Professional Documents
Culture Documents
14 03 2011 Proposal Checklist Rev1
14 03 2011 Proposal Checklist Rev1
- Electricity.
Procurement
- Procurement procedure?
- List of subcontractors for critical packages
- List of plant to be supplied from Vietnam
Construction
- QA/QC in construction
- Profile of construction subcontractors
(Fecon, PVC, Sông Đà, etc.)
- Plot Plan
- Construction equipment list
- Foundation method
- Scope of work
- Technical parameters, drawings
- Concrete Structure
- Construction Deviation
H.Tr
done a Hưng
done a Dat/ H.Tr
on-going a Thiện
on-going a Sơn
BWBC submitted preliminary proposal anh Thiện chỉ đạo
on-going a. Thiện
on-going a Thiện
on-going a Thiện
a Tuấn
(pls advise)
on-going
done
on-going a. Thiện
Done a Tuấn/H.Trang/Nhung
done a Dũng
done H.Tr
done H.Tr
on-going a Tuấn/ H.Tr
Remark
A. Vinh
A. Hưng
A. Nam
A. Thạnh
A. Vinh
(Form 12 - RFP)
A Ngoan
TM
A. Vinh
Hưng
T. Anh
A Vinh/Hưng
T. Anh
T. Anh