Sub-Contractor Contactor EETC

EL BADARY
66/11 KV S/S

AVR 1

TAPCON®230 expert

Voltage regulator

Test Report

Global Giza systems EETC


Sub-Contractor Contactor EETC
EL BADARY
66/11 KV S/S

1 Introduction:
This document verifies that the device measuring and control function works properly.

2 TESTING EQUIPMENT:
Secondary injection relay test system and power system simulator is designed to satisfy all the
needs related to commissioning and maintaining substations and to testing protection devices.

Model: CMC356
S/N: QC139Z

3 GENERAL DATA & INFORMATION

Panel No. AVR Trans. Ratio 220/66 kV


Relay Type TAPCON®230 expert CT Ratio 2000/1
Manufacturer MR In 1A
Serial No. 20962 VT Ratio 66/0.1kV
Order No. VarPlus Logic VL12 Vn 100
DC supply: 220V DC Frequency Fn 50 Hz

4 MECHANICAL CHECKS AND VISUAL INSPECTION

item Description Remarks


1. Inspect for any physical damage or defects. OK
2. Verify connections and ferrules as per approved drawings OK

3. Check tightness of all the connections. OK

Global Giza systems EETC


Sub-Contractor Contactor EETC
EL BADARY
66/11 KV S/S

5 ELECTRICAL TESTS
5.1 User I/Os:
Output Relay No. Label Checked Remarks
GPI 1 - X4:13 S. mode OK
GPI 2 - X4:14 Master OK
GPI 3 - X4:15 Follower OK
GPI 4 - X4:16 Off OK
GPI 5 - X4:17 Off OK
GPI 6 - X4:18 Off OK
GPI 7 - X6:1 Off OK
GPI 8 - X6:2 Off OK
GPO 1 - X4:9 Off OK
GPO 2 - X4:12 Off OK
GPO 3 - X5:9 Off OK
GPO 4 - X5:12 Off OK
GPO 5 - X5:18 Off OK
GPO 6 - X5:21 Off OK
GPO 7 - X5:24 Off OK

5.2 LED Selection:


Output Relay No. Label Checked Remarks
LED 1 I< OK
LED 2 Off OK
LED 3 Off OK
LED 4 Off OK

5.3 MEASURMENTS CHECK:

Applied current
Ratio Expected value Measured Value
A
1 A 2000/1 2000 2002 A
100 V 66/0.1 66 66 kV

Global Giza systems EETC


Sub-Contractor Contactor EETC
EL BADARY
66/11 KV S/S

5.4 RVT operation test:


Bandwidth is the switching threshold for switching on or switching off the OLTC Steps in
percent (%). The value of the Bandwidth is 5%.
which is the value used in the explanation below.
A step will be switched on/off if:
• The Voltage is higher than the target by 5% the AVR will take a step down to lower the voltage.
• The Voltage is lower than the target by 5% the AVR will take a step up to raise the voltage.

5.5 Timing

Time setting Checked


T1 5s OK
T2 10 s OK

5.6 Limit Values

element setting Checked


Blocking Overcurr. I> 63 % OK
Blocking Overvolt. U> 120 % OK
Blocking Undercurr. I< 0.01 % OK
Blocking Undervolt. U< 80 % OK
Delay Time U< 3s OK

5.7 Attachment RVT Setting

Global Giza systems EETC