Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

June 08, 2023

CONSTRUCTION PROGRESS

PROGRESS BILLING LOG June 08, 2023


Contract %
Scope of Work Billing Cost Remarks
Cost Completion
TEMPORARY FACILITIES
Temporary Fence/Quarters
Safety Equipments ₱49,200.00 20.00% ₱9,840.00 Equipment Cost
Mobilization / Demobilization
Temporary Water and Power
SITE CLEARING AND
EARTHWORKS
Masonry + Roofing
Demolition & Hauling ₱63,360.00 60.00% ₱38,016.00
Demolition
Site Clearing, Layouting, Staking, Footing Layout +
₱13,824.00 60.00% ₱8,294.40
Soil Poisoning Clearing
Excavation ₱25,920.00 88.00% ₱22,809.60 Footing Excavation
Earth filling and Compaction ₱25,920.00 60.00% ₱15,552.00 Site Grading
Gravel Bed / Lean Concrete ₱40,320.00 25.00% ₱10,080.00 Footing Gravel Bed
CONCRETING WORKS
Footings ₱64,951.82 89.80% ₱58,326.74 8 FTGs
Footing Tie Beam ₱79,518.43 86.61% ₱68,870.91 32.20 lineal meter
Ground Floor Slab ₱88,737.50 0.00% ₱0.00
Columns ₱165,019.68 38.54% ₱63,598.58 Average Height: 2.1m
Second Floor Beams ₱110,343.07 0.00% ₱0.00
Second Floor Slab ₱88,737.50 0.00% ₱0.00
Roof Beams ₱79,518.43 0.00% ₱0.00
Concrete Stair ₱55,823.04 0.00% ₱0.00
Formworks and Scaffolding ₱168,000.00 28.00% ₱47,040.00 Purchased and rented
MASONRY WORKS
Front & Side Wall
₱398,630.16 8.48% ₱33,803.84
Exterior Wall and Fire Wall Masonry Masonry
Interior Wall Masonry ₱61,938.24 0.00% ₱0.00
Kitchen + Nook Counter Masonry ₱14,394.24 0.00% ₱0.00
MOISTURE PROTECTION ₱28,526.40 0.00% ₱0.00
ELECTRICAL WORKS ₱119,451.36 0.00% ₱0.00
PLUMBING & SANITARY ₱126,077.28 8.00% ₱10,086.18 Septic Tank Excavation
ROOFING WORKS 0.00% ₱0.00
Roof Framing ₱153,511.68 0.00% ₱0.00
Roofing Materials ₱206,619.84 0.00% ₱0.00
Thermal Proofing ₱28,627.20 0.00% ₱0.00

Total Construction Cost ₱386,318.26

Ar. Jhean Edxer E. Magpantay, UAP


CONTRACTOR

You might also like