Professional Documents
Culture Documents
Greenberg 1985
Greenberg 1985
OF TORRIJOS AIRPORT
s
Maurice S. Greenberg 1 a n d V e r n o n A.JSmoots, 2 Fellows A S C E , '
and R u d y M.jPacal, 3 M. ASCE i '
Downloaded from ascelibrary.org by University Of Ulster AT on 06/01/15. Copyright ASCE. For personal use only; all rights reserved.
CIGALPA
MEXICO CITY 'ANAGUA
GUATEMALA CITY CARACAS
SAN SALVADOR GEORGETOWN
SAN JOSE PARAMARIBO
PANAMA CITY B060T/
ASUNCION
MONTEVIDEO
BUENOS AIRES
terminal that did not adequately serve the increasing passenger traffic
at Tocumen. The basic data for the modified original runway, taxiway
and apron facilities are listed in Table 1.
In 1970, the first of the wide-body jets, the Boeing 747, entering the
international air passenger field. Pan American Airlines, the largest sin-
gle carrier using Tocumen Airport as a key stop in its passenger runs
between North and South America, was beginning to schedule 747 air-
craft into Tocumen. Studies indicated that the existing runway, taxiway
and apron system were marginally able to accept the 747 traffic, and that
with the traffic, major degradation of these pavements would be in-
curred. Much of the jet freight traffic was load-limited for the existing
runway and consequently stage-limited in its flight operations. Still the
existing runway system was subject to reduced life and increasing main-
tenance requirements.
Added to the shortened structural integrity were additional problems
concerning security and safety. The existence of only one jet runway
under the control of the Republic of Panama placed some limitations on
the security of the nation and the convenience of the users. The Pana-
manian Air Force is based at Tocumen Airport, and its security, patrol
and rescue missions were curtailed whenever the runway was closed for
repairs or other reasons.
Runway conditions also impaired safety because of the poor drainage
of the shoulders and a lack of center-line lighting. The first 700 m (2,300
ft) of Runway 3 were constructed on a level grade. The shoulders were
generally flush with the edges of the runway and densely grassed. This
caused the water during heavy rainstorms to pond along the edges of
the runway. The DAC recorded 13 aircraft accidents at Tocumen in the
10-yr period preceding 1970; at least three of the accidents were partially
ascribed to hydroplaning or poor visibility. Some of these accidents caused
the airport to close for periods of up to 24 hr.
Obstructions in the approach surface of Runway 21 also affected air-
craft operation. A hill located approximately 7 km (4.3 mile) northeast
of the threshold of Runway 21 made it necessary to approach on a cir-
cling descent and takeoff on a climbing turn. Approaches were limited
to VFR during daylight hours and, accordingly, Runway 21 was not in-
strumented.
175
0+MO TOOt) 2000 3000 4000 5000 6000 7000 8001) 9000 10000 11000 12000 13000 FEET
With the acquisition of the initial geotechnical data, the location of the
south end of the runway-taxiway could be altered to avoid the deposits
of compressible soils. At the same time, man-made cultural develop-
ments in the north imposed limits on adjustments in runway alinement
and location. Although the latitude for fine tuning was severely limited,
a modification of approximately one degree in alinement made it pos-
sible to remove a major cultural obstruction—the Velodrome—from the
northerly airspace surface and, at the same time, lower the upper
threshold of the new runway so that fill requirements could be reduced.
Accordingly (see Fig. 5), it was decided to move the original runway
179
Runway Threshold
length, Elevations, Runway Runway,
total, in in meters grade, width, in
meters Runway Alinement (feet) meters
as a per-
Downloaded from ascelibrary.org by University Of Ulster AT on 06/01/15. Copyright ASCE. For personal use only; all rights reserved.
location 600 m (2,000 ft) north, and to shift the south end 122 m (400 ft)
west. In this fashion, the south end of the runway would be moved off
the deeper compressible deposits. Additionally, it was possible to lower
the southerly end of the runway to yield a runway slope or grade of no
more than 0.15%. The relocation and reduced fill heights would result
in less settlement. Specifics of the new parallel runway design are shown
in Table 2.
The adjustment of the new runway alinement, based on further
knowledge of the geotechnical subsurface conditions, materially im-
proved the technical practicality of the airport's final design and con-
structability. The final runway layout is shown in Fig. 6.
Additional geotechnical investigations were performed along the new
alinement to evaluate suitable structural fill materials. Soil conditions along
the new alinement were better than those previously discovered along
the initial alinement. The clayey soils, particularly the upper clays, were
found to be preconsolidated, resulting in higher shear strengths. The
presence of the preconsolidated clays, coupled with the lowering of the
embankment height, eliminated the need for the stability berms.
The final investigation confirmed the presence of interbedded lenses
1+000 0+500 0+000 0+500 1+000 1+500 2+000 2+500 3+000 0+500 1+000 1+500 2+000
12,000 14,000 16,000
STATION IN FEET
RUNWAY DESIGNATIONS
Runway Taxiway Taxiway
Old Runway New Runway
shoulders, width, shoulders,
in meters in meters in meters South North South North
Downloaded from ascelibrary.org by University Of Ulster AT on 06/01/15. Copyright ASCE. For personal use only; all rights reserved.
181
182
CONSTRUCTION
for Panama.
We understand that the earth-work contractor adhered to the con-
struction plan developed by The Ralph M. Parsons Company, the design
contractor. Earth work and grading were achieved in the first construc-
tion season, and paving was carried out in the following construction
season. The surcharges, placed at the end of the first construction sea-
son and left in place during the subsequent rainy season, achieved the
forecast settlement based on the geotechnical investigation. Concrete
runway and taxiway pavements were placed during the second con-
struction season largely as designed. The adequacy of the design and
subsequent construction are evident in the condition of the pavement
today, almost nine years after completion, especially on fills over soft
subsoils, a credit to the consultants, designers and constructors of the
airport.
Some minor adjustments in the length of foundation pilings for the
south satellite of the terminal were necessary during construction. The
design lengths of these piles were based on borings in the terminal
building area and each satellite location. When actual drilled-in piles were
installed for the south satellite, particularly in the area of the south edge
of the satellite building, the underlying unweathered tosca dipped sharply
and the lengths of these few piles had to be materially increased so that
the tips would key into the unweathered sound tosca (dark-green or
bluish-green rock). The foundations of the main terminal building founded
on the unweathered tosca were installed amid conditions consistent with
the geotechnical final design investigation results. This relatively minor
condition, detected in regard to the south satellite, had substantially no
impact on the construction schedule or final cost of the passenger ter-
minal.
As soon as the new runway and taxiway systems could be used, re-
habilitation of the original runway was begun. The rehabilitation plan
called for the replacement of all cracked or failed slabs, the majority of
which were in the south end of the old runway. Additionally, a system
of subdrainage relief was installed in the area of the south end of the
old runway so that the saturation condition that always prevailed in this
section could be reduced or eliminated. This condition was caused by
the granular subbase under the concrete pavement, which, because of
runway slope, channeled all water entering the subbase along the entire
runway length to the lower (south) end, where early design did not
provide for egress. Accordingly, the lower section of the old runway was
nearly always wet. With the installation of a subbase drainage outlet,
this condition was corrected. The next step in the rehabilitation was to
place 6 in. of leveling bituminous base over the.concrete to eliminate
reflective joint propagation. This was followed by 4 in. of bituminous
base and 2 in. of bituminous wearing surface, elevating the Load Clas-
sification Number (LCN) of the old runway from 44 to 66 to accept all
184
i»T
FIG. 7.—Close-up View of Plates and Dial Gages Mounted on Independent Ref-
erence Frame
:>5 •//:
" "• I
FIG. 8.—View North Showing Boring Crew Driving for Soil Sampling, Using 140-
Ib Drop Weight with Which Standard Penetration Test is Performed
185
FIG. 10.—Looking North from South End of New Terminal Apron Area Showing
South Satellite During Construction (Work in Foreground is Placing of Apron
Paving)
186
187
this way, the expansion of the shopping and commercial areas was
achieved.
When the new passenger terminal was completed, with its airport
control tower crowning the building, the floors below the control tower
cab and the top floor of the terminal were finished and designated as
potential but unassigned office expansion areas for the DAC. In the years
since 1978, many of these office areas have been used to house staff
activities formerly conducted in rented office structures not directly lo-
cated on the airport property, or in areas in Panama City. Now most
DAC activities are located in the terminal control-tower complex, re-
FIG. 13.—Aerial View of Torrijos Airport Looking North from just South of New
(East) Runway Threshold, Showing High-Speed Turnouts, Terminal-Area Apron
and Terminal and Connecting Taxiways to Old Runway (Now Westerly Facility),
Upgraded by Asphalt Overlay (In Distance Can be Seen Old Terminal Complex
Beyond but in Line with New Terminal)
188
ACKNOWLEDGMENT
189