Stage Plan Construct Ramp Middle Area
Stage Plan Construct Ramp Middle Area
KAMU Project
June 2023
Overview Design
Concern : Construct Ramp Middle Area
Highlight
1. Prepare access & Install Culvert HDPE (EX60)
2. Sidecast & cleaning coal (EX60)
3. Loading OB 1 Fleet to expose
4. Loading Coal to Mineout
Loading OB to
Expose (3.3 kBCM)
Sidecast &
Cleaning
Install
Culvert
Jun-23
Project Unit
25 26 27 28 29 30
Install Culvert EX60
Sidecast & Cleaning Coal EX60
Loading OB to Expose EX OB
Loading Coal to Mine Out EX Coal
2
Overview Design
Concern : Construct Ramp Middle Area
Highlight
1. Prepare access & Install Culvert HDPE (EX60)
2. Sidecast & cleaning coal (EX60)
3. Loading OB 1 Fleet to expose
4. Loading Coal to Mineout
Loading Coal to
Mineout (11.2 Kton)
Jun-23
Project Unit
25 26 27 28 29 30
Install Culvert EX60
Sidecast & Cleaning Coal EX60
Loading OB to Expose EX OB
Loading Coal to Mine Out EX Coal
3