Professional Documents
Culture Documents
1 s2.0 S0378779623001608 Main
1 s2.0 S0378779623001608 Main
A R T I C L E I N F O A B S T R A C T
Keywords: One of the important and basic parameters in electric energy production and transmission systems is maintaining
Initial events the stability and security of the power system. Transmission lines are vital elements in transferring power from
Cascading failure generation plants to load centers. Therefore, transmission line overload can be regarded as a main cause of
Failure modes and effects analysis (fmea)
consecutive outages and power system blackouts. In this paper, through a proposed cascading failure model
Risk priority number
Vulnerability
based on transmission line thermal limit, hazardous high-probability scenarios of N-K (1< K ≤ 3) contingencies
Risk level assessment are extracted and analyzed. The proposed fault evaluation method is then employed for risk assessment of
Operation mode cascading failures and identification of their initial events. The proposed approach for risk assessment of
cascading scenarios considers vulnerability criteria and operation constraints. The results of application to the
standard IEEE 39-bus test system verify the efficiency and accuracy of the proposed approach.
* Corresponding author.
E-mail address: Javad.Nikoukar@iau.ac.ir (J. Nikoukar).
https://doi.org/10.1016/j.epsr.2023.109271
Received 21 September 2022; Received in revised form 26 January 2023; Accepted 2 March 2023
Available online 14 March 2023
0378-7796/© 2023 Elsevier B.V. All rights reserved.
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
u Number of criteria
α Solar absorptivity (0.23 to 0.91)
wj Weight coefficients
Qsc Total solar and sky radiated heat intensity corrected for
akj Matrix element
elevation [ W/m2 ]
RPN Risk priority number
θ Effective angle of incidence of the sun’s rays [deg]
SEV Severity indicating the impact of the hazard or failure on
Hc Altitude of sun (0 to 90) [deg]
system performance
Zc Azimuth of sun [deg]
OCC probability of occurrence indicating the number of failures
Z1 Azimuth of line [deg]
DET is the detection probability for the given failure indicating
R(Thigh ) Conductor resistance at average high temperature [ohms/
how likely it is to detect the failure before its occurrence
m]
x The mathematical mean of the risk priority number
R(Tlow ) Conductor resistance at average low temperature [ohms/
δ The standard deviation of the risk priority number
m]
xi Value of the risk priority number
Thigh High average conductor temperature for which ac
N Number of cascading failure scenarios
resistance is specified [ ◦ C]
also been used to identify possible failure conditions in the design of the can also address failure modes such as system overloads conse
third windings for 400/230/34 kV power transformers [24] as well as quently leading to line outage.
failure modes and hazards identifications in distribution grids [25]. 5 FMEA technique has been applied to the test system in [26] in which
The proposed FMEA approach in this paper has the following ad failure modes including line overloads and abnormal voltage con
vantages over previous methods: ditions have been considered. Further to these criteria, the proposed
scheme of the current work also takes into account the network
1 The indices used in [12] suffer from computational complexity to operation condition (Alert, Emergency and Extremis states) to pro
identify the critical network lines. But, the proposed approach of the vide a more accurate analysis of the chain of cascade failures.
current paper has a simple and routine computation procedure.
2 In [6,7], the clustering method used suffers from significant limita It must be emphasized that the main goals of the introduced
tions such as scalability problems and sensitivity to initial parame approach in this paper are, as follows:
ters. This leads to long computation times as well as restrictions in
identification of initiating events. But, in the proposed approach of 1 Proposal of a cascade failure analysis method based on maximum
the current research the initiating events are identified with superior line flow aimed to reduce the search space of high-risk cascade
efficiency and accuracy. failure scenarios based on probable N-K (1<K ≤ 3) contingencies.
3 In the proposed method, the results are validated using enumeration 2 Presentation of a multi-objective function aimed to extract the most
technique. Moreover, another unique feature of the current research pertinent cascade failure scenarios.
is the detailed comparison of the proposed method in terms of pro 3 Risk-based evaluation and ranking of cascade failure scenarios in
ficiency and efficiency in initial event identification with other different power system operation modes using failure mode and ef
techniques proposed in the literature. fects analysis (FMEA) aimed to identify the most dangerous initiating
4 In [2] and [13–15], maximum flow methods as well as complex events which can potentially lead to cascade failures and blackouts.
theory-based on the network topology and graph theory have been 4 Validation of the efficiency and accuracy of the proposed method
proposed for identifying critical and vulnerable lines as the initiating against other previously-used methods for initiating event identifi
events. In this paper, however, the proposed method which is based cation as applied on the IEEE 39-bus system.
on risk evaluation, is not only capable of identifying these lines but
Since the main cause of most cascade failures is the overloading of
2
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
3
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
√̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅
qc + qr − qs In this paper, the conductor current exceeding its thermal limits is
I= ( ) (1) regarded as the threshold for relay action and the start of cascading
R Tavg
failures. In fact, relays take action, almost instantaneously, upon sensing
this current level removing the line from the live network.
where qc is the emitted heat by convection in W/m ,which depends on
several factors such as air pressure, conductor diameter, difference be
tween the ambient and conductor surface temperatures, and the wind
2.2. Vulnerability objective function
velocity. qc is defined as follows:
4
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
The failure modes and effect analysis (FMEA) is a risk assessment Upper − risk limit = δ + x (19)
technique which can be used to assess the risk of different cascading
Lower − risk limit = δ − x (20)
failure scenarios thus identifying the underlying initial events.
We have given five main reasons for using the proposed approach in where x , δ ,and xi are the mathematical mean, standard deviation and
value of the risk priority number for each scenario respectively, while N
Table 3 is the number of cascading failure scenarios.
Comparative matrix of criteria.
Criteria α β ζ 3. Theory/calculation
α 1 3 5
β 0.33 1 3 Fig. 1 shows the flowchart of the proposed cascading failure analysis
ζ 0.2 0.33 1 model and the relevant initial event identification method. This
5
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
Table 4
RI random index for random scores.
Number of criteria 1 2 3 4 5 6 7 8 9 10
Table 5 Table 9
Results of comparison of criteria by AHP method. Rating for detection (DET).
Criteria α β ζ Mean Operation Criteria Failure detection Rating
state
α 0.652 0.693 0.555 0.633
β 0.217 0.231 0.333 0.26 Extremis Uncontrolled Absolutely 10
ζ 0.13 0.077 0.111 0.106 impossible
Total 1 1 1 1 Emergency Unlikely to control Very remote 9
Alert A moderate chance of controlling Moderate 5
the next failure
Table 6
Evaluation indicators of risk priority number calculations [30]. 4 (steps 11 to 14), the risk assessment of the cascading failure scenarios
Index name Scoring based on the proposed FMEA method is carried out to identify the
Severity (SEV) 10 9 8 7 6 5 4 3 2 1
respective initial events. The initial events are ranked according to the
Max Low results from the risk priority number of the related scenarios. In the last
Occurrence probability (OCC) 10 9 8 7 6 5 4 3 2 1 step, the precision and accuracy of the proposed method are weighed
Max Low against those of other initial event identification methods.
Detection probability (DET) 10 9 8 7 6 5 4 3 2 1
Fig. 2 illustrates the blackout build-up steps caused by cascading
Low Max
failures [34]. As shown, the initial events are often the N-2 or N-3
contingencies which are mainly caused by weather or human factors.
Therefore, it is necessary for power utilities to take necessary measures
Table 7 to prevent these events even in their lowest probabilities.
Rating for severity (SEV).
Weighted Effect Rating Weighted Effect Rating 4. Simulation results
vulnerability vulnerability
objective objective
function function
The IEEE 39-bus test system is used to test and simulate the proposed
cascading failure and initial event identification approach. The sce
F>1 Hazardous 10 0.6<F ≤ 0.7 Moderate 6
narios leading to cascading failures are modeled in Digsilent software
without
warning [35]. Network planning tasks usually consider single-failure events such
0.9<F ≤ 1 Hazardous 9 0.5<F ≤ 0.6 Low 5 that the network is capable of maintaining secure powe supply. This is
with so-called N-1 security criteria. The tested network includes 34 lines, 12
warning
transformers, 10 generating units and 19 load buses. The total installed
0.8<F ≤ 0.9 Very High 8 0.4<F ≤ 0.5 Very low 4
0.7<F ≤ 0.8 High 7 0.3<F ≤ 0.4 Minor 3 capacity of generating units is 6138 MW and total load is 6097 MW.
Also, the losses are 41.23 MW.
6
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
Fig. 1. Flowchart of the proposed FMEA-based identification method for initial events of cascading failure.
in Table 10, for the 129 cascading failure scenarios. The scenarios are state, the system operators can prevent further faults through modifying
prioritized considering a resolution of 0.1 in vulnerability function the generation and transmission patterns. For these situations, suitable
values and also the three operating modes of the network. trainings are necessary to instruct operators for timely fault identifica
Based on Table 11 and Fig. 3, nearly 48 percent of the studied sce tions and fast proper actions to preserve the system stability and sus
narios put the network in critical or extremis operating conditions. In tained power supply. In cases when fast transition occurs between the
this case, the power system is very likely to experience voltage collapse alert and emergency states, no effective action can be taken by the
and consequently a major blackout. When the network enters the alert operators.
7
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
Table 10
Calculated parameters of Eqs. (1) and (7).
Primary data
Row Symbol SI units value Row Symbol SI units value
Table 11
Classification of cascading failure scenarios based on the weighted vulnerability function and the network operating state.
Weighted vulnerability objective function 0.3<F ≤ 0.4 0.4<F ≤ 0.5 0.5<F ≤ 0.6 0.6<F ≤ 0.7 0.7<F ≤ 0.8 0.8<F ≤ 0.9 0.9<F ≤ 1 F>1 sTotal
scenario
8
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
5. Discussion
Table 13
Risk rating for hazardous cascading failure scenarios.
Risk Weighted vulnerability objective function Contingency SEV OCC DET RPN Number of scenarios Total scenario
9
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
Table 14
Some cases of high-risk cascading failure steps.
RPN Scenario Occurrence of N-2 or N-3 The first initial The second event The third event The fourth event The fifth
number contingency event event
315 1 The outage of The outage of line The outage of line 13–14 Power flow
transformers 29–38 and 4–5 with 155% with 264% overload divergence
19–33 overload
315 2 The outage of transformer The outage of line The outage of line 8–9 The outage of line Unacceptable voltage drop Power flow
25–37 and line 13–14 4–5 with 132% with 179% overload 1–2 with 144% of bus 4 to 0.81 pu Δ divergence
overload overload V>10%
270 3 The outage of transformer The outage of line Power flow divergence
20–34 and lines 13–14 and 2–3 with 179%
4–5 overload
300 4 The outage of transformer The outage of line Unacceptable voltage drop Power flow
22–35 and lines 26–27 and 4–5 with 166% of bus 4 to 0.76 pu Δ divergence
2–3 overload V>10%
Table 15
Initial event identification and ranking based on the proposed approach.
Rank Line name Number of participations in scenarios Efficiency coefficient Rank Line name Number of participations in scenarios Efficiency coefficient
Table 16
Comparison of proposed method to other initial event identification techniques.
Item Method Initial event identification Total initial events Percentage of correct identifications validated by Calculation time
identified enumeration method (s)
ss1 Failure Modes and Effects Six initial events among top 10 8 47 3.53
Analysis (FMEA) identified events
2 Cascading Faults Graph (CFG) Three initial events among top 10 3 18 20.52
identified events
3 Parallel Corridor Search Five initial events among top 10 5 29 7.93
Method identified events
4 Cross Entropy-Based Method Four initial events among top 10 6 35 59.95
identified events
5 Multi-Criteria Index Evaluation Five initial events among top 10 5 29 5.94
Method identified events
6 Clustering Method One initial events among top 10 1 6 13.83
identified events
to 129 cases, the proposed method successfully identifies 47 percent of identify the initial events as it takes 3.53 s to extract the ranking list of
the total initial events in a maximum of 13 iterations. As a comparison, initial events. To calculate the provided times in Table 16, a computer
the entropy method only identifies 35 percent of initial events through with an Intel Core i7, 2.3 GHz, 8 GB RAM processor is used and the
15 iterations. Also, the proposed method is one of the fastest methods to programs are implemented in MATLAB software environment.
10
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
6. Conclusions and recommendations for future works schemes and proper network expansion measures and assess their
impact on the reduction of cascade failures through re-evaluation of the
In this paper, a new approach was introduced to identify critical and risk priority number.
highly-loaded lines whose failure can lead to cascading failures in power
systems. The approach is based on the thermal current limit modeling of Credit author statement
the lines and aims to reduce the search space of the initial events of
cascading failures for N-2 and N-3 contingencies as compared to (Mojtaba Fekri) developed the main idea and concept along with
enumeration method. The hazardous scenarios leading to cascading preliminary simulations. (Javad Nikoukar) further developed and
failures and emergency and extremis states in the network are obtained enhanced case studies and validation procedures while writing down the
through a vulnerability function which includes three indices, namely manuscript. (Gevork B. Gharehpetian) reviewed and verified the whole
line loading, transformer loading and bus voltage profiles. Then, based work and performed final paper organization.
on a proposed FMEA-based technique, a risk assessment is carried out on
the nominated cascading scenarios. This method is capable of qualita
Declaration of Competing Interest
tive assessment of the indices related to the events as well as statistical
calculation of risk priorities which can be used to identify and rank the
Herewith, I would like to declare that I, Mojtaba Fekri, the author of
initial events of cascading failures in offline mode and then be used to
this paper, am PhD student and the other coauthors are my supervisor
take preventive measures against them in realtime system operation.
and advisor, who are university professors, and their primary function is
Through vulnerability index evaluation and statistical risk analysis, the
research and education in the university. Also, we are not representative
presented approach is also capable of identifying the most hazardous
of government.
scenarios leading to emergency and extremis states. This method was
implemented on an IEEE 39-bus test system to identify the branches with
Data availability
highest failure risks.
The following statistics demonstrate the greater accuracy and speed
No data was used for the research described in the article.
of the proposed approach relative to other methods in identifying the
significant initiating events:
References
• The proposed approach determines 8 initiating events which is
[1] D.P. Nedic, I. Dobson, D.S. Kirschen, B.A. Carreras, V.E. Lynch, Criticality in a
higher number than that by other methods by a minimum of 12 cascading failure blackout model, Int. J. Electrical Power Energy Syst. 28 (2006)
and maximum of 41 percent. 627–633.
• 35 percent of the most significant initiating events are listed in the [2] A. Dwivedi, X. Yu, P. Sokolowski, Analyzing power network vulnerability with
maximum flow based centrality approach, in: 8th IEEE International Conference on
top 10 scenarios while for other approaches the maximum per Industrial Informatics, IEEE, July 2010, pp. 336–341.
centage of correct identification within the top 10 scenarios is 29 [3] M. Fekri, J. Nikoukar, G.B. Gharehpetian, Identification of initial events of
percent obtained by the parallel corridor search and multi-criteria cascading failures using graph theory methods, Turk. J. Electrical Eng. Comput.
Sci. 30 (7) (2022) 2617–2635.
methods. [4] Andrea M. Rei, Marcus Th. Schilling, Albert C.G. Melo, Monte Carlo simulation and
• The most critical initiating event, i.e., the outage of the line 4–5 is contingency enumeration in bulk power systems reliability assessment, in: 9th
ranked first in the list whereas it is ranked 2nd to 5th by other International Conference on Probabilistic Methods Applied to Power Systems KTH,
Stockholm, Sweden, 2006.
methods. [5] H. Suh, Carl K. Chang, Algorithms for the minimal cutsets enumeration of networks
• The simulation results in this network show that the new method by graph search and branch addition, in: 25th Annual IEEE Conference on Local
can detect about 47% of the initial events of cascading failures in a Computer Networks (LCN), Florida, USA, 2000, pp. 100–107.
[6] Iroshani Jayawardene, Pramod Herath, Ganesh K. Venayagamoorthy, A graph
time of about 3.5 s whereas other methods take longer times and theory-based clustering method for power system networks, in: Clemson University
their detection percentage is lower. Power Systems Conference (PSC), Clemson, SC, USA, March 2020.
[7] N. Bhatt, et al., Assessing vulnerability to cascading outages, in: IEEE/PES Power
Systems Conference and Exposition, Seattle, WA, USA, Mar. 2009, pp. 1–9.
In this research, the lines 4–5 and 13–14 of the test system were
[8] Y. Zhu, X. Liu, B. Chen, D. Sun, D. Liu, et al., Identification method of cascading
identified to have the highest contribution in high-risk cascade failure failure in high-proportion renewable energy systems based on deep learning,
scenarios with 50 and 22 percent, respectively. Therefore, these ele Energy Reports 8 (2) (May 2022) 117–122.
ments are designated as the most vulnerable points in the test network. [9] X. Wei, S. Gao, T. Huang, E. Bompard, R. Pi, T. Wang, Complex network-based
cascading faults graph for the analysis of transmission network vulnerability, IEEE
Future works can focus on the optimal adoption of remedial action Trans. Ind. Inf. 15 (3) (March 2019) 1265–1276.
11
M. Fekri et al. Electric Power Systems Research 220 (2023) 109271
[10] C. Pang, Fast Detection and Mitigation of Cascading Outages in The Power System, [24] J. Dudek, R. Hrbac, J. Veleba, I. Ullman, Examination of failure modes on tertiary
Ph.D. Thesis, Dept. Electrical and Computer Engineering, University of Texas A&M, side of transformers in Czech transmission power system, in: 18th International
December 2011. Scientific Conference on Electric Power Engineering (EPE), Kouty nad Desnou,
[11] R. Xu, D. Chen, Q. Zong, J. Luo, A cross-space cascading failure hazard assessment Czech Republic, May 2017.
method considering betweenness centrality and power loss, Turk. J. Electrical Eng. [25] M.H. Enjavimadar, M. Rastegar, Optimal reliability-centered maintenance strategy
Comput. Sci. 29 (3) (2021) 1479–1494. based on the failure modes and effect analysis in power distribution systems,
[12] F. Hajbani, H. Seyedi, K. Zare, Evaluation of power system robustness in order to Electr. Power Syst. Res. 203 (February 2022), 107647.
prevent cascading outages, Turk. J. Electrical Eng. Comput. Sci. 27 (1) (2019) [26] A. Neves Silvestre Baleia, Failure Modes and Effects Analysis (FMEA) for Smart
258–273. Electrical Distribution Systems, M.Sc. Thesis, Dept. Electrical and Computer
[13] H. Guo, C. Zheng, H. Ching, T. Fernando, A critical review of cascading failure Engineering, University of Lisboa (ULisboa, November 2018.
analysis and modeling of power system, Renewable Sustain. Energy Rev. 80 (2017) [27] O.R. Shuring, C.W. Frick, Heating& current carrying capacity of bare conductors
9–22. for outdoor service, G.E. Rev. (March 1930).
[14] Z. Guohua, W. Ce, Z. Jianhua, Y. Jingyan, Z. Yin, et al., Vulnerability assessment of [28] Marcenko, B.Drol, "Thermal loading of H.V. line conductors," CIGRE, SC-22,
bulk power grid based on complex network theory, in: 2008 Third International Sarajevo, 1989.
Conference on Electric Utility Deregulation and Restructuring and Power [29] IEEE Std. 738, IEEE standard for calculating the current-temperature relationship
Technologies, Nanjing, April 2008. of bare overhead conductors, 2012.
[15] W. Kröger, E. Zio, Vulnerable Systems, Springer-Verlag London Limited, 2011. [30] A. Wang, Y. Guangyu, P. Liu, Vulnerability assessment scheme for power system
[16] C.M. Davis, T.J. Overbye, Multiple element contingency screening, IEEE Trans. transmission networks based on the fault chain theory, in: IEEE Trans. on power
Power Syst. 26 (3) (2010) 294–301. systems, this article has been accepted for inclusion in a future issue of this journal,
[17] H. Song, M. Kezunovic, A new analysis method for early detection and prevention 2011.
of cascading events, Electr. Power Syst. Res. 77 (8) (June 2007) 1132–1142. [31] P. Pourbeik, P.S. Kundur, C.W. Taylor, The anatomy of a power grid blackout, in:
[18] Y. Liu, A. Zhang, P. Dehghanian, J. Kyo Jung, U. Habiba, T.J. Overbye, Modeling IEEE power & energy magazine, September 2006, pp. 22–29.
and Analysis of Cascading Failures in Large-Scale Power Grids, in: 2022 IEEE [32] H.H. Goh, B.C. Kok, Application of analytic hierarchy process (ahp) in load
Kansas Power and Energy Conference (KPEC), Manhattan, KS, USA, April 2022. shedding scheme for electrical power system, in: 9th International Conference on
[19] Y. Dai, R. Preece, M. Panteli, Risk assessment of cascading failures in power Environment and Electrical Engineering, Prague, Czech Republic, May 2010.
systems with increasing wind penetration, Electr. Power Syst. Res. 211 (October [33] M. Catalani, L. Ciani, D. Galar, G. Patrizi, Risk Assessment of a Wind Turbine: a
2022), 108392. New FMECA-Based Tool with RPN Threshold Estimation, IEEE Access 08 (January
[20] A. Zúñiga, A. Baleia, J. Fernandes, P. Branco, Classical failure modes and effects 2020) 20181–20190.
analysis in the context of smart grid cyber-physical systems, Energies 13 (5) (March [34] Rodney C. Hardiman, Murali Kumble, Yuri V. Makarov, An advanced tool for
2020) 1–25. analyzing multiple cascading failures, in: 8th International Conference on
[21] IEC 60812 Standard, Analysis techniques for system reliability –part2: procedure Probabilistic Methods Applied to Power Systems, Ames, Iowa, Iowa State
for failure mode and effects analysis (FMEA)’,2006. University, September .
[22] BS EN 60812, Analysis techniques for system reliability. Procedure for failure mode [35] DIgSILENT PowerFactory Manual Version 2017, DIgSILENT GmbH, Gomaringen,
and effects analysis (FMEA), 2006. Germany, June 2017.
[23] F. Moinian, M. Taghi Ameli, A reliability-based approach for integrated generation
and transmission maintenance coordination in restructured power systems, Electr.
Power Syst. Res. 206 (May 2022), 107737.
12