Professional Documents
Culture Documents
2016 - (ARTIGO) - Structural Performance of Steel Pile Caps Strengthened With Perfobond Shear Connectors Under Lateral Loading
2016 - (ARTIGO) - Structural Performance of Steel Pile Caps Strengthened With Perfobond Shear Connectors Under Lateral Loading
2016 - (ARTIGO) - Structural Performance of Steel Pile Caps Strengthened With Perfobond Shear Connectors Under Lateral Loading
sciences
Article
Structural Performance of Steel Pile Caps
Strengthened with Perfobond Shear Connectors
under Lateral Loading
Young-Ho Kim 1 , Jae-Yoon Kang 2 , Sang-Ho Kim 3 and Dae-Jin Kim 4, *
1 Institute of R&D, Ji Seung Consultant Co., Ltd., Seoul 06128, Korea; steelkyh@hanmail.net
2 Korea Institute of Civil Engineering and Building Technology, Goyang 10223, Korea; jykang@kict.re.kr
3 Hyundai Engineering Co. Ltd., Seoul 03058, Korea; skim21@live.com
4 Department of Architectural Engineering, Kyung Hee University, Yongin 17104, Korea
* Correspondence: djkim@khu.ac.kr; Tel.: +82-31-201-3329
Abstract: The conventional strengthening strategy on the connection between the steel pile cap and
reinforced concrete footing requires a series of complicated processes such as the distribution of
reinforcing bars, their anchorage into concrete, and the usage of shear keys. This study investigates
the structural performance of steel pile caps strengthened with newly proposed perfobond shear
connectors subjected to lateral loading. Test parameters include the type of perfobond shear
connectors, infilled concrete depth, and the number of L-shaped steel plates. The applied load versus
deformation curve is plotted for all specimens, and their failure modes are identified. The effects of
the test parameters on the peak load are examined in this work. From the results of this study, it can
be confirmed that the proposed perfobond shear connector can be utilized as an alternative to the
conventional steel pile cap strengthening method using steel rebars.
Keywords: steel pipe pile; perfobond connector; concrete footing; pile cap; bending resistance
1. Introduction
In case the reinforced concrete footing does not have enough bearing capacity to support various
types of loads transmitted from the upper structure, steel pipe piles can be used to provide additional
bearing capacity to the foundation. In order to guarantee the safe load transfer from the upper structure
to the supporting layer of rocks, it is highly important to integrate the steel piles into the concrete
footing slab. This can generally be achieved by the use of steel reinforcing bars (rebars) embedded into
the concrete footing. However, it is not easy to retain a sufficiently high level of bond strength between
the reinforcing bars and surrounding concrete due to their limited rib size and small cross-sectional
area unless a large number of rebars are used at the pile cap connection. This may complicate the
processes required with the use of rebars, such as their distribution into concrete footing and the usage
of shear keys, and become a critical issue when designing a pile cap connection subjected to seismic
loads as discussed in [1,2].
In order to address this issue, the perfobond shear connector illustrated in Figure 1 was proposed
in [3]. This type of perfobond shear connector can guarantee an excellent composite behavior among
the structural components at the steel pile cap. This device is basically a steel plate with holes and
embedded into concrete to ensure the perfect integration of steel members and surrounding concrete.
As external loads are applied, the dowel action of concrete inside the hole is activated and enables
the load from the upper structure to be safely transferred to the steel pipe piles. This perfobond shear
connector was originally developed to ensure the composite behavior of steel beams and slab concrete
by [4]. Since then, it has been extensively utilized in the construction industry and developed
concrete by [4]. Since then, it has been extensively utilized in the construction industry and developed
Appl. Sci. 2016, 6, 317 2 of 11
into
various forms by many researchers [5–9].
into various forms by many researchers [5–9].
concrete by [4]. Since then, it has been extensively utilized in the construction industry and developed
into various forms by many researchers [5–9].
(a) (b) (c)
Figure 1. Perfobond shear connector for steel pile cap strengthening. (a) Perfobond shear connector
Figure 1. Perfobond shear (a) connector for steel(b)
pile cap strengthening. (c)
(a) Perfobond shear connector
with closed holes. (b) Perfobond shear connector with open holes. (c) Connection between the steel
with closed holes; (b) Perfobond shear connector with open holes; (c) Connection between the steel
pile and perfobond shear connectors.
Figure 1. Perfobond shear connector for steel pile cap strengthening. (a) Perfobond shear connector
pile and perfobond shear connectors.
with closed holes. (b) Perfobond shear connector with open holes. (c) Connection between the steel
The proposed perfobond shear connector can be installed at the pile cap connection by following
pile and perfobond shear connectors.
The proposed perfobond shear connector can be installed at the pile cap connection by following
the four steps illustrated in Figure 2. In the first step, the unnecessary portion of the steel pile cap is
the four The proposed perfobond shear connector can be installed at the pile cap connection by following
removed via gas cutting with the help of a guide supporter as shown in Figure 2a. Then, bolting holes
steps illustrated in Figure 2. In the first step, the unnecessary portion of the steel pile cap is
the four steps illustrated in Figure 2. In the first step, the unnecessary portion of the steel pile cap is
are punched at the upper locations of the steel pile cap using a punching machine in Figure 2b. As a
removed via gas cutting with the help of a guide supporter as shown in Figure 2a. Then, bolting holes
removed via gas cutting with the help of a guide supporter as shown in Figure 2a. Then, bolting holes
are third step, a bottom circular form is installed inside the steel pile, and the perfobond shear connectors
punched at the upper locations of the steel pile cap using a punching machine in Figure 2b.
are punched at the upper locations of the steel pile cap using a punching machine in Figure 2b. As a
are connected into the steel pile using high‐tension bolts as illustrated in Figure 2c. In the last step,
As a third step, a bottom circular form is installed inside the steel pile, and the perfobond shear
third step, a bottom circular form is installed inside the steel pile, and the perfobond shear connectors
steel rebars are distributed in the concrete footing, and penetration rebars are put into the holes of
connectors are connected into the steel pile using high-tension bolts as illustrated in Figure 2c. In the
are connected into the steel pile using high‐tension bolts as illustrated in Figure 2c. In the last step,
the perfobond connectors as shown in Figure 2d. After all of these steps are completed, concrete can
last step, steel rebars are distributed in the concrete footing, and penetration rebars are put into the
steel rebars are distributed in the concrete footing, and penetration rebars are put into the holes of
be poured into the footing. It can be noted from this that the construction procedure of the proposed
holes of the perfobond connectors as shown in Figure 2d. After all of these steps are completed,
the perfobond connectors as shown in Figure 2d. After all of these steps are completed, concrete can
perfobond connector is much simpler and less time consuming than that of the strengthening method
concrete can be poured into the footing. It can be noted from this that the construction procedure of the
be poured into the footing. It can be noted from this that the construction procedure of the proposed
using steel rebars.
proposed perfobond connector is much simpler and less time consuming than that of the strengthening
perfobond connector is much simpler and less time consuming than that of the strengthening method
method using steel rebars.
using steel rebars.
(a) (b)
(a) (b)
(c) (d)
Figure 2. Perfobond shear connector for steel pile cap strengthening. (a) Cutting of steel pile cap. (b)
(c) (d)
Hole punching on the steel pile cap. (c) Installation of perfobond shear connectors by bolting. (d)
Distribution of steel reinforcing bars at concrete foundation.
Figure 2. Perfobond shear connector for steel pile cap strengthening. (a) Cutting of steel pile cap. (b)
Figure 2. Perfobond shear connector for steel pile cap strengthening. (a) Cutting of steel pile cap;
Hole punching on the steel pile cap. (c) Installation of perfobond shear connectors by bolting. (d)
(b) Hole punching on the steel pile cap; (c) Installation of perfobond shear connectors by bolting;
Distribution of steel reinforcing bars at concrete foundation.
(d) Distribution of steel reinforcing bars at concrete foundation.
Appl. Sci. 2016, 6, 317 3 of 11
Appl. Sci. 2016, 6, 317 3 of 11
Continuing the research in [3], the structural performance of the steel pile cap strengthened with
the proposed
Continuing perfobond
the researchconnectors
in [3], theunder lateral
structural loading were
performance of theexperimentally investigated.
steel pile cap strengthened A
with
bending
the proposedtest perfobond
was conducted on seven
connectors under specimens
lateral loadingby were
considering the type
experimentally of perfobond
investigated. shear
A bending
connectors, infilled concrete depth, and the number of L‐shaped steel plates as test parameters. The
test was conducted on seven specimens by considering the type of perfobond shear connectors, infilled
failure characteristics of the test specimens were examined, and their load‐displacement curves were
concrete depth, and the number of L-shaped steel plates as test parameters. The failure characteristics
analyzed. We also investigated the effects of the test variables on the bending resistance capacity of
of the test specimens were examined, and their load-displacement curves were analyzed. We also
the test specimens
investigated in of
the effects order to demonstrate
the test variables on the the bending
effectiveness of the
resistance proposed
capacity of theperfobond shear
test specimens in
connector. From the results
order to demonstrate of this study,
the effectiveness it can
of the be confirmed
proposed perfobondthat the proposed
shear connector.perfobond shear
From the results
connector can be utilized as an alternative to the conventional steel pile cap strengthening method
of this study, it can be confirmed that the proposed perfobond shear connector can be utilized as an
using steel rebars.
alternative to the conventional steel pile cap strengthening method using steel rebars.
2. Experimental Program
2. Experimental Program
406
200
406
LVDT 1 LVDT 3
LVDT 1
Infilled concrete depth
900
500
LVDT 3
900
700
LVDT 2
Infilled concrete
LVDT 5 LVDT 4
depth
LVDT 2
400
A-4 A-1
LVDT 5 LVDT 4
A-4 A-1
1400 1400
(a) (b)
Figure 3. Details of test specimens. (a) Specimen strengthened with conventional steel rebars. (b)
Figure 3. Details of test specimens. (a) Specimen strengthened with conventional steel rebars; (b) Specimen
Specimen strengthened with perfobond shear connectors. (unit: mm).
strengthened with perfobond shear connectors (unit: mm).
Appl. Sci. 2016, 6, 317 4 of 11
Appl. Sci. 2016, 6, 317 4 of 11
The details of the seven test specimens are summarized in Table 1. In all of the specimens,
The details of the seven test specimens are summarized in Table 1. In all of the specimens, the
the diameter of the steel pile (D) is 400 mm. The main test parameters include the type of perfobond
diameter of the steel pile (D) is 400 mm. The main test parameters include the type of perfobond shear
shear connectors, infilled concrete depths, and the number of L-shaped steel plates. Two types of
connectors, infilled concrete depths, and the number of L‐shaped steel plates. Two types of perfobond
perfobond shear connectors were used in the test specimens. The first type (PO) has open holes,
shear connectors were used in the test specimens. The first type (PO) has open holes, while the other
while the other (PC) closed holes, shown in Figure 4. They all have sectional dimensions of 100 mm by
(PC) closed holes, shown in Figure 4. They all have sectional dimensions of 100 mm by 8 mm and a
8 mm and a length of 620 mm. The reference specimen strengthened with conventional steel rebars
length of 620 mm. The reference specimen strengthened with conventional steel rebars (SB) had the
(SB) had the infilled concrete depth of 700 mm, which is greater than the diameter of the steel pile
infilled concrete depth of 700 mm, which is greater than the diameter of the steel pile and satisfies the
and satisfies the requirement of the development length for the rebars suggested in [10]. In contrast,
requirement of the development length for the rebars suggested in [10]. In contrast, the specimens
the specimens strengthened with the perfobond shear connectors had two different infilled concrete
strengthened
depths with the toperfobond
corresponding the diameter shear connectors
(D10) had two (D05)
and half diameter different infilled
of the concrete
steel pile, depths
respectively.
corresponding
Three to the diameter
different numbers (D10)
of L-shaped and
steel half diameter
plates, which are(D05) of 3the
0 (NL), steel
(L3), andpile, respectively.
6 (L6), Three
were installed in
different numbers of L‐shaped steel plates, which are 0 (NL), 3 (L3), and 6 (L6), were installed in the
the specimens strengthened with the perfobond connectors. The effects of the test parameters on the
specimens
bending strengthened
resistance with
capacity the strengthened
of the perfobond connectors. The
steel pile cap effects
are of the
discussed intest parameters
Section on the
3 in detail.
bending resistance capacity of the strengthened steel pile cap are discussed in Section 3 in detail.
Table 1. Details of test specimens.
Table 1. Details of test specimens.
Infilled Concrete Number of L-Shaped
Specimen
Specimen Name Type of Strengthening Infilled Concrete
Depth (mm)
Number of L‐Shaped
Steel Plates (EA)
Type of Strengthening
Name Depth (mm) Steel Plates (EA)
SB_D10_NL Vertical rebars 700 (≥1.0D) -
SB_D10_NL Vertical rebars 700 (≥1.0D) ‐
PC_D05_NL 0
PC_D05_NL 200 (=0.5D) 0
PC_D05_L3 Perfobond shear connectors 200 (=0.5D)
PC_D05_L3 Perfobond shear connectors
3 3
PC_D10_L3
PC_D10_L3 with closed holes
with closed holes
400 (=1.0D)
400 (=1.0D)
PC_D10_L6
PC_D10_L6 6 6
PO_D05_L3
PO_D05_L3 Perfobond shear connectors
Perfobond shear connectors 200 (=0.5D)
200 (=0.5D) 3 3
PO_D10_L3
PO_D10_L3 with open holes
with open holes 400 (=1.0D)
400 (=1.0D) 3 3
(a) (b)
Figure 4. Types of perfobond shear connectors. (a) Perfobond shear connector with closed holes. (b)
Figure 4. Types of perfobond shear connectors. (a) Perfobond shear connector with closed holes;
Perfobond shear connectors with open holes. (unit: mm).
(b) Perfobond shear connectors with open holes (unit: mm).
The compressive strength of concrete was measured in accordance with the standards of ASTM
The compressive strength of concrete was measured in accordance with the standards of ASTM
C39 [11], and the measured average strength was found to be 31.9 (MPa). Five different sizes of rebars
C39 [11], and the measured average strength was found to be 31.9 (MPa). Five different sizes of rebars
such as H10, H13, H16, H19, and H22 were used in the test specimens. The steel types used for steel
such as H10, H13, H16, H19, and H22 were used in the test specimens. The steel types used for steel
piles and steel plates are SPS490 and SS400, respectively. Their yield strength, ultimate strength, and
piles and steel plates are SPS490 and SS400, respectively. Their yield strength, ultimate strength,
maximum strain at fracture were measured per ASTM A370 [12]. The summary of the measured
and maximum strain at fracture were measured per ASTM A370 [12]. The summary of the measured
properties is provided in Table 2.
properties is provided in Table 2.
Table 2. Material properties of test specimens. (unit: MPa (strength), % (strain)).
Table 2. Material properties of test specimens (unit: MPa (strength), % (strain)).
Rebars Steel Pile Steel Plate
Title Concrete Rebars Steel Pile Steel Plate
H10 H13 H16 H19 H22 SPS400 SS400
Properties Concrete
compressive strength 31.9 H10 ‐ H13 ‐ ‐
H16 ‐
H19 ‐
H22 ‐
SPS400 ‐
SS400
yield strength
compressive strength 31.9‐ 607.5
- 524.4
- 490.1
- 475.7
- 579.6
- 242.1
- 321.4
-
ultimate strength
yield strength - ‐ 707.1
607.5 650.9
524.4 584.9 581.8
490.1 475.7 569.2
579.6 418.8
242.1 441.5
321.4
ultimate strength
maximum strain at fracture - ‐ 707.1
17.2 650.9
18.1 584.9
18.1 581.8 569.2
18.3 17.3 418.8
‐ 441.5
33.7
maximum strain at fracture - 17.2 18.1 18.1 18.3 17.3 - 33.7
2.2. Testing Equipment and Procedure
Appl. Sci. 2016, 6, 317 5 of 11
Appl. Sci. 2016, 6, 317 5 of 11
Figure 5. Test setup.
Figure 5. Test setup.
3. Test Results and Discussion
3. Test Results and Discussion
Cracking Load (kN)
Cracking Load (kN) Peak Load
Peak Load Displacement
Specimen Displacement
at Peak Load
Stage 1 Stage 2 Stage 3 Stage 4
Lateral Load Bending
Bending Moment
Specimen Lateral
(kN) (kN · m) at Peak Load
(mm)
Stage 1 Stage 2 Stage 3 Stage 4 Moment
SB_D10_NL 99 99 192 277
Load (kN)
342 308
(mm)
50.0
(kN∙m)
PC_D05_NL 82 108 164 239 279 251 32.2
SB_D10_NL
PC_D05_L3 58
99 79
99 150
192 227
277 262
342 308
236
50.0
33.2
PC_D05_NL 82 108 164 239 279 251 32.2
PC_D05_L3 58 79 150 227 262 236 33.2
PC_D10_L3 72 86 193 265 286 257 68.6
Appl. Sci. 2016, 6, 317 6 of 11
Table 3. Cont.
(a)
(a) (b)
(b)
Figure 6. Typical cracking patterns of test specimens. (a) Top surface of the concrete block. (b) Side
Figure 6. Typical cracking patterns of test specimens. (a) Top surface of the concrete block. (b) Side
Figure 6. Typical cracking patterns of test specimens. (a) Top surface of the concrete block; (b) Side
surface of the concrete block.
surface of the concrete block.
surface of the concrete block.
Figure 7 shows the cracking pattern of the reference specimen SB_D10_NL on its top and vertical
Figure 7 shows the cracking pattern of the reference specimen SB_D10_NL on its top and vertical
faces. Cracks started to develop on the top and side surfaces of the concrete block in the direction
Figure 7 shows the cracking pattern of the reference specimen SB_D10_NL on its top and vertical
faces. Cracks started to develop on the top and side surfaces of the concrete block in the direction
perpendicular to the applied load at the load
faces. Cracks started
perpendicular toapplied
to the develop on the
load at the andlevel
topload side (P)
level
of 99 kN. the
surfaces
(P) of 99 of
As concrete
kN. As
the load block
further inincreased,
the load further the direction
increased,
additional cracks were propagated on the top surface in the direction parallel to the applied load at
perpendicular to the applied load at the load level (P) of 99 kN. As the load further increased,
additional cracks were propagated on the top surface in the direction parallel to the applied load at additional
P = 192 kN. Finally, concrete crushing occurred in the compression zone of the top surface at P = 277
cracks were propagated on the top surface in the direction parallel to the applied load at P = 192 kN.
P = 192 kN. Finally, concrete crushing occurred in the compression zone of the top surface at P = 277
kN, and the developed cracks were further propagated until the test specimen reached its complete
Finally, concrete crushing occurred in the compression zone of the top surface at P = 277 kN, and the
kN, and the developed cracks were further propagated until the test specimen reached its complete
failure stage.
developed cracks were further propagated until the test specimen reached its complete failure stage.
failure stage.
Figure 7. Failure mode of Specimen SB_D10_NL.
Figure 7. Failure mode of Specimen SB_D10_NL.
7. Failure mode of Specimen SB_D10_NL.
Figure 8 shows the cracking pattern of Specimen PO_D10_L6 on its top and side faces. This type
Figure
of crack patterns was observed in all of the test specimens, where the proposed perfobond shear
Figure 8 shows the cracking pattern of Specimen PO_D10_L6 on its top and side faces. This type
connectors were installed, although their peak load values were slightly different from each other.
Figure 8 showswas
the cracking
observed pattern ofthe
Specimen PO_D10_L6
test specimens, onthe
where its top and side
proposed faces. This
of On the top surface of the concrete block, cracks started to develop in the direction perpendicular to
crack patterns in all of perfobond type
shear
of connectors were installed, although their peak load values were slightly different from each other.
crack patterns was observed in all of the test specimens, where the proposed perfobond shear
the applied load at P = 69 kN and then were propagated into the side surface of the concrete cube at
connectors were installed, although their peak load values were slightly different from each other.
On the top surface of the concrete block, cracks started to develop in the direction perpendicular to
P = 78 kN. Top surface cracks were developed in the parallel direction to the applied load at P = 187
Onthe applied load at P = 69 kN and then were propagated into the side surface of the concrete cube at
the top surface of the concrete block, cracks started to develop in the direction perpendicular
kN. Concrete crushing happened on top of the concrete cube at P = 235 kN. The test was over at P =
the applied load at P = 69 kN and then were propagated into the side surface of the concrete
to P = 78 kN. Top surface cracks were developed in the parallel direction to the applied load at P = 187
303 kN, when half‐circle shaped cracks were intensively formed on the tension side of the top surface
cube at P = 78 kN. Top surface cracks were developed in the parallel direction to the applied load at
kN. Concrete crushing happened on top of the concrete cube at P = 235 kN. The test was over at P =
as shown in the figure.
P =303 kN, when half‐circle shaped cracks were intensively formed on the tension side of the top surface
187 kN. Concrete crushing happened on top of the concrete cube at P = 235 kN. The test was over
as shown in the figure.
Appl. Sci. 2016, 6, 317 7 of 11
at P = 303 kN, when half-circle shaped cracks were intensively formed on the tension side of the top
surface as shown in the figure.
Appl. Sci. 2016, 6, 317 7 of 11
Appl. Sci. 2016, 6, 317 7 of 11
Figure 8. Failure mode of Specimen PO_D10_L6.
Figure 8. Failure mode of Specimen PO_D10_L6.
Figure 8. Failure mode of Specimen PO_D10_L6.
3.2. Effects of Test Parameters on the Bending Resistance Capacity of the Strengthened Steel Pile Cap
3.2. Effects of Test Parameters on the Bending Resistance Capacity of the Strengthened Steel Pile Cap
3.2. Effects of Test Parameters on the Bending Resistance Capacity of the Strengthened Steel Pile Cap
This section discusses the effects of test parameters such as the type of perfobond shear
This section
This section discusses
discusses the the effects
effects of
of test
test parameters such as
parameters such as the
the type
type of
of perfobond
perfobond shear
shear
connectors, infilled concrete depths, and the number of L‐shaped steel plates on the bending
connectors, infilled
connectors, infilled concrete
concrete depths, andand
depths, the number of L-shaped
the number steel plates
of L‐shaped steel onplates
the bending
on the resistance
bending
resistance capacity of the steel pile cap strengthened with the proposed perfobond connectors.
capacity ofcapacity
resistance the steelof pile
the cap strengthened
steel with the proposed
pile cap strengthened perfobond
with the proposed connectors.
perfobond Figure 9a,b
connectors.
Figures 9a,b show the load‐displacement curves of the D05_L3 and D10_L3 specimens to investigate
show the load-displacement curves of the D05_L3 and D10_L3 specimens to investigate the effect
Figures 9a,b show the load‐displacement curves of the D05_L3 and D10_L3 specimens to investigate
the effect of perfobond shear connector types on their peak strengths, respectively. Here, D05_L3
of perfobond
the shear connector
effect of perfobond types on their
shear connector types peak strengths,
on their peak respectively. Here, D05_L3
strengths, respectively. specimens
Here, D05_L3
specimens refer to the specimens with concrete infilled depth equal to the half of steel cap diameter
refer to the specimens with concrete infilled depth equal to the half of steel cap diameter (D05) and
specimens refer to the specimens with concrete infilled depth equal to the half of steel cap diameter
(D05) and three L‐shaped plates (L3). Hereafter, this notation is used throughout the section for
three L-shaped
(D05) and three plates (L3). plates
L‐shaped Hereafter,
(L3). this notationthis
Hereafter, is used throughout
notation is used the section for
throughout convenience.
the section for
convenience. The load‐displacement curve of the reference specimen SB_D10_NL is also plotted in
The load-displacement curve of the reference specimen SB_D10_NL is also plotted in the two figures
convenience. The load‐displacement curve of the reference specimen SB_D10_NL is also plotted in
the two figures for comparison. The peak strengths and peak strength ratios of D05_L3 and D10_L3
for comparison. The peak strengths and peak strength ratios of D05_L3 and D10_L3 specimens are
the two figures for comparison. The peak strengths and peak strength ratios of D05_L3 and D10_L3
specimens are listed in Tables 4 and 5, respectively.
listed in Tables 4 and 5, respectively.
specimens are listed in Tables 4 and 5, respectively.
(a) (b)
(a) (b)
Figure 9. Effect of steel pile cap strengthening methods. (a) D05_L3 specimens. (b) D10_L3 specimens.
Figure 9. Effect of steel pile cap strengthening methods. (a) D05_L3 specimens. (b) D10_L3 specimens.
Figure 9. Effect of steel pile cap strengthening methods. (a) D05_L3 specimens; (b) D10_L3 specimens.
Table 4. Effect of steel pile cap strengthening methods for D05_L3 specimens.
Table 4. Effect of steel pile cap strengthening methods for D05_L3 specimens.
Table 4. Effect of steel pile cap strengthening methods for D05_L3 specimens.
Peak Strength Ratio of Peak Strengths (%)
Specimen Peak Strength Ratio of Peak Strengths (%)
Specimen (kN) Divided by (•) Divided by (#1)
Ratio of Peak Strengths (%)
Specimen (kN) (kN)
Peak Strength Divided by (•) Divided by (#1)
SB_D10_NL (•) 342 100.0
by (•)
Divided100.0 ‐
Divided by (#1)
SB_D10_NL (•) 342 ‐
PC_D05_L3 (#1) 262 76.6 100.0
PC_D05_L3 (#1)
SB_D10_NL (•) 342262 100.076.6 - 100.0
PO_D05_L3 (#2)
PC_D05_L3 (#1) 319
262319 93.3
76.693.3 121.8
100.0 121.8
PO_D05_L3 (#2)
PO_D05_L3 (#2) 319 93.3 121.8
Table 5. Effect of steel pile cap strengthening methods for D10_L3 specimens.
Table 5. Effect of steel pile cap strengthening methods for D10_L3 specimens.
Peak Strength Ratio of Peak Strengths (%)
Specimen Peak Strength Ratio of Peak Strengths (%)
Specimen (kN) Divided by (•) Divided by (#1)
(kN) Divided by (•) Divided by (#1)
SB_D10_NL (•) 342 100.0 ‐
SB_D10_NL (•) 342 100.0 ‐
PC_D10_L3 (#1) 286 83.6 100.0
PC_D10_L3 (#1) 286 83.6 100.0
PO_D10_L3 (#2) 326 95.3 114.0
PO_D10_L3 (#2) 326 95.3 114.0
Appl. Sci. 2016, 6, 317 8 of 11
Table 5. Effect of steel pile cap strengthening methods for D10_L3 specimens.
From
From these
these results,
results, it
it can be seen
can be seen that
that the
the specimens
specimens strengthened
strengthened with
with the
the open-hole
open‐hole type
type
perfobond connectors have higher bending resistance than those with the closed‐hole
perfobond connectors have higher bending resistance than those with the closed-hole type connectors, type
connectors, and almost equal strength to that of the reference specimen. For example, the ratios of the
and almost equal strength to that of the reference specimen. For example, the ratios of the peak
peak strength of the open‐hole type perfobond specimens PO_D05_L3 and PO_D10_L3 to that of the
strength of the open-hole type perfobond specimens PO_D05_L3 and PO_D10_L3 to that of the
reference specimen are
reference specimen are 93.3%
93.3% andand 95.3%,
95.3%, respectively.
respectively. This
This is is remarkable
remarkable considering
considering that the that the
concrete
concrete infilled depths of these specimens are only in the range of 200 mm and 400 mm, while that
infilled depths of these specimens are only in the range of 200 mm and 400 mm, while that of the
of the reference specimen is 700 mm as indicated in Table 1. Furthermore, as can be seen from Figure
reference specimen is 700 mm as indicated in Table 1. Furthermore, as can be seen from Figure 9,
9, their initial stiffness is almost equal to that of the reference specimen, and they retain the level of
their initial stiffness is almost equal to that of the reference specimen, and they retain the level of
ductility comparable to that of the reference specimen. In addition, Tables 4 and 5 show that their
ductility comparable to that of the reference specimen. In addition, Tables 4 and 5 show that their
peak strengths are approximately 15% to 20% greater than those of the closed‐hole type perfobond
peak strengths are approximately 15% to 20% greater than those of the closed-hole type perfobond
specimens. This seems
specimens. This seems toto happen
happen since
since the open‐hole
the open-hole type perfobond
type perfobond connectors
connectors have a cross‐
have a cross-sectional
sectional area larger than the open‐hole type connectors as illustrated in Figure 3.
area larger than the open-hole type connectors as illustrated in Figure 3.
In order to examine the effect of concrete infilled depths on the bending resistance capacity of
In order to examine the effect of concrete infilled depths on the bending resistance capacity of the
the specimens, the load‐displacement curves of PC_L3 and PO_L3 specimens are plotted in Figures
specimens, the load-displacement curves of PC_L3 and PO_L3 specimens are plotted in Figure 10a,b,
10a,b, respectively.
respectively. The load‐displacement
The load-displacement curvecurve
of theof the reference specimen is also included in
reference specimen is also included in the plot. the
plot. Tables 6 and 7 provide the peak strengths and peak strength ratios of these specimens.
Tables 6 and 7 provide the peak strengths and peak strength ratios of these specimens.
(a) (b)
Figure 10. Effect of infilled concrete depths. (a) PC_L3 specimens. (b) PO_L3 specimens.
Figure 10. Effect of infilled concrete depths. (a) PC_L3 specimens; (b) PO_L3 specimens.
Table 6. Effect of infilled concrete depths for PC_L3 specimens.
Table 6. Effect of infilled concrete depths for PC_L3 specimens.
Peak Strength Ratio of Peak Strengths (%)
Specimen Ratio of Peak Strengths (%)
Specimen
(kN)
Peak Strength (kN)
Divided by (•) Divided by (#1)
SB_D10_NL (•) 342 by (•)
Divided100.0 Divided by (#1)
‐
PC_D05_L3 (#1)
SB_D10_NL (•) 342262 100.076.6 - 100.0
PC_D05_L3 (#1)
PC_D10_L3 (#2) 262286 76.683.6 100.0 109.2
PC_D10_L3 (#2) 286 83.6 109.2
Table 7. Effect of infilled concrete depths for PO_L3 specimens.
Peak Strength Ratio of Peak Strengths (%)
Specimen
(kN) Divided by (•) Divided by (#1)
SB_D10_NL (•) 342 100.0 ‐
PO_D05_L3 (#1) 319 93.3 100.0
PO_D10_L3 (#2) 326 95.3 102.2
Appl. Sci. 2016, 6, 317 9 of 11
It can be noted from these results that the peak strength of the specimen is increased with
increasing concrete infilled depth. For example, in the case of PC_D10_L3 specimen, its peak strength
is increased by 9.2% due to the increase of concrete infilled depth from 200 to 400 mm, while that of
PO_D10_L3 specimen only by 2.2%. Therefore, the increase of peak strength due to increasing concrete
infilled depth is more pronounced with closed-hole type perfobond specimens. As already9 of 11
Appl. Sci. 2016, 6, 317 observed
previously, the open-hole type perfobond specimens have an approximately 10%–20% higher peak
observed
strength than previously,
those with the open‐hole
closed-hole type
type perfobond connectors,
perfobond specimens have
and an approximately
almost 10%–20%
the same initial stiffness
higher peak strength than those with closed‐hole type perfobond connectors, and almost the same
as the reference specimen.
initial stiffness as the reference specimen.
Figure 11a,b show the load-displacement curves of PC_D05 and PC_D10 specimens, respectively,
Figures 11a,b show the load‐displacement curves of PC_D05 and PC_D10 specimens,
and the effects of the number of L-shaped plates on the bending resistance capacity of the specimens
respectively, and the effects of the number of L‐shaped plates on the bending resistance capacity of
are investigated. The load-displacement of the reference specimen is also included in both figures.
the specimens are investigated. The load‐displacement of the reference specimen is also included in
Tables 8 and 9 list the peak strengths and peak strength ratios of these specimens.
both figures. Tables 8 and 9 list the peak strengths and peak strength ratios of these specimens.
(a) (b)
Figure 11. Effect of the number of L‐shaped plates. (a) PC_D05 specimens. (b) PC_D10 specimens.
Figure 11. Effect of the number of L-shaped plates. (a) PC_D05 specimens; (b) PC_D10 specimens.
Table 8. Effect of the number of L‐shaped plates for PC_D05 specimens.
Table 8. Effect of the number of L-shaped plates for PC_D05 specimens.
Peak Strength Ratio of Peak Strengths (%)
Specimen
(kN) Divided by (•) Divided by (#1)
Ratio of Peak Strengths (%)
Specimen
SB_D10_NL (•) Peak Strength
342 (kN) 100.0 ‐
Divided by (•) Divided by (#1)
PC_D05_NL (#1) 279 81.6 100.0
SB_D10_NL (•)
PC_D05_L3 (#2) 342262 100.0
76.6 -93.9
PC_D05_NL (#1) 279 81.6 100.0
PC_D05_L3 (#2) 262 76.6 93.9
Table 9. Effect of the number of L‐shaped plates for PC_D10 specimens.
Peak Strength
Table 9. Effect of the number of L-shaped platesRatio of Peak Strengths (%)
for PC_D10 specimens.
Specimen
(kN) Divided by (•) Divided by (#1)
SB_D10_NL (•) 342 100.0 ‐
Ratio of Peak Strengths (%)
Specimen
PC_D10_L3 (#1) Peak Strength
286 (kN) 83.6 100.0
Divided by (•) Divided by (#1)
PC_D10_L6 (#2) 303 88.6 105.9
SB_D10_NL (•) 342 100.0 -
It can PC_D10_L3 (#1) Figure 11a and
be seen from 286 Table 8 that the 83.6 100.0
specimen with three L‐shaped plates
PC_D10_L6 (#2) 303 88.6 105.9
(PC_D05_L3) has a slightly smaller peak strength than the one with no L‐shaped plates
(PC_D05_NL). In contrast, Figure 11b and Table 9 indicate that the specimen with six L‐shaped plates
(PC_D10_L6) has a slightly higher peak strength than the one with three L‐shaped plates
(PC_D10_L3). As a consequence, it can be concluded that the number of L‐shaped plates does not
have a high impact on the bending resistance capacity of the specimen, and it may be impossible to
install any of the L‐shaped plates with the proposed perfobond shear connectors. Nonetheless, if L‐
shaped plates are installed, it is suggested that a number of the L‐shaped plates should be
Appl. Sci. 2016, 6, 317 10 of 11
It can be seen from Figure 11a and Table 8 that the specimen with three L-shaped plates
(PC_D05_L3) has a slightly smaller peak strength than the one with no L-shaped plates (PC_D05_NL).
In contrast, Figure 11b and Table 9 indicate that the specimen with six L-shaped plates (PC_D10_L6) has
a slightly higher peak strength than the one with three L-shaped plates (PC_D10_L3). As a consequence,
it can be concluded that the number of L-shaped plates does not have a high impact on the bending
resistance capacity of the specimen, and it may be impossible to install any of the L-shaped plates with
the proposed perfobond shear connectors. Nonetheless, if L-shaped plates are installed, it is suggested
that a number of the L-shaped plates should be symmetrically distributed with respect to the direction
of lateral load.
4. Conclusions
In this study, an experimental investigation was performed on the structural performance of the
steel pile cap strengthened with the proposed perfobond connectors under lateral loading. A bending
test was conducted on seven specimens by considering the type of perfobond shear connectors,
infilled concrete depth, and the number of L-shaped steel plates as test parameters. The failure
characteristics of the test specimens were examined, and their load-displacement curves were analyzed.
The main conclusions of this paper are as follows:
(1) All of the test specimens basically showed very similar crack propagation patterns. Cracking
first occurred on top of the concrete block in the direction perpendicular to the lateral load and
then propagated into its side surfaces. As the load further increased, cracks in the direction
parallel to the lateral load appeared on top of the concrete block, and concrete crushing occurred
on its compression side.
(2) In all of the test specimens, where the proposed perfobond shear connectors were installed,
the crack pattern of a half circle shape was observed on top of the concrete block. In contrast,
this phenomenon was not observed in the reference specimen, where the steel pile was
strengthened with conventional steel rebars.
(3) The specimens strengthened with the open-hole type perfobond connectors have almost the same
bending resistance capacity as the reference specimen although the concrete infilled depths
of the former are only in the range of approximately 29%–57% of the latter. Furthermore,
their initial stiffness is almost equal to that of the reference specimen, and they also retain
a level of ductility comparable to that of the reference specimen. The advantage of the proposed
perfobond connectors mainly lies in its enhanced constructability although they did not show
a significantly greater improvement in structural performance than the conventional rebar
strengthening method.
(4) The open-hole type perfobond specimens have approximately 10%–20% higher bending
resistance capacity than those with closed-hole type perfobond connectors. The increase of
peak strength due to increasing concrete infilled depth is more pronounced with closed-hole type
perfobond specimens.
(5) The number of L-shaped plates does not have a high impact on the bending resistance capacity of
the specimen; thus, it may be impossible to install any of the L-shaped plates with the proposed
perfobond shear connectors.
Acknowledgments: The corresponding author of this paper acknowledges support from the Basic Science
Research Program through the National Research Foundation of Korea (NRF) funded by the Ministry of Science,
ICT & Future Planning (Grant number: 2013R1A1A1076011).
Author Contributions: In this paper, Young-Ho Kim proposed the main concept of the new perfobond shear
connector and prepared the experimental program to investigate its structural performance when subjected to
lateral loading; Jae-Yoon Kang made a contribution to the implementation of the experimental program and
discussed the test results; Sang-Ho Kim provided a suggestion on the overall organization of the paper and
prepared the tables and figures included in the paper; Dae-Jin Kim provided the interpretation of the test results
and wrote the entire manuscript.
Appl. Sci. 2016, 6, 317 11 of 11
References
1. Joen, P.H.; Park, R. Simulated seismic load tests on prestressed concrete piles and pile-pile cap connections.
PCI J. 1990, 35, 42–61. [CrossRef]
2. Shama, A.A.; Mander, J.B.; Aref, A.J. Seismic Performance and Retrofit of Steel Pile to Concrete Cap
Connections. ACI Struct. J. 2002, 99, 51–61.
3. Kim, Y.-H.; Kim, J.-Y.; Koo, H.-B.; Kim, D.-J. Pull-out resistance capacity of a new perfobond shear connector
for steel pile cap strengthening. Adv. Mater. Sci. Eng. 2016, in press. [CrossRef]
4. Zellner, W. Recent designs of composite bridges and a new type of shear connectors. In Proceedings of
the IABSE/ASCE Engineering Foundation Conference on Composite Construction, Henniker, NH, USA,
7–12 June 1987; pp. 240–252.
5. Oguejiofor, E.C.; Hosain, M.U. A parametric study of perfobond rib shear connectors. Can. J. Civ. Eng. 1994,
21, 614–625. [CrossRef]
6. Valente, I.; Cruz, P.J.S. Experimental analysis of Perfobond shear connection between steel and lightweight
concrete. J. Constr. Steel Res. 2004, 60, 465–479. [CrossRef]
7. Kim, H.-Y.; Jeong, Y.-J. Experimental investigation on behaviour of steel–concrete composite bridge decks
with perfobond ribs. J. Constr. Steel Res. 2006, 62, 463–471. [CrossRef]
8. Viannaa, J.D.C.; Costa-Nevesb, L.F.; Vellascoc, P.C.G.D.S.; de Andradea, S.A.L. Structural behaviour of
T-Perfobond shear connectors in composite girders: An experimental approach. Eng. Struct. 2008, 30,
2381–2391. [CrossRef]
9. Kim, S.-H.; Choi, K.-T.; Park, S.-J.; Park, S.-M.; Jung, C.-Y. Experimental shear resistance evaluation of Y-type
perfobond rib shear connector. J. Constr. Steel Res. 2013, 82, 1–18. [CrossRef]
10. Korea Rail Network Authority. Design Code of Railway Bridges; Ministry of Land, Infrastructure and Transport
of Korea: Sejong, Korea, 2013.
11. American Society for Testing and Materials International. Standard Test Method for Compressive Strength of
Cylindrical Concrete Specimens; ASTM Standard C39/C39M-11; ASTM International: West Conshohocken, PA,
USA, 2011.
12. American Society for Testing and Materials International. Standard Test Methods and Definitions for Mechanical
Testing of Steel Products; ASTM Standard A370-12a; ASTM International: West Conshohocken, PA, USA, 2012.
© 2016 by the authors; licensee MDPI, Basel, Switzerland. This article is an open access
article distributed under the terms and conditions of the Creative Commons Attribution
(CC-BY) license (http://creativecommons.org/licenses/by/4.0/).