprehensive
through side, in the power cable shaft and B
communication cable shaft, the
construction unit did not make isolation
walls, resulting in the mixing of power
through cables and professional electrical
and communication cables without
isolation measures.
DK73+370-DK75+050间20#桥梁终点与
路基结合处DK 73+900电缆井内,1301#
接触网支柱,施工单位未制作隔离挡墙
,造成电力贯通电缆与电务通信专业电
缆混放无隔离措施。
In the DK73+900 cable well at the junction
of the terminal point of the 20 # bridge B
between DK73+370-DK75+050 and the
subgrade, the 1301 # catenary pillar was
not built by the construction unit, resulting
in the mixing of power through cables and
professional electrical and communication
cables without isolation measures.

DK73+370-DK75+050间20#桥梁终点与
路基结合处DK 73+900,1301#接触网支柱
,贯通电缆沟未贯通,电缆盖板无法安
装,电力电缆裸漏地面敷设。
At the junction of the terminal point of the
20 # bridge between DK73+370-
DK75+050 and the subgrade, the B
DK73+9001301 # catenary pillar is not
connected through the cable trench, the
cable cover cannot be installed, and the
power cable is laid on the ground in an
exposed manner.
Jakarta
提出问题依据
Basis
for Raising Questions

不符合《高速铁路电力牵引供电工程施工质量验收标准》(TB10758-
2018)中5.11条相关标准
It does not meet the relevant standards in Article 5.11 of the "Construction
Quality Acceptance Standards for High-speed Railway Electric Traction
Power Supply Engineering" (TB10758-2018)

根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.

根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.

根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.
根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.

根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.

根据《铁路混凝土工程施工质量验收标准》(TB 10424-2018)6.4.18条
规定;混凝土结构表面应密实平整、颜色均匀,不得有露筋、蜂窝、孔
洞、疏松、麻面和缺棱掉角等缺陷。
According to Article 6.4.18 of "Standard for Construction Quality Acceptance
of Railway Concrete Engineering" (TB 10424-2018); The surface of the
concrete structure shall be dense and flat, with uniform color, and shall be free
of defects such as exposed reinforcement, honeycomb, holes, looseness, pits,
and missing edges and corners.

根据雅万高铁电力箱式变电所基础的施工设计要求
According to the construction design requirements of the foundation of the
Jakarta-Bandung high-speed railway box-type substation

根据雅万高铁电力箱式变电所基础的施工设计要求
According to the construction design requirements of the foundation of the
Jakarta-Bandung high-speed railway box-type substation

根据雅万高铁电力箱式变电所基础的施工设计要求
According to the construction design requirements of the foundation of the
Jakarta-Bandung high-speed railway box-type substation
根据《高速铁路电力工程施工技术规程》(Q/CR 9608一2015)6.1.9“检
查电缆敷设路径不得有存在损坏电缆的因素”
According to "Technical Regulations for High-Speed Railway Electric Power
Engineering Construction" (Q/CR 9608-2015) 6.1.9 "Check the cable laying
path and there must be no factors that damage the cable"

根据:《铁路电力设计规范》(TB-10008-2015)8.3.9“当没有避让条件
,电力电缆与通信光电电缆、信号电缆同沟敷设时,应以防火阻燃材料
采取隔离措施,其平行间距不宜小于0.1m,交叉间距不宜小于0.25m
According to: "Railway Electric Power Design Code" (TB-10008-2015) 8.3.9
"When there is no avoidance condition, and power cables are laid in the same
ditch as communication photoelectric cables and signal cables, isolation
measures should be taken with fire-resistant and flame-retardant materials.
The spacing should not be less than 0.1m, and the intersection spacing should
not be less than 0.25m
根据:《铁路电力设计规范》(TB-10008-2015)8.3.9“当没有避让条件
,电力电缆与通信光电电缆、信号电缆同沟敷设时,应以防火阻燃材料
采取隔离措施,其平行间距不宜小于0.1m,交叉间距不宜小于0.25m
According to: "Railway Electric Power Design Code" (TB-10008-2015) 8.3.9
"When there is no avoidance condition, and power cables are laid in the same
ditch as communication photoelectric cables and signal cables, isolation
measures should be taken with fire-resistant and flame-retardant materials.
The spacing should not be less than 0.1m, and the intersection spacing should
not be less than 0.25m

根据《高速铁路电力工程施工技术规程》(Q/CR 9608一2015)6.1.9“检
查电缆敷设路径不得有存在损坏电缆的因素”
According to "Technical Regulations for High-Speed Railway Electric Power
Engineering Construction" (Q/CR 9608-2015) 6.1.9 "Check the cable laying
path and there must be no factors that damage the cable"
雅万高铁工程问题库
Jakarta-Bandung High-Speed Railway
建议整改方案 整改时限
Suggest a Corrective Deadline for 检查人
Action Rectifications Check Person

更改CP3位置 2023-04-30 罗斌
Change CP3 position April 30, 2023 Luo Bin

按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10
Carry out rectification Sun Guoyong,
April 10, 2023
according to design drawings Zhang Baochen
and standard inspection

按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10 Sun Guoyong,
Carry out rectification April 10, 2023
according to design drawings Zhang Baochen
and standard inspection

按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10
Carry out rectification Sun Guoyong,
April 10, 2023 Zhang Baochen
according to design drawings
and standard inspection
按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10
Carry out rectification Sun Guoyong,
April 10, 2023 Zhang Baochen
according to design drawings
and standard inspection

按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10 Sun Guoyong,
Carry out rectification April 10, 2023
according to design drawings Zhang Baochen
and standard inspection

按设计图纸、验标进行整改
落实
孙国勇、张宝辰
2023-04-10 Sun Guoyong,
Carry out rectification April 10, 2023
according to design drawings Zhang Baochen
and standard inspection

严格按照施工图施工,确保
接地良好。 李平
Strictly follow the 2023-04-15 张丙其
April 15, 2023 Li Ping,
construction drawings to
Zhang Bingqi
ensure good grounding.

严格按照施工图施工,确保
接地良好。 李平
Strictly follow the 2023-04-15 张丙其
April 15, 2023 Li Ping,
construction drawings to
Zhang Bingqi
ensure good grounding.

严格按照施工图施工,确保
接地良好。 李平
Strictly follow the 2023-04-15 张丙其
April 15, 2023 Li Ping,
construction drawings to
Zhang Bingqi
ensure good grounding.
依据《高速铁路电力工程施工
技术规程》(Q/CR 9608一
2015)有关电缆施工的要求加
强电缆敷设管理,做好电缆防
护,消除损坏电缆的因素;
According to the "Technical
Regulations for High-Speed 李平
Railway Electric Power 2023-04-15 张丙其
Engineering Construction" April 15, 2023 Li Ping,
(Q/CR 9608-2015) regarding Zhang Bingqi
cable construction
requirements, strengthen cable
laying management, do a good
job in cable protection, and
eliminate factors that damage
cables;

李平
建议增加隔离挡墙 张丙其
It is recommended to add 2023-04-15
April 15, 2023 Li Ping,
isolation walls Zhang Bingqi
李平
建议增加隔离挡墙 张丙其
It is recommended to add 2023-04-15
April 15, 2023 Li Ping,
isolation walls
Zhang Bingqi

依据《高速铁路电力工程施工
技术规程》(Q/CR 9608一
2015)有关电缆施工的要求加
强电缆敷设管理,做好电缆防
护,消除损坏电缆的因素;
According to the "Technical
Regulations for High-Speed 李平
Railway Electric Power 2023-04-15 张丙其
Engineering Construction" April 15, 2023 Li Ping,
(Q/CR 9608-2015) regarding Zhang Bingqi
cable construction
requirements, strengthen cable
laying management, do a good
job in cable protection, and
eliminate factors that damage
cables;
雅万高铁工程问题库
igh-Speed Railway Works Problem Base
责任单位
Unit of Responsibility
检查日期
Check 施工单位 监理单位
the Date Construction unit Supervision unit

2023-03-15
SINO2
March 15, 2023

2023-03-17
SINO2
March 17, 2023

2023-03-17
SINO2
March 17, 2023

2023-03-17
SINO2
March 17, 2023
2023-03-18
SINO2
March 18, 2023

2023-03-18
SINO2
March 18, 2023

2023-03-18
SINO2
March 18, 2023

2023-03-19
SINO2
March 19, 2023

2023-03-19
SINO2
March 19, 2023

2023-03-19
SINO2
March 19, 2023
2023-03-19
SINO2
March 19, 2023

2023-03-19
SINO2
March 19, 2023
2023-03-19
SINO2
March 19, 2023

2023-03-19
SINO2
March 19, 2023
m Base
责任单位
it of Responsibility
问题整改意见回复
设计单位 建设单位 Reply to Rectification
Design Unit Constructing Unit Problem
复验结论
整改情况 复验人 复验日期
Retest the
Rectification Re-Tester Retest Date
Conclusion
备注
Remarks