GAJIAN PROJECT BOARDING SCHOLL

9 Jul S/d 15 Jul 2023


NO NAMA HADIR UPAH HARIAN JUMLAH KAS BON TOTAL
1 Yusan (T) 7 Rp120.000 Rp840.000 Rp0 Rp840.000
2 Ujang (T) 7 Rp120.000 Rp840.000 Rp0 Rp840.000
3 Tono (T) 7 Rp120.000 Rp840.000 Rp0 Rp840.000
4 Iwang (T) 0 Rp120.000 Rp0 Rp0 Rp0
5 Ade (ST) 7 Rp110.000 Rp770.000 Rp0 Rp770.000
6 Wahyu (L) 7 Rp100.000 Rp700.000 Rp0 Rp700.000
7 Albar (L) 5 Rp100.000 Rp500.000 Rp0 Rp500.000
8 Yasril (L) 5 Rp100.000 Rp500.000 Rp0 Rp500.000
9 Nandang (L) 7 Rp100.000 Rp700.000 Rp0 Rp700.000
11 Yusuf (L) 5 Rp100.000 Rp500.000 Rp0 Rp500.000
12 A Anwar (P) 7 Rp125.000 Rp875.000 Rp0 Rp875.000

JUMLAH GAJIAN Rp7.065.000