Professional Documents
Culture Documents
Pinto - pm2 - Session 5 - Shared Slides
Pinto - pm2 - Session 5 - Shared Slides
Pinto - pm2 - Session 5 - Shared Slides
(SBOM207)
Session #5
Instructor: Abeer Iskander, PMP
1-1
Let’s Recap …
1-2
Critical Chain Project
Scheduling
Elevate Subordin
constrain ate
t system
CPM focuses
on TASKS CCM focuses on
RESOURCES
1-5
Psychological Aspects - CCM
1-7
CCM Mechanism
• Uses identified Critical Path
• Wastes extra safety margin(estimate of 50%
probability only)
• Add buffers to protect the project path
• Allocate resources to activities
• Identify resource constraints in terms of number
and availability
• Identify critical chain
• Add resource buffers where needed
• Monitor buffer usage vs. progress of project
1-8
Copyright - Abeer Iskander PMP
Identify the Critical Path
9 6
4
0 A 4 4 E 13 13 G 19
0 4 4 13 13 19
0 0 0 E
S 8 4
0 B8 8 F 12
7 15 15 19
7 7
ES & EF
Critical Path is Start AEG End
LS & LF
Float/slack
B F 1-10
Copyright - Abeer Iskander PMP
Adding Project Buffers
Applying CCM
Since this is 50%
Start End probability then we
A E G need to protect the
2D 4.5D 3D 5D project timings
Project Buffer with a buffer in
case delays
4D 2D happen
Usually 50% of
B F the reduced
timings is added
as buffer so now
project ends in
14.5 days saving
1-11
Copyright - Abeer Iskander PMP 2.5 days
Adding Feeding Buffers
(non-critical paths)
Start End
A E G Feeding buffers
2D 4.5D 3D 5D from paths
Project Buffer
merging with
critical path is also
4D 2D 3D
Feeding Buffer recommended to
B F protect durations
of these activities
1-12
Copyright - Abeer Iskander PMP
Allocating Resources
Start End
A E G
2D 4.5D 3D 5D
Project Buffer
4D 2D 3D
Feeding Buffer
B F End
Start
A-Bob E-Mike G- Jack
2D 4.5D 3D 5D
Project Buffer
4D 2D 3D 1-13
Feeding Buffer
B - Mike F-Jane
4D 2D 3D
Feeding Buffer
B F End
Start
A-Bob E-Mike G- Jack
2D 4.5D 3D 5D
Project Buffer
4D 1.5 2D 3D
Feeding Buffer
RB
B - Mike F-Jane
4D 2D 3D
Feeding Buffer
B F End
Start
A-Bob E-Mike G- Jack
2D 4.5D 3D 5D
Project Buffer
4D 1.5 2D 3D
Feeding Buffer
RB
B - Mike F-Jane
1-16
CCPM Changes
Due dates & milestones eliminated
Realistic estimates – 50% level not 90%
“No blame” culture
Subcontractor deliveries & work scheduled ES
Non critical activities scheduled LS
Factor the effects of resource contention
Critical chain usually not the critical path
Solve resource conflicts with minimal disruption
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-17
Resource Loading
The amounts of individual resources that a schedule requires during
specific time periods.
Resource loading table
Resource Name Work Details 5/5 5/12 5/19 5/26
Tom 40 hrs Work 8h 32h
Assign Bids 40 hrs Work 8h 32h
Jeff 40 hrs Work 8h 32h
Calculate Cost 40 hrs Work 8h 32h
Sue 40 hrs Work 8h 32h
Select Bid 40 hrs Work 8h 32h
Carol 8 hrs Work 8h
PR Campaign 8 hrs Work 8h
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 12-18
Resource Leveling (Smoothing)
Objectives
• To determine the resource requirements so that
they will be available at the right time
• To allow each activity to be scheduled with the
smoothest possible transition across resource
usage levels
1-22
Project Information
Task Name Predecessor Duration # of Resources
A - 4 2
B - 4 1
C - 4 2
D A 2 5
E B 3 2
F C 2 2
G D 3 5
H G 5 3
1-23
Schedule Network Diagram
A D G H
2 3 5
4
S B E E
4 3
C F
4 2
1-24
Allocate # Resources over time
PATHS
# of Resources - original 5 5 5 5 9 9 7 5 5 3 3 3 3 3
1-25
After 1st Attempt of Leveling
PATHS
1st Change
Start ADGH End A (2) D (5) G (5) G (3)
# of Resources - original 5 5 5 5 9 9 7 5 5 3 3 3 3 3
# of Resources - after 1st change 5 5 5 5 7 7 5 5 5 3 3 5 5 5
1-26
Leveled Resources After 2nd attempt
PATHS
1st Change
Start ADGH End A (2) D (5) G (5) G (3)
2nd Change
Start ADGH End A (2) D (5) G (5) G (3)
# of Resources - original 5 5 5 5 9 9 7 5 5 3 3 3 3 3
# of Resources - after 1st change 5 5 5 5 7 7 5 5 5 3 3 5 5 5 1-27
# of Resoures - after 1st & 2nd change 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Creating Resource Loading Charts (1/4)
4 B 5 5 D 9 9 E 11
Res = 2 Res = 7 Res = 3
1. Start with a
0 A 4 network diagram
Res = 6 11 F 12
Res = 6
4 C 7
Res = 2
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 12-28
Creating Resource Loading Charts 2/4
6
Resource
4 imbalance
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 12-30
Creating Resource Loading Charts 4/4
4. Rearrange activities within their slack
to create a more level profile. Splitting
8 C creates a more level project.
Resources
4 C
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 12-31
Solutions to Resource Leveling
Assign a
Delay certain Change task
different
tasks dependencies
resource
1-42
Where are we so far
Risk
Management
Scheduling
Effective Cost
Techniques &
estimations
its challenges
Project Evaluation and Control
3. Comparing Actual
with Planned
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-50
Milestone Analysis
Milestones are events or stages of the project
that represent a significant accomplishment.
Milestones
…show completion of important steps
…signal the team and suppliers
…can motivate the team
…offer reevaluation points
…help coordinate schedules
…identify key review gates
…delineate work packages
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-52
Tracking Gantt Chart
Work Performance
Information
Work Performance
Reports
Earned Value Technique (EVT)
As of today what
is the estimated As of today what
value of work is the estimated
planned to be Cost of value of work
done?
Cost of work actually
work Earned accomplished?
scheduled
EV
PV
Actual Cost of
Work done
AC As of today what is
the actual cost
incurred of the work
1-56
accomplished?
Earned Value Terms & Indices
• Schedule Variance (SV)
• Measure of schedule performance on a project.
SV = ( EV – PV )
• Schedule performance index (SPI)
SPI = EV/PV
• Cost Variance (CV)
• Measure of cost performance on a project.
• CV = ( EV – AC )
• Cost performance index (CPI)
CPI = EV/AC
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-57
Let’s think a step further…
1-58
SV & CV
• What does negative SV mean concerning
project progress?
• What does positive CV mean concerning project
progress?
• If SPI >1, is this a good indication?
• If CPI is <1, is this a good indication?
1-59
Completion & Forecasting
Estimated At Completion (EAC)
What do we currently expect the Total project to
cost?
1-60
Steps in Earned Value Management
Cost Overspend
PV EV
Budget
Slip
Schedule Performed
Schedule
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-63
Project Performance Management
Cost
EAC
Data date
BAC
AC
PV CV= EV - AC
SV= EV - PV
EV
Time
64
GROUP WORK
1-70
Exercise
.
71
Example - Wall
Construction
Wall Construction
Time = 1 week per wall
Cost = $ 1,000 per wall,
materials and labor
Total Schedule = 4 weeks
Total Cost = $ 4,000
5 pm Wednesday, Week 2
10 % So far….
Wall 1 100% is complete
50 %
1-74
Planned Value
5 pm Wednesday, Week 2
5 pm Wednesday, Week 2
50 %
Wall 4 0% = 0
Total = $1,600
76
Schedule & Cost Variance
5 pm Wednesday, Week 2
Earned Value
PV $1,800
EV $1,600
AC $2,250
Schedule Variance = EV - PV
= $1,600 -
$1,800
= ($200)
Cost Variance = EV - AC
= $1,600 -
$2,250
77
= ($650)
SPI & CPI
5 pm Wednesday, Week 2
Performance Indices
PV $1,800
EV $1,600
AC $2,250
SPI = EV / PV
= $1,600 /
$1,800
= .9
78
CPI = EV / AC
= $1,600 /
$2,250
= .7
Where are we so far
Project
Monitor/Control
in execution & Risk
Closing Management
Scheduling
Effective Cost
Techniques &
estimations
its challenges
1-80
Project Close-Out and
Termination
Extinction
Addition
Integration
Starvation
Gaining Harvesting
Finishing Handing
Over the Acceptance the Benefits
The Work
Product for the Reviewing
Product How
It All Went
Meeting Guidelines
Establish clear rules of behavior
Describe objectively what occurred
Fix the problem, not the blame
• Documentation
• Legal
• Cost
• Personnel
HAVE DO
Project Management Plan Close Suppliers’ Contracts
Final deliverable Close Project Team Contracts
Approval from stakeholders Finalize release plans
on final deliverable Record lessons learnt from
Suppliers’ Contracts failures & Successes
Project Team Contracts Prepare internal closure
documents (customized as per
Reports on successes and your organization)
failures
Project Status
Project Plans
Reports
Documents
Personnel Requirements
records Info
Meeting Minutes