Professional Documents
Culture Documents
Marc Notes 2
Marc Notes 2
DOCTRINE of FRUSTRATION
Effects of Doctrine of frustration is: (criteria)
MUST be that performance of the contract becomes impossible,
– Destruction of the subject matter of the contract Taylor v Caldwell
STEP 1
ANSWER The facts of this case leads us to determine whether the Doctrine of Frustration can be applied. Finally acknowledged by
courts, Taylor v Caldwell sought to counteract the Doctrine of Absolute Liability laid down in Paradine v Jane.
STEP 2 Acceptable Impossibility choose!
STEP 2a Absolute Impossibility
a) Destroyed ANSWER In this case we can determine that the supervening event [facts] makes future performance physically
impossible, as the subject matter [fact] of the contract destroyed: Taylor v Caldwell
b) Personal services ANSWER In this case we can determine that in contracts requiring personal service, person whose
services are required becomes incapable of performing, as seen by [facts]: Morgan v Manser
c) Not available ANSWER In this case we can determine that because [facts], and thus the subject matter of the contract no
longer available to the parties – Bank Line Ltd v Arthur Capel & Co
a) STEP 2b - TIME
– Mere delay or interruption to performance of contract not normally enough to frustrate it UNLESS delay or interruption makes
the possible means of performance radically different from the means that both parties contemplated when contract was
entered into
– Will depend on the probability of the length of the delay compared to the time left to run on the contract (Pioneer Shipping v
BTP Tioxide)
– Courts tend to a 'wait and see' approach to strikes because they are usually over before the start (Embiricos v Sydney Reid)
– Events are not judged with hindsight (Court Line v Dant)
STEP 4 FUTILITY
a) Futility ANSWER The [facts] of this case shows that although performance is still possible, it would be futile because the
contract’s mutually understood purpose can no longer be achieved. Krell v Henry (coronation room rent)
b) NOT futility ANSWER The [facts] of this case shows that performance is still possible, it would be not be futile because the
contract’s mutually understood purpose could be achieved. Herne bay Steam Boat Co v Hutton (hired boat to see new king
and to see regatta – can still be partially carried out cause can see regatta)
STEP 6a - CHECK
I. The event must not be provided for in the contract (Claude Neon)
II. The event must not have been foreseen by the parties (except from the case of illegality) (Codelfa)
III. It must have been a serious possibility (Codelfa)
IV. The event must not be due to the fault of one of the parties (Maritime National Fish)
V. The onus lies on the party asserting the fault (Joseph Constantine)
When a contract is frustrated;
It is automatically discharged, at least as regards all future performance
Whole contract automatically comes to an end at the point at which frustrating event occurs
Thereafter, neither party can be held to performance
However, the contract only terminates from the point of frustration – Rights, duties and liabilities that accrued prior to that point
remain ‘on foot’
– CONDITION - NOTE: Damages for Breach of a condition or serious breach of intermediate (“innominate”) term) occurs where
contract has come into being AND one of contracting parties has failed to perform all or some of its contract obligations and the
REMEDY is rescission + Damages.
STEP 3 Date of calculation of damages (6 years limit & deed limit 12 years)
a) ACTUAL BREACH ANSWER The calculate the value of the damages to be awarded, one must determine the date from
which the breach occurred and [facts] indicate that [was the date] Johnson v Perez (lawyer client – date action expired)
Johnson v Agnew (A sold to B, B went cold on deal, but A’s bank sold the property – the claim was to be the date the bank
has sold the land)
b) ANTICIPATORY BREACH ANSWER The calculate the value of the damages to be awarded, one must determine the date
from which the breach occurred and [facts] indicate show that the breach was anticipated then we can state that breach
occurred on [was the date] Melachrino v Nickoll and Knight
STEP 4 CAUSATION
a) BUT FOR ANSWER The ‘but for ‘ test established in March v Stramare [facts] allow us to determine that there was “causal
connection” between the breach of the contract by the defendant and the plaintiff has proven that the loss, based on the
balance of probabilities. Photo Production v Securicor Transport
b) Multiple cause ANSWER This case shows multiple causes for the breach so the ‘but for ‘ test established in March v
Stramare [facts] cannot be used to determine if that there was “causal connection” between the breach of the contract by the
defendant and the plaintiff has proven that the loss, based on the balance of probabilities. Photo Production v Securicor
Transport . The court will then use a common sense: Chappel v Hart, or policy consideration approach: Alexander v
Cambridge
STEP 5 REMOTENESS
a) Natural & not too remote ANSWER As established as the first limb of remoteness in Hadley v Baxendale (crankshaft for mill)
the facts [facts] allow us to determine that loss arising naturally from the breach was not too remote as clarified in Victoria
Laundry v Newman Industries and in Australia, the favoured interpretation is “sufficiently likely to result” Burns v MAN
Automotive
b) SPECIAL & not too remote ANSWER As established as the second limb of remoteness in Hadley v Baxendale the facts
[facts] allow us to determine that loss arising from the [special or exceptional circumstances] can be shown that the
defendant had actual knowledge of the plaintiff’s needs. Victoria Laundry v Newman Industries, Koufos v Czarnikow
STEP 6 MITIGATION OF DAMAGES
a) Did take steps ANSWER The general rule for mitigation is that the plaintiff must take reasonable steps to minimise their loss:
Dunkirk v Lever. As can be seen by the facts of this case [facts] the plaintiff did take all reasonable steps to minimize or
mitigate the loss and so qualifies for damages: Robinson v Hartman
b) Did NOT take steps ANSWER The general rule for mitigation is that the plaintiff must take reasonable steps to minimise their
loss: Dunkirk v Lever. As can be seen by the facts of this case [facts] the plaintiff did not take all reasonable steps to
minimize or mitigate the loss and so does not qualify for damages: Payzu v Saunders
– Extravagant steps P is only required to take steps that are reasonable, not required to resort to steps that are costly or
extravagant (Westinghouse v Underground Electric)
– new bargain If the parties had the opportunity of entering into a new bargain after breach which might have eliminated the loss
suffered, the issue is whether the P has acted reasonably in refusing to enter into a new contract (Schindler v Northern
Raincoat)
– Refusal to negotiate because of any ulterior motive may deny the P damages where entering into another contract with the D
would have been reasonable (Payzu v Saunders)
– The fact that the losses of the P have increased will not bar recovery – if they have acted reasonably they will be recoverable
(Banco v Waterlow)
– Principles of mitigation to not apply to claims for liquidated damages or other non-contractual debts (White and Carter v
McGregor)
STEP 7 DAMAGES ARE ONLY COMPENSATORY
1. ANSWER In assessing appropriate compensation, the court will attempt to place the plaintiff in same situation with respect to
damages, as if the contract had been performed as only actual loss can be compensated for in damages Commonwealth of
Australia v Amann Aviation P/L
STEP 8 Expectation losses (normal) or Reliance losses (ex not making a profit but had wasted money trying to do contract)
1. ANSWER The facts in this case [facts] show that the plaintiff is entitled to recover those losses that are expected to arise out
of this breach: Tabcorp Holdings Ltd v Bowen Investments P/L and the court will ensure that the plaintiff is not placed in a
superior position from which the plaintiff would have been in had the contract been performed: Commonwealth of Australia v
Amann Aviation P/L
– Loss of reputation or publicity (only where contract promises publicity or enhancement to reputation) (Marve v George
Edwardes Ltd)
STEP 11 Damages
1. ANSWER When assessing the amount of damages to be awarded to the plaintiff the courts must estimate to the best of its
ability: Fink v Fink as difficulty in calculating is not a ground for disallowing a claim, Howe v Teefy (lease of racehorse – future
earnings – Held because court tried to make it reasonable)
a) ORDINARY DAMAGES ANSWER based on the facts of the case [facts] the plaintiff should argue that he be compensated
for the loss suffered as a result of the breach [money]
b) Nominal DAMAGES ANSWER based on the facts of the case [facts] the plaintiff should argue that the plaintiff’s legal
rights have been infringed and although no loss has been suffered he should receive at least nominal damages [money]
NSW v Stevens, Charter v Sullivan
c) Punitive DAMAGES ANSWER The plaintiff cannot argue for punitive damages as they are not recoverable: Gray v Motor
Accident Commission
– Unliquidated damages Awarded where injured party has no fixed sum mentioned in the contract and therefore leaves it to the
court to decide the amount of damages
– PENALTY - Stipulation inserted into contract to make it punitively expensive for party to commit a breach of contract BUT NOT
enforceable because it is NOT a genuine pre estimate of the damage that will result from the breach Dunlop Pneumatic Tyre Co
v New Garage and Motor Co
NOTE Has IP lost right to sue for breach of contract? Eg statute of limitations
STEP 2
1. STATE –quantum Meruit ANSWER The facts of this case show us that the plaintiff has [does work for – supplies good –
rendered services] at the request of the defendant. However, as seen above the no longer remains any contractual
requirement to be paid for it, so we will argue that the plaintiff has the right to be reasonably remunerated through quantum
meruit. CHOOSE -
a) Mistake ANSWER The facts of this case show us that the plaintiff has the right to recover the money paid under a
mistake ANZ v Westpac, It would not matter whether it was a mistake of fact or under a mistake of law, David
Securities P/L V CBA, but it this case it was a mistake of [law/fact] because [facts]
b) Failure of consideration ANSWER The facts of this case show us that there has been a total failure of
consideration: Fibrosa SA v Fairbarn Lawson Combe Barbour LTD, because [facts] and as this was the
underlying unjust factor the plaintiff has the right to recover the money. Baltic Shipping v Dillon
c) Reasonable remuneration ANSWER The facts of this case show us that the plaintiff can argue the right to claim
for reasonable remuneration for the [work – supplies good – rendered services] under the [void – unenforceable –
ineffective or contract that didn’t eventuate] because [facts]. Pavey & Matthews P/L v Paul & Lumbers v W Cook
Builders P/L
d) Anticipated Contracts ANSWER The facts of this case show us that the plaintiff can argue the right to claim for
reasonable remuneration because the facts show that the plaintiff truly anticipated that a contract would be
forthcoming due to the [work – supplies good – rendered services] and the [actions of defendant] Angelopoulos v
Sabatino
STEP 3
1. STATE -defenses ANSWER The defendant could argue that they have not been unjustly enriched because he acted in to his
detriment on the faith of the receipt of the benefit and it would be inequitable for the money to be returned because [facts]
EQUITABLE – specific performance – Injunctions Mareva Injucntion – Anton Piller Order
– Not available where damages will suffice Lucas Stuart P/L v Hemmes Hermitage P/L
– Not available for contracts that require constant supervision Coop Insurance Society Ltd v Argyll Stores (Holdings) Ltd
– Not available where damages will suffice Lucas Stuart P/L v Hemmes Hermitage P/L
c) Mareva injunction ANSWER We believe that the defendant may move assets from the courts jurisdiction. The [facts] indicate
a real risk so we will ask the court to freeze the defendants assets through a Mareva injunction Mareva Compania Naviera
SA v International Bulkcarriers SA
d) Anton Pillar order ANSWER We believe that the defendant has in his possession evedence that is vital to our claim. The
[facts] indicate such possesion so we will ask the court to apply an Anton Piller order so that we may gain access to this
evidence Anton Piller KG v Manufacturing Processes Ltd
International sale of goods
– United nations Convention on Contracts for the International Sale of Goods (CISG) NOT SERVICES!
– COMMERCIAL only!
– 83 contracting states (as 26 Sept 2014) inc Aus, Canada, china, Japan, France, Germany, Mexico, Russia, US
– Implemented in Aus by state & territory – Queensland- Sale of Goods (Vienna Convention) Act 1986
– CISG creates uniform rules, taking into account different social, economic and legal systems
– The rules of private international law must lead to the application of the law of a contracting state/country countries -
MUST be contracting to the convention ARTICLE 1(b) CISG HOWEVER a contracting state may declare that it will apply
the CISG only when the buyer & seller are both from contracting states/countries
– Opting In & Out – parties to a contract may exclude or modify the CISG application by choice of law clause ARTICLE 6
(like UK may opt in to use it)
– Whether party can exclude a domestic law and adopt the CISG DEPENDS on the rules of the state where the case is
heard
Coverage of CISG
The formation of contracts
The rights and obligations of the parties ARTICLE 4
NO Coverage of CISG
1. Matters concerning the enforceability of contracts
– The validity of contractsARTICLE 5
– Sales of electricity
– Firm offers
– Definiteness ARTICLE 14
– Formalities ARTICLE 11
– Remedies ARTICLE 25 (Nachfirst Notice Article 47, 48 and 63(1)) - (buyer’s right to reduction in price ARTICLE 50)
Albania Denmark Japan Republic of Congo
Argentina Dominican Republic Kyrgystan Republic of Korea
Armenia Ecuador Latvia Romania
Australia Egypt Lebanon Russian Federation
Austria El Salvador Lesotho Saint Vincent & Grenadines
Bahrain Estonia Liberia San Marino
Belarus Finland Lithuania Serbia
Belgium France Luxembourg Singapore
Benin Gabon Macedonia Slovakia
Bosnia-Herzegovina Georgia Mauritania Slovenia
Brazil Germany Madagascar Spain
Bulgaria Greece Mexico Sweden
Burundi Guinea Moldova Switzerland
Canada Guyana Mongolia Syria
Chile Honduras Montenegro Turkey
China (PRC) Hungary Netherlands Uganda
Colombia Iceland New Zealand Ukraine
Croatia Iraq Norway United States
Cuba Israel Paraguay Uruguay
Cyprus Italy Peru Uzbekistan
Czech Republic Poland Yugoslavia
Zambia