02 Construction Progress - June 19 2023 Day 33

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

June 24, 2023

CONSTRUCTION PROGRESS

PROGRESS BILLING LOG June 24, 2023


%
Scope of Work Billing Cost Remarks
Completion
TEMPORARY FACILITIES
Temporary Fence/Quarters
Safety Equipments 20.00% ₱9,840.00 Equipment Cost
Mobilization / Demobilization
Temporary Water and Power
SITE CLEARING AND EARTHWORKS
Demolition & Hauling 80.00% ₱50,688.00 Masonry + Roofing Demolition
Site Clearing, Layouting, Staking, Soil
60.00% ₱8,294.40 Footing Layout + Clearing
Poisoning
Excavation 88.00% ₱22,809.60 Footing Excavation
Earth filling and Compaction 80.00% ₱20,736.00 Site Grading
Gravel Bed / Lean Concrete 25.00% ₱10,080.00 Footing Gravel Bed
CONCRETING WORKS
Footings 89.80% ₱58,326.74 8 FTGs
Footing Tie Beam 86.61% ₱68,870.91 32.20 lineal meter
Columns 42.20% ₱69,638.30 Average Height : 3.4m
Ground Floor Slab 46.67% ₱41,413.79 Ground Floor and Carport
Second Floor Beams 48.60% ₱53,626.73 2F Beam Reinforcement : 88%
Second Floor Slab 0.00% ₱0.00
Roof Beams 0.00% ₱0.00
Concrete Stair 0.00% ₱0.00
Formworks and Scaffolding 30.00% ₱50,400.00 Purchased and Rented
MASONRY WORKS 0
Exterior Wall and Fire Wall Masonry 9.16% ₱36,514.52 Front & Side Wall Masonry
Interior Wall Masonry 0.00% ₱0.00
Kitchen + Nook Counter Masonry 0.00% ₱0.00
MOISTURE PROTECTION 0.00% ₱0.00
ELECTRICAL WORKS 2.41% ₱2,878.78 Ground Floor Rough Ins
PLUMBING & SANITARY 18.60% ₱23,450.37 Septic Tank Completed
ROOFING WORKS 0.00% ₱0.00
Roof Framing 0.00% ₱0.00
Roofing Materials 0.00% ₱0.00
Thermal Proofing 0.00% ₱0.00

Total Construction Cost 22.80% ₱527,568.16

Ar. Jhean Edxer E. Magpantay, UAP


CONTRACTOR

You might also like